3/3/2014 Project Time Management Questions http://www.pmpden.com/pmbok-5-exam-questions/project-time-management-questions/ 1/14 Project Time Management Questions Results 0 of 50 questions answered correctly Your time: 00:00:03 You have reached 0 of 50 points, (0%) Keep Trying! Restart quiz View questions HOME PMBOK 5 EXAM QUESTIONS PAY & REGISTER LOGIN PROFILE CONTACT 1. Question Which statement is true about Sequence Activities? Identifying and documenting interactivity logical relationships. Establishing the activity logic and the dependencies needed to create a realistic and achievable schedule. As input list of activities, to put them into some sort of logical order, which is called Sequence Activities. All of the above Incorrect Sequence Activities : Identifying and documenting interactivity logical relationships. As input list of activities, to put them into some sort of logical order, which is called Sequence Activities. Establishing the activity logic and the dependencies needed to create a realistic and achievable schedule 2. Question Estimating the number of work periods likely to be needed to complete each activity is called : Estimate Activity Resources Estimate Activity Durations Sequence Activities Define Activities Incorrect Estimating the number of work periods likely to be needed to complete each activity is called Estimate Activity Duration . 3. Question Which statement is true ? All of the above Finish-to-finish An activity must finish before the next activity can finish. Finish-to-start An activity must finish before the next activity begins. Start-to-finish An activity must start before the next activity can finish.
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Which statement is true about Sequence Activities?
Identifying and documenting interactivity logical relationships.
Establishing the activity logic and the dependencies needed to create a realistic and achievable schedule.
As input list of activities, to put them into some sort of logical order, which is called Sequence Activities.
All o f the above
I ncorrect
Sequence Activities : Identifying and documenting interactivity logical relationships. As input list of activities, to put them into some sort of logical order,
which is called Sequence Activities. Establishing the activity logic and the dependencies needed to create a realistic and achievable schedule
2. Question
Estimating the number of work periods likely to be needed to complete each activity is called :
Estimate Activity Resources
Estimate Activity Durations
Sequence Activities
Define Activities
I ncorrect
Estimating the number of work periods likely to be needed to complete each activity is called Estimate Activity Duration .
3. Question
Which statement is true ?
All o f the above
Finish-to-finish An activity must finish before the next activity can finish.
Finish-to-start An activity must finish before the next activity begins.
Start-to-finish An activity must start before the next activity can finish.
Finish-to-start An activity must finish before the next activity begins. Finish-to-finish An activity must finish before the next activity can finish. Start-to-start An
activity must start before the next activity can start. Start-to-finish An activity must start before the next activity can finish.
4. Question
The critical path method (CPM) calculates the theoretical early start and finish dates; and late start and finish dates. The difference between the late and early
start of a task is called:
To tal float
Free float
Danger zone
Feeding buffer
I ncorrect
The difference between the early and late finish of a task is called the total float for that task. Total float is the amount of time that a schedule activity can be
delayed from its early start date without delaying the project finish date. [PMBOK 5th edition, Page 177]
5. Question
You are the project manager for a Project. You are updating the WBS during Define Activities, which is often called ________?
Updates
Refinements
Supporting detail
Activities
I ncorrect
updating the WBS during Define Activities, is often called Refinements. It occurs with riskier projects.
6. Question
Which of these is accurate regarding the Develop Schedule process?
Schedule network analysis is a technique that is carried out once the schedule is approved.
Schedules are optimized such that all non-critical activities have a zero total float.
Schedule compression shortens the project schedule while changing the project scope
The critical path method is a schedule network analysis technique that is performed using the schedule model
I ncorrect
The accurate statement regarding the Develop Schedule process is that the critical path method is a schedule network analysis technique that is performed
using the schedule model. The rest of the statements are not accurate. [PMBOK 5th edition, Page 173]
Project Manager and team develops the project plan .
8. Question
Which of the following statement is true about Corrective action ?
All
Anyth ing done to bring expected future schedule performance back in -line with the pro ject p lan
Modification to the schedule information used to manage the project
Changes to the scheduled start and finish dates in the approved (or baselined) schedule
I ncorrect
Corrective action – Anything done to bring expected future schedule performance back in-line with the project plan. Schedule updates – Modification to
the schedule information used to manage the project. Schedule revisions – Changes to the scheduled start and finish dates in the approved (or baseline)
schedule.
