Table of Contents 1. EXECUTIVE SUMMARY..................................4 2. INTRODUCTION TO PROJECT............................5 2.1 Introduction to TTS panel line:..................5 2.2 Processes done for plates at TTS panel line:....15 2.3 Schedule of the project work:...................29 3. LITERATURE REVIEW AND STUDY OF INDUSTRY...........30 3.1 Introduction to Costing.........................30 3.2 Introduction to Shipping Industry...............33 3.2.1....................History of shipping industry 33 3.2.2...................Industrial shipping Carriers: 33 3.3 Introduction to PSL.............................36 3.3.1...................................Stake Holders 37 3.3.2...........Association With World Leading Groups 37 3.3.3...............................Business strategy 39 1
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
In oxy-fuel cutting, a cutting torch is used to heat metal to kindling
temperature
18
A stream of oxygen is then trained on the metal and metal burns in that
oxygen and then flows out of the cut (kerf) as an oxide slag.
The oxygen flow rate is critical — too little will make a slow ragged cut; too
much will waste oxygen and produce a wide concave cut. Oxygen Lances
and other custom made torches do not have a separate pressure control for the
cutting oxygen, so the cutting oxygen pressure must be controlled using the
oxygen regulator. The oxygen cutting pressure should match the cutting tip
oxygen orifice. Consult the tip manufacturer's equipment data for the proper
cutting oxygen pressures for the specific cutting tip.
The oxidation of iron by this method is highly exothermic. Once started, steel
can be cut at a surprising rate, far faster than if it was merely melted through.
At this point, the pre-heat jets are there purely for assistance. The rise in
temperature will be obvious by the intense glare from the ejected material,
even through proper goggles. (A thermal lance is a tool which also uses rapid
oxidation of iron to cut through almost any material.)
Since the melted metal flows out of the work piece, there must be room on
the opposite side of the work piece for the spray to exit. When possible,
pieces of metal are cut on a grate that lets the melted metal fall freely to the
ground. The same equipment can be used for oxyacetylene blowtorches and
welding torches, by exchanging the part of the torch in front of the torch.
19
II. Plasma Cutting:
Plasma cutting is a process that is used to cut steel and other metals of
different thicknesses (or sometimes other materials) using a plasma torch.
In this process, an inert gas (in some units, compressed air) is blown at high
speed out of a nozzle; at the same time an electrical arc is formed through
that gas from the nozzle to the surface being cut, turning some of that gas to
plasma.
The plasma is sufficiently hot to melt the metal being cut and moves
sufficiently fast to blow molten metal away from the cut.
First, a high-voltage, low current circuit is used to initialize a very small
high-intensity spark within the torch body, thereby generating a small pocket
of plasma gas.
Plasma is an effective means of cutting thin and thick materials alike.
Hand-held torches can usually cut up to 2 inches (51 mm) thick steel plate,
and stronger computer-controlled torches can cut steel up to 6 inches
(150 mm) thick.
Since plasma cutters produce a very hot and very localized "cone" to cut
with, they are extremely useful for cutting sheet metal in curved or angled
shapes.
Plasma torches were once quite expensive.
7.
Bending:
20
It the process of changing the shape of the plate by applying pressure.
Bending of plate can be done by two methods, cold working and hot working.
Name of bending equipments and its type
Plate straightening m/c - Himalaya
Hydraulic press 1600t – VP 16 Himalaya
Hydraulic press 800t – VP 08 Himalaya
Hydraulic press 300t – RF03 Himalaya
Frame and face bending m/c 500-SBK 500Nieland
I. Cold Bending:
High amount of pressure applied with the help of hydraulic press on the plate
which results required change in shape.
With the help of wooden template, Accuracy of curve can be maintained.
According to thickness of the plate, required pressure also changes.
This process done at room temperature.
It doesn’t require any amount of heat but it can’t be done without high
pressure.
II. Hot Bending:
Heat is given to the plate till it reaches to the recrystallization temperature.
With the help of very little amount of pressure at recrystallization
temperature, shape of plate can be changed according to specification.
There is no need of hydraulic or pneumatic press. Plate shape can be changed
with the help of Mechanical press also.
21
8. Line Heating:
Some critical curves cannot be produced by bending.
When the heat is applied on the metal plate, gradually structure of the
molecules changes.
When new structured formed because of heat and if it does not cool down
immediately then it may gets its original shape so heating time and cooling
time of plate is the critical parameters for curvature plates.
9. Welding:
With help of melting of parent metal and filler metal, two parts can be weld.
Some welding process there is need of pressure to complete the weld.
I. Arc Welding
Arc welding is a type of welding that uses a welding power supply to create
an electric arc between an electrode and the base material to melt the metals
at the welding point.
They can use either direct (DC) or alternating (AC) current, and consumable
or non-consumable electrodes.
The welding region is sometimes protected by some type of inert or semi-
inert gas, known as a shielding gas, and/or an evaporating filler material.
The process of arc welding is widely used because of its low capital and
running costs.
Getting the arc started is called striking the arc. An arc may be struck by
either lightly tapping the electrode against the metal or scratching the
electrode against the metal at high speed.
22
I. Metal Active Gas Welding
23
Gas metal arc welding (GMAW), sometimes referred to by its subtypes
metal inert gas (MIG) welding or metal active gas (MAG) welding, is a
semi-automatic or automatic arc welding process in which a continuous
and consumable wire electrode and a shielding gas are fed through a
welding gun.
