    3/3/2014 Project Quality Management Questions

    http://www.pmpden.com/pmbok-5-exam-questions/project-quality-management-questions/ 3/14

    Quality audits

    Histogram

    Incorrect

    Quality audits are part of the Perform Quality Assurance process.

    8. QuestionThe purpose of a quality audit is:

    Study organizational behavior

    To identify project quality for customer

    To identify inefficient and ineffective po licies

    Prepare a report for the quality team

    Incorrect

    Purpose of quality audit is to identify inefficient and ineffective policies.

    9. Question

    An external auditor is auditing the quality of your projects management processes. Which of the following processes this activity relates to?

    Validate Scope

    Perform Quality Assurance

    Control Quality

    Control Procurements

    Incorrect

    This is an example of a quality audit by an external auditor. This is a tool and technique of the Perform Quality Assurance process. [PMBOK 5th edition,

    Page 247]

    10. Question

    Which of the following is Demings formula for continuous improvement?

    Plan-Act-Check-Do

    Plan-Do-Check-Act

    Check-Plan-Do-Act

    Plan-Check-Do-Act

    Incorrect

    Demings model is Plan-Do-Check-Act. [PMBOK 5th edition, Page 229]

    11. QuestionWho defines quality ?

    Project Manager

    Customer

  • 8/10/2019 Project Quality Management Questions

    4/14

    3/3/2014 Project Quality Management Questions

    http://www.pmpden.com/pmbok-5-exam-questions/project-quality-management-questions/ 4/14

    Engineering staff

    Management

    Incorrect

    The customer defines quality according to the modern concept.

    12. QuestionWhich of the following is part of the Perform Quality Assurance process?

    Cost of Quality

    Design of experiments

    Benchmarking

    Quality audits

    Incorrect

    Quality audits are part of the Perform Quality Assurance process.

    13. Question

    Quality Checklists are used ______

    To keep quality inspectors busy

    To prevent project audits

    To ensu re that Quality Assurance steps were followed

    All

    Incorrect

    Quality Checklists are used to Ensure that Quality Assurance steps were followed.

    14. Question

    What is a control chart?

    A type of a RACI chart

    A chart that shows the root cause of a problem

    A type of a fishbone diagram

    A chart that shows the stability of a process

    Incorrect

    A control chart shows the stability of a process over time. [PMBOK 5th edition, Page 238]

    15. Question

    The Quality Management Plan describes:

    Need of quality

    When to apply quality

  • 8/10/2019 Project Quality Management Questions

    5/14

    3/3/2014 Project Quality Management Questions

    http://www.pmpden.com/pmbok-5-exam-questions/project-quality-management-questions/ 5/14

    How quality policies will be implemented

    Where in the project quality is important

    Incorrect

    Quality management plan Describes how the PM team will implement quality policies. Addresses quality control, quality assurance, and quality

    improvement for the project.

    16. Question

    The Pareto chart helps:

    Determine whether or not process is stable and within set limits.

    Determine how various factors are linked to potential problems

    Focus o n critical issues to improve quality

    Focus on root cause analysis

    Incorrect

    Pareto chart: Focus on critical issues to improve quality Fishbone diagram/Ishikawa: Determines how various factors linked to potential problems or

    effects, root cause Control chart: Determines whether or not process is stable and within set limits .

    17. Question

    What is a control chart?

    A type of a RACI chart

    A type of a fishbone diagram

    A chart that shows the root cause of a problem

    A chart that shows the stability of a process

    Incorrect

    A control chart shows the stability of a process over time. [PMBOK 5th edition, Page 238]

    18. Question

    Conformance to requirements and fitness for use are key concepts in quality management. Which of the following tools translates the customer

    requirements into technical requirements?

    Process mapping

    Scope creep

    Voice of the customer

    Quality checklist

    Incorrect

    Voice of the customer is a non-proprietary approach to quality management and is used to elicit stated as well as unstated customer needs (quality and

    requirements). This technique translates the customer requirements into technical requirements. [PMBOK 5th edition, Page 566]

    19. Question

    Which process group corresponds to the act component of the plan-do-check-act cycle?

