Page 1
On
“DRILLING AND PRODUCTION OPERATIONS”
Drilling Services, ONGC, Ankleshwar Asset
Indian School of Mines University, Dhanbad
Report Submitted By:
Md Hamid Siddique, Saumya,
Saurabh Mishra, Mohit Garg,
Praveen Kumar, Prakash Mishra
(M.Tech in Petroleum Engineering)
Page 2
Summer Training
Page 2
CERTIFICATE
This is to certify that following Students of M.tech, 1st Year, Petroleum Engineering, Indian
School of Mines, Dhanbad has successfully completed summer training and submitted
project-report titled ―DRILLING AND PRODUCTION OPERATIONS‖ at Drilling
Services, Ankleshwar Asset, ONGC.
Md Hamid Siddique, Saumya,
Saurabh Mishra, Mohit Garg,
Praveen Kumar, Prakash Mishra
(M.Tech in Petroleum Engineering)
Indian School of Mines, Dhanbad
Mr. S.K.Mandloi
Chief Engineer (D),
Drilling Services, ONGC Ankleshwar Asset.
Page 3
Summer Training
Page 3
ACKNOWLEDGEMENT
The trainee wishes to thank OIL AND NATURAL GAS CORPORATION Ltd. Ankleshwar
Asset for allowing to conduct training program at their premises and for providing all the
needful facilities required for completion of the entire program.
We would like to express our sincere gratitude towards our mentor Mr. S.K. Mandloi (SE) –
Drilling Services for his continuous guidance and for enlightening us with vital knowledge
throughout the program. Working under his guidance has been a privilege and a fruitful
learning experience. We would also like to thank Mr. Aloke Deb (CE) – Cementing Services
for his constant support and for arranging several field visits during the course of my training.
We are also thankful to Mr. M.C. Sharma, SE (D)-(DTYS); Mr. Sunder Lal, SC (Mud
Services); Mr. P.K. Gupta, CE (Cementing); Mr. S.K. Sindha, EE (Drilling); Mr. P.K.
Jog, EE (Drilling); Mr. Sanjeev Kumar, EE (drilling) in providing us with valuable
knowledge about drilling operations.
We express our deep gratitude to those who have helped and encouraged us in
various ways in carrying out this project work. We would like to extend our thanks and
would like to acknowledge the ONGC personnel for sharing their valuable knowledge with
us without which the completion of this project would have been rather impossible.
_____________________
Mr. S.K. Mandloi (SE)
Page 4
Summer Training
Page 4
INDEX
1. INTRODUCTION
2. ABOUT ANKLESHWAR ASSET
2.1 INTRODUCTION
2.2 GEOLOGY OF ANKLESHWAR
2.3 RESERVOIR PROPERTIES
2.4 BASIN INTRODUCTION
2.5 PETROLEUM SYSTEM
3. INTRODUCTION TO DRILLING
4. PRODUCTION OPERATION
5. WELL LOGGING SERVICES
6. SITE VISIT
7. CASE STUDY
REFERENCES
Page 5
Summer Training
Page 5
1 INTRODUCTION
The story of oil exploration in India began in dense jungles of Assam in the extreme
northeast corner of India. Oil was struck at Makum near Margherita in Assam in 1867
just nine years after the historical Drake well in Pennsylvania in 1859. First commercial
oil was discovered in Digboi in 1889. However, exploration and production started in a
systematic way in 1899 after the Assam Oil Company (AOC) was formed.
After India attained independence in 1947, Geological Survey of India carried out extensive
reconnaissance surveys and mapping to locate structures suitable for exploration of oil and
gas. The real thrust to petroleum exploration in country was achieved only after the setting up
of Oil and Natural Gas Commission (ONGC) in 1955. The first gas and oil pool were
discovered in Jwalamukhi (Punjab) and Cambay (Gujarat) in 1958 respectively and in the
same year Oil India Limited (OIL) was setup. The two public sectors companies, ONGC and
OIL have discovered over 260 oil and gas fields located in Assam, Bombay Offshore
Cambay, Cauvery, Krishna-Godavari, Tripura-Cachar and West Rajasthan basins.
Government of India (GOI) offered acreages for exploration in 1980, 1982 and 1986 but the
response was not encouraging. The government of India further liberalized the petroleum
exploitation and exploration policy in 1991 inviting private companies, both overseas and
indigenous, to participate in exploration in oil and gas field development activities to meet
the ever-increasing national demand for oil and gas. A more attractive policy was formulated
by the Government in 1999 and designated as the New Exploration Licensing Policy (NELP).
Since 1980, eight exploration rounds, one round for joint venture and six rounds under NELP
have been offered for global bidding. In order to introduce new technology and oil
production, the GOI offered 69 small and medium sized oil and gas fields in onshore and
offshore to private sector in 1992 and 1993. The Government of India signed Production
Sharing Contracts (PSCs) for 28 exploration blocks under Pre-NELP rounds since 1993. Out
of these 12 blocks have been relinquished / surrendered. At present, 12 exploration blocks are
under operation and 4 blocks are awaited for approval of additional exploration.
1. Under the first round of New Exploration Licensing Policy, Government of India
invited bids on 8th January 1999 for 48 blocks for exploration of oil and natural gas.
2. Under the second round of New Exploration Licensing Policy, Government of India
invited bids on 15th December 2000 for 25 blocks for exploration of oil and natural
gas.
3. Under the third round of New Exploration Licensing Policy, Government of India
invited bids on 27th March 2002 for 27 blocks for exploration of oil and natural gas.
4. Under the Fourth round of New Exploration Licensing Policy, Government of India
invited bids on 8th May 2003 for 24 blocks for exploration of oil and natural gas.
5. Under the fifth round of New Exploration Licensing Policy twenty exploration blocks
have been awarded to different consortiums/ individual company. A total of two
discoveries have been made a KG deepwater block.
Page 6
Summer Training
Page 6
6. Fifty five exploration blocks were offered under the sixth round on 23rd February,
2006, the highest offering so far under NELP, covering an area of 3.52 lakhs Sq.Km.
in order to enhance country’s energy security.
7. Fifty-seven exploration blocks were offered under the seventh round, proposed bid
closing date is 30th June.
THE ORGANIZATION
ONSHORE
ONGC has got seven producing asserts in Onshore - Ahmedabad, Mehasana,
Ankleshwar, Assam, Tripura, Rajahmundry and Cauvery Assets.
Two producing basins- Cambay and Assam Arakan Fold Belt (AAFB).
Cumulative Crude oil production- 282.114 MMT.
Cumulative Gas production- 110.27 BCM.
IOR schemes implemented in 13 major onshore fields.
OFFSHORE
Three producing Assets- Mumbai High, Neelam & Heera and Bassein & Satellite.
Joint ventures and production sharing contract for Ravva, Panna-Mukta and Tapti
fields.
Development of several Marginal Fields like- Vasai West (SB-11), Vasai East, C-
series, G-1 and GS-15 Offshore fields in East Coast, KG Basin, B-22 cluster, etc.
Oil and Gas produced from offshore processed at Uran and Hazira plant.
Cumulative Crude oil production-453.83 MMT.
Cumulative Gas production- 336.34 BCM
ONGC VIDESH LIMITED (OVL):
ONGC’s overseas arm ONGC Videsh Limited (OVL) is engaged in Exploration and
Production of Oil and Gas across the globe. It is the 2nd
largest E&P Company in India,
both In terms of oil production and oil gas reserve holdings. It has marked presence in 39
E & P projects in 17 countries; Vietnam, Sudan, Russia, Iraq, Iran, Myanmar, Libya,
Cuba, Columbia, Nigeria, Nigeria Sao Tome JDZ, Egypt, Brazil, Congo BR,
Turkmenistan, Syria, Venezuela. OVL has produced 8.80 MMT of O+OEG in 2007-08
and an investment of over 4.5 billion USD.
Page 7
Summer Training
Page 7
2 ABOUT ANKLESHWAR ASSET
2.1 Introduction:-
Field discovered in 1960.
