Top Banner
SUPREME MANAGEMENT CONSULTANTS CHARLES COTTER 11-12 OCTOBER 2013 RANDBURG TOWERS PROJECT PERFORMANCE TRACKING, ANALYSIS AND REPORTING
38

Project performance tracking analysis and reporting

Sep 14, 2014

Download

Business

Project Performance Management - Tracking, Analysis and Reporting
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Project performance tracking analysis and reporting

SUPREME MANAGEMENT CONSULTANTS

CHARLES COTTER

11-12 OCTOBER 2013

RANDBURG TOWERS

PROJECT PERFORMANCE TRACKING, ANALYSIS AND

REPORTING

Page 2: Project performance tracking analysis and reporting

TRAINING PROGRAMME OVERVIEW

The Project Performance Framework Key Performance Indicators and Monitoring of Outcomes:

Guide to Identification and Selection Developing and Analyzing Project Performance Objectives:

Outputs and Outcomes Project Performance Benchmarking Measuring and Monitoring Project Performance Reporting & Documenting Project Performance Research Methods in Project Performance Management Establishing Baselines and Gathering Data Project Information Management Systems in Project

Performance Management

Page 3: Project performance tracking analysis and reporting

THE FUNDAMENTAL CONCEPTS

Defining Project/Project Management

Defining Performance Management

The Project Management Triple Constraint

The Project Management Life-cycle

The Performance Management process/cycle

Page 4: Project performance tracking analysis and reporting

DEFINING PROJECT/PROJECT MANAGEMENT

According to Gray & Larson (2008) a project is defined as a complex, non-routine, one-time effort limited by time, budget, resources and performance specifications designed to meet specific needs.

PMBOK (2000) define project management as the application of knowledge, skills, tools and techniques to project activities to meet project requirements.

Page 5: Project performance tracking analysis and reporting

DEFINING PERFORMANCE MANAGEMENT

Performance management can be seen as a comprehensive management system aimed at constantly improving and monitoring the performance of others.

It therefore concerns itself with improving productivity, delivering a better quality service/product and is aimed at achieving the goals of both the institution and the employee.

Page 6: Project performance tracking analysis and reporting

PROJECT MANAGEMENT TRIPLE CONSTRAINT

Page 7: Project performance tracking analysis and reporting

PROJECT MANAGEMENT LIFE- CYCLE

Page 8: Project performance tracking analysis and reporting

THE PERFORMANCE MANAGEMENT CYCLE

Page 9: Project performance tracking analysis and reporting

MODEL OF VALUE

Page 10: Project performance tracking analysis and reporting

MEASURES TO DETERMINE THE VALUE OF A PROJECT – BALANCED SCORECARD

PERSPECTIVE

Page 11: Project performance tracking analysis and reporting

PHASES OF PROJECT PERFORMANCE MONITORING AND TRACKING

• Preventative - Prior to Initiation

Project Selection Risk Management

• Concurrent – Project Implementation

Project Monitoring Information System Project Control Process Earned Value Management Control Charts

• Reactive – Post Project Evaluation

Post project metrics

Page 12: Project performance tracking analysis and reporting

PROJECT SELECTION TOOLS – NUMERIC MODELS

Financial Models:

Payback period

Return on Investment (ROI)

Net Present Value (NPV)

Internal Rate of Return (IRR)

Page 13: Project performance tracking analysis and reporting

PROJECT SELECTION TOOLS – NUMERIC MODELS

Scoring Models:

Factor model

Decision Matrix

Cost Breakeven Analysis

Page 14: Project performance tracking analysis and reporting

RISK MANAGEMENT PROCESS

Risk Identification

Risk Analysis

Risk Control

Risk Evaluation

Page 15: Project performance tracking analysis and reporting

LEARNING ACTIVITY

Syndicate Group Discussion

Complete the activity

Provide feedback

Page 16: Project performance tracking analysis and reporting

PROJECT MONITORING INFORMATION SYSTEM

Creating a Data Collection structure and process

Analysis of the data

Reporting current process

Page 17: Project performance tracking analysis and reporting

DATA COLLECTION

Data collection determined by which metrics will be used for project control

What data to collect?

How will data be collected?

Who will collect the data?

When will data be collected?

Page 18: Project performance tracking analysis and reporting

DATA ANALYSIS

Methods – electronic and/or manual

Process

Collation

Analysis

Interpretation

Verification

Page 19: Project performance tracking analysis and reporting

DATA REPORTING

Form – written or oral

Format:

Progress since last reportCurrent status of project – schedule, cost and scopeCumulative trendsProblems and issues – new variances and

resolutionsCorrective action planned

Page 20: Project performance tracking analysis and reporting

PROJECT CONTROL PROCESS

Page 21: Project performance tracking analysis and reporting

LEARNING ACTIVITY

Syndicate Group Discussion

Complete the activity

Provide feedback

Page 22: Project performance tracking analysis and reporting

DEFINING EARNED VALUE MANAGEMENT (EVM)

Earned Value Management (EVM) is a project management technique for measuring project performance and progress.

