Quality audits
Histogram
Incorrect
Quality audits are part of the Perform Quality Assurance process.
8. QuestionThe purpose of a quality audit is:
Study organizational behavior
To identify project quality for customer
To identify inefficient and ineffective po licies
Prepare a report for the quality team
Incorrect
Purpose of quality audit is to identify inefficient and ineffective policies.
9. Question
An external auditor is auditing the quality of your projects management processes. Which of the following processes this activity relates to?
Validate Scope
Perform Quality Assurance
Control Quality
Control Procurements
Incorrect
This is an example of a quality audit by an external auditor. This is a tool and technique of the Perform Quality Assurance process. [PMBOK 5th edition,
Page 247]
10. Question
Which of the following is Demings formula for continuous improvement?
Plan-Act-Check-Do
Plan-Do-Check-Act
Check-Plan-Do-Act
Plan-Check-Do-Act
Incorrect
Demings model is Plan-Do-Check-Act. [PMBOK 5th edition, Page 229]
11. QuestionWho defines quality ?
Project Manager
Customer
8/10/2019 Project Quality Management Questions
4/14
3/3/2014 Project Quality Management Questions
http://www.pmpden.com/pmbok-5-exam-questions/project-quality-management-questions/ 4/14
Engineering staff
Management
Incorrect
The customer defines quality according to the modern concept.
12. QuestionWhich of the following is part of the Perform Quality Assurance process?
Cost of Quality
Design of experiments
Benchmarking
Quality audits
Incorrect
Quality audits are part of the Perform Quality Assurance process.
13. Question
Quality Checklists are used ______
To keep quality inspectors busy
To prevent project audits
To ensu re that Quality Assurance steps were followed
All
Incorrect
Quality Checklists are used to Ensure that Quality Assurance steps were followed.
14. Question
What is a control chart?
A type of a RACI chart
A chart that shows the root cause of a problem
A type of a fishbone diagram
A chart that shows the stability of a process
Incorrect
A control chart shows the stability of a process over time. [PMBOK 5th edition, Page 238]
15. Question
The Quality Management Plan describes:
Need of quality
When to apply quality
8/10/2019 Project Quality Management Questions
5/14
3/3/2014 Project Quality Management Questions
http://www.pmpden.com/pmbok-5-exam-questions/project-quality-management-questions/ 5/14
How quality policies will be implemented
Where in the project quality is important
Incorrect
Quality management plan Describes how the PM team will implement quality policies. Addresses quality control, quality assurance, and quality
improvement for the project.
16. Question
The Pareto chart helps:
Determine whether or not process is stable and within set limits.
Determine how various factors are linked to potential problems
Focus o n critical issues to improve quality
Focus on root cause analysis
Incorrect
Pareto chart: Focus on critical issues to improve quality Fishbone diagram/Ishikawa: Determines how various factors linked to potential problems or
effects, root cause Control chart: Determines whether or not process is stable and within set limits .
17. Question
What is a control chart?
A type of a RACI chart
A type of a fishbone diagram
A chart that shows the root cause of a problem
A chart that shows the stability of a process
Incorrect
A control chart shows the stability of a process over time. [PMBOK 5th edition, Page 238]
18. Question
Conformance to requirements and fitness for use are key concepts in quality management. Which of the following tools translates the customer
requirements into technical requirements?
Process mapping
Scope creep
Voice of the customer
Quality checklist
Incorrect
Voice of the customer is a non-proprietary approach to quality management and is used to elicit stated as well as unstated customer needs (quality and
requirements). This technique translates the customer requirements into technical requirements. [PMBOK 5th edition, Page 566]
19. Question
Which process group corresponds to the act component of the plan-do-check-act cycle?
8/10/2019 Project Quality Management Questions
6/14
3/3/2014 Project Quality Management Questions
http://www.pmpden.com/pmbok-5-exam-questions/project-quality-management-questions/ 6/14
Monitoring and Controlling
Planning
Initiating
Executing
Incorrect
The act component of the plan-do-check-act cycle relates to the Monitoring and Controlling process group. The plan-do-check-act cycle was created by
Shewhart and modified by Deming to illustrate how different results from one cycle become an input to another cycle. [PMBOK 5th edition, Page 231
20. Question
According to the PMBOK, the definition of Project Quality Management process does not include:
Planning
Control
Con firmation
Assurance
Incorrect
According to the PMBOK, the definition of Project Quality Management does not include Confirmation.
