Top Banner

of 57

Risk Analysis in Capital Investment Decisions

May 30, 2018

Download

Documents

anindya_kundu
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
  • 8/9/2019 Risk Analysis in Capital Investment Decisions

    1/57

    Risk Analysis in Capital

    Investment Decisions Measurement of Risk Method of Incorporating Risk into

    Capital Budgeting

  • 8/9/2019 Risk Analysis in Capital Investment Decisions

    2/57

    Measures of Risk

    Range

    Mean absolute Deviation

    Semi-Variance Coefficient of Variation

  • 8/9/2019 Risk Analysis in Capital Investment Decisions

    3/57

    example

    NPV Probability

    200 0.3

    600 0.5

    900 0.2

  • 8/9/2019 Risk Analysis in Capital Investment Decisions

    4/57

    For your Project

    Assign uneven probability for your cashflow and calculate , variance and semi-variance and coefficient of variation

  • 8/9/2019 Risk Analysis in Capital Investment Decisions

    5/57

    Method of Incorporating Risk intoCapital Budgeting

    Certainty Equivalent Method

    Risk adjusted Discount Rate Method

    -Perfectly Correlated cashflows

    -Uncorrelated cash flows

    -Moderately correlated cashflows

  • 8/9/2019 Risk Analysis in Capital Investment Decisions

    6/57

    Certainty Equivalent Method

    Utility of Decision Maker for the returnobtained by taking each additional unit ofrisk

    Useful when the Decision makers risk-return perception vary from one year toanother

  • 8/9/2019 Risk Analysis in Capital Investment Decisions

    7/57

    Certainty Equivalent Method

    Outcome probability

    1000 0.30

    5000 0.70

    Expected Value=

    Which alternative uwill take?

    Find out Certainty

    Equivalent Coefficient

    Sure cash flow Rs 3000

  • 8/9/2019 Risk Analysis in Capital Investment Decisions

    8/57

    Certainty Equivalent Coefficient

    =Sure Cash flow/Exp cash flow

    =3000/3800

    =0.79 Shows the level of confidence of the top

    mgt about the receipt of the cash flow from

    the project.

  • 8/9/2019 Risk Analysis in Capital Investment Decisions

    9/57

    Example (00 000)

    Year Cash flow CEC

    1 10 0.9

    2 15 0.85

    3 20 0.82

    4 25 0.72

    Find out CEC? And Comment on your findings, if

    Initial investment is 45 lakhs; Rf=5%pa

  • 8/9/2019 Risk Analysis in Capital Investment Decisions

    10/57

    Use formula for CEC in aboveproblem

    Ii

    ANPV

    n

    t

    t

    tt +

    ==1 )1(

    =CEC for the cash flow

    A= the expected relevant cash flow

    i=risk free rate

    I=initial investment

  • 8/9/2019 Risk Analysis in Capital Investment Decisions

    11/57

    CEC

    Varies between 0-1

    Higher the CEC, higher the confidence ofthe decision maker

    CEC=1 for T-bills & Risk free instruments

    If cash flows are highly correlated CEC will

    be same in all the years

  • 8/9/2019 Risk Analysis in Capital Investment Decisions

    12/57

    Cash Flows as RandomVariables

    Risk is chance that a random variable will takeon a value significantly different from theexpected value In capital budgeting the estimate of each future

    period's cash flow is a random variable

    The NPV and IRR of any project are random variableswith expected values and variances that reflect risk

    Thus, the actual value is likely to be different than the mean

    The amount the actual value is likely to differ from theexpected is related to the variance or standard deviation

