-
Responses to Questions Submitted by
Chairman John Parete and Members of
The Ulster County Legislature
Regarding the Agreement with the City of New York to Accept
Grant Funding for and Facilitate Creation of a Public
Recreational
Trail Along the Ashokan Reservoir
Respectfully Submitted
May 14, 2015
-
Table of Contents
I. Responses to Questions from Hon. John Parete Pages 1-2
II. Responses to Questions from Hon. Tracey Bartels Pages
3-8
III. Responses to Questions from Hon. David Donaldson Pages
9-17
IV. Responses to Questions from Hon. Manna Jo Greene Pages
18-25
V. Appendix A: Trail Maintenance Estimates Page 26 Source:
Rails-to-Trails Conservancy
VI. Appendix B: Letter for Maintenance Support Page 27 Source:
NY-NJ Trail Conference
VII. Appendix C: Memo on Type of SEQR Action Page 28 Source:
Dennis Doyle, Planning Director
-
Responses to MOA Questions Submitted by
Chairman of the Ulster County Legislature John Parete
May 14, 2015
NOTE: Questions and requests from the Chairman are numbered.
Responses are italicized and in red.
1) He (the Chairman) would like a copy of the agreement
referenced in the third WHEREAS
dated June 15, 1911.
This document has been provided to the Legislative staff.
2) In the fifth WHEREAS, would anything besides a resolution of
the Legislature deem freight
rail use as infeasible?
This WHEREAS clause is related to the Countys option to pursue
federal Railbanking if it chooses. The determination that freight
rail use is infeasible would be approved by the Surface
Transportation Board (STB).
3) Explain the relevance of the National Trails System Act to
this project, as referenced in the
sixth WHEREAS.
The County has the option under the MOA to undertake federal
Railbanking of the corridor for
interim use as a trail. This would be done under the National
Trails System Act, which provides
for interim trail use of railroad corridors until such time that
freight operations are reactivated
on the right-of-way.
4) Eighth WHEREAS, "The County will design the Ashokan Rail
Trail, subject to DEP
approval.." What is the process?
The County will issue a competitive RFQ to procure engineering
and design services for trail
design. The planning process will involve meetings with
stakeholder groups and local
communities and include multiple opportunities for public input.
DEP will have input into the
design and will have to approve the final plans prior to
construction of the trail, which will be
put out to competitive bidding.
5) The tenth WHEREAS, says IF the County obtains a certificate,
OR upon written request from
the City or County. Why would the County need a certificate if
we can make a written request?
The County does not need a certificate to modify its easement
for trail use or to preserve its
perpetual railroad easement. The MOA provides the option to the
County of Railbanking and
the certificate is one route for obtaining STB approval.
Page 1 of 25
-
Responses to MOA Questions Submitted by
Chairman of the Ulster County Legislature John Parete
May 14, 2015
6) Section 1. (A) 2.5 million goes to the County for planning,
design and construction of the
trail. Do we know the estimated cost of planning, design and
construction of the Trail.
The County estimates design and future construction of the trail
along the Ashokan will be
covered by the $4.5 million in available funding from DEP and
through the 2013 NYS EPF
award ($2 million). The only costs not covered by this funding
are for the reconstruction of the
Butternut Creek Culvert, for which the County has received a NYS
DEC Water Quality grant and
has additional grant requests pending.
7) Section 1.(C) references sanitary facilities. Will these
facilities be provided/available/ maintained year round?
The location, design and operation of sanitary facilities will
be determined during the planning
process for trailheads.
8) Will the proposed trail follow the existing bed with no
deviation for any reason whatsoever?
The trail will follow the existing bed to the maximum extent
possible. There has been no reason
identified to date for deviations of the trail from the existing
railroad bed, but this will be
confirmed through the planning and design process.
9) Throughout the document, it is stated that DEP approval is
required on many items. It appears
however, they have no responsibility in reference to the items
they approve. Please confirm.
The DEP is funding the planning and a large percentage of the
construction of the trail and is
also responsible for constructing and maintaining the public
trailheads. That is the primary
DEP responsibility on the trail design. The DEP and County will
also share security
responsibilities, which will be negotiated and included in the
Joint Security Agreement.
10) Exhibit B. 4. c. The City can temporarily shut the trail
down for water supply purposes.
What exactly are said purposes?
The DEP is able to close the trail temporarily in the event to
protect its water supply. This could
include security issues that threaten the water supply and
related infrastructure.
Page 2 of 25
-
Responses to MOA Questions Submitted by
U&D Corridor Advisory Committee Chair Tracey Bartels
May 14, 2015
NOTE: Questions are in black. Responses are italicized and in
red.
1. Page 2, first Whereas
Please explain why the MOA refers to freight rail use.
Resolution 275 does not address the
feasibility of rail use in any way and never refers to freight
rail use. This paragraph states that
resolution 275 is evidence of the infeasibility of freight rail
use.
The Whereas clauses simply frame the intent of the Agreement;
the subsequent terms and condition constitute the actual Agreement.
The MOA reference to freight rail use pertains to
federal Railbanking. This clause states that if freight rail is
infeasible (which is the conditional
language the Railbanking attorney asked us to include), the
Countyseeks to develop, in an environmentally sensitive manner, the
existing railroad corridor along the Ashokan Railroad
Easement into a recreation trail as evidenced by Legislative
Resolution 275, which called for this U&D corridor segment to
be converted to trail only. Resolution 275 did not evidence
that
freight rail is infeasible but rather that the County seeks to
develop trail along the Ashokan
Reservoir easement (where there has been no freight, passenger,
or tourism railroad service
since 1976).
2. Page 2, third Whereas
Same question. The whereas states preserve the corridor for
freight rail use. Please explain why all references to preservation
of rail rights refer to freight rail use. It was explained that
this
was one means to pursuing abandonment or Railbanking rights with
the STB. Is it the only
means? Does the term freight have a legal meaning that is
distinct from passenger or tourist as it
applies to rail operation? By signing this agreement are we in
any way limiting our ability to
pursue abandonment or Railbanking for future passenger rail use
or tourist rail use? If not, why
does it specify freight only? Why not use the broadest language
and simply say rail use?
The MOA references to freight rail preserve one option for the
County-- if it chooses-- to seek
federal Railbanking through the Surface Transportation Board
(STB). The County, whether it
chooses federal Railbanking or not, has preserved the perpetual
easement for railroad purposes, which includes freight, passenger
and tourism rail operations. However, for STB jurisdictional
purposes, the MOA language cites freight rail operations to allow
an avenue for
Railbanking. It doesnt limit the County to freight rail. The MOA
in no way limits the Countys ability to resume, at some future
date, railroad operations, including freight, passenger and/or
tourism trains.
3. Page 2, sixth Whereas
the parties shall modify the existing Ashokan Rail Easement or
establish an alternative property interest Please explain the
difference between the two and the benefit of one over the
other.
The MOA allows several options for a permanent easement for
trail use. This could be a
modification to the existing railroad easement or a separate
additional easement for trail use.