Put on production since 1960.
Location at a distance of 15 km from Ankleshwar town.
Part of Narmada Block of Cambay basin.
Spread over an area of approx. 32.27 sq.km.
Hydrocarbon entrapment in multi-layered sandstone reservoir.
2.2 GEOLOGY OF ANKLESHWAR
Ankleshwar is the oldest on-shore oil field owned by ONGC. This field is
located at a distance of 6 km from the Ankleshwar town of Gujarat state of India. The
field is situated at Narmada – Tapti tectonic block of Cambay basin with the aerial
extent of 32 sq.km.
Geological Survey of India started exploration of oil and gas in the field as
early as 1930s. Subsequently the geologists of Oil and Natural Directorate of India
mapped the area and carried out the Gravity Magnetic survey during the year 1957-
58. Seismic survey was carried out in the year 1958-59.
An exploratory test well was released for confirming the hydrocarbon
potential and the well was drilled in the year 1960 to a depth of 1969 meters.
Large amount of oil and gas reserves have been established during subsequent
exploration and development activities in association with Russian Geoscientists. The
major oil and gas reserves are present within Hazad and Adol member of Ankleshwar
formation.
Ankleshwar field comprise of mainly three producing horizons, i.e. Lower
productive group developed in Cambay shale, middle and upper producing group
developed in Ankleshwar formation.
The upper producing horizon, called Adol member of Ankleshwar formation is located within
the Telwa and Kanwa and Cambay shale. Six important sand bodies are identified as S-6, S-
7, S-8, S-9, S-10 and S-11 in Adol member. The Hazad member is sub divided in to five
sands i.e. S-1, S-2, S-3, S-4 and S-5. There is only one sand body in lower producing
horizons, called LS-1 developed at the bottom of the Cambay shale In addition to that, there
are two gas bearing sands, i.e. Dadar sands within Tarkeshwar and Ankleshwar formation and
Miocene sands in Babaguru formation. In addition to that, there are two gas bearing sands,
i.e. Dadar sands within Tarkeshwar and Ankleshwar formation and Miocene sands in
Babaguru formation.
2.3 RESERVOIR PROPERTIES
Major formations are in the Ankleshwar formation and Cambay shale
Page 8
Summer Training
Page 8
Initial super hydrostatic pressure has presently reduced to the sub hydrostatic.
The sands S-5 and LS-1hve got good porosity and moderate permeability values.
All other sand layers are having good values of porosity and permeability.
MAIN OPERATION ACTIVITES
Exploration and exploitation of hydrocarbon to meet committed target to production
and supply.
Reservoir health management to optimize recovery.
Well servicing and minimizing non flowing wells and improving productivity.
Quality, Health, Safety and Environment (QHSE) Management.
2.4 BASIN INTRODUCTION
Geographic Location of the basin
The Cambay rift Basin, a rich Petroleum Province of India, is a narrow, elongated rift graben,
extending from Surat in the south to Sanchor in the north. In the north, the basin narrows, but
tectonically continues beyond Sanchor to pass into the Barmer Basin of Rajasthan. On the
southern side, the basin merges with the Bombay Offshore Basin in the Arabian Sea. The
basin is roughly limited by latitudes 21˚ 00' and 25˚ 00' N and longitudes 71˚ 30' and 73˚ 30'
E. (FIG: 1, Index Map)
Category of the basin
Proved
Area
The total area of the basin is about 53,500 sq. km.
Age of the Basin & Sediment-thickness
The evolution of the Cambay basin began following the extensive outpour of Deccan Basalts
(Deccan Trap) during late cretaceous covering large tracts of western and central India. It’s a
narrow half graben trending roughly NNW-SSE filled with Tertiary sedimentswithrifting due
to extensional tectonics. Seismic and drilled well data indicate a thickness of about 8 km of
Tertiary sediments resting over the Deccan volcanics.
Major Discoveries, Total Seismic coverage, 2D/3D and exploratory wells drilled
A total of 12,937 gravity and magnetic stations were measured by the ONGC in the entire
Cambay Basin. The Bouguer anomaly map has helped in identification of the major structural
highs and lows in the basin. The magnetic anomaly map also depicts the broad structural
configuration of the basin. A total of more than 30,688 LKM of conventional data has been
acquired.
The total volume of seismic reflection data acquired from the Cambay Basin is of the order of
Page 9
Summer Training
Page 9
104113 LKM (2D) and 7895 sq. km (3D). (Fig: 2, Showing Density of Seismic coverage)
In 1958, ONGC drilled its first exploratory well on Lunej structure near Cambay. This turned
out to be a discovery well, which produced oil and gas. The discovery of oil in Ankleshwar
structure in 1960 gave boost to the exploration in the Cambay Basin. More than 2318
exploratory wells have been drilled in Cambay Basin. Out of 244 prospects drilled, 97 are oil
and gas
Exploration Status
(Fig: 2 & 3 showing exploration status of N.Cambay & S.Cambay)
PEL AREAS
„P‟
ML AREA
„M‟
TOTAL AREAS
„T‟
UNEXPLORED AREAS „U‟ = T –
( P+M )
15,838.04 Sq.
KM
5,083.62 Sq.
KM 53,500 Sq. KM 32578.34 Sq. KM
bearing.
Fields of Cambay Basin
Field Date of Signing contract Area(Sq Km) Field Size
Lohar-ONGC 8.29
Cambay-ONGC 161
Umra Ext. – II 34.43
Kosamba Ext. – I 39
Kim Ext. – I 56.11
Pakhajan Ext. – II 38.50
Olpad - Dandi Ext. – I 94.40
Gandhar Ext. – IX 40.91
Kural (Ml) 83.49
Gandhar Ext. – VIII 7.23
Gandhar Ext. - VII (G#155) 25.82
Dabka Ext. - V (D#38) 2
Nada Ext. – I 6.12
Gandhar Ext. - VI (G#388) 644.47
Kim (Ml) 18.33
Dabka Ext. - IV (D#6) 1
Olpad (A) 2.75
Kosamba 19.07
Kharach 0.70
Elav 10.37
Kudara 2.60
Page 10
Summer Training
Page 10
Sanaokhurd 23.29
Motwana 42.21
Ankleshwar (Main) 38.98
Ankleshwar Ext. – I 17.43
Kasiyabet 5.06
Pakhajan Ext. – I 18
Pakhajan (Ml) 6.25
Dahej 18.52
Dahej Ext. – I 90.90
Gandhar Ext. – V 29.43
Gandhar Ext. – III 235.38
Gandhar Ext. - II (Denwa) 54.30
Gandhar 11.78
Gandhar Ext. – I 32.75
Gandhar Ext. – IV 36.75
Nada 9.85
Malpur (Ml) 1
Umera Ext. – I 9.93
Umera 8.44
Dabka Ext. – III 1.15
Dabka 21.67
Dabka Ext. – II 0.56
Dabka Ext. – I 12.85
Kathana Ext. – I 16.99
Anklav Ext. – I 61
Akholjuni 81.25
Padra Ext. – IX 21
Padra Ext. – VIII 15.68
Padra Ext. – VII 7.11
Padra Ext. – VI 83.95
Padra Ext. – V 3.58
Padra Ext. – IV 6.37
Padra Ext. – III 0.38
Padra 1.25
Padra Ext. – I 8.42
Padra Ext. – II 14.50
Kathana 16.95
Page 11
Summer Training
Page 11
Siswa 37.78