A constant voltage, direct current power source is most commonly used
with GMAW, but constant current systems, as well as alternating current,
can be used. There are four primary methods of metal transfer in GMAW,
called globular, short-circuiting, spray, and pulsed-spray, each of which
has distinct properties and corresponding advantages and limitations.
The contact tip, normally made of copper and sometimes chemically
treated to reduce spatter, is connected to the welding power source
through the power cable and transmits the electrical energy to the
electrode while directing it to the weld area.
Larger nozzles provide greater shielding gas flow, which is useful for high
current welding operations, in which the size of the molten weld pool is
increased.
A shorter arc length will cause a much greater heat input, which will make
the wire electrode melt more quickly and thereby restore the original arc
length.
Alternating current is rarely used with GMAW; instead, direct current is
employed and the electrode is generally positively charged. Since the
anode tends to have a greater heat concentration, this results in faster
melting of the feed wire, which increases weld penetration and welding
speed.
The polarity can be reversed only when special emissive-coated electrode
wires are used, but since these are not popular, a negatively charged
electrode is rarely employed.
24
Shielding gases are necessary for gas metal arc welding to protect the
welding area from atmospheric gases such as nitrogen and oxygen, which
can cause fusion defects, porosity, and they come in contact with the
electrode, the arc, or the welding metal.
Pure inert gases such as argon and helium are only used for nonferrous
welding; with steel they do not provide adequate weld penetration (argon)
or cause an erratic arc and encourage spatter (with helium).
Pure carbon dioxide, on the other hand, allows for deep penetration welds
but encourages oxide formation, which adversely affect the mechanical
properties of the weld.
Its low cost makes it an attractive choice, but because of the reactivity of
the arc plasma, spatter is unavoidable and welding thin materials is
difficult.
Adding to its economic advantage was its high deposition rate, allowing
welding speeds of up to 110 mm/s (250 in/min).
As the weld is made, a ball of molten metal from the electrode tends to
build up on the end of the electrode, often in irregular shapes with a larger
diameter than the electrode itself.
When the droplet finally detaches either by gravity or short circuiting, it
falls to the workpiece, leaving an uneven surface and often causing
spatter.
As a result of the large molten droplet, the process is generally limited to
flat and horizontal welding positions.
The high amount of heat generated also is a downside, because it forces
the welder to use a larger electrode wire, increases the size of the weld
pool, and causes greater residual stresses and distortion in the weld area.
25
II. Sub Merged Arc Welding
In
SMAW, the molten weld and the arc zone are protected from atmospheric
contamination by being “submerged” under a blanket of granular fusible
flux.
When molten, the flux becomes conductive, and provides a current path
between the electrode and the work. This thick layer of flux completely
covers the molten metal thus preventing spatter and sparks as well as
suppressing the intense ultraviolet radiation and fumes that are a part of
the shielded metal arc welding (SMAW) process.
The process is normally limited to the flat or horizontal-fillet welding
positions (although horizontal groove position welds have been done with
a special arrangement to support the flux).
Single or multiple (2 to 5) electrode wire variations of the process exist.
SAW strip-cladding utilizes a flat strip electrode (e.g. 60 mm wide x
0.5 mm thick). DC or AC power can be used, and combinations of DC
and AC are common on multiple electrode systems. Constant voltage
welding power supplies are most commonly used; however, constant
current systems in combination with a voltage sensing wire-feeder are
available.
High deposition rates (over 100 lb/h (45 kg/h) have been reported). High
operating factors in mechanized applications. Deep weld penetration.
Sound welds are readily made (with good process design and control).
High speed welding of thin sheet steels up to 5 m/min (16 ft/min) is
26
possible. Minimal welding fume or arc light is emitted. Practically no
edge preparation is necessary. The process is suitable for both indoor and
outdoor works. Distortion is much less. Welds produced are sound,
uniform, ductile, corrosion resistant and have good impact value. Single
pass welds can be made in thick plates with normal equipment. The arc is
always covered under a blanket of flux, thus there is no chance of spatter
of weld. 50% to 90% of the flux is recoverable
Limited to ferrous (steel or stainless steels) and some nickel based alloys.
Normally limited to the 1F, 1G, and 2F positions. Normally limited to
long straight seams or rotated pipes or vessels. Requires relatively
troublesome flux handling systems. Flux and slag residue can present a
health & safety concern. Requires inter-pass and post weld slag removal.
27
28
The project work is divided in to two parts:
Figure 1: Project Work Flow Diagram
29
Project Work
Cost Calculation
Labour Cost
Material
Cost
Maintanence Cost
Depriciation Cost
To Find The Ways To Reduce The Costs
2.3 Schedule of the project work:
30
Figure 2: Schedule of Project Work
3. LITERATURE REVIEW AND STUDY OF INDUSTRY
3.1 Introduction to Costing
The method of costing to be adopted depends on the nature of manufacturing activity.
There are various methods of costing. They are:
Standard costing
Marginal Costing
Job costing
Batch costing
Contract or Terminal costing
Single or output costing
Process costing
Operation costing
Departmental costing
Multiple costing
Historical costing
Standard Costing:
Under this technique, standard costs are established even before the actual
expenditures are incurred. Then the actual costs incurred are compared with the
standard costs and the differences between the two are calculated.
Marginal Costing:
The purpose of this type of costing is to study the relationship between cost, volume
and profit. It is also called as variable costing or differential costing.
31
Job Costing:
Under this method, work is performed against the individual orders accepted from the
customers. A distinct “Job” number is given for each order accepted.
