PROJECT STATUS OF PROTOTYPE FAST BREEDER REACTOR (PFBR) UNDER CONSTRUCTION AT KALPAKKAM, INDIA Tarun Kumar Mitra Director (Technical), BHAVINI
37

PROJECT STATUS OF PROTOTYPE FAST … STATUS OF PROTOTYPE FAST BREEDER REACTOR (PFBR) UNDER CONSTRUCTION AT KALPAKKAM, INDIA Tarun Kumar Mitra Director (Technical), BHAVINI Type : Fast

Mar 30, 2018

Download

Documents

trankhue
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: PROJECT STATUS OF PROTOTYPE FAST … STATUS OF PROTOTYPE FAST BREEDER REACTOR (PFBR) UNDER CONSTRUCTION AT KALPAKKAM, INDIA Tarun Kumar Mitra Director (Technical), BHAVINI Type : Fast

1

PROJECT STATUS OF PROTOTYPE FAST

BREEDER REACTOR (PFBR) UNDER

CONSTRUCTION AT KALPAKKAM, INDIA

Tarun Kumar Mitra

Director (Technical), BHAVINI

Page 2: PROJECT STATUS OF PROTOTYPE FAST … STATUS OF PROTOTYPE FAST BREEDER REACTOR (PFBR) UNDER CONSTRUCTION AT KALPAKKAM, INDIA Tarun Kumar Mitra Director (Technical), BHAVINI Type : Fast

Type : Fast Breeder

Reactor (pool

type)

Fuel : PuO2 + UO2

Reactor thermal Power : 1250 MWth.

Electrical output : 500/470 MWe

Coolant : Sodium

Gross thermal Efficiency : 40%

PFBR Project Details

PFBR REACTOR

ASSEMBLY

Page 3: PROJECT STATUS OF PROTOTYPE FAST … STATUS OF PROTOTYPE FAST BREEDER REACTOR (PFBR) UNDER CONSTRUCTION AT KALPAKKAM, INDIA Tarun Kumar Mitra Director (Technical), BHAVINI Type : Fast

Sectional View of PFBR Reactor Assembly

Page 4: PROJECT STATUS OF PROTOTYPE FAST … STATUS OF PROTOTYPE FAST BREEDER REACTOR (PFBR) UNDER CONSTRUCTION AT KALPAKKAM, INDIA Tarun Kumar Mitra Director (Technical), BHAVINI Type : Fast

PFBR is the first of its kind 500 MWe Fast Breeder Reactor in INDIA.

Sodium cooled mixed oxide fuel pool type reactor.

Forerunner of the second stage of the nuclear power program.

Largest and deepest excavated pit in Indian nuclear plants.

First Reactor on common RAFT.

Fabrication and manufacturing of critical NSSS components for the first

time at site by industry with close tolerances.

Salient Features

Page 5: PROJECT STATUS OF PROTOTYPE FAST … STATUS OF PROTOTYPE FAST BREEDER REACTOR (PFBR) UNDER CONSTRUCTION AT KALPAKKAM, INDIA Tarun Kumar Mitra Director (Technical), BHAVINI Type : Fast
Page 6: PROJECT STATUS OF PROTOTYPE FAST … STATUS OF PROTOTYPE FAST BREEDER REACTOR (PFBR) UNDER CONSTRUCTION AT KALPAKKAM, INDIA Tarun Kumar Mitra Director (Technical), BHAVINI Type : Fast

PFBR- Status of major equipments erection

All heavy large diameter reactor components like, Safety vessel, Main

vessel, Thermal Baffle, Grid plate, Inner vessel & Roof slab erection has

been completed.

Both small and large rotatable plugs erected and Insitu heavy density

concreting also have been completed.

Long components like steam generators, Decay Heat Exchanger, Hot &

Cold pool level detector housing etc., have been completed.

Fuel handling equipment like, Primary tilting mechanism, primary ramp ,

transfer pot and fuel building components have been erected and pre-

commissioning works are in progress.