21. Question
Deliverables are input of ___ process.
Control Quality
Identify risk
Perform Quality Assurance
Plan Quality Management
Incorrect
Deliverables are input of Control Quality process. PMBOK page no 229.
22. Question
Which of the following processes will determine the correctness of deliverables?
Plan Quality Management
Plan Quality Assurance
Control Quality
Perform Quality Assurance
Incorrect
An important goal of quality control is to determine the correctness of deliverables. The results of the execution of quality control processes are validated
deliverables. These are then an input to the Validate Scope process for formalized acceptance. [PMBOK 5th edition, Page 248]
23. Question
Cindy has been working in a manufacturing project as a project manager. This project is designed to produce high quality semiconductors to use in
8/10/2019 Project Quality Management Questions
7/14
3/3/2014 Project Quality Management Questions
http://www.pmpden.com/pmbok-5-exam-questions/project-quality-management-questions/ 7/14
computers. Since semiconductors are produced from silicon wafers, she contracted a company to provide silicon wafers to the project on an ongoing basis.
Due to unknown reasons from the contractor, low quality wafers have been transferred to the project compromising the electrical performance of
semiconductors. Overwhelmed by the complaints from the computer division, Cindy is obligated to correct the manufacturing defects to avoid future
liabilities. In this scenario, the costs incurred by Cindy is known as:
Internal failure costs or Cost of conformance
External failure costs or Cost of nonconformance
Prevention costs or Cost of conformance
Appraisal costs or Cost of nonconformance
Incorrect
In this scenario, Cindy is performing warranty work to correct manufacturing defects. These defects are identified by external customers and the costs are
known as ex ternal failure costs. These costs are also known as costs of nonconformance because the product did not meet the quality requirements. The
cost of nonconformance is a part of the cost of quality. Therefore, Cindy is incurring external failure costs or cost o f nonconformance. [PMBOK 5th edition,
Page 235]
24. Question
Project Quality Management includes:
Customer satisfaction
Prevention over inspection
A ll
Continuous improvement
Incorrect
Project Quality Management includes: Customer satisfaction, Prevention over inspection, Continuous improvement and Management responsibility.
25. Question
What is the purpose of Fishbone d iagram?
To illustrate how various factors might be linked to potential problems or effects
Are used to determine if the process are in control
Show trends in a process over time
Shows the pattern of relationship between two variables
Incorrect
To illustrate how various factors might be linked to potential problems or effects.
26. Question
Which of the following tools are used in the quality plan?
Process Analysis
Quality audits
Qu ality Checklists
Histogram
Incorrect
8/10/2019 Project Quality Management Questions
8/14
8/10/2019 Project Quality Management Questions
9/14
3/3/2014 Project Quality Management Questions
http://www.pmpden.com/pmbok-5-exam-questions/project-quality-management-questions/ 9/14
Incorrect
Quality Control (QC) requires an inspection of the work results. QC: Monitoring results to determine if they comply with relevant quality standards and
identifying ways to eliminate problem causes.
31. Question
Conformance to specifications document is a description of:
Scope
Quality
Integration
None
Incorrect
Quality on a project means that you are conforming to a standard that is set before you start the project.
32. Question
Who is primarily responsible for creating design and test specifications?
Engineering
Quality Control
Management
Support
Incorrect
Engineering is primarily responsible for creating design and test specifications.
33. Question
Bench-marking is :
All
useful for measuring you r level of quality against a standard
useful for engineering quality only
useful for so ftware quality only
Incorrect
Benchmarking is useful for measuring your level of quality against a standard. Benchmarking: Comparing actual or planned project practices to o ther
projects, in order to generate ideas for improvement.