Both would protect the Countys perpetual railroad easement and
allow for interim trail use (until such time that the County
re-established railroad operations.) This option was added to
add flexibility in protecting the Countys right with respect to
the easement.
Page 3 of 25
-
Responses to MOA Questions Submitted by
U&D Corridor Advisory Committee Chair Tracey Bartels
May 14, 2015
4. Page 4, Section 1 City Obligations B.
Please explain the how the interaction between the DEP and CWC
works. How was the
monetary figure arrived at?
The City of New York, through the DEP, provides funding to the
CWC, and DEP has a position
and vote on the Board of Directors of the CWC (there are also
two representatives from Ulster
County. The figure represented a reasonable amount that would
allow enhancements to be
added to the trail along the Ashokan Reservoir.
5. Page 4, Section 1 City Obligations C
The City requires that DEP have final approval of the final
design of the trail. This paragraph
talks about mutual agreement and input from the County as to the
portions of the project to be
constructed by the City. It reads that we are mutually agreeing
upon the location of the
additional trail support amenities not the trailheads
themselves. I want to confirm that this is
acceptable to the County.
The trailhead amenities-- and the locations-- will be mutually
agreed upon by the County and
City. The MOA clause reads, at locations, mutually agreed upon
by the Parties. This is acceptable to the County as it includes the
locations and support facilities.
6. Page 5, Section 1 City Obligations G
This paragraph refers to a Land Use Permit or a Modified Ashokan
Railroad Easement. What is
the benefit of one over the other? Do we know what the terms of
the Permit would be? Has this
yet been discussed?
The Land Use Permit is an interim step towards the Modified
Easement (or alternative property
interest), which will outlive the Permit. The Permit simply
establishes the foundation or
framework for the City to provide funding to the County,
authorize trail use on the railroad
easement, and begin the public planning and design process. As
the County begins planning, it
will work with DEP on developing the Modified Easement. The
terms of the Permit are
contained in Exhibit B and would be included in the Modified
Easement. The Land Use Permit
essentially allows the project planning to begin while the
County and City work out the Modified
Easement. The Permit is a shorter-term first step, and the
Modified Easement is the longer-term, permanent instrument for
trail use.
7. Page 5, Section 2 County Obligations C
Who will determine where the fencing and guardrails go? Do we
have an estimate of the
quantity and cost?
The detailed design of the trail, including fencing, amenities
(such as benches, signage, kiosks),
and trail surface will all be determined through the public
planning process. The planning
process will include input from the County Legislature, DEP, the
local communities, area
businesses, and residents of the County. The current estimates
for trail construction along the
Ashokan Reservoir include allowances for fencing at expected
locations, such as the narrow
causeway in the western part of the corridor and along steep
embankments.
Page 4 of 25
-
Responses to MOA Questions Submitted by
U&D Corridor Advisory Committee Chair Tracey Bartels
May 14, 2015
8. Page 6, Section 2 County Obligations D
Would the DEP be afforded all the rights of an involved agency
during an environmental review
of additional areas of the U&D Corridor in the NYC Watershed
by right or is this something that
the MOA is granting?
DEP has permitting authority over components of the trail within
its Watershed and therefore
would by right be an involved agency, with or without the
MOA.
Please define all the areas of the U&D corridor that are in
the watershed.
The entire U&D corridor from milepost 10.05 at Basin Road in
West Hurley to milepost 38.6 in
Highmount is located in the New York City Watershed. The U&D
corridor east of Basin Road is
not in the Watershed.
9. Page 6, Section 2 County Obligations E
Is the County responsible for obtaining all the permits for the
trailhead work? Section C of the
Citys responsibilities fails to address obtaining all required
federal, State and local permits and approvals for design,
construction, operation and maintenance of the trailheads as
addressed in
this section for the Rail Trail.
The DEP is responsible for any permits that might be needed for
trailhead work, while the
County is responsible for including the trailhead work in its
SEQR review.
(There is a typo on Page 6, Section 2 County Obligations F
reopening or of other actions)
This is not a typo. The clause is written as intended.
10. Page 7, Section 3 Railbanking or Abandonment of the U&D
Railroad B
The City reserves its right to comment on such submission to
ensure that any action by the STB is consistent with the purposes
of this Agreement and, in (sic?) Ashokan Rail Trail and, in
particular the development and operation of the Ashokan Rail
Trail in an environmentally
sensitive manner.
Clearly, the City has right to comment on any action of the STB.
How might an action of the
STB be inconsistent with the purposes of this agreement?
This was included as a protection to DEP to ensure that the
County did not apply for federal
Railbanking to authorize trail use without a commitment to the
protection of DEPs drinking water supply. For instance, if the
County decided to withdraw from the MOA and pursue
Railbanking with the intent to construct an impervious trail or
trail that allowed motorized
vehicles, the DEP has retained its right to comment on the
Railbanking application to express
concerns about possible impacts to its water quality from such
activities.
Page 5 of 25
-
Responses to MOA Questions Submitted by
U&D Corridor Advisory Committee Chair Tracey Bartels
May 14, 2015
10. Page 7, Section 3 Railbanking or Abandonment of the U&D
Railroad D
Same issue with specifying freight. Why not call it the
feasibility of establishing rail operations
on the line?
Please see answer to Question 2.
11. Page 8, Effective Date and Term B
Why five years? Can there be an automatic extension?
Five years was negotiated as a reasonable term for this
short-term agreement as a bridge to the future Modified Easement.
It is not anticipated that the extension will be needed, but
the
mutually agreed upon extension was added in case additional time
was needed.
12. Page 8, Effective Date and Term C
This section is of great concern to me. The County has a
perpetual easement over City land for
rail use. The City has recognized the fact (2005 letter to Bill
Tobin from Jeffrey Graf, DEP)
Why would we not have a perpetual easement for trail
activities?
The County would have a perpetual easement for trail activities
through the Modified Easement.
The 120 day escape clause pertains only to the MOA and Land Use
Permit and is consistent with
other such clauses in Ulster County contracts. It is also
important to note that the Countys perpetual rail easement is
protected. Section 3, Paragraph E states, Except as partieis
consensually agree to undertake in the future as set forth herein,
this agreement does not modify
or extinguish in any manner whatsoever, the Ashokan Railroad
Easement
Exhibit B
13. Exhibit B, page 1, Process/Approvals 1a
this Land Use Permit Is Exhibit B the land use permit referenced
earlier? This is confusing. Exhibit B is described as special
conditions to be included in the permit for construction and
maintenance of the Ashokan Rail Trail. Earlier in the document
there are many references to a
Land Use permit. This does not appear to be a Land Use permit.
Could be a typo the Land Use Permit.
Exhibit B is not the actual Land Use Permit, which will be
issued following execution of the
MOA. However, the language and conditions in Exhibit B will be
included the future Land Use
Permit.
14. Exhibit B, page 1, Process/Approvals 1b and c
Are there examples of Operations and Maintenance Plans and
Security Cooperative Agreements
with DEP for watershed land use? Maybe for fishing or hunting
use? It would be nice to see
what they have already approved.