9. Question
Discretionary dependencies are identified during __________.
Define Activities
Control Schedule
Sequence Activities
Develop Schedule
I ncorrect
Discretionary dependencies are identified during Sequence Activities process. PMPBOK Page no 171.
10. Question
_____________ allows conditional branches and loops .
ADM
PDM
None of the above
GERT
I ncorrect
Conditional branches are not used in PDM and ADM. GERT (Graphical Evaluation and Review Technique) allows conditional branches and loops .
11. Question
Starting a new task before finish the old one is an example of a __________ dependency.
Start-to-finish An activity must start before the next activity can finish.
12. Question
Project Time Management includes _________ ?
Sequence Activities
Control Schedule
Define Activities
All o f the above
I ncorrect
The process areas listed for Project Time Management in the PMBOK are: Define Activities, Sequence Activities, Estimate Activity Resources, Estimate Activity
Duration, Develop Schedule, and Control Schedule.
13. Question
If you are doing revisions and schedule updates than you are making changes to _________ ?
Costs
Resources
Start and Fin ish Dates
None
I ncorrect
Schedule updates means Start and Finish Date changes.
14. Question
The technique most commonly used by project management software packages to construct a project schedule network diagram is:
Node-On-Activity (NOA)
Activity-In-Node (AIN)
Activity-On-Node (AON)
Finish-to-Start (FS)
I ncorrect
The method used by most project management software packages to construct a project schedule network diagram is Activity-On-Node (AON). This uses
boxes or rectangles, called nodes to represent activities and connects them with arrows showing the logical relationship between them. [PMBOK 5th
edition, Page 156]
15. Question
Which of the following is not a Project Time Management process?
The Project Time Management processes include Plan Schedule Management, Define Activities, Sequence Activities, Estimate Activity resources, Estimate
Activity durations, Develop Schedule, and Control Schedule. [PMBOK 5th Edition, Page 141]
16. Question
A project has three critical paths. How does this affect the project ?
It needs more time.
I t increases pro ject risk.
It needs more resources.
It costs more.
I ncorrect
It increases project risk.
17. Question
Total activity float is the amount of time :
that can be delayed without delaying pro ject completion date.
that can be delayed without delaying project.
delayed for indefinite time.
Not related with project.
I ncorrect
Total activity float is the amount of time that can be delayed without delaying project completion date.
18. Question
Which of the following is NOT a valid statement regarding the critical path method?
The flexibility of the schedule is measured by the difference between early and late dates.
A forward pass and backward pass are performed through the project network paths.
The early start and finish dates and late start and finish dates are calculated without factoring in resource limitations
The resulting late start and fin ish dates will be the pro ject schedule baseline.
I ncorrect
The critical path method is a technique that calculates the earliest and latest possible start and finish times for work activities in a project. It uses the
estimated duration of activities and the dependencies among them to determine limits for when each activity can be performed. [PMBOK 5th edition, Page
Which of the following are inputs of Define Activities ?
Organizational Process Assets
Enterprise environmental factors
Scope baseline
All o f the above
I ncorrect
Inputs of Define Activities : Scope baseline, Organizational Process Assets and Enterprise environmental factors
21. Question
You have decided to apply Resource Leveling to a project due to a critical required resource being available only at certain times. Which of the following will
likely be true?
Resource Leveling will over allocate resources to schedule the project before the deadline.
Resource Leveling will never alter the original critical path
Resource Leveling can o ften cause the orig inal critical path to change.
Resource Leveling will require additional resources to complete the project.
I ncorrect
Resource Leveling can often cause the original critical path to change. [PMBOK 5th edition, Page 179]
22. Question
You are in charge of constructing the Ferris wheel in each town a carnival visits. However, this is something you have never done before and you are getting
different opinions from others on how long it takes. Joe, is new and has given you what you believe to be an optimistic estimate of 3 hours, Bill says it will take
10 hours, which seems too long to you and quite pessimistic. Lastly, Margie, who is the most experienced at this task is telling you it will take 8 hours. You are
not sure who to believe, so you decide to do a PERT estimation, based on this you have determined it will take how many hours to assemble the Ferris wheel.
8 hours
7 hours
7.5 hours
21 hours
I ncorrect
The PERT formula is Estimate= (Optimistic + (Most Likely *4) + Pessimistic)/6. [PMBOK 5th edition, Page 171]
Which of the following statement is true about Schedule revisions ?