Page 7: PROJECT STATUS OF PROTOTYPE FAST … STATUS OF PROTOTYPE FAST BREEDER REACTOR (PFBR) UNDER CONSTRUCTION AT KALPAKKAM, INDIA Tarun Kumar Mitra Director (Technical), BHAVINI Type : Fast

Safety vessel Main vessel Thermal baffle

Grid plate Inner vessel Roof slab

MAJOR REACTOR COMPONENTS ERECTION

Page 8: PROJECT STATUS OF PROTOTYPE FAST … STATUS OF PROTOTYPE FAST BREEDER REACTOR (PFBR) UNDER CONSTRUCTION AT KALPAKKAM, INDIA Tarun Kumar Mitra Director (Technical), BHAVINI Type : Fast

LRP & SRP Erection

Page 9: PROJECT STATUS OF PROTOTYPE FAST … STATUS OF PROTOTYPE FAST BREEDER REACTOR (PFBR) UNDER CONSTRUCTION AT KALPAKKAM, INDIA Tarun Kumar Mitra Director (Technical), BHAVINI Type : Fast

IHX ERECTION

Page 10: PROJECT STATUS OF PROTOTYPE FAST … STATUS OF PROTOTYPE FAST BREEDER REACTOR (PFBR) UNDER CONSTRUCTION AT KALPAKKAM, INDIA Tarun Kumar Mitra Director (Technical), BHAVINI Type : Fast

DHX ERECTION

Page 11: PROJECT STATUS OF PROTOTYPE FAST … STATUS OF PROTOTYPE FAST BREEDER REACTOR (PFBR) UNDER CONSTRUCTION AT KALPAKKAM, INDIA Tarun Kumar Mitra Director (Technical), BHAVINI Type : Fast

SG ERECTION

Page 12: PROJECT STATUS OF PROTOTYPE FAST … STATUS OF PROTOTYPE FAST BREEDER REACTOR (PFBR) UNDER CONSTRUCTION AT KALPAKKAM, INDIA Tarun Kumar Mitra Director (Technical), BHAVINI Type : Fast

PTM ERECTION OVER GRID PLATE

Page 13: PROJECT STATUS OF PROTOTYPE FAST … STATUS OF PROTOTYPE FAST BREEDER REACTOR (PFBR) UNDER CONSTRUCTION AT KALPAKKAM, INDIA Tarun Kumar Mitra Director (Technical), BHAVINI Type : Fast

Both the primary and secondary sodium pumps have been erected .

CSRDM & DSRDM have been erected. Control plug has been erected.

Two nos. of AHX- Type (A) has been erected . Two more AHX ( Type-B)

erection under progress.

All the equipment below roof slab and inside main vessel has been erected

Two nos. of CCW pump has been erected in the concrete volute pump in

SWPH.

PFBR- Recent erection activities

completed

13

Page 14: PROJECT STATUS OF PROTOTYPE FAST … STATUS OF PROTOTYPE FAST BREEDER REACTOR (PFBR) UNDER CONSTRUCTION AT KALPAKKAM, INDIA Tarun Kumar Mitra Director (Technical), BHAVINI Type : Fast

14

Primary sodium Pump Erection

Page 15: PROJECT STATUS OF PROTOTYPE FAST … STATUS OF PROTOTYPE FAST BREEDER REACTOR (PFBR) UNDER CONSTRUCTION AT KALPAKKAM, INDIA Tarun Kumar Mitra Director (Technical), BHAVINI Type : Fast

PSP erection and assembly

Page 16: PROJECT STATUS OF PROTOTYPE FAST … STATUS OF PROTOTYPE FAST BREEDER REACTOR (PFBR) UNDER CONSTRUCTION AT KALPAKKAM, INDIA Tarun Kumar Mitra Director (Technical), BHAVINI Type : Fast

CONTROL PLUG

ERECTION

Page 17: PROJECT STATUS OF PROTOTYPE FAST … STATUS OF PROTOTYPE FAST BREEDER REACTOR (PFBR) UNDER CONSTRUCTION AT KALPAKKAM, INDIA Tarun Kumar Mitra Director (Technical), BHAVINI Type : Fast

CCW Pump Impeller erection

Page 18: PROJECT STATUS OF PROTOTYPE FAST … STATUS OF PROTOTYPE FAST BREEDER REACTOR (PFBR) UNDER CONSTRUCTION AT KALPAKKAM, INDIA Tarun Kumar Mitra Director (Technical), BHAVINI Type : Fast

18

Reactor Top View

Page 19: PROJECT STATUS OF PROTOTYPE FAST … STATUS OF PROTOTYPE FAST BREEDER REACTOR (PFBR) UNDER CONSTRUCTION AT KALPAKKAM, INDIA Tarun Kumar Mitra Director (Technical), BHAVINI Type : Fast