Nawagam South Ext. - III 53.71
Kadi Ext. – IV 5.28
Rupal 14.06
Nawagam South Ext. - II 43.94
Nawagam South Ext. - I 30.88
Kalol West Ml 14.53
Kalol West Ext. – I 54.25
Nawagam Ext. – III 56
South Wamaj ML 18.29
Gamij Ext. – II 116.22
Nadej Ext. – I 56.18
Gamij Ext. - III Ml 15.41
Ahemdabad Ext. – V 17.75
Nawagam Ext. – II 14.66
Kadi Ext. – III 16.07
Asmali Ml 43.26
Raipur Ext. – I 8.70
Ahemdabad Ext. – IV 10.21
Wadu Ext. – I 55.17
Mawagam Ext. I 2077.77
Nawagam Main 72.23
Nadej 90.18
Nadej East 20.92
Ahmedabad Ext. –III 34.75
Ahmedabad Ext. –II 5.98
Ahmedabad Ext. –I 17.29
Ahmedabad – Bakrol 30.16
Hirapur 87.92
Gamij Ext. –I 81.22
Gamij 39.16
Sanand Ext. –III 19.30
Sanand Ext. –II 10.37
Sanand Ext. –I 18.51
Sanand 81.36
Viraj 17.49
Wamaj 19.44
Page 12
Summer Training
Page 12
Motera Ext. –I 23.64
Motera 15.86
Motera Ext. –II 26.02
Kalol Ext. –II 15.50
Kalol Ext. –I 159.82
Kalol Main 35.84
Halisa 143.44
Limbodra Ext. –I 14.96
Limbodra 15.75
Paliyad-Kalol-Limbodra 161.48
Kalol North East 9.44
Wadu 15.41
Rajpur 6.76
Jotana – Warosan 38.05
Kadi Asjol 0.72
Chandrora 1.39
Langhnaj ML 17.90
Sanganpur ML 6.97
Langnaj – Wadasma 13.84
West Mewad (ML) 13.02
North Sobhasan Ext. -II 23
East Sobhasan 22.42
N. Sobhasan Pt. A+B 12.05
South Patan 6.99
Joksana (ML) 9.80
Jotana Ext. –II 0.87
Lanwa Ext. –I 2.15
Dedana (ML) 5.44
Chansama 2.81
Nandasan – Langnaj 61.90
Mansa 58.72
Nandasan Ext. –I 26.39
Linch 43.73
Linch Ext. –I 34.25
North Kadi 64.49
N. Kadi Ext. –I 20.42
Kadi Ext. –II 41.01
Page 13
Summer Training
Page 13
Bechraji Ext. –I 3.06
Bechraji 37.11
Santhal 19.46
Jotana 39.50
North Sobhasan Ext. –I 56.85
Linch Ext.- II 13.35
Geratpur 18.31
Sobhasan 35.89
Mehsana City Ext. –II 7.58
Mehsana City 8.85
West Sobhasan 9.60
Jotana Extn. – I 57.70
Balol 24
Lanwa 30
CB-OS/2 201.76 4
Cb-On/3 7.81 4
Cb-Onn-2000/2_Nsa/Bheema 24.25 4
CB-ONN-2000/1 01/01/1900 14.10 4
Palej-Pramoda(CB-ON/7) 01/01/1900 3.54 4
Bheema(CB-ONN-2002/2) 01/01/1900 4.03 3
NS-A(CB-ONN-2002/2) 01/01/1900 20.22 4
CB-X 01/01/1900 33.30 3
Gauri(CB-OS/2) 01/01/1900 80.70 3
lakshmi(CB-OS/2) 01/01/1900 121.06 3
Modhera 23/02/2001 12.70 1
Ognaj 16/02/2004 13.65 1
Karjisan 16/02/2004 5 1
N.Balol 23/02/2001 27.30 1
Baola 05/04/1995 4 1
Lohar 13/03/1995 5 1
Bakrol 13/03/1995 36 1
Indrora 13/03/1995 130 1
Wavel 20/02/1995 9 1
Dholka 20/02/1995 48 1
Sabarmati 23/09/1994 6 1
Matar 01/01/1900 0 1
Cambay 23/09/1994 161 1
Page 14
Summer Training
Page 14
Bhandut 23/09/1994 6 1
Hazira 23/09/1994 50 1
Asjol 03/02/1995 15 1
Sanganpur 23/02/2001 4 1
Unawa 23/02/2001 6 1
Kanawara 23/02/2001 6.30 1
Allora 23/02/2001 6.85 1
North Kathana 23/02/2001 12.20 1
Dholasan 23/02/2001 8.80 1
Tectonic History
Type of Basin Intracratonic rift graben.
Different Tectonic Zones with in the Basin The Cambay rift valley is bounded by well demarcated basin margin step faults. Based on the
cross trends the basin has been divided into five tectonic blocks. From north to south, the
blocks are:
Sanchor – Tharad
Mehsana – Ahmedabad
Cambay – Tarapur
Jambusar – Broach and
Narmada Block.(FIG 4: Tectonic Map of the Basin)
2.5 Petroleum System
Source Rock Thick Cambay Shale has been the main hydrocarbon source rock in the Cambay Basin. In the
northern part of the Ahmedabad-Mehsana Block, coal, which is well developed within the
deltaic sequence in Kalol, Sobhasan and Mehsana fields, is also inferred to be an important
hydrocarbon source rock. The total organic carbon and maturation studies suggest that shales
of the Ankleshwar/Kalol formations also are organically rich, thermally mature and have
generated oil and gas in commercial quantities. The same is true for the Tarapur Shale. Shales
within the Miocene section in the Broach depression might have also acted as source rocks.
Reservoir Rock There are a number of the reservoirs within the trapwacke sequence of the Olpad Formation.
These consist of sand size basalt fragments. Besides this, localized sandstone reservoirs
within the Cambay Shale as in the Unawa, Linch, Mandhali, Mehsana, Sobhasan, fields, etc
are also present.
Trap Rock The most significant factor that controlled the accumulation of hydrocarbons in the Olpad
Formation is the favorable lithological change with structural support and short distance
migration. The lithological heterogeneity gave rise to permeability barriers, which facilitated
Page 15
Summer Training
Page 15
entrapment of hydrocarbons. The associated unconformity also helped in the development of
secondary porosity.
Transgressive shales within deltaic sequences provided a good cap rock. (Fig 6: Generalized
Tectono Stratigraphy Map Showing Source rock, Reservoir Rock, and Oil and Gas
Occurrences.)
Timing of migration & Trap formation: The peak of oil generation and migration is
understood to have taken place during Early to Middle Miocene.
Petroleum Plays
Structural Highs and fault closures & Stratigraphic traps (pinchouts / wedgeouts, lenticular
sands, oolitic sands, weathered trap) in Paleocene to Miocene sequences have been proved as
important plays of Cambay Basin.
Paleocene – Early Eocene Play :
Formations : Olpad Formation/ Lower Cambay Shale.
Reservoir Rocks : Sand size basalt fragments & localized sandstone. Unconformities
within the Cambay Shale and between the Olpad Formation and the Cambay Shale
have played a positive role in the generation of secondary porosities. The Olpad
Formation is characterised by the development of piedmont deposits against fault
scarps and fan delta complexes.
Middle Eocene Play:
Formations: Upper Tharad Formation
Reservoir Rocks: In Southern part, Hazad delta sands of Mid to Late Eocene & in the
Northern part the deltaic sequence is made up of alternations of sandstone and shale
associated with coal. Plays are also developed in many paleo-delta sequences of
Middle Eocene both in northern and southern Cambay In the Northern Cambay Basin,
two delta systems have been recognised.
Late Eocene – Oligocene Play:
Formations : Trapur Shale, Dadhar Formation.
Reservoir Rocks : This sequence is observed to possess good reservoir facies in the
entire Gulf of Cambay. North of the Mahi river, a thick deltaic sequence, developed
during Oligo–Miocene, has prograded upto south Tapti area.
Miocene Play:
Formations: Deodar: Formation (LR. Miocene), Dhima Formation (Mid Miocene),
Antrol Formation (UP. Miocene) The Mahi River delta sequence extends further
westward to Cambay area where Miocene rocks are hydrocarbon bearing.