Modification to the schedule information used to manage the project
Anything done to bring expected future schedule performance back in-line with the project plan
Changes to the scheduled start and fin ish dates in the approved (or baselined) schedule
All
I ncorrect
Corrective action – Anything done to bring expected future schedule performance back in-line with the project plan. Schedule updates – Modification to
the schedule information used to manage the project. Schedule revisions – Changes to the scheduled start and finish dates in the approved (or baseline)
schedule.
24. Question
Which of the following statement is true about Resource leveling ?
Reducing peak overloads by re-d istributing allocations to activities with float
To fast track, shorten the duration of critical activities, or increase working hours
Decreasing the total project duration with the least cost possible
Doing activities in parallel that, normally, would be done in sequence
I ncorrect
Resource leveling : Reducing peak overloads by re-distributing allocations to activities with float.
25. Question
Linda is a first-time project manager and is analyzing a project schedule. She intends to apply resource leveling and has been given the following guidelines
on resource leveling. Which of these four statements is incorrect?
Resource leveling is necessary when resources have been over-allocated.
Resource Leveling can often cause the critical path to change.
Resource leveling is applied to keep resource usage at a constant level.
Resource leveling is applied to a schedule before it has been analyzed by the critical path method.
I ncorrect
Resource leveling is a schedule network analysis technique. It is applied to a schedule that has already been analyzed by the critical path method. [PMBOK
5th edition, Page 179]
26. Question
You are the project manager for a large Project. You have identified and documented relationship among the project activities and created project schedule
Finish to Start relationships indicate that the next task is not able to start until the one preceding it is completed. This is the most commonly used type of
Progressive elaboration is least applicable to which of the following processes?
Contro l Schedule
Develop Schedule
Estimate Activity Duration
Create WBS
I ncorrect
Progressive elaboration applies when only a certain amount of information is available initially and additional information is obtained as the project or
phase progresses. It is the progressive detailing of the project management plan and relates more closely to the processes from the planning process
group. [PMBOK 5th edition, Page 55]
32. Question
Which of the following is accurate regarding the Estimate Activity Resources process?
It produces project resource calendars as the output
This process is coordinated independent of the Estimate Cost process
It determines dependencies that may require a lead or lag to define the relationship
I t invo lves determining what and how many resources will be used
I ncorrect
The Estimate Activity Resources process determines what and how many resources will be used. The resource calendars are inputs to this process and this
process is closely coordinated with the Estimate Costs process. Activity leads and lags are not determined during this process. [PMBOK 5th edition, Page
160]
33. Question
During a work breakdown structure meeting you have decomposed the deliverable into work packages and created your WBS dictionary. However, you now
want to decompose the work packages to assist you in estimating, executing and control the project. These decomposed work packages are called?
Control Accounts
Work Packages can't be decomposed into smaller units
Milestones
Activities
I ncorrect
Activities represent the effort needed to complete a work package and are an output of the Define Activities process. During this process, the work
packages are further decomposed into project activities. [PMBOK 5th edition, Page 152]
34. Question
The Three estimates are : Pessimistic (P) : 30 Most Likely (M) : 25 Optimistic (O) : 14 What is Standard deviation ?
Standard deviation formula = (P – O) / 6 then (30-14)/6 = 2.66
35. Question
Which statement is true about Finish-to-start activity ?
An activity must fin ish before the nex t activity begins.
An activity must start before the next activity can start.
An activity must start before the next activity can finish.
An activity must finish before the next activity can finish.
I ncorrect
Finish-to-start An activity must finish before the next activity begins.
36. Question
What are Milestones ?
Deliverables
Activities with durations
Project plan
S ign ificant events in the pro ject life cycle
I ncorrect
Milestones – Events need to be part of the Sequence Activities to assure that the requirements for meeting the milestone (s) are met.
37. Question
You are the project manager for a large Project. You are currently busy with approximating number of work periods required to complete individual activities
with estimated resources. Which of the following inputs do you need for this ?
Activity resource requirements
All of the above
Activity List
Resource Breakdown structure
I ncorrect
Approximating number of work periods required to complete individual activities with estimated resources is done in Estimate Activity Duration process.
Activity List,Activity resource requirements and Resource Breakdown structure are inputs of Estimate Activity Duration process. PMBOK Page no 142.
