Steering Committee Agenda 22-1-14 • Overall Program Status • Status By Track • Phasing Slide • Schedule – High level schedule – Channel migration schedule – Rollout schedule – January/February releases • Headcount Discussion • Recent Accomplishments – Local Build Highlights – Aspera Highlights – Network Highlight – MCM Design Highlights • Next Steps • Appendix – Financial summary – Contract status
18
Embed
Steering Committee Agenda 22-1-14 Overall Program Status Status By Track Phasing Slide Schedule – High level schedule – Channel migration schedule – Rollout.
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Steering Committee Agenda 22-1-14
• Overall Program Status• Status By Track• Phasing Slide• Schedule
Initial Build & Launch• Initial AWS Build with MAM & Initial screens
• MCS Tools• Initial Integrations including GPMS to UK Vision
• Network Project Complete• Local build complete• Aspera Project Complete• VOD workflows• First Channel live
April-June 2014 – Phase 2: Channel Rollout
Rollout Channels• Rollout channels on MediaCentre (All UK Channels live)
• Stabilize & Tune system• Additional Integration services live
• BCM Integration• Continued development and testing
July-Sept 2014 – Phase 3: Additional Automation
First Wave of Automations• New automated workflows• Additional screens and enhancements
• Additional integration services
• Cloud NLE prototype• Madrid Requirements
October 2014 – December Phase 4: BMS enhancements
Second Wave of Automation & BMS Enhancements• Additional workflow automation
• BMS enhancements• Additional Integration• Screen enhancements• Madrid Development
Dec - April 2015 – Phase 5: Madrid & Budapest Archive
Expand to Madrid & CE (Archive)• Launch Madrid Channels• Vision CE integrated• MediaCentre Services available
• CE Archive available
Overall Program Status
•Contracting: Completed 9 of 16 contracts/production licenses•Finance: On track and reconciled weekly•Staffing: Giant Source more heavily leveragedProject Setup
•Go Live moved to 4/29 with the channel migrations ending 6/27 •Revised schedule enables channel migration activities to be supported early in the process based on planned rollout of functionality
•MAM P0 release completed 3 weeks later than plannedSchedule
•Original Scope OK•High level Madrid scope determinedScope
•Project financials are on track and have been submitted as part of the January forecast. Detailed reviews with individual project managers to update forecasts.
•Preliminary budget discussions have taken place regarding Madrid. Planned green light meeting in April
Project Budget
•Deployment risks mitigated based on new phased rollout•Still working on AWS contract•Resource availability through Q4•Vision 4.06 dependency
Issues & Risks
The MediaCentre’s Projects
Asp
era
Asp
era
JBOSS ESB & Rules120 ESB
MAM
Metadata
Update
GPMS
Vision
BCM
ODS
2
1
INTEGRATION BMS Systems
3
MAM in Cloud
4
Network
ESB
Local56 MASTER7
MCS ???UI Screens
• On track• Vision upgrade
scheduled for 2/17• Provys migration
(March – May)• Vision integration
almost complete (working on scheduling data)
• On track• ODIN UI
development completed
• UAT starts next week• Prod. Planned for
2/24• Schedule Ingest
from Vision in progress
• Vision data migration in progress
• Development behind initial plan schedule by 4-6 weeks for P1, assessing overall impact on P2-3
• Project Structure changes to address schedule
• All screens to support P0 – P3 functionality have been completed and approved
• P0 UAT Completed and signed off with minor bugs/defects identified for P1 fix
• Vidispine configured, deployed and demonstrated in HA configuration
• MCS integration activities focusing on authentication and Vidispine
• On track• Training complete• Workstations
upgraded and connected to new SAN
• Adobe Premier in use
• On track• Training complete• London and
Budapest using Aspera
• Hypercare begins this week
• On track• Two major SOWs
submitted for COFA• Financials on track• Training partner selected
and plan being finalized this week
• On track• Both
primary/back-up 10G connections are up and running
•Workflow Tasks:•Delivery Management•Compliance•Reports•Priority ranking•Rank by TX•File management rules
•Localization
•VOD/Catchup•Enhanced XML transform capability to support VOD catchup servicing•Additional VOD specific transcode profiles
01/22/2014 March 2014 (TBD) April 2014 (TBD) May 2014 (TBD)
UAT Complete Dates
ODIN
Local Build
Network
Aspera
UK Channel Launch Schedule Update
Channel Go Live Review
Sony Max Africa 29/04/14 13/05/14
SET Africa 29/04/14 13/05/14
SET Russia 29/04/14 13/05/14
SET Baltics 29/04/14 13/05/14
Sony Turbo Russia 29/04/14 13/05/14
Sony Turbo Baltics 29/04/14 13/05/14
Movies4Men 06/05/14 19/05/14
More Than Movies 06/05/14 19/05/14
SET UK 06/05/14 19/05/14
SMC UK 06/05/14 19/05/14
AXN Sci-Fi Italy 19/05/14 02/06/14
AXN Italy 19/05/14 02/06/14
AXN Germany 02/06/14 13/06/14
AXN Sci-Fi Russia 02/06/14 13/06/14
Animax Germany 16/06/14 27/06/14
SET Germany 16/06/14 27/06/14
Ongoing parallel work for migration:• Distributor on-boarding
migration and standard operating procedure.
• Aspera in place• Schedule has been validated in
meetings with core teams• Confirm training plan based on
schedule and confirm annual leave of core user group
Staff efficiencies in MediaCentre - Greenlight
Switch 3 QC to channels; 3 tech to MC
Current QC staffing to QC staffing w/ MC
Current QC staffing to QC staffing w/ MC
Go-Live RecapJanuary• 10G connectivity to AWS (primary and backup)• Internet equipment upgrades in place• Aspera software installed • Encompass Aspera planned Jan 28• Tape ingest and Aspera training next week• Upgraded workstations are connected to the new SAN storage • Adobe Premier software rolled out with training completed• ODIN UAT/training sessions this week
February • ODIN live with Vision (autopublish in March)• Vision upgraded to 4.06• Arqiva and Encompass upgrades
Highlights – Local Build
Consolidated
Streamlined
Before After
Highlights – Network/Aspera
Key Accomplishments• Direct Connections in place• Encompass Aspera go-live
planned Jan 28
Highlights – Media Centre Manager
Inbound Search
Matching Manual QC
Next Steps
• Upcoming Focus– MAM Buildout for P1– ODIN UAT – Tape Ingest and Aspera Training– Change management– Channel onboarding– Production licenses– Continue Vision upgrade & Provys migrations
work
Appendix
• Media Centre Project Financials• Contract Summary Status