Directorate General of Civil Aviation, Indonesia Publication Date : 09 FEB 12 Effective Date : 05 APR 12 Web : http://hubud.dephub.go.id/?id+page+detail+41 IMPLEMENTATION OF THE NEW RAPID EXIT TAXIWAY, RE‐DESIGNATION OF THE TAXIWAY N3 TO N7, AND REVISION OF RELATED TAXI ROUTE PROCEDURES AT SOEKARNO HATTA INTERNATIONAL AIRPORT 1. INTRODUCTION 1.1 In order to enhance the airport service bu expediting the taxi out of the runway, The Soekarno Hatta International Airport has built the new Rapid Exit Taxiway that located between the existing taxiway N2 and N3 which namely N3, width 26 m and strength 56 RAWT. 1.2 The addition of Rapid Exit Taxiway causing changes on taxi routing procedure the numbering of taxiway as follows : ‐ N1 not changed; ‐ N2 not changed; ‐ The new N3 (between existing N2 and N3 that exist) ; ‐ N3 will be N4; ‐ N4 will be N5; ‐ N5 will be N6; ‐ N6 will be N7; REPUBLIC OF INDONESIA DIRECTORATE GENERAL OF CIVIL AVIATION DIRECTORATE OF AIR NAVIGATION SUB DIRECTORATE MANAGEMENT OF AERONAUTICAL INFORMATION Jl. Medan Merdeka Barat No. 8 Gedung Karya Lt. 7 Jakarta 10110 or P.O.Box 3109/JKT, Jakarta 10000 Email :[email protected], ais_ [email protected]AIRAC AIP SUPPLEMENT Phone/ Fax : 62 21 3507603 Telegraphic Address AFS : WRRRYNYX Nr : 02 / 12 09 FEB 12
13
Embed
REPUBLIC OF INDONESIA - Perhubungan Udara SUPP 02 Tahun...PROCEDURES AT SOEKARNO HATTA INTERNATIONAL AIRPORT 1. INTRODUCTION 1.1 In order to enhance the airport service bu expediting
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Directorate General of Civil Aviation, Indonesia Publication Date : 09 FEB 12 Effective Date : 05 APR 12
Web : http://hubud.dephub.go.id/?id+page+detail+41
IMPLEMENTATION OF THE NEW RAPID EXIT TAXIWAY, RE‐DESIGNATION OF
THE TAXIWAY N3 TO N7, AND REVISION OF RELATED TAXI ROUTE PROCEDURES AT SOEKARNO HATTA INTERNATIONAL AIRPORT
1. INTRODUCTION
1.1 In order to enhance the airport service bu expediting the taxi out of the runway, The Soekarno Hatta International Airport has built the new Rapid Exit Taxiway that located between the existing taxiway N2 and N3 which namely N3, width 26 m and strength 56 RAWT.
1.2 The addition of Rapid Exit Taxiway causing changes on taxi routing procedure the numbering of taxiway as follows :
‐ N1 not changed;
‐ N2 not changed;
‐ The new N3 (between existing N2 and N3 that exist) ;
‐ N3 will be N4;
‐ N4 will be N5;
‐ N5 will be N6;
‐ N6 will be N7;
REPUBLIC OF INDONESIA DIRECTORATE GENERAL OF CIVIL AVIATION
DIRECTORATE OF AIR NAVIGATION SUB DIRECTORATE MANAGEMENT OF
AERONAUTICAL INFORMATION Jl. Medan Merdeka Barat No. 8 Gedung Karya Lt. 7
Directorate General of Civil Aviation, Indonesia Publication Date : 09 FEB 12 Effective Date : 05 APR 12
1.3 The changes published on this AIP Supplement will revise the data on AIP Indonesia Volume II page WIII on pages as follows :
WIII AD 2‐3, WIII AD 2.24 ‐1A, WIII AD 2.24 ‐1B, WIII AD 2.24 ‐2A, WIII AD 2.24 ‐2B, WIII AD 2.24 ‐2C, WIII AD 2.24 ‐2D, WIII AD 2.24 ‐2E, WIII AD 2.24 ‐2F, WIII AD 2.24 ‐2G, WIII AD 2.24 ‐24H, and WIII AD 2.24‐3.
2. PROCEDURE
2.1 Taxiing route procedures described on paragraph above will changed as depicted on attachments as follows:
‐ Attachment ‘A’ for Taxiing Route‐Take Off RWY 07R;
‐ Attachment ‘B’ for Taxiing Route‐Take Off RWY 07L;
‐ Attachment ‘C’ for Taxiing Route‐Take Off RWY 25R;
‐ Attachment ‘D’ for Taxiing Route‐Take Off RWY 25L;
‐ Attachment ‘E’ for Taxiing Route‐Landing RWY 07R;
‐ Attachment ‘F’ for Taxiing Route‐Landing RWY 07L;
‐ Attachment ‘G’ for Taxiing Route‐Landing RWY 25R; and
‐ Attachment ‘H’ for Taxiing Route‐Landing RWY 25L;
2.2 New Rapid Exit Taxiway and Taxi Guidance Sign layout changes are also shown on attachments as follows :
‐ Attachment ‘I’ for Aerodrome Chart;
‐ Attachment ‘J’ for Taxi Guidance Sign Chart.
AIRAC AIP SUPPLEMENT 02 / 12 Page 3 of 3
Directorate General of Civil Aviation, Indonesia Publication Date : 09 FEB 12 Effective Date : 05 APR 12
3. IMPLEMENTATION
The operation of the new Rapid Exit Taxiway, Re‐Designation of the Taxiway N3 to N7, and Revision of Related Taxi Route Procedures at Soekarno Hatta International Airport will be effective on 05 April 2012 at 00.01 UTC.
4. ANY CHANGES TO THE CONTENT OF THIS AIRAC AIP SUPPLEMENT WILL BE NOTIFIED BY NOTAM OR SUPERSEDED BY OTHER AIP SUPPLEMENT.