Commissioning – (systems completed)

• Water System

– Demineralized plant

– Raw water system

– Emergency & safety raw water system

– Emergency & safety service water system

• Electrical System

– Switch yard

– 6.6KV switchgear boards

– Battery charging

– Diesel Generators

• Fire protection system

– Fire alarm system

• Communication system

– Public Addressing system

• Air system

– Compressors

• Component handling system

– Under water trolley

– Fresh Sub Assembly

inspection facility

– Fresh Sub Assembly

Transfer chamber carriage

– All Cranes

Page 20: PROJECT STATUS OF PROTOTYPE FAST … STATUS OF PROTOTYPE FAST BREEDER REACTOR (PFBR) UNDER CONSTRUCTION AT KALPAKKAM, INDIA Tarun Kumar Mitra Director (Technical), BHAVINI Type : Fast

Sodium piping system

20

Sodium piping termination to

Steam generator , IHX, DHX, SSP

and Tanks, Surge tanks , etc has

been completed.

Heater cables, Thermocouples,

Wire type leak detectors

installation completed.

Insulation and cladding also

completed for major sodium

systems.

Leak collection trays erection

under progress.

Pre-commissioning under progress

Page 21: PROJECT STATUS OF PROTOTYPE FAST … STATUS OF PROTOTYPE FAST BREEDER REACTOR (PFBR) UNDER CONSTRUCTION AT KALPAKKAM, INDIA Tarun Kumar Mitra Director (Technical), BHAVINI Type : Fast

Piping work 100% completed.

I&C works are in progress and are nearing completion.

Erection and testing of field instruments , flow transmitters etc., are in

progress.

Utility Piping

SWPH

COMMISSIONING

Page 22: PROJECT STATUS OF PROTOTYPE FAST … STATUS OF PROTOTYPE FAST BREEDER REACTOR (PFBR) UNDER CONSTRUCTION AT KALPAKKAM, INDIA Tarun Kumar Mitra Director (Technical), BHAVINI Type : Fast

6.6kv Switchgear

Battery banks

Battery Charger panels

PCC panels

MCC panels

Switch yard

Transmission

lines

Electrical systems

Switch yard

Majority of the electrical systems completed

Page 23: PROJECT STATUS OF PROTOTYPE FAST … STATUS OF PROTOTYPE FAST BREEDER REACTOR (PFBR) UNDER CONSTRUCTION AT KALPAKKAM, INDIA Tarun Kumar Mitra Director (Technical), BHAVINI Type : Fast

Switch yard with Outgoing Transmission lines

Page 24: PROJECT STATUS OF PROTOTYPE FAST … STATUS OF PROTOTYPE FAST BREEDER REACTOR (PFBR) UNDER CONSTRUCTION AT KALPAKKAM, INDIA Tarun Kumar Mitra Director (Technical), BHAVINI Type : Fast

Diesel Generator Facility

Page 25: PROJECT STATUS OF PROTOTYPE FAST … STATUS OF PROTOTYPE FAST BREEDER REACTOR (PFBR) UNDER CONSTRUCTION AT KALPAKKAM, INDIA Tarun Kumar Mitra Director (Technical), BHAVINI Type : Fast

Diesel Generators commissioned

Page 26: PROJECT STATUS OF PROTOTYPE FAST … STATUS OF PROTOTYPE FAST BREEDER REACTOR (PFBR) UNDER CONSTRUCTION AT KALPAKKAM, INDIA Tarun Kumar Mitra Director (Technical), BHAVINI Type : Fast

Nuclear Island & Power Island

Power Island – Turbine Building

Nuclear Island – Reactor Building

Page 27: PROJECT STATUS OF PROTOTYPE FAST … STATUS OF PROTOTYPE FAST BREEDER REACTOR (PFBR) UNDER CONSTRUCTION AT KALPAKKAM, INDIA Tarun Kumar Mitra Director (Technical), BHAVINI Type : Fast

Turbine Building Progress

• Turbine on barring Gear has been successfully

achieved.

• Auxiliary boiler Commissioned.

• 97 % of the erection progress has been completed till

date.