The City does have other approved maintenance agreements with
local organizations and
municipalities for use of other recreational facilities on its
properties, such as trails and ball
Page 6 of 25
-
Responses to MOA Questions Submitted by
U&D Corridor Advisory Committee Chair Tracey Bartels
May 14, 2015
fields. The County has requested copies of these agreements.
Hunting and fishing activities
require individuals to obtain access permits from DEP, and the
MOA recognizes and allows
continued use of Watershed lands along the trail for hunting and
fishing.
15. Exhibit B, page 1, Process/Approvals 1e
This paragraph states that the County is responsible for
monitoring the trail and the trailheads.
Earlier it was stated that it was a City responsibility to
maintain the trailheads. What exactly
does monitor mean? Considering that a failure to monitor could
result in termination of the
permit, we need a very clear definition.
Monitor has a common meeting, which according to Websters
Dictionary is to watch or keep track of. Monitoring of the
trailheads is a shared responsibility between the DEP and County.
Failure to monitor would require DEP notice to the County, and
termination would
only result if the County failed to cure the issue for a
prolonged period of time.
16. Exhibit B, Page 2, Trail Construction 2c
The language is confusing. Does this mean that we can open the
trail as we complete certain
portions?
Yes. This allows the construction of the trail to be completed
in phases that can be opened as
long as the County has constructed them based on an approved
design and consistent with the
provisions of the Land Use Permit. It is anticipated that the
County would do the project along
the Ashokan Reservoir in two phases, but this would be fleshed
out during the public planning
process.
17. Exhibit B, Page 2 Trail Operation and Maintenance 3c
Will the trailheads be open and maintained from dusk to dawn
year round including sanitary
facilities and plowed parking?
The trail and trailheads will be open from dawn to dusk year
round, and the mutually agreed
upon support facilities at these sites, including sanitary
facilities and parking areas, will be
maintained by DEP year round. Parking areas will be plowed to
allow year round access.
18. Exhibit B, Page 3 Trail Operation and Maintenance 3f
How does the County get approval for special events? What is the
criteria? What is the lead
time? Can we include the language that will not be unreasonably
withheld?
The details, including time frames and threshold criteria, for
special event approvals will be
negotiated between DEP and the County and included in the
Operation and Maintenance Plan.
That language can certainly be considered and added as we
develop the O&M Plan.
Page 7 of 25
-
Responses to MOA Questions Submitted by
U&D Corridor Advisory Committee Chair Tracey Bartels
May 14, 2015
19 Exhibit B, Page 3 Trail Operation and Maintenance 3g
Is the City responsible for trash and litter removal at
trailheads, public parking facilities, sanitary
facilities, additional entrance points and other mutually agreed
upon trail support amenities?
As per Section 1, Paragraph C, the City is responsible for
constructing, funding, and operating
the trailheads, including sanitary facilities. This would
include litter and debris removal at
trailheads. The County would be responsible for litter at
additional entry points.
20. Exhibit B, Page 3 Trail Security 4c
How will the City notice the County of a temporary shutdown?
As per Section 6 (Notices) of the MOA, the City would notify the
County Executive with copy to
the County Attorney.
21. Exhibit B, Page 4 Insurance and Indemnification 5ai
What is the estimate on the cost of insurance policy like
this?
The County currently maintains sufficient insurance coverage to
comply with this requirement.
This was confirmed by the Insurance Department and the Countys
insurance carrier.
22. Exhibit B, Page 4 Insurance and Indemnification 5aii
Does this insurance policy include the trailheads, parking etc?
Does the County need to be
named on the Citys insurance for those areas?
No. As per Section 8, Paragraph D, the City retains all
liability for the trailheads.
23. Exhibit B, page 4 Additional Conditions 6a
What might this include? Do we have the right to agree? We
should have the right to see the
conditions before they are imposed.
DEP cannot add conditions that unreasonably interfere with the
publics use of the Ashokan Rail Trail. DEP would notify the County
of concerns related to water quality or public safety that if left
uncured could result in additional conditions. For instance, there
might be safety
concerns identified after the opening of the trail, such as an
area where safety fencing might be
needed. The County could challenge proposed additional
conditions if it feels such conditions
would impose unreasonable restrictions on the publics ability to
use the trail.
Page 8 of 25
-
Responses to MOA Questions Submitted by
Railroad Advisory Committee Chairman David Donaldson
May 14, 2015
NOTE: The Q&A in black is from a prior FAQ provided to the
Legislature.
Comments submitted by Chairman Donaldson are italicized and
copied below in blue.
Responses to the comments that follow are italicized and in
red.
Q: Why did Ulster County and the New York City Department of
Environmental Protection (NYCDEP)
develop a Memorandum of Agreement (MOA)?
A: The MOA enables Ulster County to convert the 11.5-mile Ulster
& Delaware (U&D) railroad corridor along
the Ashokan Reservoir into a public recreational trail available
for use year-round without fee or permit.
The trail, which will extend from West Hurley to Boiceville,
will open the northern shore of the Ashokan
to the public for the first time since the Reservoir was put
into service in 1915 as well as provide significant
funding and other support from NYCDEP. The County and NYCDEP
agreed that trail development along
this section of the U&D corridor would enhance recreational
opportunities, provide an economic
development boost to area businesses, bolster tourism in the
Catskills, and improve the quality of life and
public health. The trail development will also ensure protection
of the City of New Yorks drinking water supply.
*Comment: Agreement can be cancelled on 120 day notice and the
trails can at any time be closed by DEP.
A. The termination terms are consistent with other agreements
the County has entered into. This provision obligates the City to
reimburse the County as to costs incurred or obligated prior to the
cancellation. This
clause protects the County as well as the City. It should be
noted that the funding for this Agreement is
being provide by the City prior to expenditure by the County,
and it provides for the County to drawdown
certain amounts, spend the available funds, and then provide
documentation as to the expenditures or
obligations of the County. The trail can only be closed on a
temporary basis for public safety emergencies.
*Comment: The MOA limits the trail surface to dirt, gravel or
crushed stone- asphalt is not allowed. This
means no high speed bicycles.
A. In order to protect Ashokan Reservoir water quality, the MOA
requires that trail surface materials not be impermeable, as
defined in the NYC Watershed Rules & Regulations. Allowable
trail surface materials include dirt, gravel, and crushed stone, as
well as permeable asphalt surfaces. Professionally constructed
non-asphalt surfaces will accommodate most bicycles, including
many road bicycles, as well as comply with
ADA specifications.
Q: What does the MOA provide to the County?
A: The MOA provides the following benefits to the County:
$2.5 Million in NYCDEP grant funding for planning and
construction with $1 million payable upon contract signing and
registration of the contract with the City of New York
$1 Million in additional grant support through the Catskill
Watershed Corporation
NYCDEP funding, construction and maintenance of multiple public
trailheads with parking, signage and sanitary facilities
Joint marketing of Ashokan Trail to New York City residents
Bicycle and pedestrian improvements to NYCDEPs Ashokan Dividing
Weir Bridge and Five Arch Bridge (Route 28A in Boiceville)
Page 9 of 25
-
Responses to MOA Questions Submitted by
Railroad Advisory Committee Chairman David Donaldson
May 14, 2015
Preservation of Countys perpetual U&D railroad easement
*Comment: $2.5 million will be mostly for design and most
construction funding will need to come from
other sources. Full cost unknown.
