Calcu 1,5DAFTAR KALKULASI & KUANTITASPEKERJAANPEMBANGUNAN
JERAMBA LR. 1 GP. PUSONG LAMALOKASIKECAMATAN BANDA SAKTI KOTA
LHOKSEUMAWEVOLUME1 (Satu) UNITTAHUN ANGGARAN20141 (Satu) UNITNo.
& UraianSta. & Diameter (A)Panjang (B)Lebar (.C)Tinggi
/Tebal (D)Jumlah (E)Volume (F)SatuanRumusDibultkanSketsa/GambarNo.
MataUraianUmumPlat LantaiGelagarBalok0.00.00.0Jarak & Jmlah
BalokJeramba1Informasi
UmumPanjang82.0082.0082.001.500.00.00.02.50Lebar1.501.500.170.250.00.00.032.0032.80Tinggi0.150.150.200.200.00.00.00.0A.PEKERJAAN
JERAMBA BETONBeton K.2501Jeramba 1,5
mLantai0.082.001.500.151.0018.45M3B x C x D x
EJumlah18.45M3Gelagar82.000.170.202.005.58M3B x C x D x
EJumlah5.58M3Balok1.500.250.2032.002.40M3B x C x D x
EGelagar0.250.170.2064.000.54M3B x C x D x EJumlah1.86M31.86+Final
Total25.88M325.887.1 (6)Cetakan/Bekisting2Jeramba 1,5
mLantai82.001.500.01.00123.00M2B x C x
EGelagar82.000.200.02.0032.80M2B x C x
EJumlah90.20M2Gelagar82.000.540.02.0088.56M2B x C x EJumlah88.56M2X
UnitBalok1.500.400.032.0019.20M2B x C x
EGelagar0.250.202.0064.006.40M2B x C x D x
EJumlah12.80M212.80+Final Total191.56M2191.567.3 (1)Baja Tulangan
U24 PolosDiameterPjg Besi/BhBerat Kg/MJumlah0.01Plat LantaiArah
Y10.00164.100.6110.001,002.83B x D x E10.0010.0082.00Pajang (Y)Arah
X12.003.100.88547.001,492.22B x D x E547.00546.671.50Lebar (X)Over
Head5%0.00.00.0124.750.15JarakTotal2,619.80Kg2GelagarDiameterBerat/MPjg
BesiLebarTinggiJumlah6Tulang/bh12.000.8881.950.200.356.00432.70A x
B x E0.15Jarak Behel8.000.390.900.00.0546.00192.19A x B x
E546.00546.67Over
Head5%0.00.00.031.24Total656.13kg3BalokDiameterBerat/MPjg
BesiLebarTinggiJumlah6Tulang/bh12.000.881.450.250.206.007.66A x B x
E0.15Jarak Behel8.000.390.700.00.09.002.46A x B x E9.009.67Over
Head5%0.00.00.00.51Total1.0Buah balok10.63KgJumlah total
balok32.0340.03Kg@ x Jlh Blk32.0032.80Final
Total3,615.97kg/bh3,615.97
VolLEMBAR PERHITUNGAN VOLUMEPekerjaan:PEMBANGUNAN JERAMBA LR. 1
GP. PUSONG LAMALokasi:KECAMATAN BANDA SAKTI KOTA
LHOKSEUMAWETahun:2014DATA AWALPanjang Jeramba=28MLebar
Jeramba=1.5MJarak antar balok=2MJumlah Pilar/cincin
Tambahan=4bhJumlah cincin/pilar=3bhKedalaman Pilar=1.5MDIVISI 3
PEKERJAAN TANAH3.1(3)Galian Struktur Kedalaman 0-2 m1Pondasi
SumuranVolume =4.8m3Diameter=0.8mTinggi=1.5mJumlah=4bhJumlah Volume