  • 8/9/2019 Risk Analysis in Capital Investment Decisions

    13/57

    The Probability Distribution of a FutureCash Flow as a Random Variable

  • 8/9/2019 Risk Analysis in Capital Investment Decisions

    14/57

    Risk in Estimated Cash Flows

  • 8/9/2019 Risk Analysis in Capital Investment Decisions

    15/57

    Risk Adjusted Discount Rate Method

    Category of Investment Discount Rate

    Replacement ofInvestments

    Cost of capital +2%

    New Projects Cost of capital +4%

    R&D Investments Cost of capital +5%

  • 8/9/2019 Risk Analysis in Capital Investment Decisions

    16/57

    Calculation of SD of NPV

    Un-correlated cash flows-use Rf as discounting rate

    expected NPV

    Expected cash flowfor year t

    i = Rf

    I=Initial outlay

    VPN

    Ii

    AVPN

    n

    t

    t

    t +

    ==1 )1(

    A2/1

    1

    2

    2

    )1(

    )(

    +

    = =

    n

    t

    t

    t

    i

    NPV

  • 8/9/2019 Risk Analysis in Capital Investment Decisions

    17/57

    Example

    Year 1 Year 2 Year 3

    3000 0.3 2000 0.2 3000 0.3

    5000 0.4 4000 0.6 5000 0.4

    7000 0.3 6000 0.2 7000 0.3

  • 8/9/2019 Risk Analysis in Capital Investment Decisions

    18/57

    Perfectly correlated cash flows

    Ii

    AVPN

    n

    tt

    t +

    ==1 )1(

    +=

    =

    n

    t

    t

    t

    iNPV

    1 )1()(

  • 8/9/2019 Risk Analysis in Capital Investment Decisions

    19/57

    Example

    Work out previousone

    Next, see table; given

    I=10,000

    Year Aver.CF

    Std DevCF

    1 5000 1500

    2 3000 1000

    3 4000 20004 3000 1200

  • 8/9/2019 Risk Analysis in Capital Investment Decisions

    20/57

    Moderately correlated cash flow

    Page 212

  • 8/9/2019 Risk Analysis in Capital Investment Decisions

    21/57

    Using probability table

    Given average NPV=96,000

    Dtd devn NPV = 60,000

    What is the probability that NPV will beless than 0?

  • 8/9/2019 Risk Analysis in Capital Investment Decisions

    22/57

  • 8/9/2019 Risk Analysis in Capital Investment Decisions

    23/57

    Advanced Techniques in RA

    Sensitivity Analysis

    Scenario Analysis

    Simulation approach Decision Tree Analysis

  • 8/9/2019 Risk Analysis in Capital Investment Decisions

    24/57

    Sensitivity Analysis I

    Method Sensitivity analysis is a risk analysis technique that tells how

    much NPV will change in response to given changes in one cashflow factor with other factors held constant.

    -5% 20%15%10%5%-10%-15%-20%

    Deviation from Base-Case Value (%)

    NPV ($)

    $ 0

    0%

    Unit sales price

    NPV based on the originallyestimated unit sales price

    NPV when unit sales pricegoes up by 15%

    NPV when unit sales pricegoes down by 20%

    Based on: Financial Management, Eugene F. Brigham and Michael C. Ehrhardt, 2008

  • 8/9/2019 Risk Analysis in Capital Investment Decisions

    25/57

    Sensitivity Analysis II

    The slopes of the lines indicate how sensitive NPV is to changes ineach individual cash flow.

    Relatively small error in estimating individual cash flow with steeperslope leads to a large error in estimating projects NPV.

    -5% 20%15%10%5%-10%-15%-20%

    Deviation from Base-Case Value (%)

    NPV ($)

    $ 0

    0%

    Unit sales price

    Estimated values of cashflow factors

    Price growth rate

    Sales quantity

    Asset beta

    Utility price

    Input price

    Input price growth

    Operating costs

    Construction costsNPV breakevenanalysis

    Original NPVvalue

    Based on: Financial Management, Eugene F. Brigham and Michael C. Ehrhardt, 2008

  • 8/9/2019 Risk Analysis in Capital Investment Decisions

    26/57

    Sensitivity Analysis III

    Implication Sensitivity analysis is a powerful technique to understand which factors

    need to be more accurately examined to reduce the entire credit risk.