Batch Costing:
Where small parts are manufactured in lots, it would be convenient to ascertain the
cost of each batch of articles so manufactured. Such type of costing is known as batch
costing.
Contract or Terminal Costing:
This is a method of costing applicable to contractors’ job.
Single or Output costing:
Where there is only one product, output costing is adopted. A cost sheet or a
production account is drawn, to show the cost of production of the product.
Process costing:
If a product passes through different stages of manufacture or processes, the method
of costing suitable is process costing. The special feature of this method is the
product at the end of a process becomes the raw material for the next process till it
reaches the last process.
Operation costing:
32
Under this method, the cost of each operation is calculated. This is suitable for
industries in which producing a product requires stages of operation.
Multiple costing:
It means combination of two or more of the above methods of costing. Where a
product comprises many assembled parts or components (as in case of motor car)
costs have to be ascertained for each component as well as for the finished product
for different components, different methods of costing may be used. It is also known
as composite costing.
Here, the multiple costing method is used for calculation of cost at TTS panel line.
33
3.2 Introduction to Shipping Industry
3.2.1 History of shipping industry
Commercial shipping can be traced back to the Phoenician merchants who
transported goods across the Mediterranean. The Venetians owned huge merchant
fleets from 1300 AD to 1500 AD. The Dutch held the largest shipping fleet from
1600 AD to 1650 AD. Till the nineteenth century, the shipping industry was
dominated by merchants. The common freight carrier service started in 1818 with the
launch of ‘James Monroe.’
The shipping industry boomed after the opening of the Suez Canal (1869), which
facilitated faster trade between Europe and Asia. In 1960, the first nuclear powered
cargo and passenger ship ‘Savannah’ was launched. From the 1970s to the 1980s, the
container shipping sector grew exponentially. The industry continued its growth,
especially in Asia, with Hong Kong inaugurating the world’s largest container port in
1989.
3.2.2 Industrial shipping Carriers:
Industrial carriers are vessels operated by large corporations to provide transportation
essential to the processes of manufacture and distribution. These vessels are run to
ports and on schedules determined by the specific needs of the owners. The ships
may belong to the corporations or may be chartered. For example, the Bethlehem
Steel Corp. maintains a fleet of Great Lakes ore carriers, a number of specialized
ships that haul ore from South America to Baltimore, Maryland, and a fleet of dry-
cargo ships that transports steel products from Baltimore to the Pacific coast. Many
oil companies maintain large fleets of deep-sea tankers, towboats, and river barges to
carry petroleum to and from refineries. The ships often operate under contracts of
affreightment.
34
3.2.2.1 Vessel Types
Merchant ships are classified as passenger carriers, cargo ships, and tankers. During
the height of passenger travel by ship, the largest as well as the most glamorous ships
afloat were the famed liners of the North Atlantic, which, beginning in the mid-19th
century, sailed regular schedules between the Americas and Europe. Competing in
speed as well as in size and appointments, such ships as the Mauretania, the Queen
Mary, the Queen Elizabeth, the United States, and the France gradually reduced the
time for the North Atlantic crossing to less than four days. Their size, from about
45,000 to 75,000 metric tons and up to 300 m (1,000 ft) in length, was gigantic by the
standards of the first half of the 20th century, but they have been dwarfed by the oil
tankers of the 1970s and '80s. Today's passenger liners operate principally in the
cruise trade.
Cargo Ships
Cargo ships carry packaged goods, unitized cargo (cargo in which a number of items
are consolidated into one large shipping unit for easier handling), and limited
amounts of grain, ore, and liquids such as latex and edible oils. A few passengers are
accepted on some cargo liners. Specialized ships are designed and built to carry
certain types of cargo, for example, automobiles or grain.
Container Ships
In the late 1950s container ships set the pattern for technological change in cargo
handling and linked the trucking industry to deep-Sea shipping. These highly
specialized ships carry large truck bodies and can discharge and load in one day, in
contrast to the ten days required by conventional ships of the same size. The rapid
development of the container ship began in 1956, when Sea-Land Service
35
commenced operations between New York City and Houston, Texas. Barge-aboard,
or lighter-aboard, ships, also called seabees (sea barges) or LASH (lighter-aboard
ships), resulted from an evolutionary development of the container ship. They are
capable of carrying about 38 barges, or up to 1,600 containers, or a combination of
containers and barges. Their design enables them to deliver cargo to developed or
undeveloped ports, without the need for berthing.
Tankers
Tankers, designed specifically to carry liquid cargoes, usually petroleum, have grown
to many-compartmented giants of a million metric tons and more. Despite their great
size, their construction is simple, as is, for the most part, their operation. A major
problem with the giant tankers is the severe environmental damage of oil spills,
resulting from collision, storm damage, or leakage from other causes. Specialized
tankers transport liquefied natural gas (LNG), liquid chemicals, wine, molasses, and
refrigerated products.
36
3.3 Introduction to PSL
Pipavav Shipyard Limited (PSL) is a testimony to the vision and active participation
of the private sector in India’s quest to become a major player in the global maritime
industry.
Covering over 200 hectares with approximately 720 m of sea front and 685 m of
outfit quay, PSL is the largest shipyard in India. It has one of the largest dry dock in
the world. Two Goliath cranes of 600 T capacity each, which service the dry dock
and the adjoining pre-erection berth, enabling PSL to handle up to 1200 T pre-
outfitted ship blocks. A host of other technologically advanced infrastructure and use
of modern shipbuilding process,m[l,.l.ses, including modular construction and line
heating technique, make PSL one of the most modern shipyards in the world.