It integrates scope, cost and schedule measures to assess the performance of a project.

Based on the three measures a baseline cost and schedule is developed and actual performance is measured with regards to the baseline values. 

Page 23: Project performance tracking analysis and reporting

EARNED VALUE MANAGEMENT

Mastering the terminology:

Planned Value (PV)Earned Value (EV)Actual Cost (AC)Schedule Variance (SV)Cost Variance (CV)Schedule Performance Index (SPI)Cost Performance Index (CPI)Critical Ratio (CR)

Page 24: Project performance tracking analysis and reporting

EARNED VALUE MANAGEMENT - CONCEPTS

Budget at Completion (BAC): The original cost estimate, budget or quotation.

Planned Value (PV): This is the authorized budget allocated to the work to be accomplished for an activity. It is also known as budgeted cost of work scheduled (BCWS)

Earned Value (EV): This is the value of work performed expressed in terms of the approved budget assigned to work for an activity. It is also known as budgeted cost of work performed (BCWP). BCWP = % complete X BAC

Actual Cost (AC): This is the actual cost incurred in accomplishing the work performed for an activity. It is also known as Actual Cost of Work Performed (ACWP).

Page 25: Project performance tracking analysis and reporting

WORKED EXAMPLE

Page 26: Project performance tracking analysis and reporting

EARNED VALUE MANAGEMENT - CONCEPTS

Schedule Variance (SV): Schedule variance is calculated as SV = EV –PV

Cost Variance (CV): Cost variance is calculated as CV = EV-AC

Schedule Performance Index (SPI): This represents efficiency of the time utilized on the project. It is calculated as measure of progress achieved compared to progress planned for a project.  SPI = EV/PV

Cost Performance Index (CPI): This represents the efficiency of the resource (cost) utilized on the project. It is calculated as measure of value of work completed compared to the actual cost or progress made on the project. CPI = EV/AC

Estimate at completion (EAC) is the expected total cost of a task or project, based on performance as of the status date. EAC is also called forecast at completion, and is calculated like this: EAC = ACWP + (BAC - BCWP) / CPI.

Critical Ratio (CR): This indicator combines both the cost performance index (CPI) and schedule performance index (SPI) to represent the project status. This indicator takes care of cost and schedule trade-offs.

Page 27: Project performance tracking analysis and reporting

THE SIGNIFICANCE OF THE CRITICAL RATIO

Indicates whether project performance is stable or not over project duration.

Predicts future performance from a stable project performance.

Indicates whether project has experienced special cause variation during the project duration.

Indicates any special trend or pattern observed in project performance.

Page 29: Project performance tracking analysis and reporting

WORKED EXAMPLE

Page 30: Project performance tracking analysis and reporting

WORKED EXAMPLE

Page 31: Project performance tracking analysis and reporting

LEARNING ACTIVITY

Syndicate Group Discussion

Complete the activity

Provide feedback

Page 32: Project performance tracking analysis and reporting

LIMITATIONS OF EVM

EVM indexes are point estimates; they represent the performance of the project at a particular reporting instance. They do not provide information about project performance over a period of a time.

They do not capture the trend of project performance.

Page 33: Project performance tracking analysis and reporting

CONTROL CHARTS

Control Charts are a quality tool which displays process data over time against the process control limits. Control limits define the area three standard deviations (by default) on either side of the centerline, or mean, of data plotted on a control chart where expected variation is observed.

A control chart is used to determine whether a given process is stable (contains only common cause variation) or it is subjected to special cause variation.

Page 34: Project performance tracking analysis and reporting

BASIC COMPONENTS OF A CONTROL CHART

Centerline representing the mean value of the data points

Horizontal border lines, Upper Control Limit (UCL) and Lower Control Limit (LCL) that define the limits of common cause variations

Data points plotted over time

Page 35: Project performance tracking analysis and reporting

TYPES OF VARIATION

Common Cause Variation (or Controlled Variation): These variations are present in the process due to its inherent nature. These are predictable and expected variations.

Special Cause Variation (or Uncontrolled Variation): These variations are introduced in the process by non–random events /factors external to process. If special cause variation is present in the process then process is said to be in unstable state.

Page 36: Project performance tracking analysis and reporting

LEARNING ACTIVITY

Syndicate Group Discussion

Complete the activity

Provide feedback

Page 37: Project performance tracking analysis and reporting

POST-PROJECT EVALUATION

Perform a Post Implementation Review of the project

Close-out report

Assessment of the project against actual performance, quality of management (focusing on quality and risk management)

The lessons learnt that can be applied to future projects

Page 38: Project performance tracking analysis and reporting

CONCLUSION

Summary

Questions

Contact details:

Charles Cotter +27 84 562 9446 [email protected] Linked In Twitter: @Charles_Cotter