    Weak Points

    Sensitivity analysis does not incorporate a concept of probability

    It can deal with only one cash flow for each analysis NPV Breakeven Analysis

    NPV breakeven analysis examines a value of each factor which makesNPV exactly zero.

    Based on: Financial Management, Eugene F. Brigham and Michael C. Ehrhardt, 2008

  • 8/9/2019 Risk Analysis in Capital Investment Decisions

    27/57

    Sensitivity Analysis for your project

    Find what happens to your projects NPV ifthe cash flow affected by:

    Increase/decrease in Initial Outlay

    fall / rise in Saleshike / dip in Variable Costs

    up / down in Fixed Costs

    Only one variable is varied at a time

  • 8/9/2019 Risk Analysis in Capital Investment Decisions

    28/57

    Sensitivity Analysis for Your Project

    Key variable Range

    Pessimistic Expected Optimistic

    Investment -20% Normal +20%

    Sales Rs m -16% Normal +16%

    Variablecost as % ofsales

    +10% Normal -5%

    Fixed costs +30% Normal -20%

  • 8/9/2019 Risk Analysis in Capital Investment Decisions

    29/57

    Advantages Vs Disadvantages

    How robust orvulnerable to changesin underlying

    variables Help explore where

    the vulnerability ismore

    Intuitively appealing

    Nothing about thelikelihood of thesechanges

    Specified variablebased

    Inherently subjective

  • 8/9/2019 Risk Analysis in Capital Investment Decisions

    30/57

  • 8/9/2019 Risk Analysis in Capital Investment Decisions

    31/57

    Scenario Analysis I

    Method Scenario analysis examines a set of scenarios under tha

    assamption that each scenario occurs with a certain probability

    Example 1: sales price would drop by 6% with 25% probability forworst case scenario.

    Example 2: operating cost would be reduced by 2% with 25%probability for best case scenario.

    Then obtain base-case, best-case, and worst-case NPV andcalculate mean NPV and standard deviation to (roughly)estimate the magnitude of the risk inherent to the project.

    Implication Scenario analysis is very useful technique to grasp the worst

    case situation of the project (by assuming 1.0 correlation).

    Based on: Financial Management, Eugene F. Brigham and Michael C. Ehrhardt, 2008

  • 8/9/2019 Risk Analysis in Capital Investment Decisions

    32/57

    Scenario Analysis II

    Simplified illustration of scenario analysis process

    Standard Deviation

    of NPV

    Expected NPV(mean value)

    Base-, best-, and worst-case scenarios of each cashflow

    Slot in all base-, best-,and worst-case scenariosof each cash

    Excel

    Sheet

    NPV ($)$0

    50%

    40%

    30%

    Probability (%)

    FCF from best-

    case scenario

    FCF from base-

    case scenario

    FCF from worst-

    case scenario

    Mean value

    20%

    10%

    Projected NPVs on the basis of the three scenarios

  • 8/9/2019 Risk Analysis in Capital Investment Decisions

    33/57

    Your Projects Scenario Analysis

    Considerworst, normal, best scenario foryour project & work out scenario analysis

    All items in P&L undergo changes

  • 8/9/2019 Risk Analysis in Capital Investment Decisions

    34/57

    Monte Carlo Simulation

    Technique for evaluation of

    capital investments underconditions of risk

  • 8/9/2019 Risk Analysis in Capital Investment Decisions

    35/57

    An Imitation of a real worldsystem, using a mathematical

    model that captures thecharacteristic features of thesystem as it encounters random

    events in time.