Coupled with the above, PSL’s commitment is, uncompromising quality and an
increased focus on customer service to make PSL comparable with the best in the
world.
Vision
To make the Company one of the best in the world in every aspect with focus on Defence,
Offshore and Heavy Engineering in the coming decade and to contribute humbly towards
India becoming net exporter of warships, oil and gas assets.
Mission
To create visibility and value for all stakeholders on a sustainable basis by leveraging
on most advanced capabilities to exploit global opportunities.
37
3.3.1 Stake Holders
Promoter:
SKIL Infrastructure Ltd. (SKIL)
Foreign Companies:
SembCorp Marine Ltd.
Financial Institutions and Banks:
Infrastructure Leasing & Financial Service Ltd.(IL&FS)
LIC and LIC sponsored Mutual Funds (LIC)
Export Import Bank of INDIA(EXIM Bank)
IDBI Bank Ltd. (IDBI)
Sundaram BNP Paribas Mutual Fund
Foreign Institutional Investors:
Small cap World Fund, Inc.
New York Life Investment Management India Fund (FVCI),II LLC, Mauritius
American Funds Insurance Series Global Small Capitalisation Fund
Commonwealth Equity Fund Ltd.
The California Public Employees’ Retirement System
Battermarch Financial Management Inc.
The India Fund, Inc.
3.3.2 Association With World Leading Groups
SembCorp Marine, a leading global marine engineering and shipyard group,
has been advising PSL on yard layout and manufacturing processes.
38
Northrop Grumman Overseas Service Corporation, USA:The company
had signed a memorandum of understanding (MoU) with Northrop Grumman
Overseas Service Corporation, Delaware, USA. Northrop is one of the largest
defense companies in the segment with an expertise in defense systems,
airspace management systems, navigation systems, precision weapons and
marine systems. Pipavav Shipyard endeavors to indigenously produce military
hardware for India and other friendly nations with such partnerships.
SAAB Dynamics :Pipavav Shipyard has signed an MoU with SAAB
Dynamics AB as part of a defense co-production initiative taken by
Wallenberg Group in India. This will enable Pipavav to enter the army and air
force segments. SAAB Dynamics AB is a part of the Wallenberg Group,A
Swedish multinational company. The department of industrial policy and
promotion (DIPP) issued the license after screening by the ministries of home
and defense and other related agencies. The license allows the shipyard to bid
for construction of submarines, destroyers, frigates, LDP, coverettes as also
aircraft carriers
39
3.3.3 Business strategy
PSL’s long-term strategy is to have four pillars to
stand on, each capable of supporting the Shipyard
on its own. The Company has engaged in activities
in the following business sectors:
Commercial shipbuilding
Offshore fabrication and
servicing
Naval War-Ship Building
Ship repair
This strategy will insulate PSL from the the risks of relying on one market segment
alone, and also allow for profitable business opportunities in each segment to be
grasped as market conditions dictate.
PSL has been set up with the in-built flexibility to switch from one product type to
another, without compromising on the efficiency or cost-effectiveness of the yard
operations.
Accordingly, there will be capability to build and repair (dry dock & afloat) most
kinds of commercial ships from very large crude carrier to cape size bulk carrier and
large container ships.
In Naval shipbuilding and repair, PSL has the necessary infrastructure and facility to
build all kinds of naval vessels. Initially the yard intends to take up refit dry docking
and afloat repairs and later enter into conversions.
Given the increasing focus on offshore exploration for oil and gas around the coast of
India, and in the Middle East, the Shipyard has been designed to exploit the
40
opportunities that this sector has to offer. Our capabilities in this regard include
fabrication / construction of offshore platforms, SBM’s, rigs, jackets, vessels, etc. for
upstream oil and gas sector / companies both in India and abroad. The yard has
already started construction of 12 offshore supply vessels for ONGC and are
competitively bidding for high end anchor handlers. The dredger market is another
potential under consideration.
At its site at Pipavav, PSL has installed and commissioned some of the most modern
shipbuilding equipment that can be purchased – inter-alia, from leading companies in
Norway, Japan, Italy and Norway. Two Goliath cranes, each having a lifting capacity
of 600 Ton, the largest in India, are also erected at the site.
This modern plant, when combined with PSL’s highly experienced management
team, comprising Indians and multi-national expatriates and the competitively priced
skilled labour available in India, have enabled PSL to make an impressive beginning
in the various business segments.
41
3.3.4 Infrastructure
3.3.4.1 Dry Dock:
The Pipavav Shipyard originally consisted of two wet basins – one
approximately 680 meters long and 65 meters wide, and the other
approximately 680 meters long and 60 meters wide.
The first of these has been converted into a dry dock measuring 662 meters
longs, and 65 meters wide.
Two Goliath cranes with a span of 150 meters & height of 175 meters together
capable of handling up to 1200 Ton block, and two Level Lifting cranes are
erected to service this dry dock.
To facilitate afloat fit-out and commissioning of ships, including afloat repairs,
a 300–meter long quay, with the capacity for berthing on both sides, has been
constructed with adequate draft and serviced by a Level Lifting crane. The
entrance of the dry dock also has a 100 meter extension track for the Goliath
cranes for unloading heavy machinery and equipment weighing up to 1200
Tons directly from ships and heavy lift barges.
The dry dock and surrounding facilities are located on 103.92 hectares
(approximately 256.79 acres) adjoining approx 720 meters of dedicated waterfront.