38. Question
What are the three-point estimates used during the Estimate Activity Duration process?
Most likely, optimistic, and pessimistic are the three-point estimates used during the Estimate Activity Duration process. [PMBOK 5th Edition, Page 170]
39. Question
Which statement is true about Critical Path Method (CPM) ?
Calculates a single, deterministic early and late start and finish date for each activity
None
Calcu lates a single, deterministic early and late start and fin ish date for each activity and also Used to determine which activities
must be completed on time to avo id impacting the fin ish date o f the pro ject
Used to determine which activities must be completed on time to avoid impacting the finish date of the project
I ncorrect
Critical Path Method (CPM) – Calculates a single, deterministic early and late start and finish date for each activity, to be used to determine which activities
must be completed on time to avoid impacting the finish date of the project.
40. Question
Which of the following is an output of the Define Activity process?
Project schedule activity diagrams
Resource calendar
Activity duration estimates
Milestone list
I ncorrect
A milestone list is a valid output of the Define Activity process. [PMBOK 5th edition, Page 149]
41. Question
In a small office construction project, the following activities are scheduled in sequence. i) Digging and pouring footings – 5 days ii) Working on the slab and
pouring – 3 days iii) Framing the floor – 5 days iv) Wall framing – 4 days v) Roof framing – 6 days vi) Insulation and drywall – 7 days vii) Interior doors and trim
– 3 days viii) Hardware and fixtures – 2 days. What is the minimum time to complete the project if all activities are on a critical path except number viii, and
activity iii is delayed by 1 day?
35 days
34 days
33 days
32 days
I ncorrect
A critical path has a zero total float. That means, any delay in the critical path activity delays the project finish date. In other words, critical path gives the
minimum time required to complete a project. So, adding the duration for all critical path activities give the minimum time required as 33 days. If activity iii is
delayed by one day, the total duration or the minimum time required to complete the project will also be delayed by one day, thus making it 34 days.
[PMBOK 5th edition, Page 176]
42. Question
Precedence Diagramming Method (PDM) is also known as _______?
Activity dependency
Activity On Node (AON)
Activity On Arrow (AOA)
All of the above
I ncorrect
The Precedence Diagramming Method (PDM) uses boxes or nodes as activities and arrows as dependencies between the nodes. PDM is also known as
Activity On Nodes (AON). ADM (Arrow Diagramming Method) is also known as Activity On Arrows (AOA).
43. Question
Decomposition of the Scope Statement results in _____ ?
WBS
Business plans
SOW
Project plan
I ncorrect
The WBS defines all activities you will need to do in order to successfully complete the project.
44. Question
Work periods between the finish of one activity and the start of another activity is called ______ ?
E lapsed time (Delay)
Estimation time
Schedule
None
I ncorrect
Elapsed time (Delay) – Work periods between the finish of one activity and the start of another activity.
45. Question
While developing the project schedule, you find that the completion of a successor activity depends on the completion of its predecessor activity. What is this
In a Finish-to-Finish dependency , the completion of the successor activity depends upon the completion of its predecessor activity. [PMBOK 5th edition,
Page 156]
46. Question
As you are creating the Activity List, which technique is recommended for subdividing the project into smaller components called activities?
Rolling Wave Planning
Decomposition
Expert judgment
Deconstruction
I ncorrect
The decomposition technique allows the project manager to create smaller and more manageable pieces of work from the larger work packages. [PMBOK
5th edition, Page 151]
47. Question
________ are examples of corrective actions that can be taken.
Crashing
Tracking and Tracking
None
Tracking
I ncorrect
Tracking and Crashing are examples of corrective actions that can be taken.
48. Question
An experienced project manager was assigned a project of very small scope. Which of the following scenarios could be representative of the project?
Developing and Controlling the schedule could be viewed as a single process
Estimating activity resources may be skipped for the project
Defin ing Activities, sequencing activities, estimating activity resources, and develop ing the schedule could be viewed as a single
process
Defining Activities, estimating activity resources, developing the schedule, and controlling the schedule could be viewed as a single process
I ncorrect
On projects with small scope, defining activities, sequencing activities, estimating activity resources and durations, and developing the schedule are very
tightly linked, and are often viewed as a single process. The other choices are incorrect. [PMBOK 5th edition, Page 142]
49. Question
You are the project manager of a software project. Your team member want to make technical changes to an activity which will add more time to that activity.