Page 16
Summer Training
Page 16
SST of Ankleshwar Asset has been divided into 6 groups:
Area
Drilling & Monitoring Group
Work Over Monitoring
Specialist Pool
Reservoir Data Acquisition Group (RDAG)
Figure 2.1: Hydrocarbon bearing fields of Ankleshwar Asset, South Cambay Basin
TOTAL WELLS DRILLED : 604
OIL WELLS : 218
GAS WELLS : 58
INJ WELLS : 118
EFF. DISP. WELLS : 4
ABND : 86
To Be ABND : 3
OFF INJ : 4
OBS/FU : 113
Page 17
Summer Training
Page 17
3. INTRODUCTION TO DRILLNG
The Rotary Drilling method is comparatively new, having first been practiced
by Leschot, a French civil engineer, in 1863. United States patents on rotary equipment were
issued as early as 1866 but, as was the case with cable tools, the early application was for
Water Well Drilling. It was not until approximately 1900 that two water well drilling
contractors, M.C. and C.E. Baker, moved their rotary equipment from South Dakota to
Corsicana, Texas where it found use in the soft rock drilling of that area. In Texas in 1901,
Captain Lucas drilled the Spindle top discovery well with rotary tools. This spectacular
discovery is credited with initiating both the Southwest’s oil industry and the widespread use
of the rotary method. The inherent advantages of this method in the soft rock areas of Texas
and California insured its acceptance, and it was in general use by the early 1920’s.
In this Method, the hole is drilled by a rotating bit to which a downward force
is applied. The bit is fastened to, and rotated by, a drill string, composed of high quality drill
pipe and drill collars, with new sections or joints being added as drilling progresses. The
cuttings are lifted from the hole by the drilling fluid which is continuously circulated down
the inside of the drill string through water courses or nozzles in the bit. And upward in the
annular space between the drill pipe and bore hole. At the Surface, the returning fluid (Mud)
is diverted through a series of tanks or pits which afford a sufficient quiescent period to allow
cutting separation and any interesting treating. In the last of these pits the mud is picked up
by the pump suction and repeats the cycle.
DRILLING RIG SPECIFICATION
ONSHORE
BY POWER USED:
Mechanical — the rig uses torque converters, clutches, and transmissions powered by
its own engines, often diesel
Electric — the major items of machinery are driven by electric motors, usually with
power generated on-site using internal combustion engines
Hydraulic — the rig primarily uses hydraulic power
Pneumatic — the rig is primarily powered by pressurized air
Steam — the rig uses steam-powered engines and pumps (obsolete after middle of
20th Century)
BY PIPE USED:
Cable — a cable is used to raise and drop the drill bit
Conventional — uses metal or plastic drill pipe of varying types
Coil tubing — uses a giant coil of tube and a downhole drilling motor
BY POSITION OF DERRICK:
Conventional — derrick is vertical
Page 18
Summer Training
Page 18
Slant — derrick is slanted at a 45 degree angle to facilitate horizontal drilling
Figure 3.1 Offshore
1, 2) conventional fixed platforms; 3) compliant tower; 4, 5) vertically moored tension leg
and mini-tension leg platform; 6) Spar ; 7,8) Semi-submersibles ; 9) Floating production,
storage, and offloading facility; 10) sub-sea completion and tie-back to host facility
BASIC DRILLING RIG AND COMPONENTS
Rotary drilling equipment is complex and any detailed discussion would of necessity involve
intricate mechanical design problems. The basic rig components in following order:
1-Derricks, masts, and substructures
2-Drawworks
3-Mud pumps
4-Prime movers
5-Drill string
6-Bits
7-Drilling line
8-Miscellanious and auxiliary equipments
Page 19
Summer Training
Page 19
Figure 3.2: A complete Drilling site
1. Crown Block 2. Catline Boom and Hoist Line
3. Drilling Line 4. Monkeyboard
5. Traveling Block 6. Top Drive
7. Mast 8. Drill Pipe
9. Doghouse 10. BOPs
11. Water Tank 12. Electric Cable Tray
13. Engine Generator Sets 14. Fuel Tank
15. Electrical Control House 16. Mud Pumps
17. Bulk Mud Component Tanks 18. Mud Tanks (Pits)
19. Waste Pit 20. Mud-Gas Separator
21. Shale Shakers 22. Choke Manifold
23. Pipe Ramp 24. Pipe Racks
Page 20
Summer Training
Page 20
HOISTING COMPONENTS:-the function of hoistig system is to provide a means of
lowering and raising drill stirings, casing strings and other surface equipment in to or out of
the hole. The principle components of the hoisting system are
1-the derrick and substructure 2- block and tackle ,3-drawworks.two routine drilling
operations performed with the hoisting system are called (1)- making a connection and (2)-
making a trip.
Derrick and portable mast:-the function of deriick is to provide vertical hight required to raise
sections of pipe from or lower them in to hole. Greater the hight , the longer the section of
pipe that can be handeled and thus, the faster a long string of pipe can be inserted and
removed from the hole.
Figure 3.3: Block and tackle system
BLOCK AND TACKLE:-
The block and tackle comprised of (1) the crown block (2) Trevelling block and (3) Drilling
line .The principal function of block and tackle is to provide a Mechanical advantage.
DRAWWORKS:-
The drawworks provide the hoisting and braking power required to raise or lower the heavy
string of pipe.the principal parts of drawworks are (1) the drum (2) the brakes (3) the
transmission and (4) the catheads.
Page 21
Summer Training
Page 21
Figure 3.4: Drawworks
TREVELLING BLOCK:-
A trevlling block is the freely moving section of a block and tackle that contains a set of
pulleys or sheaves through which the drill line (wire rope) is threaded or reeved and is
opposite (and under) the crown block (the stationary section). The set of sheaves that move
up and down in the derrick.
Figure 3.5 Travelling Block
Page 22
Summer Training
Page 22
CROWN BLOCK:- a crown block is the stationary section of block and tackle. The fixed set
of pulleys (called sheaves) located at the top of the derrick or mast, over which the drilling
line is threaded.
Figure 3.6: Crown Block
HOOK: - The high-capacity J-shaped equipment used to hang various other equipment,
particularly the swivel and kelly, the elevator bails or topdrive units. The hook is attached to
the bottom of the traveling block and provides a way to pick up heavy loads with the
traveling block. The hook is either locked (the normal condition) or free to rotate, so that it
may be mated or decoupled with items positioned around the rig floor, not limited to a single
direction.
Page 23
Summer Training
Page 23
Figure 3.6 Hook and Swivel
DRILLING LINE:-
In a drilling rig, the drill line is a multi-thread, twisted wire rope that is threaded
or reeved through the traveling block and crown blockto facilitate the lowering and lifting of
the drill string into and out of the wellbore.
Figure 3.7 Drilling Line
Page 24
Summer Training
Page 24
ROTATING EQUIPMENT
ROTARY TABLE: - The revolving or spinning section of the drillfloor that provides power
to turn the drillstring in a clockwise direction. The rotary motion and power are transmitted
through the kelly bushing and the kelly to the drillstring. Almost all rigs today have a rotary
table, either as primary or backup system for rotating the drillstring.
Topdrive technology, which allows continuous rotation of the drillstring, has replaced the
rotary table in certain operations. A few rigs are being built today with topdrive systems only,
and lack the traditional kelly system.
Figure 3.8 Rotary table
KELLY: - The Kelly is the first section of pipe below the swivel.the out side cross section of
the Kelly is square or hexagonal to permit to be gripped easily for turning. Torque is
transmitted to the Kelly through Kelly bushings, which fit inside the master bushing of rotary
table .the Kelly must be kept straight as possible. Rotation of a crooked Kelly causes a
whipping motion that results in unnecessary wear on crown block, drilling line, swivel and
threaded connections through out a large part of drill string.
Page 25
Summer Training
Page 25
Figure 3.9: Kelly bushing
KELLY BUSHINGS: - An adapter that serves to connect the rotary table to the kelly. The
kelly bushing has an inside diameter profile that matches that of the kelly, usually square or
hexagonal. It is connected to the rotary table by four large steel pins that fit into mating holes
in the rotary table. The rotary motion from the rotary table is transmitted to the bushing
through the pins, and then to the kelly itself through the square or hexagonal flat surfaces
between the kelly and the kelly bushing. The kelly then turns the entire drillstring because it
is screwed into the top of the drillstring itself. Depth measurements are commonly referenced
to the KB, such as 8327 ft KB, meaning 8327 feet below the kelly bushing.