This entire area has been approved as an Export Oriented Unit (EOU) by the
Government of India.
42
3.3.4.2 Workshop and Facilities:
Approximately 4.5 kilometers away from the dry-dock, and located on 95
hectares of land in a Special Economic Zone approved by the Government of India, a
state of the art block-making facility has been set up for fabrication of hull blocks
By having located the workshops and fabrication facilities in a SEZ away from the
dockyard site, PSL has the dual advantage of having been able to reserve the
maximum area of water frontage available at the shipyard site for ship assembly,
offshore fabrication and ship repair activities whilst carrying out its fabrication and
other similar activities through a highly tax-efficient SEZ unit.
The blocks manufactured at this site are pre-outfitted to the maximum extent. This is
done in the ideal working conditions offered by covered fabrication shops. When
ready, the blocks are moved to the dock-side for pre-erection of mega/giga-blocks
followed by lowering them on the dock floor for final assembly and vessel launching.
The block-making site is equipped with, among others, the following facilities:
A very large fabrication facility, spread over an area of 235 acres, having closed
working areas of approximately 2 million square feet
The fabrication facility can cut steel and fabricate blocks of up to 144,000 Ton
43
per annum, as it is equipped with :
270 meter long panel line with one side welding machine from TTS Norway
8 Plasma/gas cutting machines from Koike, Japan
2 Marking machines from Koike Japan
Auto blast and paint line of 185 m length and
9 blast and paint cells from Hanfu China
Profile cutting machine from HGG Netherlands
Ring frame bender from Nieland Netherlands
Horizontal bending press for ring frame from Himalaya, India
2 Hydraulic presses having capacities of up to 1600 Ton from Himalaya, India
2 Plate straightening machines from Himalaya, India
28 EOT cranes having up to 150 Ton capacity each
30 Semi gantry cranes having up to 7 Ton capacity each
3 Gantry cranes having up to 60 Ton capacity each
3 Transporters, one of 370 tons capacity & two of 200 tons capacity each
In addition, the Shipyard’s utility infrastructure includes the following:
2 x 66 KVA power line along with switchyard, transmission and distribution systems Water pipeline and fire fighting system along with pumps, overhead tanks and pumping systemsLow pressure compressed air systemInfrastructure relating to consumable gases such as O2, CO2, LPG and nitrogen
3.3.5 Products of PSL
Commercial Shipbuilding:
44
Offshore Platforms:
Naval Vessels:
45
Ship Repair:
4. OBJECTIVE OF THE PROJECT
TTS panel line is a 270 meters long panel line at where blocks are prepared by
cutting, block fitting, welding, sub assembling and grinding. So, there is a very large
46
cost company is paying to the employees, contractors and suppliers for TTS panel
line.
The main objective of the work is to be aware of how the calculation of cost has been
done at corporate level practically and put my as possible efforts to find the ways to
reduce these cost.
5. RESEARCH METHODOLOGY
47
Research methodology is a methodology for collecting all sorts of information &
data pertaining to the subject. The objective is to examine all the issues involved.
The methodology includes the overall research design, & fieldwork done & finally
the analysis procedure.
Usefulness of the study
This study will be useful to company to calculate the cost at TTS panel
line and take effective steps to reduce these costs.
The study will also be useful to increase my knowledge.
Research Technique:
Research technique used is exploratory as well as constructive. The subject of the
study deals with defining the problem and understanding all the issues involved and
constructive because it gives an ongoing solution for the problem.
Observational Study:
The research was done by observing all the techniques, block designs and
procedures at the TTS panel line and then the problem was defined.
In Depth Interview:
The research also includes asking the questions to the employees and workers at the
plant and to know exactly that what problem they are facing at the plant.
6. DATA ANALYSIS AND INTERPRETATION
Cost Calculation
48
6.1 Labour Cost
The first task of the project is to calculate the labour cost. After calculation, we found
that in TTS panel line, there are 56 PTSPL employees, whose average salary is
`25,000 /month and the lists of employees are as under:
Table 1: Employee Distribution
No.of
employees
Designation of employees
36 Welders
4 Fitters
3 Supervisors
4 Engineers
6 Riggers
1 Incharge
So, the total fixed labour cost of PTSPL employees per month = 25000 × 56
= `13,50,000
Half the work has been given to the shakti construction on the contract basis. And it
is on tonnage basis. so shakti construction have their own employees who are
working on TTS panel line. The work contactor is doing is grinding, block fitting and
sub assembling. The cost of the work is as follows:
Grinding = `925/tone
Block fitting = `3650/tone
Sub assembly = `3650/tone
The block fitting should be calculated as 30% of the total production.