  • 8/9/2019 Risk Analysis in Capital Investment Decisions

    36/57

    Monte Carlo Simulation

    Simplified illustration of monte-carlo simulation process

    Probability distribution of each cashflow and correlations between them

    Randomly picking upscenarios

    NPV ($)$0

    10%

    8%

    6%

    4%

    2%

    Probability (%)

    Simplified illustration of probability distribution of NPVs

    NPVs probabilityDistribution

    Standard Deviationof NPV

    Expected NPV(mean value)

  • 8/9/2019 Risk Analysis in Capital Investment Decisions

    37/57

    6 step process

    Define the problem

    Identify the fixed & variable factors

    Identify the alternatives available Construct a mathematical model

    Run the model & get results

    Decide best of the alternatives

  • 8/9/2019 Risk Analysis in Capital Investment Decisions

    38/57

    For Your Project

    Assign same probabilities as in the bookwith respect to the three variables Cost ofthe Project, Life of the project and annual

    cash flows Your mathematical model could be NPV,

    IRR

  • 8/9/2019 Risk Analysis in Capital Investment Decisions

    39/57

    example

    Annual Cash Flow ################################

    ################################

    ####################

    Project life

    Value Probability 3 0.05

    1000 0.02 4 0.10

    1500 0.03 5 0.302000 0.15 6 0.25

    2500 0.15 7 0.15

    3000 0.30 8 0.103500 0.20 9 0.03

    4000 0.15 10 0.02

  • 8/9/2019 Risk Analysis in Capital Investment Decisions

    40/57

    Initial Decisions

    1. You want to set 10 runs of simulations

    2. Exogenous variables identified areAnnual cash flows and Life of project

    3. You want to use two-digit randomnumbers only

    4. Model applied is NPV

    ( )estmentInitialInv

    teRiskfreera

    FlowAnnualCashNPV

    n

    t

    +

    ==1 1

  • 8/9/2019 Risk Analysis in Capital Investment Decisions

    41/57

    Steps

    1. assign two-digit random numbers rangefrom 0-99

    2. Assign probabilities

    Set up correspondence between

  • 8/9/2019 Risk Analysis in Capital Investment Decisions

    42/57

    Set up correspondence betweenValues of Exogenous variables & 2

    digit random numbersAnnual cash flow

    alue

    Rs.

    PROB CUMPROB

    2 DIGIT

    R N

    1000 0.02 0.02 00-01

    1500 0.03 0.05 02-04

    2000 0.15 0.20 05-19

    2500 0.15 0.35 20-34

    3000 0.30 0.65 35-64

    3500 0.20 0.85 65-84

    4000 0.15 1.00 86-99

    Project LifeValue Yrs Prob Cum Prob 2 Digi

    R N

    3 0.05 0.05 00-04

    4 0.10 0.15 05-14

    5 0.30 0.45 15-44

    6 0.25 0.70 45-69

    7 0.15 0.85 70-84

    8 0.10 0.95 85-94

    9 0.03 0.98 95-97

    10 0.02 1.00 98-99

  • 8/9/2019 Risk Analysis in Capital Investment Decisions

    43/57

    Choosing the Probabilitydistribution for basic variables

    Portrait Approach - like police

    Building Block approach expert dividethe data according to pattern & arrive at

  • 8/9/2019 Risk Analysis in Capital Investment Decisions

    44/57

    Uniform DistTrapezoidal Distribution

    Normal

    Step Rectangular

    Distbn

  • 8/9/2019 Risk Analysis in Capital Investment Decisions

    45/57

    What to use when

    Uniform Distribution : safe limits

    Trapezoidal : data in a small range around itsbest estimate large class of subjective

    judgments satisfactorily Step Rectangular : divides data into ranges &assign different probability to each

    Normal where no statistical errors or random

    disturbances affect the data

  • 8/9/2019 Risk Analysis in Capital Investment Decisions

    46/57

    Simulation resultsRun RN Rs CF

    1 53 3000

    2 66 3500

    3 30 2500

    4 19 2000

    5 31 2500

    6 81 3500

    7 38 3000

    8 48 3000

    9 90 4000

    10 58 3000

    R N Yrs NPV

    97 9 4277

    99 10 8506

    81 7 (829)

    09 4 (7660)

    67 6 (2112)

    70 7 4039

    75 7 1605

    83 7 1605

    33 5 2163

    52 6 66

    http://random%20numbers.xls/http://random%20numbers.xls/
  • 8/9/2019 Risk Analysis in Capital Investment Decisions