Figure 3.10 Components
Page 26
Summer Training
Page 26
TOP DRIVE: - A device that turns the drillstring. This is radically different from the more
conventional rotary table and kelly method of turning the drillstring because it enables
drilling to be done with three joint stands instead of single joints of pipe. It also enables the
driller to quickly engage the pumps or the rotary while tripping pipe, which cannot be done
easily with the kelly system. While not a panacea, modern topdrives are a major improvement
to drilling rig technology and are a large contributor to the ability to drill more difficult
extended-reach wellbores. In addition, the topdrive enables drillers to minimize both
frequency and cost per incident of stuck pipe.
SWIVEL: - Swivel supports the weight of the drill string and permits rotation. the bail of the
swivel is attached to the hook of the travelling block, and the gooseneck of the swivel
provides a downword-pointing connection for the rotary hose. Swivels are rated according to
their load capacities.
Figure 3.11 Swivel
Page 27
Summer Training
Page 27
KELLY HOSE:- A Kelly hose (also known as a mud hose or rotary hose) is a flexible, steel
reinforced, high pressure hose that connects the standpipe to the kelly (or more specifically to
the goose-neck on the swivel above the kelly) and allows free vertical movement of
the kelly while facilitating the flow of drilling fluid through the system and down the drill
string.
Figure 3.12 Kelly hose
MUD CIRCULATING SYSTEM:-
A major function of the fluid circulating system is to remove the rock cuttings from the hole
as drilling progresses. the principal components of the rig circulating system include (1) mud
pumps (2) mud pits (3) mud-mixing equipments (4) contaminant-removal equipments.
MUD PUMPS: - A mud pump is a reciprocating piston/plunger device designed to
circulate drilling fluid under high pressure (up to 7,500 psi (52,000 kPa)) down the
drillstring and back up the annulus. Mud pumps come in a variety of sizes and configurations
but for the typical petroleum drilling rig, the triplex (three piston/plunger) mud pump is the
pump of choice. Duplex mud pumps (two piston/plungers) have generally been replaced by
the triplex pump, but are still common in developing countries. Two later developments are
the hex pump with six vertical pistons/plungers, and various quintuplex's with five horizontal
piston/plungers. The advantages that these new pumps have over convention triplex pumps is
a lower mud noise which assists with better MWD and LWD retrieval.
Page 28
Summer Training
Page 28
Figure 2.13 Mud Pump
SHALE SHAKER:- Shale shakers typically consist of large, flat sheets of wire mesh screens
or sieves of various mesh sizes that shake or vibrate the drill cuttings, commonly shale across
and off of the screens as the drilling fluid (mud) flows through them and back into the drilling
fluid system. This separates the solid drill cuttings from the fluid so that it can be recirculated
back down the wellbore.
Figure 3.14 Shale shaker
Page 29
Summer Training
Page 29
DESANDER: - A hydrocyclone device that removes large drill solids from the whole mud
system. The desander should be located downstream of the shale shakers and degassers, but
before the desilters or mud cleaners.Various size desander and desilter cones are functionally
identical, with the size of the cone determining the size of particles the device removes from
the mud system.
DESILTRER:
A hydrocyclone much like a desander except that its design incorporates a greater number of
smaller cones. As with the desander, its purpose is to remove unwanted solids from the mud
system. The smaller cones allow the desilter to efficiently remove smaller diameter drill
solids than a desander does. For that reason, the desilter is located downstream from the
desander in the surface mud system.
MUD PIT: - A large tank that holds drilling fluid on the rig or at a mud-mixing plant. For
land rigs, most mud pits are rectangular steel construction, with partitions that hold about 200
barrels each. They are set in series for the active mud system. On most offshore rigs, pits are
constructed into the drilling vessel and are larger, holding up to 1000 barrels. Circular pits are
used at mixing plants and on some drilling rigs to improve mixing efficiency and reduce dead
spots that allow settling. Earthen mud pits were the earliest type of mud pit, but
environmental protection concernhas led to less frequent use of open pits in the ground.
Today, earthen pits are used only to store used or waste mud and cuttings prior to disposal
and remediation of the site of the pit.
DRILL PIPE AND BHA
Page 30
Summer Training
Page 30
ROTARY DRILL BIT:- Rotary drilling bits usually are classified according to their design as
”Fixed cutter bits(Drag bits)” and ‖Tri Conical Roller”.
Fixed Cutter Bits:
PDC(Polycrystalline Diamond Compact) bit:
A drilling tool that uses polycrystalline diamond compact (PDC) cutters to shear rock with a
continuous scraping motion. These cutters are synthetic diamond disks about 1/8-in. thick and
about
1/2 to 1 in. in diameter. PDC bits are effective at drilling shale formations, especially when
used in combination with oil-base muds.
Figure 3.15: Tri Conical Roller Bits (TCR Bits):
A tool designed to crush rock efficiently while incurring a minimal amount of wear on the
cutting surfaces. As the drillstring is rotated, the bit cones roll along the bottom of the hole in
a circle. As they roll, new teeth come in contact with the bottom of the hole, crushing the
rock immediately below and around the bit tooth. As the cone rolls, the tooth then lifts off the
bottom of the hole and a high-velocity fluid jet strikes the crushed rock chips to remove them
from the bottom of the hole and up the annulus.
MILLED TOOTH BITS [For Soft Formations] CARBON INSERT BITS [For Hard
Formations]
Page 31
Summer Training
Page 31
Figure 3.16 TCR bit
DRILL PIPE:
Drill pipe is a tubular steel conduit fitted with special threaded ends called tool joints. The
drillpipe connects the rig surface equipment with the bottomhole assembly and the bit, both
to pump drilling fluid to the bit and to be able to raise, lower and rotate the bottomhole
assembly and bit.
Figure 3.17: Drill pipe
BOTTOM HOLE ASSEMBLY (BHA):
The lower portion of the drillstring, consisting of (from the bottom up in a vertical well) the
bit, bit sub, a mud motor (in certain cases), stabilizers, drill collars, heavy-weight drillpipe,
jarring devices ("jars") and crossovers for various threadforms. Oftentimes the assembly
includes a mud motor, directional drilling and measuring equipment, measurements-while-
drillingtools, logging-while-drilling tools and other specialized devices.
A simple BHA consisting of a bit, various crossovers, and drill collars may be relatively
inexpensive (less than $100,000 US in 1999), while a complex one may cost ten or more
times that amount.
SAFETY EQUIPMENT
BLOW OUT PREVENTERS: - A blowout is an uncontrolled flow of gas, oil, or water from a
well. A blowout frequently sends debris flying through the air and catches the well on fire or
Page 32
Summer Training
Page 32
both. And this kind of situation is very dangerous to anyone working on the well. Blowouts
can occur before casing is set or long after drilling, when the well is being serviced or
repaired.
Blowout preventers shut off a well white it is being drilled or serviced and allow the well to
be closed in with or without pipe in the hole. A well with a beam pumping unit always has a
blowout preventer that closes the space around the polished rod. Whenever crew members
pull tubing, they install blowout preventers on the wellhead.
Figure 3.18: PIPE RAM BOP & ANNULAR TYPE BOP
BOPs come in two basic types, RAM and ANNULAR. Both are often used together in
drilling rig.
RAM TYPE BOP is similar in operation to a gate valve, but uses a pair of opposing steel
plungers, rams. The rams extend toward the centre of the wellbore to restrict flow or retract
open in order to permit flow. The inner and top faces of the rams are fitted with packers
(elastomeric seals) that press against each other, against the wellbore, and around tubing
running through the wellbore. Outlets at the sides of the BOP housing (body) are used for
connection to choke and kill lines or valves.