49
The total production, sub assembly and block fitting in tonnage are given in the
following table and chart:
Table 2: table of total production, sub assembly and block fitting
Month(2011) Total production(ton)Sub assembly(ton)
Block fitting(ton)
January 501.9 118 150.57
February 402.8 181.7 120.84
March 797.3 322.7 239.19
April 773.4 253.7 232.02
May 431 409 129.3
jan feb mar apr may0
100
200
300
400
500
600
700
800
900
total productionsub assemblyblock fitting
Figure 3: Production Summary
So, variable labour cost given to contractors is as follows:
50
Table 3: variable cast data
Month(2011) Sub assembly(`) Block fitting(`) Grinding(`)
January 4,30,700 5,49,580 4,64,257
February 6,63,205 4,41,066 3,72,590
March 11,77,855 8,73,043 7,37,590
April 9,26,005 8,46,873 7,15,395
May 14,95,405 4,71,945 3,98,675
jan feb mar apr may0
200,000
400,000
600,000
800,000
1,000,000
1,200,000
1,400,000
1,600,000
sub assemblyblock fittinggrinding
Figure 4: Variable Costs
So total labour cost at TTS panel line:
51
Table 4: Total Cost Data
Month(2011) Fixed cost(`) Variable cost(`) Total cost(`)
January 13,50,000 14,44,537 27,94,537
February 13,50,000 14,76,861 28,26,861
March 13,50,000 27,94,400 41,44,400
April 13,50,000 24,88,223 38,38,223
May 13,50,000 23,66,025 37,16,025
jan feb mar apr may0
500,000
1,000,000
1,500,000
2,000,000
2,500,000
3,000,000
3,500,000
4,000,000
4,500,000
fixed costvariable costtotal cost
Figure 5: Total Cost
Labour cost in 2011 is as follows:
52
Table 5: Labour Cost
Month(2011) Labour Cost(`/ton)
January 5567.9
February 7018.0
March 5190.5
April 4962.9
May 8621.8
Total Monthly Average Labour Cost In 2011 = `6273.42/ton
6.2 Material Cost
For calculation of material cost, we did very complex and tricky job. Because without
this job, we could not get the material cost. Following materials are used in TTS line.
53
Wire Spool (Welding Material)
Gouging Electrodes
Welding Screen
Safety Goggles
Contact Tips (Panasonic)
Contact Tips (ESAB)
Safety Gloves
O2 Consumption
CO2 Consumption
LPG Consumption
Flux Consumption
At TTS panel line, the most consuming material is a wire spool. So, our first task is to
find how many wire spools are used in the month.
Procedure for calculating the wire spool (welding material)
Step 1: So, for calculating the consumption of wire spool, we have one thumb rule
that with each wire spool, the welder can make an average of 40 meters of welding.
Step 2: Our second task is to find out how many meters of welding is needed in a
block. Each block needs different meters of welding.
Step 3: So, now we need to see, in a month, how many blocks are manufactured.
54
Step 4: For that, we took a design of each block and according to the design, we
calculated how much meters of welding is essential for making this block in the
presence of the engineers.
Step 5: And if we are not getting the welding meter length directly by design, we
have to follow the equation to find the length of the welding. The equation is
weight=L× h× t ×7.856
Where, H= Height
L= Length
T= Thickness
Step 6: Add all the meters and divided it by 40 (thumb rule), we got the number of
wire spool used. Each wire spool contains 15 kg of wires.
Example of a practice we did for calculating meters of welding for a block no.521
Here, it is given the welding length of all the components used in the block no.521
S2 = 0.9*2 = 1.8 m
E1 = 0.314*2 = 0.628 m
E3 = 1.020*2 = 2.040 m
Calculation for FR44A, FR50A, FR56A:
S1 = 2.276*2*3 = 13.7 m
S10 = 0.748*2*3 = 4.488 m
S11 = 1.031*2*3 = 6.186 m
S2 = 1.878*2*3 = 11.27 m
55
S3 = 1.481*2*3 = 8.886 m
S4 =1.069*2*3 = 6.42 m
S5 = 4.10*2*3 = 24.6 m
S6 = 3.2*2*3 = 19.2 m
S7 = 1.2*2*3 = 7.2 m
S8 = 0.8*2*3 = 4.8 m
S9 = 0.82*2*3 = 5.0 m
But joint = 180 m
T bar welding = 303.5 m
Straight welding = 1616.8 m
So, total welding meters = 2240.6 m
So, total welding wire spool = 56.015 wire spool
So, wires used in kg for the block no.521 = 840.25 kg
The cost of wire = `160/kg
So, total cost of welding material for the block no.521 = `1,34,400
Likewise, we did the same practice for each and every block for two months and then
we got one more thumb rule that the length of welding meters is nearly 2% of the
weight of the block. So if the block is of 60,000 kg then the welding meters are 12,00
metes.
56
So by these thumb rule we got the cost of welding material for 2011 as given in the
table:
Table 6: Cost of Welding Material
Month Of 2011 Weight Of Wire Spool
(Kg)
Cost Of Wire Spool (`)
January 10,038 16,06,080
February 8,056 12,88,960
March 15,946 25,51,360
April 15,468 24,74,880
May 8,620 13,79,200
So, average welding material cost in 2011 = `15,71,016 /month
Then for calculating the cost of O2, CO2, LPG and flux:
Table 7: Consumption of gases by weight
Month O2
consumption
(kg)
CO2
consumption
(kg)
LPG
consumption
(kg)
Flux
consumption
(packet)
January 7.465 13,751 6,160 45
February 6,885 18,856 6,160 51
March 8,172 21,470 6,160 110
April 9,222 20,922 6,160 83
May 12,297 27,404 6,160 77
O2 consumption was given in the cubic meters, we converted into first kg and then
cost of O2 is also converted by us in Rs/kg from Rs/cubic meter by using following
equation:
1 cubic meter = 0.775 kg of O2
57
Cost of O2 → `12.67 = 0.775 kg
Cost of CO2 → ` 8.5 = 1 kg
Cost of LPG → ` 63.51 = 1 kg
Cost of Flux → `770 = 1 packet
Table 8: Cost of gas consumption
Month O2
consumption
(`)
CO2
consumption
(`)
LPG
consumption
(`)
Flux
consumption
(`)
January 1,22,061 1,16,885 3,91,221 34,650
February 1,12,579 1,60,278 3,91,221 39,270
March 1,33,627 1,82,495 3,91,221 84,700
April 1,50,793 1,77,841 3,91,221 63,910
May 2,01,064 2,32,937 3,91,221 59,290
As same as welding material and flux and gases consumption, we found other
material cost as following:
Table 9: Material Cost
Material Name Average Material Cost(`)
Total Wire Spool 15,71,016
Gouging Electrodes 2,600
Welding Screen 375
Goggles 2,000
Contact Tips (Panasonic) 10,500
Contact Tips (Esab) 3,200
Gloves 2,000
O2 Consumption 1,44,024
58
CO2 Consumption 1,54,087
LPG Consumption 3,91,221
Flux Consumption 56,364
Total Monthly Average Material Cost in 2011 = `23,37,387
6.3 Maintenance Cost
According to the manager of TTS line, calculation of maintenance cost per month is
very tedious, complex and difficult task. Because there are lots of parts are used for
maintenance over here and all the parts have different cost. No one knows when the
maintenance parts of machines would be needed. For example, in any month, any
machine can be damaged and repair and maintenance cost can be occurred. So,
calculation of maintenance cost per month would not be accurate.