Galian Struktur Kedalaman 0-2 m [m3]4.8m3Penurunan Cincin
sumuran1Pengadaan Cincin SumuranVolume =6Jumlah=6MJumlah Volume
Penurunan Cincin Sumuran [ M ]6MDIVISI
STRUKTUR0.950.950.087.1(7)Beton Mutu Sedang K-2501PLAT BETONVolume
=6.3m3Panjang=28mLebar=1.5mTinggi=0.15mJumlah=1bh2GELAGAR
BALOKVolume
=1.904m3Panjang=28mLebar=0.17mTinggi=0.2mJumlah=2sisi3KOLOM PILAR
(C)Volume
=0.3325m3Panjang=0.35mLebar=0.25mTinggi=0.95mJumlah=4bh4KOLOM PILAR
(B)Volume =0.18m3Panjang
(a+b)/2=0.6mLebar=0.3mTinggi=0.25mJumlah=4bh5KEPALA PILAR (A)Volume
=0.45m3Panjang=1.5mLebar=0.25mTinggi=0.3mJumlah=4bhJumlah Volume
Beton Mutu Sedang K-250 [m3]9.16657.1(9)Beton cyclope1Isi
SumuranVolume =3.0144m3Diameter=0.8mTinggi=1.5mJumlah=4unitJumlah
Volume Beton cyclope [m3]3.0144CETAKAN / BEKISTING1Plat
LantaiVolume =40.88m2Panjang=28mLebar bersih ( L+2t-2 Lb
)=1.46mJumlah=1unit2Balok GelagarVolume =31.92m2Panjang=28mLebar (
l+2t )=0.57mJumlah=2sisi3Kolom Pilar CVolume
=6.15m2Keliling=1.2mTinggi=0.95mJumlah pilar=4bh4Kepala Pilar
BVolume =4.85m2Lebar (a+b)/2=0.6mTinggi=0.25mjumlah
sisi=4sisiJumlah=4bh5Kepala Pilar AVolume
=6.35m210Keliling=0.85mPanjang=1.5mJumlah pilar=4bhJumlah Volume
Cetakan Beton [M2]90.15M226.46.66666666677.3(1)Baja Tulangan BJ 24
PolosL [m]Dia. [mm]Berat [kg/m]Jumlah [Btg.]Berat [Kg]Balok
Gelagar1Tul. Geser Balok Tumpuan
(6)Longitudinal28.00120.8812295.68013.25balok11.252Tul. Geser
Balok0.9080.39450157.950Angker1Tul. Longitudinal (shear
conector)0.5120.882410.56011KOLOM2Tul.
Longitudinal2141.22457.600PILAR3Tul.
Geser1.1880.395726.385KEPALA4Tul.
Longitudinal1.7141.22448.96044.94PILAR5Tul.
Geser0.9880.394416.817Plat Lantai5Tul. Longitudinal arah -
x28.2120.8822545.952116Tul. Longitudinal -
y1.6120.88375528.4697.1333333333Jumlah Baja Tulangan BJ 24 Polos
[Kg]1688.373Total Baja Tulangan BJ 241688.373
Bahan & UpahHARGA UPAH DAN BAHANKOTA LHOKSEUMAWE - 2014HARGA
UPAH TENAGA KERJANo.JENIS TEGARA KERJAHARGA
SATUANSATUANKETERANGAN1MandorRp.80,000.00Hari2Kepala
TukangRp.100,000.00Hari3Tukang Kayu / Batu / Tanah &
BesiRp.80,000.00Hari8PekerjaRp.70,000.00Hari0.0HARGA BAHAN
MATERIALNo.JENIS BAHAN MATERIALHARGA
SATUANSATUANKETERANGAN0.961.921Air Bersih Material Cor
BetonRp.50.00Ltr2Batu KaliRp.260,000.00M33Batu
BataRp.570.00Bh65000Batu BelahRp.260,000.004Besi Beton