A. Planning and design for the trail are estimated to utilize
less than one-quarter of the committed DEP funding. The remainder
of DEP funds and the $2 million in NYS EPF funding awarded in 2013
should be
sufficient to fully design and construct the trail- excluding
Butternut Creek Culvert and the Boiceville
Trestle, for which other funding has been awarded or is pending
for design and construction.
*Comment: There is no guarantee in the MOA that the CWC grant
will be funded.
A. This MOA provision provides for DEP support of future CWC
grant requests. The CWC funding is only one of the possible
additional funding sources for the trail project and is not
integral to completing the Ashokan
Reservoir trail segment. As stated in the prior response, the
available funds are estimated to be sufficient
for trail design and future construction, with the exception of
the Butternut Creek Culvert and Boiceville
Trestle, for which other funding sources are available or
pending.
*Comment: Trailhead locations are undetermined and controlled by
the DEP which will determine parking
spaces and number of users.
A. The trailhead locations, design and parking capacity will be
determined through a community planning process with input from the
local municipalities, area residents, and nearby businesses. The
MOA
purposely left the trailhead locations and other trailhead
details to be determined during the planning
process so that public input could be obtained on preferred
locations, number of parking spaces, needed
support facilities (such as sanitary facilities),and signage/
information kiosks.
*Comment: No funds are committed to joint marketing.
A. The DEP will market the trail directly to its water customers
through regular water bills, which would reach millions of
households with little or no additional cost.
*Comment: Bicycle and pedestrian improvements are only referred
to as consideration of a possible shared-
use lane.
A. Section 1 (D) states, The City.shall accommodate bicycle and
pedestrian traffic (on the Dividing Weir and Five Arch bridges)
including consideration of a dedicated shared-use lane. This allows
the flexibility to construct a separate dedicated lane or
alternatively, widened shoulders on both sides of the bridge,
depending on which is better for connectivity for bicyclists and
pedestrians.
*Comment: Once the rails are removed, this easement will be
vulnerable to cancellation.
A. The removal of the rails in no way extinguishes or modifies
the Countys perpetual railroad easement. In Section 3, Paragraph E,
the MOA states, This agreement does not modify or extinguish in any
manner whatsoever the Ashokan Railroad Easement as described in the
Book of Deeds at Liber 443, Page 58 as
filed in the Office of the Ulster County Clerk.
Page 10 of 25
-
Responses to MOA Questions Submitted by
Railroad Advisory Committee Chairman David Donaldson
May 14, 2015
*Comment: Once the easement is cancelled, the trail is 100%
subject to closure by DEP.
A. The railroad easement cannot be cancelled or modified
unilaterally by DEP. The modified easement that is called for in
the MOA will add interim trail use until such time as the County
chooses to restore rail use and
will only allow temporary closure of the trail by DEP for public
safety and water supply emergencies. If
railroad operations were ever restored, the DEP would also
likely have the ability to stop tourism trains in
the event of a public safety emergency since tourism trains have
no federal protections or pre-emptions.
Q: What does the MOA require from the County?
A: The MOA requires the County to do the following:
Design and construct the trail and related facilities and seek
all necessary environmental permits
Maintain and operate the trail in a manner that does not harm
the Citys drinking water supply
Submit to NYCDEP for approval the design of the trail, an
operation and maintenance plan, and a joint security agreement
Advise NYCDEP of any actions related to federal Railbanking
*Comment: The cost of design, construction and permitting is
unknown.
A. As per the 2015-2020 Capital Improvement Program, the County
Planning Department has provided preliminary estimates of costs for
the 11.5 mile trail from Basin Road to Boiceville, including the
Butternut
Creek Culvert and Boiceville Trestle. The available DEP and NYS
EPF funding- totaling $4.5 million- is
estimated to cover design, permitting and trail construction
costs of the trail, except for the Butternut Creek
Culvert and Boiceville Trestle, for which other State and
federal funding has been awarded or is pending.
*Comment: Maintenance costs are unknown.
A. If the County does 100% of the trail maintenance, the average
annual maintenance cost for the 11.5 mile trail along the Ashokan
is estimated to be approximately $11,500 to $23,000 (approximately
$1000-2000
per mile per year, depending on whether the trail surface is
asphalt or non-asphalt.) These figures are
based on trail maintenance cost information from the
Rails-to-Trails Conservancy (please see Attachment
A) based on surveys of 200 existing rail trails in the Northern
US. These estimates are consistent with
actual costs incurred to maintain the local Marbletown O&W
Trail in Ulster County, which are
approximately $1,380 per mile per year (including some minor
capital expenses).
It is also likely that Ulster County will partner with private,
non-profit organizations to reduce the Countys costs and share of
maintenance further. The NY-NJ Trail Conference, whose volunteers
maintain more than
1000 miles of trails in two states, has sent a letter of
interest stating that their organization will recruit and
organize volunteers to do maintenance work (please see
Attachment B). Once the trail is constructed to
professional standards, maintenance will mostly be comprised of
mowing and trimming trail edges,
cleaning ditches and culverts, fixing potholes, removing debris
and litter, and making minor repairs to
fencing and kiosks, all of which can be done by volunteer
organizations (as is done by the Trail Conference
on other trails.) According to the Rails-to-Trails Conservancy,
it is common for trails owned by a
government entity to be maintained by volunteers, including
Scouts and community service groups.
Page 11 of 25
-
Responses to MOA Questions Submitted by
Railroad Advisory Committee Chairman David Donaldson
May 14, 2015
*Comment: The design of the trail, an operation and maintenance
(O&M) plan, and a joint security
agreement have not been negotiated.
A. Correct. The design of the trail has not yet begun and will
be commenced once DEP funding is approved, at which time a
community planning process will begin. The O&M plan and Joint
Security Agreement will be
negotiated and developed prior to the construction and opening
of the trail but cannot be finalized until the
trail design is determined with public input and approved by the
County and DEP (so that the specifics of
the trail, such as fencing, trail surface, drainage
improvements, etc. are fully detailed.)
Q: How does the MOA impact the Countys rail easement?
A: The MOA establishes a framework for the County to add a
conditional trail easement to its perpetual
railroad easement for the U&D along the Ashokan Reservoir.
The Countys railroad easement is fully preserved for the future,
and the MOA allows for trail use on the U&D corridor until such
time as the
County chooses to re-establish railroad operations, which it has
the right to do. However, the MOA does
not allow concurrent railroad operations and trail use along the
Ashokan Reservoir.
*Comment: The MOA does not actually say that concurrent rail and
trail operations are prohibited.