59
For calculation of maintenance cost per month, we calculated the maintenance cost of
whole year and then divided it by 12, we got average monthly maintenance cost. And
for yearly maintenance cost, company generally prepares a budget every year. This
year’s budget for maintenance cost at TTS panel line = 5% of the value of whole
panel line.
The value of TTS panel line = `40,00,00,000
So, maintenance cost for year 2011 = `2,00,00,000
Total Monthly Average Maintenance Cost in 2011 = `16,66,666
6.4 Depreciation Cost
Depreciation cost can be calculated widely by two methods:
Straight Line Method
Written Down Method
Here, we used Straight Line Method for calculation of depreciation cost by using the
equation:
60
The value of TTS panel line = `40,00,00,000
The useful life of TTS panel line = 20 years
Scrap(residual) value of TTS panel line = `6,00,00,000
So by SLM method, the depreciation cost in 2011 = 40,00,00,000−6,00,00,000
20
= `1,70,00,000
Total Monthly Average Depreciation Cost in 2011 = `14,16,666
Average Total Monthly Cost at TTS Panel Line
LABOUR COST = `34,62,819
MATERIAL COST = `23,37,387
MAINTENANCE COST = `16,66,666
DEPRICIATION COST = `14,16,666
61
Average Total Monthly Cost at TTS Panel Line = `88,83,538
And, monthly average production of TTS panel line = 581 ton
so, labour cost per ton = `5,960
Material Cost per ton = `4,023
Maintenance Cost per ton = `2,868
Depreciation Cost per ton = `2,438
Average cost per ton = `3,822
So, For Production of 1 Ton, TTS Panel Line Costs `15,289
The Ways to Reduce the Cost At TTS Panel Line
1. By increasing the tonnage:
For example,
In January, the production at TTS panel line = 501.9 tone
62
Salaries paid to PTSPL employees = `13,50,000
So , fixed money paid for production of 1 tone = `2,689
Whereas,
In March, the production at TTS panel line = 797.3 tone
Salaries paid to PTSPL employees = `13,50,000
So, fixed money paid for production of 1 tone = `1,693
So, average monthly reduction = `5,81,000 as per month production is 581 tone.
So, by increasing the tonnage, we had reduce labour cost of `1,000 per tone in
March and in upcoming future, if we produce more blocks in a month, we can
gain more profit by reducing the cost of labour.
2. Material (steel plates) should be available at TTS line on time:
During my training period, I have heard lots of time that material has not reached on
time. If the material would be delayed, no one can work efficiently. All costs would
be increased if the steel plates would be late.
For example,
63
P011 522/532 had been started very late because of delay in material supply. So all
other tasks would be late and because of this, it will cause delay in dry dock to
complete the ship. If this type of problems would be continue in future then it will
cause great impact on company’s image as well as company’s cost. So, for that,
material management should be done accurately from top to bottom. Proper planning
is required by the top management.
3. There is a space of reduction in contractor’s rates:
At TTS panel line, sub assemble, block fitting and grinding work is given to the
Shakti contractors.
The rate of Shakti contractor for a particular work is as follows:
Grinding = `925/tone
Block fitting = `3650/tone
Sub assembly = `3650 /tone
The block fitting should be calculated as 30% of the total production.
For example,
We have calculated the cost of work Shakti construction had paid to their employees
for 350 tone:
They employed 38 employers for working with 350 tone and the average salary is
`17,000
For 350 tone, the payment given by shakti construction to their employees =
`6,46,000
64
Cost of consumables which Shakti construction is using for grinding and other tasks
= `1,75,000
So, total cost of Shakti construction for 350 tone = `8,21,000
And payment given by PSL to Shakti construction for 350 tone is,
Grinding = `3,23,750
Sub assembly = `3,19,375
Block fitting = `3,83,250
Payment paid to shakti construction by PSL = `10,26,375
So, total profit of Shakti construction = `2,05,375 for 350 tone
= `590 per tone
So on an average, Shakti construction is earning `3,42,790 form PSL as average
production at TTS panel line = 581 tone.
So, there is a scope for reducing the rate of sub assembly, grinding and block
fitting. Or we can employ that much skilled persons by our own and we can
reduce this cost.\
4. No proper arrangement of material keeping:
Here, at BMS site, there is no proper arrangement for keeping the steel plates. All the
plates are put together like a bunch. And because of dust, moisture and humidity, if
one plate get started of pitting, all other plates easily get pitted. And the pitting is the
biggest difficulty at TTS panel line.