Rams, or ram blocks, are of four common types:
Pipe Ram
Blind Ram
Shear ram
Blind shear Ram
Page 33
Summer Training
Page 33
Pipe Rams close around a drill pipe, restricting flow in the annulus (ring-shaped space
between concentric objects) between the outside of the drill pipe and the wellbore, but do not
obstruct flow within the drill pipe. Variable-bore pipe rams can accommodate tubing in a
wider range of outside diameters than standard pipe rams, but typically with some loss of
pressure capacity and longevity.
Blind Rams (also known as sealing rams), which have no openings for tubing, can close off
the well when the well does not contain a drill string or other tubing, and seal it.
Shear Rams cut through the drill string or casing with hardened steel shears.
Blind Shear Rams (also known as shear seal rams, or sealing shear rams) are intended to
seal a wellbore, even when the bore is occupied by a drill string, by cutting through the drill
string as the rams close off the well. The upper portion of the severed drill string is freed
from the ram, while the lower portion may be crimped and the ―fish tail‖ captured to hang the
drill string off the BOP.
In addition to the standard ram functions, Variable-Bore Pipe Rams are frequently used as
test rams in a modified blowout preventer device known as a stack test valve. Stack test
valves are positioned at the bottom of a BOP stack and resist downward pressure (unlike
BOPs, which resist upward pressures). By closing the test ram and a BOP ram about the drill
string and pressurizing the annulus, the BOP is pressure-tested for proper function.
Shear-Type Ram BOPs require the greatest closing force in order to cut through tubing
occupying the wellbore. Boosters (auxiliary hydraulic actuators) are frequently mounted to
the outer ends of a BOP’s hydraulic actuators to provide additional shearing force for shear
rams.
Technological development of ram BOPs has been directed towards deeper and higher
pressure wells, greater reliability, reduced maintenance, facilitated replacement of
components, facilitated ROV intervention, reduced hydraulic fluid consumption, and
improved connectors, packers, seals, locks and ram.
DERRICK:
The structure used to support the crown blocks and the drillstring of a drilling rig. Derricks
are usually pyramidal in shape, and offer a good strength-to-weight ratio. If the derrick design
does not allow it to be moved easily in one piece, special ironworkers must assemble them
piece by piece, and in some cases disassemble them if they are to be moved.
Page 34
Summer Training
Page 34
Figure 3.19: Derrick
DRILL PIPE, DRILL COLLAR AND CASING SLIPS:
A device used to grip the drillstring in a relatively nondamaging manner and suspend it in the
rotary table. This device consists of three or more steel wedges that are hinged together,
forming a near circle around the drillpipe. On the drillpipe side (inside surface), the slips are
fitted with replaceable, hardened tool steel teeth that embed slightly into the side of the pipe.
The outsides of the slips are tapered to match the taper of the rotary table.
Figure 3.20: Casing and pipe slips
Page 35
Summer Training
Page 35
TONG:
The large wrenches used for turning when making up or breaking out drill pipe, casing,
tubing, or other pipe; variously called casing tongs, rotary tongs, and so forth according to the
specific use. Power tongs are pneumatically or hydraulically operated tools that spin the pipe
up and, in some instances, apply the final makeup torque.
Figure 3.21: Tong
CHEMISTRY
ROLL OF CHEMISTRY IN DRILLING: - (1) Drilling (2) Laboratory
DRILLING:-
(1) Drilling fluid ( mud)
(2) Classification of Drilling fluid
(3) Drilling fluid preparation
(4) Functions of drilling fluid
(5) Parameters of drilling fluid
(6) Drilling fluid used in Sub Asset Cambay
Definition of drilling fluid
API DEFINITION:
―A Circulating Fluid Used In Rotary Drilling To Perform Any Or All Of The Various
Functions Required In A Drilling Operation.‖
Page 36
Summer Training
Page 36
Preparation of drilling fluid:
7.5% Bentonite suspension - 7.5% Bentonite powder in basic water for 6-8 hrs while keeping
the agitators off.
Functions of Drilling Fluid:
Transport drilled cuttings to the surface and hole cleaning
Viscosity
Density
Annular viscosity
Cutting size and shape
Drill string rotation etc
Control subsurface pressure
Help suspend the weight of the drill string and casing
Help suspend the weight of the drill string and casing
Deliver hydraulic energy upon the formation beneath bit
Provide suitable medium for wire line logs
Seal permeable formation
Improves wellbore stability and prevents a number of drilling and production
problems.
Control corrosion.
Direct Indicating Viscometer:
Apparent Viscosity:
The apparent viscosity in centipoises equals the 600 rpm reading divided by 2
[A.V. = 600/2 IN CENTIPOISE]
Plastic Viscosity:
Friction force between two particles known as plastic viscosity Reading At 600 Rpm –
Reading At 300 Rpm
[P.V. = 600 – 300 IN CENTIPOISE]
Yield Point:
300 Rpm Reading – Plastic Viscosity
[Y.P. = 300 – PV in Lb/100 Sq.Ft.]
Plastic Viscosity (PV):
Drilling Muds are usually composed of a continuous fluid phase in which solids are
dispersed. Plastic viscosity is that part of the resistance to flow caused by mechanical friction.
The friction is caused by:
Solids concentration,
Size and shape of solids,
Viscosity of the fluid phase.
Page 37
Summer Training
Page 37
Yield Point (YP):
The yield point is the initial resistance to flow caused by electrochemical forces between the
particles. This electrochemical force is due to charges on the surface of the particles dispersed
in the fluid phase. Yield point is a measure of these forces under flow conditions and is
dependent upon:
The surface properties of the mud solids,
The volume concentration of the solids and
Ionic environment of the liquid surrounding the solids.
Thixotropy can be estimated by observing the change in strength taking place in a gel as a
function of time.
GEL10 /GEL0 should not be more than 2.
Excessive gel strengths can cause:
Swabbing, when pipe is pulled,
Surging, when pipe is lowered,
Difficulty in getting logging tools to bottom,
Retaining of entrapped air or gas in the mud, and
Retaining of sand and cuttings while drilling.
Gel strengths and yield point are both a measure of the attractive forces in a mud system. A
decrease in one usually results in a decrease in the other; therefore, similar chemical
treatments are used to modify them both.
Classification of Drilling Fluid
Water Based - for higher reservoir pressures and non-hydratable shales
Oil Based - to drill hydratable shales
Gas Based - for depleting reservoir pressures and chemical precipitation.
Water Based Mud
CL-CLS System
Weighing agent- Barite
Viscosifier - CMC, XC polymer, Bentonite, HEC
Thinner- CLS, Water.
Shale stabilizer- Sulphonated Asphalt
Alkali- NaoH
Lost Circulation Material- Mica flakes.CaCO3
Ca and cement contamination- Soda Ash
Page 38
Summer Training
Page 38
Water Treatment
The following chemicals are used to treat the separated water:
Alum-Flocculating agent
Sodium Sulphite-Oxygen scavenger
Bactericide aldehyde
Bactericide amine
HEDP-Descaling agent
SAFETY ASPECTS IN DRILLING RIG:-
Dos & Don’ts in Drilling Rig:
-Use proper handling tools. Tools should be in good working condition.
-Wear proper Personal Protective Equipment (PPE) & safety kits while working.
- Keep the derrick area clean.
Safety line of crown block should invariably be fitted & be in working condition.
Always provide complete B.O.P assembly.
Always check drill-o-meter before starting operation for to be in working condition.
Provide guards on all moving/ rotating parts of equipments.
Do ensure the use of flame proof light on the derrick of the rig.
Test B.O.P before starting the operation.
Casing line, brakes, hydraulic & pneumatic system should be in good working
condition.
Keep the working place clean and free of oil/mud/water etc.
Anchor flow lines properly.
Provide railings on derrick & engine floor.
Fit all guy ropes properly with U-clamps as per specification of rope size used.
Provide all ladders with side railings.
Always provide pressure gauge at Mud Pump discharge line, B.O.P
Accumulator, compressor tank, and hydraulic system of the rig.
Always keep B.O.P control unit at a safer distance readily accessible.