A. The MOA repeatedly references federal Railbanking and a
modified railroad easement to allow interim trail use with an
option to return rail service in the future. The MOA allows for
trail use to be added to the Countys perpetual rail easement until
such time as the County restores rail use. Implicit in the interim
trail use is the suspension of rail operations, although no
freight, passenger, or tourism railroad operations currently take
place on the Ashokan Reservoir section of the U&D corridor and
have not taken
place since 1976. While the County has the right in the future
to restore rail service, it does not have the
right under the current easement or the MOA to operate both rail
and trail concurrently.
Q: How does the MOA work?
A: The MOA initially provides the County a land-use permit
allowing the County to start planning, design and
permitting of the new trail and committing significant NYCDEP
funding support for trail development.
Prior to any trail construction, the County and City will
negotiate a modified railroad easement, subject to
Legislative approval, that adds trail use to the railroad
easement, as long as conditions in the MOA are met
and the County does not restore rail operations, which the
County retains the right to do. The modified
easement will replace the land-use permit and contain the
land-use permit conditions, including provisions
that protect the Reservoirs water quality. The County has the
choice to pursue federal Railbanking as well, but it is not
required for the MOA or the modified easement.
*Comment: Construction cannot start until modified rail easement
is negotiation. This agreement is highly
dependent on Railbanking the line via the STB. This has never
been accomplished for a line that has been
out Federal Jurisdiction for nearly 40 years. The Catskill
Mountain Railroad could easily obtain such due
to their position as a railroad. This is where working with CMRR
would greatly benefit the County.
A. Under the MOA, the County is not required to undertake
federal Railbanking in order to modify its perpetual rail easement
to allow for interim trail use. However, the MOA allows the County
the option for
Railbanking if it chooses to do so. Since DEP is the only
landowner on this segment of the U&D right-of-
way, the negotiated modified easement can and will fully protect
the Countys permanent rail easement
Page 12 of 25
-
Responses to MOA Questions Submitted by
Railroad Advisory Committee Chairman David Donaldson
May 14, 2015
while allowing for interim trail use (until rail operations are
restored), which is essentially what federal
Railbanking does. As the County is the owner of the U&D,
CMRR assistance is not required for either
Railbanking or modification of the easement, and CMRRs lease
ends in May 2016.
Q: What uses does the MOA allow and prohibit?
A: The MOA allows walking, bicycling, running, cross country
skiing, snowshoeing, and other non-motorized
uses, including walking dogs on leashes, without permit or fee
year-round. Special events, such as
fundraising walks and marathon races, are allowed if
mutually-approved by the County and NYCDEP.
Horses and motorized vehicles, other than motorized wheelchairs
and security and maintenance vehicles,
are prohibited. The MOA prohibits the use of impervious trail
surfaces, such as pavement, unless mutually-
agreed upon by the County and the NYCDEP.
*Comment: No asphalt means no long-distance bicycles, so no
reasons for bicyclers (sic) to come here from
Walkway Over the Hudson.
A. The MOA does not prohibit pervious asphalt so if the County
chooses to pave the trail using pervious asphalt, it may do so. In
addition, the use of other non-asphalt materials, such as compacted
crushed stone
or stone dust, will accommodate the overwhelming majority of
bicyclists, including those who would use the
Countys rail trail network to travel from the Walkway to the
Ashokan. Since the Wallkill Valley Rail Trail is on that route and
is also not paved, most of the cyclists who would come from the
Walkway would likely
use mountain bikes, hybrids, cross trail bikes and road bikes
with wider tires, which can easily ride a non-
paved trail. In fact, many people who tour use hybrids and cross
trail bicycles, and non-asphalt surfaces
when professionally installed will accommodate tires on
strollers and wheel chairs.
Q: Why is this MOA being brought to the Legislature now?
A: The County and NYCDEP negotiated the detailed terms of this
MOA between December 2013 and January
2014, at which time the MOA was submitted by NYCDEP for legal
review to the City of New York Law
Department. On April 20, 2015 the County was notified the legal
reviews were completed, and NYCDEP
provided a notice of contract award for signature. The MOA is
consistent with standing Ulster County
policy under Resolution No. 275 (Passed August 2014), and both
parties negotiated in good faith towards
this final MOA with the understanding of this Legislative
policy. The MOA contains all the major
provisions in announced in December 2013 as part of an Agreement
in Principle.
*Comment: If the Agreement has been around so long, why does the
Legislature have less than 2 weeks to
review and comment on it?
A. The MOA was finalized on April 20, 2015, and the Legislature
received a copy the following week. Prior to April 20, the MOA
required approval by the City Law Department and could have been
amended or
withdrawn. The terms of the MOA are consistent with the
Agreement in Principle publicly discussed since
December 2013 and comply with the existing Ulster County policy
under Resolution No. 275 passed in
August 2014. It is also important to note that the Legislature
regularly approves contracts for revenues and
services that are submitted by the prior months resolution
deadline, as this contract was.
Page 13 of 25
-
Responses to MOA Questions Submitted by
Railroad Advisory Committee Chairman David Donaldson
May 14, 2015
Q: What are the risks of delaying signing of the MOA?
A: The financial and other benefits afforded by the MOA and the
ability to develop a public recreational trail
along the Ashokan Reservoir are not secured until the MOU is
signed. The risks of delaying execution of
the MOU include the following:
The $2.5 Million in direct NYCDEP grant funding is in the Citys
operational budget and could be withdrawn at any time without a
signed MOA. As the County has seen with other public project
funding, these funds could be reprogrammed for other needs that
arise at the NYCDEP or in the City
budget absent a signed agreement.
The County was awarded $2 million in New York State
Environmental Protection Fund (EFP) grants for the rail trail in
2013 and has not been able to draw down these funds. The MOA will
allow the County
to move forward in utilizing these funds for the rail trail so
that they are not reprogrammed or reduced in
future State budgets.
The County was awarded $330,000 in 2014 New York State
Department of Environmental Conservation (DEC) Water Quality grants
for restoration of Butternut Creek Culvert on the U&D in this
section. This
funding is likely to expire if the County cannot advance the MOA
and begin planning and design on the
culvert replacement.
Without a signed MOA, the County cannot secure additional
funding commitments from major private donors, some of which have
already committed funding to the project.
NYCDEP is currently planning bridge improvements and
replacements for the Ashokan Dividing Weir and the Five Arch
Bridge, and the executed MOA will guarantee improved pedestrian and
bicycle
accommodations on these new structures that enhance community
connectivity.
Delays in approving MOA undermine the Countys ability to
negotiate future agreements with the City of New York and
NYCDEP.
Planning needs to begin this summer if the trail is to be
constructed in a reasonable time frame following the May 31, 2016
expiration of the Catskill Mountain Railroad lease.
*Comment: The $2.5 million was promised in December 2013. There
is no reason another few months need
prevent this money from being funded.
A. There is no guarantee that the funding remains available
without a signed agreement. As with other public infrastructure
funding, final funding is not guaranteed without execution of the
revenue contract. The DEP
funding is available in the current City of New York fiscal
year, which ends June 30, 2015. The only way to
guarantee the funding is to execute the agreement so the funds
are obligated in this years DEP budget.