  • 8/10/2019 Project Quality Management Questions

    6/14

    3/3/2014 Project Quality Management Questions

    http://www.pmpden.com/pmbok-5-exam-questions/project-quality-management-questions/ 6/14

    Monitoring and Controlling

    Planning

    Initiating

    Executing

    Incorrect

    The act component of the plan-do-check-act cycle relates to the Monitoring and Controlling process group. The plan-do-check-act cycle was created by

    Shewhart and modified by Deming to illustrate how different results from one cycle become an input to another cycle. [PMBOK 5th edition, Page 231

    20. Question

    According to the PMBOK, the definition of Project Quality Management process does not include:

    Planning

    Control

    Con firmation

    Assurance

    Incorrect

    According to the PMBOK, the definition of Project Quality Management does not include Confirmation.

    21. Question

    Deliverables are input of ___ process.

    Control Quality

    Identify risk

    Perform Quality Assurance

    Plan Quality Management

    Incorrect

    Deliverables are input of Control Quality process. PMBOK page no 229.

    22. Question

    Which of the following processes will determine the correctness of deliverables?

    Plan Quality Management

    Plan Quality Assurance

    Control Quality

    Perform Quality Assurance

    Incorrect

    An important goal of quality control is to determine the correctness of deliverables. The results of the execution of quality control processes are validated

    deliverables. These are then an input to the Validate Scope process for formalized acceptance. [PMBOK 5th edition, Page 248]

    23. Question

    Cindy has been working in a manufacturing project as a project manager. This project is designed to produce high quality semiconductors to use in

  • 8/10/2019 Project Quality Management Questions

    7/14

    3/3/2014 Project Quality Management Questions

    http://www.pmpden.com/pmbok-5-exam-questions/project-quality-management-questions/ 7/14

    computers. Since semiconductors are produced from silicon wafers, she contracted a company to provide silicon wafers to the project on an ongoing basis.

    Due to unknown reasons from the contractor, low quality wafers have been transferred to the project compromising the electrical performance of

    semiconductors. Overwhelmed by the complaints from the computer division, Cindy is obligated to correct the manufacturing defects to avoid future

    liabilities. In this scenario, the costs incurred by Cindy is known as:

    Internal failure costs or Cost of conformance

    External failure costs or Cost of nonconformance

    Prevention costs or Cost of conformance

    Appraisal costs or Cost of nonconformance

    Incorrect

    In this scenario, Cindy is performing warranty work to correct manufacturing defects. These defects are identified by external customers and the costs are

    known as ex ternal failure costs. These costs are also known as costs of nonconformance because the product did not meet the quality requirements. The

    cost of nonconformance is a part of the cost of quality. Therefore, Cindy is incurring external failure costs or cost o f nonconformance. [PMBOK 5th edition,

    Page 235]

    24. Question

    Project Quality Management includes:

    Customer satisfaction

    Prevention over inspection

    A ll

    Continuous improvement

    Incorrect

    Project Quality Management includes: Customer satisfaction, Prevention over inspection, Continuous improvement and Management responsibility.

    25. Question

    What is the purpose of Fishbone d iagram?

    To illustrate how various factors might be linked to potential problems or effects

    Are used to determine if the process are in control

    Show trends in a process over time

    Shows the pattern of relationship between two variables

    Incorrect

    To illustrate how various factors might be linked to potential problems or effects.

    26. Question

    Which of the following tools are used in the quality plan?

    Process Analysis

    Quality audits

    Qu ality Checklists

    Histogram

    Incorrect

  • 8/10/2019 Project Quality Management Questions

    8/14

  • 8/10/2019 Project Quality Management Questions

    9/14

    3/3/2014 Project Quality Management Questions

    http://www.pmpden.com/pmbok-5-exam-questions/project-quality-management-questions/ 9/14

    Incorrect

    Quality Control (QC) requires an inspection of the work results. QC: Monitoring results to determine if they comply with relevant quality standards and

    identifying ways to eliminate problem causes.

    31. Question

    Conformance to specifications document is a description of:

    Scope

    Quality

    Integration

    None

    Incorrect

    Quality on a project means that you are conforming to a standard that is set before you start the project.

    32. Question

    Who is primarily responsible for creating design and test specifications?

    Engineering

    Quality Control

    Management

    Support

    Incorrect

    Engineering is primarily responsible for creating design and test specifications.

    33. Question

    Bench-marking is :

    All

    useful for measuring you r level of quality against a standard

    useful for engineering quality only

    useful for so ftware quality only

    Incorrect

    Benchmarking is useful for measuring your level of quality against a standard. Benchmarking: Comparing actual or planned project practices to o ther

    projects, in order to generate ideas for improvement.