And because of pitted material, the TTS panel line had paid a lot. There is a chances
of rejecting a block due to the pitting. Pitted material is increasing the labour cost.
65
And for removing the pitting, grinding charge specially for pitting is `110/ square
meter. By converting square meter into kilograms, We found that a square meter =
165 kg.
For this year average 60% of plates get pitted. So nearly 385 tone plates needed
grinding. And the cost of grinding these material is `2,56,666.
So, for reducing the troubles by pitted material, the material should be kept in a
proper SHELF. (as shown in figure.) This is a figure of another shipyard where the
steel plates are kept in shelf. Where they are saving their nearly 50% of grinding cost.
Figure 6: Shelf Stacking
There should be a shelf of each and every plate (like 12 mm, 14 mm, 16 mm, etc.).
So, if water will touch to the plate, it will easily go to the downside of plate and not
make much harm to the plate.
And if the plates are kept in shelf, then it would be very convenient to take. If the
plates are in bunch and put together on land then if I want to get the plate which is at
last then it would be very difficult to take it out. And if the plates are in shelf, then it
would be easy to get any plate. By this way, we can save `1,28,333
.
66
5. Reduction of cost in wire spool:
Here, 1 wire spool (welding material) of 15 kg is having 1800 meters length of the
welding wire. For welding in blocks, there are criteria. One criteria for welding is: leg
length of welding should be 6.5 mm. Less than 6.5 mm should not be allowed.
So, for avoiding the mistakes, the welders generally make the welding having the leg
length of nearly 7.5 mm.
For 6.5 mm leg length, 35 meters of welding material is required for 1 meter welding.
And for 7.5 mm, 45 meters of welding material is required. So, we are loosing 10
meters of welding material per 1 meter welding by the welders. So, in 1 kg of
material 20 meters of welding material is wasted by the welders. And Average
monthly consumption of wire spool is 11,625 kg
Because of these, per month, 23,250 meters of wires are wasting. So, nearly 13 wires
pools get wasted which costs `32,135
If we train the welders perfectly and welders put more concentration on proper
welding, then we can save `32,135 per month from material cost.
6. Reduction of cost in CO 2 consumption:
Here, the regulator is assembled for regulating the CO2 consumption. The regulator is
made up of aluminium and there is a connector between the hose pipe and the
regulator which is known as nipple which is made up of brass. Sometimes because of
lacking of proper threading, damaged in hose pipe and the material difference of
regulator and nipple, on an average 20% of CO2 is leakage.
So, per month, there is an average CO2 consumption of `30,800.
67
For, solving this problem, we should use regulator and nipple of same material and
threading of nipple should be done properly as well as if the hose pipe get damaged
then the hose pipe should be changed or repaired quickly.
7. Inconsistent quality of contact tips:
From material handling department, they are providing a different quality contact
tips.
They have two types of contact tips having different quality and different costs. The
rate of contact tips are as follows:
Contact tips (panasonic) = `70
Contact tips (ESAB) = `32
Because of inconsistent quality of contact tips, 20-25 contact tips get wasted worth of
`650-`700.
8. Reduction in cost of O 2 consumption:
Many a times, I have found that the workers working with O2, they are wasting the O2
gas flow for cleaning the material. This O2 gas should not be used for cleaning. It is
only for cutting.
Because of this mishandling of O2 gas flow, there is a 5% loss of O2 which costs
nearly `7,200.
So, by proper handling, per month, saving of `7,200 can be possible.
68
Possible Total Cost Reduction Per Month = `11,22,958
7. CONCLUSIONS
For mass production in less time with higher accuracy of Flat Blocks of the ship can
be manufactured by TTS Panel Line only and for that cost control should be very
necessary. For cost control, there must be a calculation of all costs. The calculation of
cost has been done by the multiple costing method.
69
At TTS panel line, the mangers control the labour cost, material cost, maintenance
cost as possible as they can. But there is a little more scope of reduction in cost at
TTS panel line.
8. RECOMMENDATIONS
The reduction of cost at TTS panel line can be done as follows:
By increasing the tonnage
Material (steel plates) should be available at TTS line on time
There is a space of reduction in contractor’s rates
70
No proper arrangement of material keeping
Reduction of cost in wire spool
Reduction of cost in CO2 consumption
Inconsistent quality of contact tips
Reduction in cost of O2 consumption.
Labour cost:
The previous average monthly labour cost = `36,44,857.
The possible reduction in labour cost can be achieved by:
Table 10: reduction in labour cost
Particular Cost (`)
Increasing the tonnage 5,81,000
Reducing Contractor’s wages 3,42,790
Proper Material Storage (using shelves) 1,28,333
Total Reduction 10,52,123
After applying the solution, the new labour cost can be = `25,92,734
Material cost:
The previous average monthly material cost = `23,37,387.
The possible reduction in material cost can be achieved by:
Table 11: reduction in material cost
Particular Cost (`)
Reducing the cost of CO2 consumption 30,800
71
Reducing the cost of wire spool 32,135
Assuring consistent quality of contact tips 700
Reducing the cost of O2 consumption 7,200
Total Reduction 70,835
After applying the solution, the new material cost can be = `22,66,552
The total average monthly cost is currently = `88,83,538. By implementing these cost
reductions, a total cost reduction of `11,22,958 per month is achievable.
The total possible percentage reduction can be of 12.6%.