27

Page 28: PROJECT STATUS OF PROTOTYPE FAST … STATUS OF PROTOTYPE FAST BREEDER REACTOR (PFBR) UNDER CONSTRUCTION AT KALPAKKAM, INDIA Tarun Kumar Mitra Director (Technical), BHAVINI Type : Fast

28 TG Overall view

Page 29: PROJECT STATUS OF PROTOTYPE FAST … STATUS OF PROTOTYPE FAST BREEDER REACTOR (PFBR) UNDER CONSTRUCTION AT KALPAKKAM, INDIA Tarun Kumar Mitra Director (Technical), BHAVINI Type : Fast

29

Auxiliary Boiler

Auxiliary Boiler

Commissioning completed.

Boiler light up

Safety valve floating

Steam blowing

Page 30: PROJECT STATUS OF PROTOTYPE FAST … STATUS OF PROTOTYPE FAST BREEDER REACTOR (PFBR) UNDER CONSTRUCTION AT KALPAKKAM, INDIA Tarun Kumar Mitra Director (Technical), BHAVINI Type : Fast

DM PLANT COMMISIONING

Page 31: PROJECT STATUS OF PROTOTYPE FAST … STATUS OF PROTOTYPE FAST BREEDER REACTOR (PFBR) UNDER CONSTRUCTION AT KALPAKKAM, INDIA Tarun Kumar Mitra Director (Technical), BHAVINI Type : Fast

KEY ACTIVITIES UNDER

PROGRESS

31

Pre-heating trials of main vessel commenced and is in progress

Pre-commissioning activities of sodium piping has commenced.

Commissioning of the auxiliary supporting systems are nearing completion.

RCB leak test commenced and under progress.

Page 32: PROJECT STATUS OF PROTOTYPE FAST … STATUS OF PROTOTYPE FAST BREEDER REACTOR (PFBR) UNDER CONSTRUCTION AT KALPAKKAM, INDIA Tarun Kumar Mitra Director (Technical), BHAVINI Type : Fast

PFBR Project

progress 2.45%

Civil99.68

Mechanical

97.93

Electrical99.28

I&C93.31

Physical progress

till Apr-1497.55%

Page 33: PROJECT STATUS OF PROTOTYPE FAST … STATUS OF PROTOTYPE FAST BREEDER REACTOR (PFBR) UNDER CONSTRUCTION AT KALPAKKAM, INDIA Tarun Kumar Mitra Director (Technical), BHAVINI Type : Fast

FBR 1&2

Page 34: PROJECT STATUS OF PROTOTYPE FAST … STATUS OF PROTOTYPE FAST BREEDER REACTOR (PFBR) UNDER CONSTRUCTION AT KALPAKKAM, INDIA Tarun Kumar Mitra Director (Technical), BHAVINI Type : Fast

Pre-project activities completed

• Site selection – by Site Selection Committee

• Financial sanction for Pre-Project activities by Govt.

• Geo-technical investigations – Preliminary & additional.

• TOR ( Term Of Reference ) from MoEF obtained.

• Site Evaluation Report

• Plant layout finalized

• Design and construction drawings have been completed for the

construction of Site Assembly Shop (SAS).

• Detailed Project Report (DPR)

• Environmental Impact assessment (EIA) / Environmental Management

Plan (EMP) has been prepared and submitted to Tamil Nadu Pollution

Control Board (TNPCB)

Page 35: PROJECT STATUS OF PROTOTYPE FAST … STATUS OF PROTOTYPE FAST BREEDER REACTOR (PFBR) UNDER CONSTRUCTION AT KALPAKKAM, INDIA Tarun Kumar Mitra Director (Technical), BHAVINI Type : Fast

Pre-project activities planned in the near future

Public hearing

Application for MoEF clearance

Application to govt. for financial sanction

• FBR 1 & 2 will be treated as a single project.

• Design will be similar as that of PFBR.

• First pour of concrete planned simultaneously.

Salient features

Page 36: PROJECT STATUS OF PROTOTYPE FAST … STATUS OF PROTOTYPE FAST BREEDER REACTOR (PFBR) UNDER CONSTRUCTION AT KALPAKKAM, INDIA Tarun Kumar Mitra Director (Technical), BHAVINI Type : Fast

Project 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023

FBR-1

FBR-2

Preliminary Schedule for construction of FBR 1&2 project

Need for early launch of FBR 1&2

Page 37: PROJECT STATUS OF PROTOTYPE FAST … STATUS OF PROTOTYPE FAST BREEDER REACTOR (PFBR) UNDER CONSTRUCTION AT KALPAKKAM, INDIA Tarun Kumar Mitra Director (Technical), BHAVINI Type : Fast