Project Status Project Phasing Questions

Feb 22, 2016

Download

Documents

AFRA

Project Status Project Phasing Questions. Project released for Bid February 7, 2011 Notice of Bid sent to 80+ Contractors on February 2, 2011 C&S occupied the field office on January 18, 2011 Architectural Approval from SED on December 17, 2010. As of Today. Moving Forward . - PowerPoint PPT Presentation
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Project Status Project Phasing  Questions
Page 2: Project Status Project Phasing  Questions

• Project Status

• Project Phasing

• Questions

2

Page 3: Project Status Project Phasing  Questions

As of Today

• Project released for Bid February 7, 2011

• Notice of Bid sent to 80+ Contractors on February 2, 2011

• C&S occupied the field office on January 18, 2011

• Architectural Approval from SED on December 17, 2010

3

Page 4: Project Status Project Phasing  Questions

Moving Forward • Contractor walk through scheduled for February 22,

2011

• Project Bids accepted March 3, 2011

• Contractor recommendations to the BOE on March 8, 2011

• Contractor mobilization beginning in early April, 2011

4

Page 5: Project Status Project Phasing  Questions

Phasing : • Scheduling Goals:• Minimize disruption to students / staff during the

school year• Upgrade HVAC systems by September 2011

• Main Campus Overall Staging Area• Large Permanent Staging Area in gravel lot below

the District Office • Summer Lay Down Areas at both the High School

and Wheeler Elementary School 5

Page 6: Project Status Project Phasing  Questions

HIGH SCHOOL : • TWO PHASES SUMMER 2011 & SUMMER 2012

• SUMMER 2011 • HVAC UPGRADES• MAIN OFFICE/GUIDANCE/HEALTH SUITE• FIRST FLOOR CLASSROOM RENOVATIONS• SINGLE SCEINCE CLASSROOM RENOVATION• ROOFING

6

Page 7: Project Status Project Phasing  Questions

HIGH SCHOOL : • SUMMER 2012 • TWO SCIENCE CLASSROOMS • SECOND FLOOR CLASSROOM RENOVATIONS• MEDIA CENTER RENOVATIONS• SITEWORK

7

Page 8: Project Status Project Phasing  Questions

TECHNOLOGY BUILDING: • UPGRADES COMPLETED BY SEPTEMBER 2011

8

Page 9: Project Status Project Phasing  Questions

WHEELER ELEMENTARY: • SUMMER 2011• PROJECT COMPLETED• HVAC UPGRADES• ROOFING • CLASSROOM RENOVATIONS

9

Page 10: Project Status Project Phasing  Questions

ROCKWELL ELEMENTARY: • TWO PHASES – SUMMER 2011 & SUMMER 2012

• SUMMER LAY DOWN AREA

• SUMMER 2011• HVAC UPGRADES COMPLETED • ROOFING • ADMINSTRATIVE AREA • SECOND FLOOR WEST WING CLASSROOMS

10

Page 11: Project Status Project Phasing  Questions

ROCKWELL ELEMENTARY: • SUMMER 2012• FIRST FLOOR CLASSROOMS• SECOND FLOOR EAST CLASSROOMS• SITEWORK

11

Page 12: Project Status Project Phasing  Questions

Questions

12