    34. Question

    The Fishbone diagram helps:

    All

    Focus on critical issues to improve quality

    Determine how various factors are linked to po tential problems or effects

    Determine whether or not process is stable and within set limits

  • 8/10/2019 Project Quality Management Questions

    10/14

    3/3/2014 Project Quality Management Questions

    http://www.pmpden.com/pmbok-5-exam-questions/project-quality-management-questions/ 10/14

    Incorrect

    Pareto chart: Focus on critical issues to improve quality Fishbone diagram/Ishikawa: How various factors linked to potential problems or effects, root cause

    Control chart: Determine whether or not process is stable and within set limits.

    35. Question

    _________are similar to control chart without displayed limits.

    Run charts

    Ish ikawa diagrams

    Pareto charts

    Histograms

    Incorrect

    Run charts are similar to control charts without displayed limits.

    36. Question

    You work at a so ftware company that authors Material Safety Data Sheets (MSDS) for chemical companies. Prior to releasing the MSDS to the company you

    have created a list of items to be reviewed to see that they appear on the document such as: chemical name, CAS#, protection required, what to do an

    emergency, etc. This is an example of what type of tool?

    Checklist

    Process Improvement Plan

    Quality Metrics

    Quality Management Plan

    Incorrect

    The scenario describes a checklist that someone would use to review the document prior to it being released. Creating checklists is a tool in the Plan

    Quality Management process. [PMBOK 5th edition, Page 242]

    37. Question

    Which of the following do not include Organizational Process Assets?

    Lessons learned

    Best practices

    Quality methodology

    Federal regulations

    Incorrect

    All others options except Federal regulations are in the Organizational Process Assets.

    38. QuestionWhat is the other term for Fishbone Diagrams?

    Metrics

    Project requirements

  • 8/10/2019 Project Quality Management Questions

    11/14

    3/3/2014 Project Quality Management Questions

    http://www.pmpden.com/pmbok-5-exam-questions/project-quality-management-questions/ 11/14

    Ishikawa Diagrams

    Trend Analysis

    Incorrect

    Ishikawa Diagrams sometimes called Fishbone Diagrams. Also called Cause and Effect Diagrams. Cause and effect diagram Illustrates how causes and

    subcauses relate and create potential problems or effects.

    39. Question

    You are managing a project. This project must satisfy industry standards in order to be accepted by the customer. You and your team have studied the

    requirements and have created a plan to implement the deliverables with the level of quality. This process is called ________.

    Quality Control

    All

    Quality assurance

    Plan Quality Management

    Incorrect

    Plan Quality Management: Identifying the quality standards that are relevant to the project and determining how to meet them.

    40. Question

    A project manager used a control chart to determine whether a process was stable or not, and to determine if its performance was predictable. He

    determined the upper and lower specification limits based on the contractual requirements. A set of eighteen data points were taken. Of these, 8 consecutive

    data points were above the mean. What can you say about such a process?

    A process is considered as out of control if six consecutive data points are above or below the mean. Hence the process is within control.

    A process is considered as out of control if five consecutive data points are above or below the mean. Hence the process is out of control.

    A process is con sidered as out o f control if seven consecutive data points are above or below the mean. Hence the process is

    out of control.

    A process is considered as being within control if less than half the data points are above or below the mean. Hence the process is within control.

    Incorrect

    A process is considered as out of control if a data point exceeds a control limit or if seven consecutive data points are above or below the mean. Hence the

    process is out of control. [PMBOK 5th edition, Page 238]

    41. Question

    Which of the following is true about quality?

    Quality is prevention driven.

    Quality is inspection driven.

    It will cost more money to build quality into the project

    Quality is not requested for small projects

    Incorrect

    Quality is prevention driven.

    42. Question

  • 8/10/2019 Project Quality Management Questions

    12/14

    3/3/2014 Project Quality Management Questions

    http://www.pmpden.com/pmbok-5-exam-questions/project-quality-management-questions/ 12/14

    Outputs of Plan Quality Management process are:

    Quality Checklist

    Quality management plan

    Quality Metrics

    A ll

    Incorrect

    Outputs of Plan Quality Management process: Quality management plan Describes how the PM team will implement quality policy. Addresses quality

    control, quality assurance, and quality improvement for the project. Operational definitions (Metrics) Describes what something is and how it is

    measured by the quality control process. Checklist Used to verify that a set of required steps has been performed. Project document updates and

    Process improvement plan.