    47/57

  • 8/9/2019 Risk Analysis in Capital Investment Decisions

    48/57

    World Bank

    Powerful technique

    Efficient medium of communication

    Not replacing skilled judgment; morejudgment than traditional analysis

    Treatment of correlations betweenvariables can be completely misleading ifcorrelations are not handled properly

  • 8/9/2019 Risk Analysis in Capital Investment Decisions

    49/57

    Decision Tree Analysis

    Decision Tree analysis lets us approximate the NPVdistribution if we can estimate the probability of certainevents within the project

    A decision tree is an expanded time line which branches

    into alternate paths whenever an event can turn outmore than one way The place at which branches separate is called a node

    Any number of branches can emanate from a node but theprobabilities must sum to 1.0 (or 100%)

    A path represents following the tree along a branch Evaluating a project involves calculating NPVs along all possible

    paths and developing a probability distribution

  • 8/9/2019 Risk Analysis in Capital Investment Decisions

    50/57

    Decision tree analysis

    Identify the problem

    Delineate the decision tree

    Specify probability & monetary outcomes Evaluate the decision alternatives

    Decision Tree Analysis

  • 8/9/2019 Risk Analysis in Capital Investment Decisions

    51/57

    Q: The Wing Foot Shoe Company is considering a three-year projectto market a running shoe based on new technology. Successdepends on how well consumers accept the new idea and demandthe product. Demand can vary from great to terrible, but forplanning purposes management has collapsed that variation into

    just two possibilities, good and poor. A market study indicates a60% probability that demand will be good and a 40% chance that itwill be poor.

    It will cost Rs5M to bring the new shoe to market. Cash flowestimates indicate inflows of Rs3M per year for three years at full

    manufacturing capacity if demand is good, but just Rs1.5M per yearif its poor. Wing Foots cost of capital is 10%. Analyze the projectand develop a rough probability distribution for NPV.

    Example

    Decision Tree AnalysisExample 1

    Decision Tree Analysis

  • 8/9/2019 Risk Analysis in Capital Investment Decisions

    52/57

    Decision Tree AnalysisExample

    A: First, draw a decision tree diagram for the project. Then calculatethe NPV along each path.

    Examp

    leRs1.5MRs1.5MRs1.5M

    (Rs5M)

    Rs3MRs3MRs3M

    3210

    P = .6

    P = .4

    NPV

    Rs2.461M

    Rs-

    1.270M

    Then calculate the weighted NPV for the tree.

    Rs1.077MExpectedNPV =

    Rs-.508M40%-1.270MPoor

    Rs1.585M60%2.641MGood

    ProductProbabilityNPVDemand

    The decisiontree explicitly

    calls out the fact

    that a big loss isquite possible,although the

    expected NPVis positive.

  • 8/9/2019 Risk Analysis in Capital Investment Decisions

    53/57

    Example 2

    The scientists at Spectrum have come upwith an electric moped. The firm is readyfor pilot production and test marketing .

    This will cost Rs. 20 million and take 6months. Mgt believes that there is 70%chance that the pilot production and test

    marketing will be successful. In the caseof success , they can build the plantcosting Rs 150m.

  • 8/9/2019 Risk Analysis in Capital Investment Decisions

    54/57

    - contd

    The plant will generate an annual cashinflow of Rs.30m for 20 yrs if the demandis high or an annual cash inflow of Rs.20m

    if the demand is low. High demand has aprobability 0.6; low demand 0.4; pl advisethe co using decision tree analysis

    E l 3 E t d V l &

  • 8/9/2019 Risk Analysis in Capital Investment Decisions

    55/57

    Example 3- Expected Value &Decision Tree

    Decision

  • 8/9/2019 Risk Analysis in Capital Investment Decisions

    56/57

    Expected Value

  • 8/9/2019 Risk Analysis in Capital Investment Decisions

    57/57

    Decision Tree