PolosRp.12,000.00Kg5Koral beton / kerikilRp.220,000.00M30.06Koral
beton / kerikilRp.162.96Kg0.07Kayu Klas I ( Seumatok/Ulin/ Dll
)Rp.10,400,000.00M310,140,000.008Kayu Klas II ( kamper/Kruing/ Dll
)Rp.7,800,000.00M39Kayu
Bekisting/PerancahRp.3,250,000.00M30.010Kayu Klas II Papan
LisplankRp.93,000.00M211Kayu Dolken kayu 8 - 10/4
mRp.54,000.00Btg12Kawat BetonRp.19,500.00Kg13Kertas
PasirRp.6,500.00Lbr0.014Minyak BekistingRp.5,500.00Lt15Paku biasa
2" - 5"Rp.17,000.00Kg16Pasir urugRp.130,000.00M317Pasir
BetonRp.190,000.00M30.018Pasir BetonRp.135.71Kg0.019Pasir
PasangRp.180,000.00M320Plywood 4 mmRp.71,500.00Lbr1,2 x 2,4
m2.8821Plywood 9 mmRp.136,500.00Lbr1,2 x 2,4 m0.022Semen Portland
40 KgRp.63,700.00zak1592.523Semen Portland 40
KgRp.1,592.50Kg24Semen Putih 50 KgRp.80,600.00Zak25Semen Putih 50
KgRp.1,612.00Kg26Tanah TimbunRp.52,000.00M327Tanah Timbun Pilihan -
Tanah BerbatuRp.104,000.00M3Lhokseumawe, Maret 2014CV. MULTI
PRASARANA DESIGNODRA SAIFA, STDIREKTRIS
Analisa SNIDAFTAR ANALISA HARGA SATUAN BANGUNANKOTA LHOKSEUMAWE
- 2014PEKERJAAN TANAHSNI 2835-2008-6-11 m3 galian tanah biasa
sedalam 1
meterTenaga-Pekerja0.750OhxRp.70,000.00=Rp.52,500.000-Mandor0.025OhxRp.80,000.00=Rp.2,000.000Jumlah=Rp.54,500.000SNI
2835-2008-6-91 m3 Urugan
kembaliTenaga-Pekerja0.2500OhxRp.70,000.00=Rp.17,500.000-Mandor0.0080OhxRp.80,000.00=Rp.640.000Jumlah=Rp.18,140.000SNI
2835-2008-6-10a1 m3 Timbunan dan pemadatan tanahBahan-Tanah
Timbun1.200M3xRp.52,000.00=Rp.62,400.000Jumlah
(1)=Rp.62,400.000Tenaga-Pekerja0.500OhxRp.70,000.00=Rp.35,000.000-Mandor0.050OhxRp.80,000.00=Rp.4,000.000Jumlah
(2)=Rp.39,000.000Jumlah (1) + (2)=Rp.101,400.000SNI
2835-2008-6-10b1 m3 Timbunan Pilihan dan pemadatannyaBahan-Tanah
Timbun - Tanah Berbatu1.200M3xRp.104,000.00=Rp.124,800.000Jumlah
(1)=Rp.124,800.000Tenaga-Pekerja0.500OhxRp.70,000.00=Rp.35,000.000-Mandor0.050OhxRp.80,000.00=Rp.4,000.000Jumlah
(2)=Rp.39,000.000Jumlah (1) + (2)=Rp.163,800.000SNI 2835-2008-6-111
m3 Urugan pasirBahan-Pasir
urug1.200M3xRp.130,000.00=Rp.156,000.000Jumlah
(1)=Rp.156,000.000Tenaga-Pekerja0.300OhxRp.70,000.00=Rp.21,000.000-Mandor0.010OhxRp.80,000.00=Rp.800.000Jumlah
(2)=Rp.21,800.000Jumlah (1) + (2)=Rp.177,800.000PEKERJAAN BETONSNI
7394-2008-6.1Membuat 1 m3 beton mutu fc = 7,4 MPa (K 100), slump
(12 2) cm, w/c = 0,87Bahan-Semen