*Comment: The $2 million in State funding has not been provided
because the County Executive has never
consented to the public planning process required for the use of
the funds.
A. Incorrect. The execution of the MOA with DEP is the first of
a number of steps in moving forward with the public planning
process and design for the rail trail, and the $2 million that was
awarded to the County in
2013 will be utilized for the rail trail following execution of
the MOA and creation of the capital project for
the rail trail along the Ashokan Reservoir. At the Countys
request, the MOA with DEP intentionally did not detail the trail
design, including trailhead locations, so that the public and local
communities could be
part of the planning process for the trail.
Page 14 of 25
-
Responses to MOA Questions Submitted by
Railroad Advisory Committee Chairman David Donaldson
May 14, 2015
*Comment: The Butternut Creek Culvert project can commence at
any time and does not require the MOA.
A. The Butternut Creek Culvert project requires the complete
replacement of a major concrete arch culvert that supports the
railroad embankment along the Ashokan Reservoir, which is badly
damaged and causing
ongoing erosion of the Countys right-of-way. It will save the
County hundreds of thousands of dollars in site access costs to
rebuild this Culvert during trail construction, which does require
the MOA. Without the
MOA and trail construction, the County would be forced to build
a temporary access road for heavy
machinery which would add significant costs to the project.
*Comment: If it was true that the County cannot secure
additional funding commitments from major private
donors, some of which have already committed funding to the
project, why have they already committed
money to the project?
A. Private organizations contributed funding for survey and
mapping of the Ashokan Reservoir segment of the U&D and an
analysis of existing conditions, such as locations of culverts. The
organizations, which include
the Open Space Institute, The Dyson Foundation, and the
Woodstock Land Conservancy, are committed to
the rail trail project but cannot raise additional funds from
their donors without a commitment from the
County to move forward with the trail project. Without the MOA,
there is no ability for the County to move
forward with trail development along the Ashokan and therefore,
no project for which to raise private funds.
*Comment: Without consensus with the Legislature, no future
agreements should be negotiated with DEP.
A. Agreements between the County and other municipal entities
require Legislative approval by a majority of the members. All
future agreements with DEP, including the Joint Security Agreement
and Modified
Easement, will require approval of a majority of the
Legislature.
Q: What about the Catskill Mountain Railroads plan to extend its
rail operations to the Glenford Dike on the Ashokan Reservoir?
A: Firstly, under the County Legislatures Resolution No. 275,
the segment of the U&D corridor along the Ashokan Reservoir is
slated for redevelopment as trail only. Secondly, the NYCDEP has
clearly stated its
long-term position that rail with trail along its Reservoir
property will not be allowed, and it now supports development of
trail only as the best course for protecting its drinking water
supply and
expanding recreational opportunities. Thirdly, the Catskill
Mountain Railroad has not operated passenger,
freight or tourism trains on the Ashokan Reservoir section since
the beginning of its 25-year lease in 1991
or during the shorter term leases which started in 1983. The
last trains, other than work vehicles, that
operated on this segment were in 1976. Finally, this 11.5 mile
section of rail corridor does not meet even
minimum federal railroad standards (Class 1) for freight,
passenger or tourism train operations, which is
documented in the 2014 HDR Track Inspection Report.
*Comment: There is no reason that rail operations cannot be
extended to this section of the easement, which
was formerly a railroad station with multiple tracks, and only
constitutes 10% of the easement. The DEP
has never said that it will not permit any rail use- it has only
stated that that (sic) is the Countys policy through resolution
275. At present, they cannot deny rail use.
A. The MOA is predicated on the conversion of the existing rail
corridor, which is overwhelmingly single track only along the
Ashokan Reservoir, into trail only, which is the Ulster County
policy codified in Resolution
Page 15 of 25
-
Responses to MOA Questions Submitted by
Railroad Advisory Committee Chairman David Donaldson
May 14, 2015
No. 275. The DEP has been clear that based on water quality
concerns, it will not allow the construction of
trail alongside rail along its reservoir, and DEP financial and
other support is based on trail use only. It is
also important to note that no passenger, freight or tourism
trains have run on this section of track, or in the
section approaching the track between Hurley Mountain Road and
Basin Road, in nearly 40 years. It would
take many years for CMRR to rehabilitate the track to the
Ashokan Reservoir based on its rate of
rehabilitation over the past years.
Q: Some have said that the County Legislatures recent passage of
Resolution No. 155 rescinded the prior policy under Resolution No.
275. Is that assessment correct?
A: No. Resolution No. 155 (April 2015) created a new Ulster
& Delaware Corridor Advisory Committee
to examine information on the U&D and assess whether changes
to established County policy might be
warranted. Resolution No. 155 did not rescind or modify the
existing policy, and according to one of
the sponsors, it was not intended to reopen the issue of the
U&D corridor along the Reservoir. Rather, it
was to focus on a possible compromise for modifying Resolution
275 to allow railroad operations in the
U&D section in and near the City of Kingston where theme
trains operated in the past year.
*Comment: Resolution 155 was not limited in any way to exclude
the Ashokan easement area or any other
part of the Corridor.
A. Resolution 155 did not rescind or amend Resolution 275, which
is consistent with the MOA and remains Ulster County policy.
Q: Could NYCDEP unilaterally close the trail so that there is
neither railroad nor trail use?
A: NYCDEP is allowed to close the trail temporarily in the event
of serious threats to its drinking water
supply or public safety. However, such closures are temporary
and only for the time necessary to protect public health and
safety. The County has the right to re-establish railroad uses if
it chooses.
*Comment: The agreement can be cancelled by the DEP on 120 days
notice. Re-establishing the railroad will be highly difficult if
the rails have been removed and will likely be fought by the
DEP.
A. The agreement can be terminated by either party with 120 days
notice. Re-establishing the railroad in this section now would
currently be highly difficult and require significant investment to
improve the
deteriorated ties and railbed from Hurley Mountain Road to the
Reservoir and to the Glenford Dike to FRA
Class I standards, which is the minimum standard for any train
operations.
Q: Who is going to maintain the trail and how much will it
cost?
A: The County is responsible for maintenance, but it is allowed
to contract with third parties for maintenance
of the trail with the consent of NYCDEP. Private trail
organizations have expressed interest maintaining
the trail, and a recent letter from the New York- New Jersey
Trail Conference, which maintains nearly
1000 miles of trail in the two states it operates, has offered
to recruit volunteers to help with trail
maintenance. The maintenance costs could be fully covered or
significantly reduced by private trail
organizations as additional organizations step forward.
Page 16 of 25
-
Responses to MOA Questions Submitted by
Railroad Advisory Committee Chairman David Donaldson
May 14, 2015
*Comment: The costs of maintaining the trail should be estimated
in hard numbers, not counting on
volunteers who have not even been recruited or organized.
A. Based on the Rails-to-Trails survey attached as Appendix A,
the estimate for maintenance without volunteer labor and donations
would be in the range of $11,500 to $23,000 per year for this 11.5
mile
section of track. Based on the probable use of non-asphalt
materials and the actual costs of similar trails
in Ulster County, the estimate would likely be at the lower end
of this range.