Do organize mock drill at least once in a month & operate fire fighting equipment
during the drill.
Do ensure that all the engines at well site should have spark arrester in their exhaust
pipe.
Do keep first aid medicines and stretches at well site and all the crew members are
trained in first aid.
Use waste bins for waste disposal
Page 39
Summer Training
Page 39
4 PRODUCTION OPERATIONS
4.1 Introduction to oil production
Oil has been used for lighting purposes for many thousand years. In areas where Oil is found
in shallow reservoirs, seeps of Crude Oil or Gas may naturally develop, and some Oil could
simply be collected from seepage or tar ponds. Historically, we know of tales of eternal fires
where Oil and Gas seeps would ignite and burn. One example1000 B.C. is the site where the
famous oracle of Delphi would be built, and 500 B.C .Chinese were using natural gas to boil
water. But it was not until 1859 that "Colonel" Edwin Drake drilled the first successful Oil
well, for the sole purpose of finding Oil. The Drake Well was located in the middle of quiet
farm country in north-western Pennsylvania, and began the international search for and
industrial use of Petroleum.
These wells were shallow by modern standards,
often less than 50 meters, but could give quite
large production. In the picture from the Tarr
Farm, Oil Creek Valley, the Phillips well on the
right was flowing initially at 4000 barrels per
day in October1861, and the Woodford well
came in at 1500 barrels per day in July,1862.
The Oil was collected in the wooden tank in the
foreground. Note the many different sized
barrels in the background. At this time, barrel
size was not yet standardized, which made terms like "Oil is selling at $5 per barrel" very
confusing (today a barrel is 159 liters. But even in those days, overproduction was an issue
to be avoided.
When the ―Empire well‖ was completed in September 1861, it gave 3,000 barrels per day,
flooding the market, and the price of oil plummeted to 10 cents a barrel. Soon, oil had
replaced most other fuels for mobile use.
The automobile industry developed at the end of the 19th century, and quickly adopted the
fuel. Gasoline engines were essential for designing successful aircraft. Ships driven by oil
could move up to twice as fast as their coal fired counterparts, a vital military advantage.
Gas was burned off or left in the ground. Despite attempts at gas transportation as far back as
1821, it was not until after the World War II that welding techniques, pipe rolling, and
metallurgical advances allowed for the construction of reliable long distance pipelines,
resulting in a natural gas industry boom. At the same time the petrochemical industry with its
new plastic materials quickly increased production. Even now gas production is gaining
market share as LNG provides an economical way of transporting the gas from even to
remotest sites.
With Oil prices of 50 dollars per barrel or more, even more difficult to access sources become
economically interesting. Such sources include tar sands in Venezuela and Canada as well as
oil shale’s. Synthetic diesel (syndiesel) from natural gas and biological sources (biodiesel,
ethanol) has also become commercially viable. These sources may eventually more than
triple the potential reserves of hydrocarbon fuels.
Page 40
Summer Training
Page 40
4.2. Process Overview
The following figure gives a simplified overview of the typical Oil and Gas
Production process
Fig 4.1 Facilities
Page 41
Summer Training
Page 41
Figure 4.2 Offshore Platforms
Page 42
Summer Training
Page 42
4.3 ONSHORE
Onshore production is economically viable from a few tens of barrels a day upwards. Oil and
Gas is produced from several million wells world-wide. In particular, a Gas Gathering
network can become very large, with production from hundreds of wells, several hundred
kilometers/miles apart, feeding through a gathering network into a Processing Plant.
The picture shows a well equipped
with a sucker rod pump (donkey
pump) often associated with Onshore
Oil production (Ankleshwar Asset has
several wells). However, as we shall
see later, there are many other ways of
extracting oil from an on-free flowing
well For the smallest reservoirs, oil is
simply collected in a holding tank and
collected at regular intervals by tanker
truck or railcar to be processed at a
refinery. But Onshore Wells in Oil rich
areas are also high capacity wells with
thousands of barrels per day,
connected to a 1.000.000 barrel a day
Figure 4.3 Sucker Rod Pump
gas oil separation plant(GOSP) ONGC Mumbai high is one such location. Product is sent
from the plant by pipeline or tankers to BPCL, HPCL, IOC Refineries in India.
4.4 Offshore
Offshore, depending on size and water depth, a whole range of different structures are used.
In the last few years, we have seen pure sea
bottom installations with multiphase piping to
shore and no offshore topside structure at all.
Replacing outlying wellhead towers, deviation
drilling is used to reach different parts of the
reservoir from a few wellhead cluster locations.
All such Installations are available in Offshore
Mumbai High, Krishna Godavari Basins.
Gravity Base: Enormous concrete fixed
structures placed on the bottom, typically with oil
storage cells in the ―skirt‖ that rests on the sea
bottom. The large deck receives all parts of the
Figure 4.4 Concrete fixed structure
Page 43
Summer Training
Page 43
process and utilities in large modules. Typical for 80s and 90s large fields in 100 to 500 water
depth. The concrete was poured at an at shore location, with enough air in the storage cells to
keep the structure floating until two out and lowering on to the seabed. The picture shows the
world’s largest GBS platform, the Troll A during construction.
Compliant towers are much like fixed platforms. They consist of a narrow tower, attached to
a foundation on the seafloor and extending up to the platform. This tower is flexible, as
opposed to the relatively rigid legs of a fixed platform. This flexibility allows it to operate in
much deeper water, as it can 'absorb' much of the pressure exerted on it by the wind and sea.
Compliant towers are used between 500 and 1000 meters water depth.
Floating production, where all top side systems are located on a floating structure with dry or
subsea wells. Some floaters are:
FPSO: Floating Production, Storage and Offloading. Typically a tanker type hull or barge
with wellheads on a turret that the ship can
rotate freely around (to point into wind, waves
or current). The turret has wire rope and chain
connections to several anchors (position
mooring - POSMOR), or it can be
dynamically positioned using thrusters
(dynamic positioning – DYNPOS). Water
depths 200 to 2000 meters. Common with
subsea wells. The main process is placed on
the deck, while the hullis used for storage and
offloading to a shuttle tanker. May also be
used with pipeline transport.
Figure 4.5 FPSO
SPAR: The SPAR consists of a single tall floating cylinder hull, supporting a fixed deck. The
cylinder however does not extend all the way to the seafloor, but instead is tethered to the
bottom by a series of cables and lines. The large cylinder serves to stabilize the platform in
the water, and allows for movement to absorb the force of potentiall hurricanes. Spars can be
quite large and are used for water depths from 300 and up to 3000 meters. SPAR is not an
acronym, but refers to its likeness with a ship’s spar. Spars can support dry completion wells,
but is more often used with subsea wells.
Page 44
Summer Training
Page 44
Figure 4.6 SPAR
Subsea production systems EA, EB, EC, &ED in Mumbai High are wells located on the
sea floor, as opposed to at the surface. Like in a floating production system, the
petroleum is extracted at the seafloor, and then can be 'tied-back' to an already existing
production platform or even an onshore facility, limited by horizontal distance or
“offset”. The well is drilled by a moveable rig and the extracted oil and natural gas is
transported by undersea pipeline and riser to a processing facility. This allows one
strategically placed production platform to service many wells over a reasonably large
area. Subsea systems are typically in use at depths of 7,000 feet or more, and do not
have the ability to drill, only to extract and transport. Drilling and completion is
performed from a surface rig. Horizontal offsets up to 250 kilometers, 150 miles are
currently possible.
Figure 4.7 Main Process Sections
4.5 Wellheads
The wellhead sits on top of the actual Oil or Gas well leading down to the reservoir. A
wellhead may also be an injection well, used to inject water or gas back into the
reservoir to maintain pressure and levels to maximize production. Once a natural gas or
oil well is drilled, and it has been verified that commercially viable quantities of natural
gas are present for extraction, the well must be 'completed' to allow for the flow of
petroleum or natural gas out of the formation and up to the surface. This process
Page 45
Summer Training
Page 45
includes strengthening the well hole with casing, evaluating the pressure and
temperature of the formation, and then installing the proper equipment to ensure an
efficient flow of natural gas out of the well. The well flow is controlled with a choke. We
differentiate between dry completion with is either onshore or on the deck of an
offshore structure, and Subsea completions below the surface. The wellhead structure,
often called a Christmas tree, must allow for a number of operations relating to
production and well work over. Well work over refers to various technologies for
maintaining the well and improving its production capacity.