Portland247.000KgxRp.1,592.50=Rp.393,347.500-Pasir
beton869.000KgxRp.135.71=Rp.117,935.7148690.520-Kerikil999.000KgxRp.162.96=Rp.162,800.0009990.870-Air
Bersih215.000LtrxRp.50.00=Rp.10,750.000Jumlah ( 1
)Rp.684,833.214Tenaga-Pekerja1.650OhxRp.70,000.00=Rp.115,500.000-Tukang
batu0.275OhxRp.80,000.00=Rp.22,000.000-Kepala
tukang0.028OhxRp.100,000.00=Rp.2,800.000-Mandor0.083OhxRp.80,000.00=Rp.6,640.000Jumlah
( 2 )=Rp.146,940.000Jumlah (1) + (2)=Rp.831,773.214SNI
2836-2008-6.101 M3 Memasang pondasi siklop, 60 % beton campuran 1
PC : 2 PB : 3 KrSNI 2836-2008-6.10Bahan1 M3 Memasang pondasi
siklop, 60 % beton campuran 1 PC : 2 PB : 3 KrBatu Belah
15/200.480KgxRp260,000.00=Rp124,800.000BahanSemen Portland 40
Kg194.000KgxRp1,592.50=Rp308,945.000-Batu Belah
15/200.480M3xRp.215,000.00=Rp.103,200.00Pasir
beton0.312KgxRp135.71=Rp42.343-Semen Portland 40
Kg194.000KgxRp.1,300.00=Rp.252,200.00Koral beton
/kerikil0.468LtrxRp162.96=Rp76.267-Pasir
beton0.312M3xRp.156,000.00=Rp.48,672.00TenagaJumlah ( 1
)Rp.433,863.610-Koral beton
/kerikil0.468M3xRp.185,000.00=Rp.86,580.00TenagaPekerja3.400OhxRp70,000.00=Rp238,000.000-Pekerja3.400OhxRp.50,000.00=Rp.170,000.00Tukang
Batu0.850OhxRp80,000.00=Rp68,000.000-Tukang
Batu0.850OhxRp.78,000.00=Rp.66,300.00Kepala
tukang0.085OhxRp100,000.00=Rp8,500.000-Kepala
tukang0.085OhxRp.90,000.00=Rp.7,650.00Mandor0.170OhxRp80,000.00=Rp13,600.000-Mandor0.170OhxRp.73,000.00=Rp.12,410.00Jumlah
( 2 )Rp.328,100.000Jumlah=Rp.747,012.00Jumlah (1) +
(2)=Rp.761,963.610Dibulatkan=Rp.747,012.00SNI 7394-2008-6.7SNI
7394-2008-6.5Membuat 1 m3 beton mutu fc = 19,3 MPa (K 225), slump
(12 2) cm, w/c = 0,581 M3 Beton mutu fc = 14,5 Mpa (K 175), slump
(12 2) cm, w/c = 0,66BahanBahan-Semen
Portland371.000KgxRp.1,592.50=Rp.590,817.500-Semen Portland 40
Kg326.000KgxRp.1,300.00=Rp.423,800.00-Pasir
beton698.000KgxRp.135.71=Rp.94,728.571-Pasir beton
(Kg)760.000KgxRp.100.00=Rp.76,000.00-Kerikil1,047.000KgxRp.162.96=Rp.170,622.222-Koral
beton /kerikil (Kg)1,029.000KgxRp.120.00=Rp.123,480.00-Air
Bersih215.000LtrxRp.50.00=Rp.10,750.000-Air215.000LtrxRp.75.00=Rp.16,125.00Jumlah
( 1
)Rp.866,918.294TenagaTenaga-Pekerja1.650OhxRp.50,000.00=Rp.82,500.00-Pekerja1.6500OhxRp.70,000.00=Rp.115,500.000-Tukang
Batu0.275OhxRp.78,000.00=Rp.21,450.00-Tukang
batu0.2750OhxRp.80,000.00=Rp.22,000.000-Kepala