Q: Is the approval of the MOA with NYCDEP the last step before
building a trail?
A: No. The resolution to execute the MOA with NYCDEP is only the
first step in a longer process. There
will be multiple future resolutions that require approval by the
Ulster County Legislature, including
resolutions establishing a capital project for planning,
accepting NYCDEP grant funding once the contract
is processed and registered with the City of New York
Comptroller, approving receipt of other pending
rail trail grants, adopting additional intergovernmental
agreements with NYCDEP (such as the Joint
Security Agreement), and authorizing the removal of rails prior
to construction (as required in Resolution
No. 275.)
Approving the MOA simply allows the City of New York to award
funding to Ulster County and allows
the County to begin a public trail planning and design process,
with repeated opportunities for community
and Legislative input on the project, including, but not limited
to, the design of the trail, locations of
trailheads and selection of amenities related to the trail, such
as signage and benches.
*Comment: The report from the committee created in Resolution
155 is necessary to be incorporated into
this agreement so that it is in the best long term interest of
the citizens of Ulster County, not any particularly
politicians short-term interests. This vote should be delayed
until the committees work is complete. The easement has been here
for 100 years. Another 6 months will only improve the final
outcome.
A. Resolution 155 did not suspend or amend current Ulster County
policy for trail only along the Ashokan Reservoir. It did not
specifically include the Ashokan Reservoir section or instruct
County departments to
suspend implementation of Resolution 275 until the report is
completed. There is no requirement to delay
project implementation until the Committees work is complete,
and there is no guarantee that a six-month delay would not
jeopardize available funding through DEP and other sources.
*Comment: The resolution also states that changes can be made to
the agreement by the County Executive
without Legislative approval. Regardless of who the County
Executive is, how dangerous is that?
A. Resolution 187 uses standard language that is contained in
numerous contracts approved by the Ulster County Legislature. In
addition, the Chairman of the Legislature has been added as a
signatory to the MOA
so any amendments would require his signature as well. This
resolution passed the Legislature unanimously
without any questions about amendments/modifications that would
be approved by the County Attorney,
which is regularly included in contract resolutions.
Page 17 of 25
-
Responses to MOA Questions Submitted by
Legislator Manna Jo Greene
May 14, 2015
NOTE: Questions/ comments are in black.
Responses are italicized and in red.
1) SEQRA: Resolution 187 state in its final Whereas: WHEREAS,
based upon the examination of the Ulster County Legislature, and
pursuant to the County of Ulsters State Environmental Quality
Review Act (SEQRA) Type II List that was adopted by the County in
Resolution No.
118 on April 20, 2010, and as per Section 4.2.5 of that list, it
has been determined the proposed
agreement provides that an approved design, including necessary
permits and environmental
findings be in place prior to construction and as such it does
not pose a significant
environmental impact and therefore has been determined to be a
Type II Action pursuant
to 6NYCRR, Part 617, of SEQRA, and does not require any
determination or procedure
under SEQRA; Resolution 187 states that the proposed Memorandum
of Agreement (MOA), which will essentially convert the last
remaining passenger and tourism railroad in
Ulster County to recreation trail for the Ashokan section of the
Ulster & Delaware Rail Corridor,
is exempt under SEQRA as a Type II Action. The MOA itself
indicates that SEQRA will be
undertaken by the County, in coordination with the City of New
York to design and construct the
Ashokan Rail Trail. It seems to me that SEQRA should be done on
the MOA itself, since this is a
major decision for Ulster County elected officials to consider.
At the very least a full and open
public process, with a formal public hearing, should be afforded
to this important decision. The
MOA cites Resolution 275 as the justification for proceeding
with this agreement, however,
following a very successful year of special railroad events
offered by the Catskill Mountain
Railroad, the County Executive and staff in the Executive branch
have acknowledged that
Resolution 275 will need to be modified to keep the section from
Kingston Plaza to Hurley
Mountain Road operating as a railroad, and have asked the
Legislature to consider this
modification. The best way to do this is in the context of
well-conceived overall plan for the
Ulster County stretch of this rail corridor, not piecemeal. The
recently formed Ulster & Delaware
Corridor Advisory Committee was created to gather all available
information, process it, seek
consultants assistance as needed, and make recommendations to
the Legislature in this regard. Asking the Legislature to authorize
the MOA between the County and NYC DEP prior to
allowing the U&D Corridor Advisory Committee to do the work
it was created to engage in is
premature and preemptive, and would severely limit the options
the Committee can consider for
this valuable and historic resource.
As I understand it, 6NYCRR 617.4, indicates that the proposed
MOA is a TYPE I (Non-Exempt)
action because the proposed action includes land that exceeds 10
acres in area: See
www.dec.ny.gov/regs/4490.html#18106 (b) The following actions
are Type I if they are to be
directly undertaken, funded or approved by an agency:
(6) activities, other than the construction of residential
facilities, that meet or exceed any of the
following thresholds: (i) a project or action that involves the
physical alteration of 10 acres;
The proposed trail will be at least 14 feet wide (not counting
trailheads, parking, etc.) for 11.5
miles, which covers 850,080 square feet or 19.51 acres. This
project is clearly more than 10 acres
and would therefore subject to SEQRA. In addition there are
historic designations and other
reason to consider this action Type 1 and to perform an
environmental review on the
Memorandum itself.
Page 18 of 25
-
Responses to MOA Questions Submitted by
Legislator Manna Jo Greene
May 14, 2015
Question: Please clarify:
Can the County act on Resolution 187 or sign the MOA without
first going through a
Type I SEQRA review?
Yes. The action is Type II under SEQR. Please see the memo from
Planning Director Dennis
Doyle in Appendix C.
Will the action or contract be subject to reversal in an Article
78 proceeding?
The County Attorney sees no basis for reversal in an Article 78
proceeding.
Will this incur more litigation, instead of cooperation?
The County Attorney sees no basis for litigation.
2) Trailheads (Section 1C): If, as proposed, trailheads are
entirely designed, built and
maintained by the NYC DEP, the DEP will be able to control and
limit access. For example, if
there are only a few parking spaces at the trailhead, trail use
will be limited to a small group of
people. The County should have a say in the design of trailheads
and should share access
management with the DEP, including ensuring access to people
with disabilities to the most
scenic areas, such as the Glenford Dike.
As per Section 1, Paragraph C, the trailhead locations, design
and parking capacity will be
determined through a community planning process with input from
the local municipalities, area
residents, and nearby businesses. The MOA purposely left the
trailhead locations and other
trailhead details to be determined during the planning process
so that public input could be
obtained on preferred locations, number of parking spaces,
needed support facilities (such as
sanitary facilities),and signage/ information kiosks.
3) Shared Use Lane (Section 1D): The City of New York does not
commit to building a shared-
use bicycle/pedestrian lane on the dividing weir. The MOA only
says that they will consider it.
Section 1 (D) states, The City.shall accommodate bicycle and
pedestrian traffic (on the Dividing Weir and Five Arch bridges)
including consideration of a dedicated shared-use lane. This allows
the flexibility to construct a separate dedicated lane or
alternatively, widened
shoulders on both sides of the bridge, depending on which is
better for connectivity for bicyclists
and pedestrians.