34. Question
The Fishbone diagram helps:
All
Focus on critical issues to improve quality
Determine how various factors are linked to po tential problems or effects
Determine whether or not process is stable and within set limits
8/10/2019 Project Quality Management Questions
10/14
3/3/2014 Project Quality Management Questions
http://www.pmpden.com/pmbok-5-exam-questions/project-quality-management-questions/ 10/14
Incorrect
Pareto chart: Focus on critical issues to improve quality Fishbone diagram/Ishikawa: How various factors linked to potential problems or effects, root cause
Control chart: Determine whether or not process is stable and within set limits.
35. Question
_________are similar to control chart without displayed limits.
Run charts
Ish ikawa diagrams
Pareto charts
Histograms
Incorrect
Run charts are similar to control charts without displayed limits.
36. Question
You work at a so ftware company that authors Material Safety Data Sheets (MSDS) for chemical companies. Prior to releasing the MSDS to the company you
have created a list of items to be reviewed to see that they appear on the document such as: chemical name, CAS#, protection required, what to do an
emergency, etc. This is an example of what type of tool?
Checklist
Process Improvement Plan
Quality Metrics
Quality Management Plan
Incorrect
The scenario describes a checklist that someone would use to review the document prior to it being released. Creating checklists is a tool in the Plan
Quality Management process. [PMBOK 5th edition, Page 242]
37. Question
Which of the following do not include Organizational Process Assets?
Lessons learned
Best practices
Quality methodology
Federal regulations
Incorrect
All others options except Federal regulations are in the Organizational Process Assets.
38. QuestionWhat is the other term for Fishbone Diagrams?
Metrics
Project requirements
8/10/2019 Project Quality Management Questions
11/14
3/3/2014 Project Quality Management Questions
http://www.pmpden.com/pmbok-5-exam-questions/project-quality-management-questions/ 11/14
Ishikawa Diagrams
Trend Analysis
Incorrect
Ishikawa Diagrams sometimes called Fishbone Diagrams. Also called Cause and Effect Diagrams. Cause and effect diagram Illustrates how causes and
subcauses relate and create potential problems or effects.
39. Question
You are managing a project. This project must satisfy industry standards in order to be accepted by the customer. You and your team have studied the
requirements and have created a plan to implement the deliverables with the level of quality. This process is called ________.
Quality Control
All
Quality assurance
Plan Quality Management
Incorrect
Plan Quality Management: Identifying the quality standards that are relevant to the project and determining how to meet them.
40. Question
A project manager used a control chart to determine whether a process was stable or not, and to determine if its performance was predictable. He
determined the upper and lower specification limits based on the contractual requirements. A set of eighteen data points were taken. Of these, 8 consecutive
data points were above the mean. What can you say about such a process?
A process is considered as out of control if six consecutive data points are above or below the mean. Hence the process is within control.
A process is considered as out of control if five consecutive data points are above or below the mean. Hence the process is out of control.
A process is con sidered as out o f control if seven consecutive data points are above or below the mean. Hence the process is
out of control.
A process is considered as being within control if less than half the data points are above or below the mean. Hence the process is within control.
Incorrect
A process is considered as out of control if a data point exceeds a control limit or if seven consecutive data points are above or below the mean. Hence the
process is out of control. [PMBOK 5th edition, Page 238]
41. Question
Which of the following is true about quality?
Quality is prevention driven.
Quality is inspection driven.
It will cost more money to build quality into the project
Quality is not requested for small projects
Incorrect
Quality is prevention driven.
42. Question
8/10/2019 Project Quality Management Questions
12/14
3/3/2014 Project Quality Management Questions
http://www.pmpden.com/pmbok-5-exam-questions/project-quality-management-questions/ 12/14
Outputs of Plan Quality Management process are:
Quality Checklist
Quality management plan
Quality Metrics
A ll
Incorrect
Outputs of Plan Quality Management process: Quality management plan Describes how the PM team will implement quality policy. Addresses quality
control, quality assurance, and quality improvement for the project. Operational definitions (Metrics) Describes what something is and how it is
measured by the quality control process. Checklist Used to verify that a set of required steps has been performed. Project document updates and
Process improvement plan.