tukang0.028OhxRp.90,000.00=Rp.2,520.00-Kepala
tukang0.0280OhxRp.100,000.00=Rp.2,800.000-Mandor0.083OhxRp.73,000.00=Rp.6,059.00-Mandor0.0830OhxRp.80,000.00=Rp.6,640.000Jumlah=Rp.751,934.00Jumlah
( 2 )=Rp.146,940.000Dibulatkan=Rp.751,934.00Jumlah (1) +
(2)=Rp.1,013,858.294SNI 7394-2008-6.8Membuat 1 m3 beton mutu fc =
21,7 MPa (K 250), slump (12 2) cm, w/c = 0,56Bahan-Semen
Portland384.000KgxRp.1,592.50=Rp.611,520.000-Pasir
beton692.000KgxRp.135.71=Rp.93,914.2866980.650-Kerikil1,039.000KgxRp.162.96=Rp.169,318.51910470.650-Air
Bersih215.000LtrxRp.50.00=Rp.10,750.000Jumlah ( 1
)=Rp.885,502.804Tenaga-Pekerja1.650OhxRp.70,000.00=Rp.115,500.000-Tukang
batu0.275OhxRp.80,000.00=Rp.22,000.000-Kepala
tukang0.028OhxRp.100,000.00=Rp.2,800.000-Mandor0.083OhxRp.80,000.00=Rp.6,640.000Jumlah
( 2 )=Rp.146,940.000Jumlah (1) + (2)=Rp.1,032,442.804SNI
7394-2008-6.17a1 Kg Pembesian dengan besi polos atau besi
ulirBahan-Besi beton ( polos
)1.050KgxRp.12,000.00=Rp.12,600.000-Kawat
beton0.015KgxRp.19,500.00=Rp.292.500Jumlah ( 1
)=Rp.12,892.500Tenaga-Pekerja0.007OhxRp.70,000.00=Rp.490.000-Tukang
besi0.007OhxRp.80,000.00=Rp.560.000-Kepala
tukang0.0007OhxRp.100,000.00=Rp.70.000-Mandor0.0004OhxRp.80,000.00=Rp.32.000Jumlah
( 2 )=Rp.1,152.000Jumlah (1) + (2)=Rp.14,044.500SNI 7394-2008-6.231
m2 Pasang bekistingBahan-Kayu
bekisting0.040M3xRp.3,250,000.00=Rp.130,000.000-Paku biasa 2" -
5"0.400KgxRp.17,000.00=Rp.6,800.000-Minyak
bekisting0.200LtxRp.5,500.00=Rp.1,100.000-Balok kayu Klas
II0.018M3xRp.7,800,000.00=Rp.140,400.000-Plywood tebal 9
mm0.350LbrxRp.136,500.00=Rp.47,775.000-Dolken kayu 8 - 10/4
m2.000BtgxRp.54,000.00=Rp.108,000.000Jumlah ( 1
)=Rp.434,075.000Tenaga-Pekerja0.660OhxRp.70,000.00=Rp.46,200.000-Tukang
kayu0.330OhxRp.80,000.00=Rp.26,400.000-Kepala
tukang0.033OhxRp.100,000.00=Rp.3,300.000-Mandor0.033OhxRp.80,000.00=Rp.2,640.000Jumlah
( 2 )=Rp.78,540.000Jumlah (1) + (2)=Rp.512,615.000Maka untuk 3x
pakai =512,615.000/ 3=Rp.170,871.667Analisa TaksirUntuk membongkar
1 M2 cetakan dan menyiram beton
diperlukan-Pekerja0.050OhxRp.70,000.00=Rp.3,500Jumlah ( 1
)=Rp.3,500Lhokseumawe, Maret 2014CV. Multi Prasarana DesignOdra
Saifa, STDirektris
SATUANSATUANSATUANSATUANSATUANSATUANSATUANSATUANSATUANSATUANSATUANSATUANSATUANSATUAN
RABRENCANA ANGGARAN BIAYA (RAB)PEKERJAAN:PEMBANGUNAN JERAMBA LR.