    43. Question

    Which of the following tools is used during Trend Analysis?

    Earned Value Analysis

    Scatter Diagram

    Decision Tree Analysis

    Cause and Effect Diagram

    Incorrect

    Earned value analysis is used as a trend analysis technique for monitoring overall project performance. [PMBOK 5th edition, Page 352]

    44. Question

    Statistical sampling involves choosing part of a population for inspection. Appropriate sampling can often ___________the cost of quality control.

    reduce

    increase

    neutralize

    mitigate

    Incorrect

    Appropriate sampling can often reduce the cost of the quality control. In some application areas, it may be necessary for the project management team tobe familiar with a variety of sampling techniques. [PMBOK 5th edition, Page 240]

    45. Question

    A cost, time, quality, technical or resource value is used as a parameter and included in product specifications. Crossing this value triggers some action such

    as an exception report. This value would be called:

    A turning-point

    An exception-point

    A threshold

    A trigger

    Incorrect

  • 8/10/2019 Project Quality Management Questions

    13/14

    3/3/2014 Project Quality Management Questions

    http://www.pmpden.com/pmbok-5-exam-questions/project-quality-management-questions/ 13/14

    This is called a threshold. I t is a cost, time, quality, technical or resource value used as a parameter and may be included in product specifications. Crossing

    the threshold generally triggers an action such as generating an exception report which can get appropriately escalated. [PMBOK 5th edition, Page 565]

    46. Question

    Gordon has recently taken over a project as the project manager. The project is already halfway through the execution. Reviewing the project management

    plan, Gordon found outs that the projects WBS is not aligned with the project management plan and the 100% rule was ignored. What does this mean?

    The pro ject cannot be completed on time.

    The project management plan can never be 100% complete

    The WBS doesn't con tain all of the project and product work mentioned in the project management plan

    The project is not halfway through the execution.

    Incorrect

    The WBS must contain all of the project and product work including the project management work. This is also called as 100% rule. [PMBOK 5th edition,

    Page 131]

    47. Question

    You have been contracted to build a manufacturing plant in Kuala Lumpur, however you are not familiar with the building codes in the city of Kuala Lumpur

    or in the country of Malaysia, so you are reviewing all of their building codes prior to putting a shovel in the ground. This is an example of?

    Quality assurance

    Project initiation

    Quality control

    Quality planning

    Incorrect

    Any type of quality plans, such as building codes, OSHA guidelines, ISO9000 or company quality plans are examples of Organizational Process Assets

    which are inputs in the Plan Quality Management process. [PMBOK 5th Edition, Page 234]

    48. Question

    The Control chart helps:

    Focus on critical issues to improve quality

    Determines how various factors are linked to potential problems or effects

    Determine whether or not pro cess is stable and w ithin set limits

    Focus on root cause analysis

    Incorrect

    Pareto chart: Focus on critical issues to improve quality Fishbone diagram/Ishikawa: How various factors linked to potential problems or effects, root cause

    Control chart: Determine whether or not process is stable and within set limits.

    49. Question

    During a discussion with the quality department, a project manager was given to understand that both prevention and inspection meant the same as

    applied to projects. However, he had a different understanding of the terms. What would you comment on this situation?

    The project manager is correct. Inspection is about keeping errors out of the process whereas prevention is about keeping errors out of the hands of

    the customer.

  • 8/10/2019 Project Quality Management Questions

    14/14

    3/3/2014 Project Quality Management Questions

    RETURN TO TOP OF PAGE COPYRIGHT 2014 LOG OUT

    The project manager is wrong. Both inspection and prevention are about keeping errors out of the hands of the customer. They are used in different

    contexts.

    The project manager is correct. Prevention is about keeping errors ou t of the process whereas insp ection is about keeping

    errors out of the hand s of the customer.

    The project manager is wrong. Both inspection and prevention are about keeping errors out of the process. They are used in different contexts.

    Incorrect

    The project manager is correct. Prevention is about keeping errors out of the process whereas inspection is about keeping errors out of the hands of the

    customer. This is an important that the project management team needs to be aware of. [PMBOK 5th edition, Page 250]

    50. Question

    Another name for a Metric is:

    Product appearance

    Operational definitions

    Standards and regulations

    None

    Incorrect

    Operational definitions (Metrics) Describes what something is and how it is measured by the quality control process