43. Question
Which of the following tools is used during Trend Analysis?
Earned Value Analysis
Scatter Diagram
Decision Tree Analysis
Cause and Effect Diagram
Incorrect
Earned value analysis is used as a trend analysis technique for monitoring overall project performance. [PMBOK 5th edition, Page 352]
44. Question
Statistical sampling involves choosing part of a population for inspection. Appropriate sampling can often ___________the cost of quality control.
reduce
increase
neutralize
mitigate
Incorrect
Appropriate sampling can often reduce the cost of the quality control. In some application areas, it may be necessary for the project management team tobe familiar with a variety of sampling techniques. [PMBOK 5th edition, Page 240]
45. Question
A cost, time, quality, technical or resource value is used as a parameter and included in product specifications. Crossing this value triggers some action such
as an exception report. This value would be called:
A turning-point
An exception-point
A threshold
A trigger
Incorrect
8/10/2019 Project Quality Management Questions
13/14
3/3/2014 Project Quality Management Questions
http://www.pmpden.com/pmbok-5-exam-questions/project-quality-management-questions/ 13/14
This is called a threshold. I t is a cost, time, quality, technical or resource value used as a parameter and may be included in product specifications. Crossing
the threshold generally triggers an action such as generating an exception report which can get appropriately escalated. [PMBOK 5th edition, Page 565]
46. Question
Gordon has recently taken over a project as the project manager. The project is already halfway through the execution. Reviewing the project management
plan, Gordon found outs that the projects WBS is not aligned with the project management plan and the 100% rule was ignored. What does this mean?
The pro ject cannot be completed on time.
The project management plan can never be 100% complete
The WBS doesn't con tain all of the project and product work mentioned in the project management plan
The project is not halfway through the execution.
Incorrect
The WBS must contain all of the project and product work including the project management work. This is also called as 100% rule. [PMBOK 5th edition,
Page 131]
47. Question
You have been contracted to build a manufacturing plant in Kuala Lumpur, however you are not familiar with the building codes in the city of Kuala Lumpur
or in the country of Malaysia, so you are reviewing all of their building codes prior to putting a shovel in the ground. This is an example of?
Quality assurance
Project initiation
Quality control
Quality planning
Incorrect
Any type of quality plans, such as building codes, OSHA guidelines, ISO9000 or company quality plans are examples of Organizational Process Assets
which are inputs in the Plan Quality Management process. [PMBOK 5th Edition, Page 234]
48. Question
The Control chart helps:
Focus on critical issues to improve quality
Determines how various factors are linked to potential problems or effects
Determine whether or not pro cess is stable and w ithin set limits
Focus on root cause analysis
Incorrect
Pareto chart: Focus on critical issues to improve quality Fishbone diagram/Ishikawa: How various factors linked to potential problems or effects, root cause
Control chart: Determine whether or not process is stable and within set limits.
49. Question
During a discussion with the quality department, a project manager was given to understand that both prevention and inspection meant the same as
applied to projects. However, he had a different understanding of the terms. What would you comment on this situation?
The project manager is correct. Inspection is about keeping errors out of the process whereas prevention is about keeping errors out of the hands of
the customer.
8/10/2019 Project Quality Management Questions
14/14
3/3/2014 Project Quality Management Questions
RETURN TO TOP OF PAGE COPYRIGHT 2014 LOG OUT
The project manager is wrong. Both inspection and prevention are about keeping errors out of the hands of the customer. They are used in different
contexts.
The project manager is correct. Prevention is about keeping errors ou t of the process whereas insp ection is about keeping
errors out of the hand s of the customer.
The project manager is wrong. Both inspection and prevention are about keeping errors out of the process. They are used in different contexts.
Incorrect
The project manager is correct. Prevention is about keeping errors out of the process whereas inspection is about keeping errors out of the hands of the
customer. This is an important that the project management team needs to be aware of. [PMBOK 5th edition, Page 250]
50. Question
Another name for a Metric is:
Product appearance
Operational definitions
Standards and regulations
None
Incorrect
Operational definitions (Metrics) Describes what something is and how it is measured by the quality control process