1 GP. PUSONG LAMALOKASI:KECAMATAN BANDA SAKTI KOTA
LHOKSEUMAWEVOLUME:1 (Satu) UNITTAHUN ANGGARAN:2014NONAMA
PEKERJAANVOLUMESATUANANALISAHARGA SATUANJUMLAH HARGA( RP )( RP
)A.PEKERJAAN PERSIAPAN1Pembersihan Lapangan diawal dan diakhir
PekerjaanLs-Taksir650,000.00650,000.002Pengukuran dan pemasangan
bouwplankLs-Taksir600,000.00600,000.003Pembongkaran Bangunan
ExistingLs-Taksir733,000.00733,000.004Administrasi dan
DokumentasiLs-Taksir600,000.00600,000.005Papan Nama
ProyekLs-Taksir300,000.00300,000.00Sub Total PEKERJAAN PERSIAPAN
:2,883,000.00B.PEKERJAAN BETON BERTULANG - STA 0+281Pemasangan
Bekisting/Perancah90.15M2SNI
7394-2008-6.23170,871.6715,404,080.752Pengadaan + penurunan cincin
sumuran6.00M1Taksir400,000.002,400,000.003Pembesian Balok, Gelagar,
Lantai & Pilar, Besi Beton Polos1,688.37KgSNI
7394-2008-6.17a14,044.5023,712,353.664Pengecoran Balok, Gelagar ,
Lantai & Pilar - Beton K.2509.17M3SNI
7394-2008-6.81,032,442.809,463,886.975Pengecoran Isi sumuran beton
cyclope3.01M3SNI 2836-2008-6.10761,963.612,296,863.106Pembongkaran
Bekisting/Perancah90.15M2Taksir3,500.00315,525.00Sub Total
PEKERJAAN BETON BERTULANG - STA 0+28 :53,592,709.48Lhokseumawe,
Maret 2014CV. Multi Prasarana DesignOdra Saifa, STDirektris
REKABR E K A P I T U L A S IPEKERJAAN:PEMBANGUNAN JERAMBA LR. 1
GP. PUSONG LAMALOKASI:KECAMATAN BANDA SAKTI KOTA
LHOKSEUMAWEVOLUME:1 (Satu) UNITTAHUN ANGGARAN:201456,475,000.00NO.U
R A I A N P E K E R J A A NJUMLAH HARGA0.00123A.PEKERJAAN
PERSIAPANRp.2,883,000.00B.PEKERJAAN BETON BERTULANG - STA
0+28Rp.53,592,709.48JUMLAH
TOTALRp.56,475,709.4856,500,000.00DIBULATKANRp.56,475,000.00150,000,000.00PerencanaanPengawasanTerbilang
: Lima Puluh Enam Juta Empat Ratus Tujuh Puluh Lima Ribu
Rupiah93,525,000.00500,000,000.00Yo500,000,000.00Yo500,000,000.00Yo362,682,000.00Y1362,682,000.00Y1362,682,000.00Y1910,887.10250,000,000.00Y2250,000,000.00Y2250,000,000.00Y25.63X13.90X11.16X1Disetujui
Oleh:Lhokseumawe, Maret 20146.83X24.62X21.45X2Pejabat Pembuat
Komitmen (PPK)Direncanakan Oleh :Dinas Pekerjaan UmumCV. Multi
Prasarana Design0.00250,000,000.00250,000,000.00250,000,000.00Kota
Lhokseumawe1.2000.7200.2900.00.00.0T. Syahrial A. MdOdra Saifa,
STNip. 19820321 200504 1 002Direktris56,475,000.000.00Diketahui /
Disetujui Oleh :Diketahui Oleh :Kepala Dinas Pekerjaan UmumKabid
Program Dan PerencanaanKota LhokseumaweDinas Pekerjaan UmumKota
LhokseumaweIr. Teuku Zahedi, MTTuti Indriani, ST., MMPembina Utama
Muda / Nip. 19621103 199203 1 001Nip. 19680614 199703 2 002