4) Railbanking (Section 3): Railbanking is preserving railroad
rights-of-way for possible future use. Railbanking leaves the
tracks, bridges, and other infrastructure intact, relieving the
railroad
operating company from responsibility of maintenance and
taxation. Often the tracks are put in
custody of a state transportation agency, who then seeks a new
operator for possible rehab or
reactivation. This helps ensure the possibility of future
restored rail service when new economic
conditions may warrant resuming operation.1 As I understand it,
railbanking instead of total abandonment of a railroad requires
federal jurisdiction, and this only applies to freight, should
Page 19 of 25
-
Responses to MOA Questions Submitted by
Legislator Manna Jo Greene
May 14, 2015
the County decide to utilize the railroad for this purpose in
the future. In this case, the MOA
should allow Ulster County to expand to passenger use for the
Ashokan section of the rail
corridor, should future interest and resources become available
for a full rail with trail. NYC
DEP should agree to this combined use and with widespread County
support, might be convinced to. Far better than railbanking is not
to abandon this section of rail in the first place.
http://en.wikipedia.org/wiki/Rail_trail When the U & D
Railroad was moved to allow the
construction of the Ashokan Reservoir in 1911, it was imbued
with a wide range of powers,
rights and privileges, including a clearly defined right-of-way.
[Note: The U&D Corridor
Advisory Committee should get a copy of the original contract
between NYC DEP and U &D as
part of the library of documents we are compiling.] Do we want
to give up the rights established
in the Ashokan Railroad Easement in favor of the less secure,
more tenuous and less certain,
modified version that is proposed by Resolution 187.
I would like to hear an explanation of Railbanking from the
Catskill Mountain Railroad
(CMRR), since I believe they have extensive knowledge and
understanding about this process.
Here is what
www.railstotrails.org/build-trails/trail-building-toolbox/railbanking/
says.
Railbanking, as defined by the National Trails System Act, 16
USC 1247 (d), is a voluntary agreement between a railroad company
and a trail agency to use an out-of-service rail corridor as
a trail until a railroad might need the corridor again for rail
service. Because a railbanked
corridor is not considered abandoned, it can be sold, leased or
donated to a trail manager without
reverting to adjacent landowners.
Railbanking takes place during the rail corridor abandonment
process. Official negotiations with the railroad begin after the
railroad submits an initial notification to abandon the line to
the
Surface Transportation Board (STB). Negotiations end with either
railbanking or line
abandonment. Are we really ready to abandon/railbank, rather
than repair, our last remaining passenger/tourism
railroad? CMRR estimates that they can repair the railroad ties
for about $10,000 per mile, with
volunteer labor, using used tracks that are still in good
condition, or $60,000 using new ones.
There is no eminent domain for trails that I know of. It seems
to me, therefore, that, if the
existing rail corridor agreement is to be modified, it is
critical that the rails are kept in place
throughout the reservoir easement. Without them, the County
could lose full access to the
easement, if the MOA were to be cancelled by the NYC DEP at some
time in the future.
Question: If the proposed trail is built and puts an end to the
Railroad, do we know that
property owners who have land outside of DEP-controlled portions
of the Corridor will
willingly allow the trail to be built and used?
The Countys perpetual railroad easement is protected in the MOA.
Property owners who have land outside the DEP-owned segments of the
corridor will be included in the public planning
process but have no legal standing with regard to the trail
across DEP Watershed lands, which
is the subject of the MOA.
Also the term environmentally sensitive needs to be defined.
The trail will be developed in compliance with the New York City
Watershed Rules and
Regulations, which set high environmental standards for many
types of development and which
Page 20 of 25
-
Responses to MOA Questions Submitted by
Legislator Manna Jo Greene
May 14, 2015
preclude use of impervious materials. The County will also
undertake environmental reviews to
ensure that the trail is protective of endangered species,
wetland areas, and water quality.
6) Termination (Section 4C): The Memorandum of Agreement can be
cancelled by either party
with 120 days written notice. If the rails have been removed,
the County could lose complete
access, either by rail or trail. Because of this possibility,
the rails should remain in place, even if
the Ashokan Rail Trail proposal is adopted. The trail can be
constructed in-between or on top of
the rails in constrained areas.
The removal of the rails in no way extinguishes or modifies the
Countys perpetual railroad easement. In Section 3, Paragraph E, the
MOA states, This agreement does not modify or extinguish in any
manner whatsoever the Ashokan Railroad Easement as described in the
Book
of Deeds at Liber 443, Page 58 as filed in the Office of the
Ulster County Clerk. A trail constructed in between the rails would
not meet modern multi-use trail standards and
constructing a trail on top of the rails is not practical or
advisable based on consultations with
trail designers and engineers.
7) Costs: The Legislature is being asked to authorize an MOA for
the construction of the
Ashokan Rail Trail, while the costs of maintaining, insuring and
providing security for the trail,
as well as its ultimate construction cost, are still unknown.
These costs would mostly be paid for
by the County, not the DEP. Understanding the costs and benefits
of all alternatives is the main
purpose of the U&D Corridor Advisory Committee.
Question: What percent of total design, build and maintenance
costs do the grants totaling
$2.5 million represent? Where will the rest come from?
The County estimates design and future construction of the trail
along the Ashokan will be
covered by the $4.5 million in available funding from DEP and
through the 2013 NYS EPF
award ($2 million). The only costs not covered by this funding
are for the reconstruction of the
Butternut Creek Culvert, for which the County has received a NYS
DEC Water Quality grant and
has additional grant requests pending.
8) Amendments: Resolution 187 allows for all future amendments
to be made by the County
Executive without the consent of the Legislature. The words and
any amendments thereto should be deleted from the last paragraph.
It is very important to be sure the Legislature approves
any and all future changes to this agreement, if indeed an
acceptable agreement can be crafted.
This version has a long way to go.
Resolution 187 and the MOA have been revised to include the
signature of the Chairman of the
Ulster County Legislature.
General Concern: I believe that bringing forward the MOA at this
time preempts the work of Ulster & Delaware
Corridor Advisory Committee, who have agreed to take a fair,
open and comprehensive look at
Page 21 of 25
-
Responses to MOA Questions Submitted by
Legislator Manna Jo Greene
May 14, 2015
the Corridor and all information related to its future use, and
to make recommendations that will
most benefit the County, its residents, businesses and
visitors.
Resolution 155 did not suspend or amend current Ulster County
policy for trail only along the
Ashokan Reservoir. It did not specifically include the Ashokan
Reservoir section or instruct
County departments to suspend implementation of Resolution 275
until the report is completed.
There is no requirement to delay project implementation until
the Committees work is complete, and there is no guarantee that a
six-month delay would not jeopardize available funding through
DEP and other sources.
Page 22 of 25
-
APPENDIX A
Page 23 of 25
-
APPENDIX B
Page 24 of 25
-
APPENDIX C
Page 25 of 25