Figure 4.8 Manifolds/Gathering
Onshore, the individual well streams are brought into the main production facilities
over a network of gathering pipelines and manifold systems. The purpose of these is to
allow set up of production “well sets” so that for a given production level, the best
reservoir utilization, well flow composition (Gas, Oil, water) etc. can be selected from
the available wells. For gas gathering systems, it is common to meter the individual
gathering lines into the manifold as shown on the illustration. For multiphase
(combination of gas, oil and water) flows, the high cost of multiphase flow meters often
lead to the use of software flow rate estimators that use well test data to calculate the
actual flow. Offshore, the dry completion wells on the main field centre feed directly
into production manifolds, while outlying wellhead towers and subsea installations feed
via multiphase pipelines back to the production risers. Risers are the system that allows
a pipeline to “rise” up to the topside structure. For floating or structures, this involves a
way to take up weight and movement. For heavy crude and in arctic areas, diluents and
heating may be needed to reduce viscosity and allow flow.
Figure 4.9 Separation
Page 46
Summer Training
Page 46
Some wells have pure gas production which can be taken directly to gas treatment and/or
compression. More often, the well gives a combination of Gas, Oil and Water and various
contaminants which must be separated and processed. The production separators come in
many forms and designs, with the classical variant being the gravity separator. In gravity
separation the well flow is fed into a horizontal vessel. The retention period is typically 5
minutes, allowing the gas to bubble out, water to settle at the bottom and oil to be taken out in
the middle. The pressure is often reduced in several stages (high pressure separator, low
pressure separator etc.) to allow controlled separation of volatile components. A sudden
pressure reduction might allow flash vaporization leading to instabilities and safety hazards.
Figure 4.10 Separator
4.6 Gas compression
Gas from a pure natural gas wellhead might have sufficient pressure to feed directly into a
pipeline transport system. Gas from separators has generally lost so much pressure that it
must be recompressed to be transported. Turbine compressors gain their energy by using up a
small proportion of the natural gas that they compress. The turbine itself serves to operate a
centrifugal compressor, which contains a type of fan that compresses and pumps the natural
gas through the pipeline. Some compressor stations are operated by using an electric motor to
turn the same type of centrifugal compressor. This type of compression does not require the
use of any of the natural gas from the pipe; however it does require a reliable source of
electricity nearby. The compression includes a large section of associated equipment such as
scrubbers (removing liquid droplets) and heat exchangers, lube oil treatment etc. Whatever
the source of the natural gas, once separated from crude oil (if present) it commonly exists in
mixtures with other hydrocarbons; principally ethane, propane, butane, and pentanes. In
addition, raw natural gas contains water vapor, hydrogen sulfide (H2S), carbon dioxide,
helium, nitrogen, and other compounds. Natural gas processing consists of separating all of
the various hydrocarbons and fluids from the pure natural gas, to produce what is known as
'pipeline quality' dry natural gas. Major transportation pipelines usually impose restrictions
on the make-up of the natural gas that is allowed into the pipeline. That means that before the
natural gas can be transported it must be purified. Associated hydrocarbons, known as
'natural gas liquids' (NGL) are used as raw materials for oil refineries or petrochemical plants,
and as sources of energy.
Page 47
Summer Training
Page 47
Figure 4.11 Metering, Storage and Export
Most plants do not allow local gas storage, but Oil is often stored before loading on a vessel,
such as a shuttle tanker taking the oil to a larger tanker terminal, or direct to crude carrier.
Offshore production facilities connection generally relies on crude storage in the base or hull,
to allow a shuttle tanker to offload about once a week. A larger production complex generally
has an associated tank farm terminal allowing the storage of different grades of crude to take
up changes in demand, delays in transport etc.
Metering stations allow operators to monitor and manage the natural gas and oil exported
from the production installation. These metering stations employ specialized meters to
measure the natural gas or oil as it flows through the pipeline, without impeding its
movement. This metered volume represents a transfer of ownership from a producer to a
customer (or another division within the company) and is therefore called Custody Transfer
Metering. It forms the basis for invoicing sold product and also for production taxes and
revenue sharing between partners and accuracy requirements are often set by governmental
authorities.
Typically the metering installation consists of a number of meter runs so that one meter will
not have to handle the full capacity range, and associated prover loops so that the meter
accuracy can be tested and calibrated at regular intervals. Pipelines can measure anywhere
from 6 to 48 inches in diameter. In order to ensure the efficient and safe operation of the
pipelines, operators routinely inspect their pipelines for corrosion and defects. This is done
through the use of sophisticated pieces of equipment known as pigs. Pigs are intelligent
robotic devices that are propelled down pipelines to evaluate the interior of the pipe.
Page 48
Summer Training
Page 48
Figure 4.12 GGS
Pigs can test pipe thickness, and roundness, check for signs of corrosion, detect minute leaks,
and any other defect along the interior of the pipeline that may either impede the flow of gas,
or pose a potential safety risk for the operation of the pipeline. Sending a pig down a pipeline
is fittingly known as 'pigging' the pipeline. The export facility must contain equipment to
safely insert and retrieve pigs form the pipeline as well as depressurization, referred to as pig
launchers and pig receivers loading on tankers involve loading systems, ranging from tanker
jetties to sophisticated single point mooring and loading systems that allow the tanker to dock
and load product even in bad weather.
The well
Figure 4.13 Oil well
Oil
Produced
to Surface
Surface
Casing
Cement
Produced
Casing
Tubing
Packer
Oil Enters
Through
Perforation
Perforation
Page 49
Summer Training
Page 49
When the well has been drilled, it must be completed. Completing a well consists of a
number of steps; installing the well casing, completing the well, installing the wellhead, and
installing lifting equipment or treating the formation should that be required.
3.5Wellhead
Wellheads can be
Dry or Subsea
completion. Dry
Completion means
that the well is
onshore on the
topside structure on
an offshore
installation. Subsea
wellheads are
located under water
on a special sea bed
template.
The wellhead
consists of the
pieces of equipment
mounted at the
opening of the well
to regulate and
monitor the
extraction of
hydrocarbons from
the underground formation. It also prevents leaking of oil or natural gas out of the well, and
prevents blowouts due to high pressure formations.
Formations that are under high pressure typically require wellheads that can withstand a great
deal of upward pressure from the escaping gases and liquids. These wellheads must be able to
withstand pressures of up to 140 MPa (1400 Bar). The wellhead consists of three
components: the casing head, the tubing head, and the 'Christmas tree'.
Page 50
Summer Training
Page 50
A typical Christmas tree composed of a
master gate valve, a pressure gauge, a
wing valve, a swab valve and a choke is
shown here. The Christmas tree may
also have a number of check valves.
The functions of these devices are
explained in the following paragraphs.
Ill: Vetco international At the bottom
we find the Casing Head and casing
Hangers. The casing will be screwed,
bolted or welded to the hanger. Several
valves and plugs will normally be fitted
to give access to the casing. This will
permit the casing to be opened, closed,
bled down, and, in some cases, allow
the flowing well to be produced through
the casing as well as the tubing. The
valve can be used to determine leaks in
casing, tubing or the packer, and will
also be used for lift gas injection into
the casing.
The tubing hanger: (also called donut)
is used to position the tubing correctly
in the well. Sealing also allows
Christmas tree removal with pressure in
the casing.
Master gate valve: The master gate
valve is a high quality valve. It will
provide full opening, which means that
it opens to the same inside diameter as
the tubing so that specialized tools may
be run through it. It must be capable of
holding the full pressure of the well
safely for all anticipated purposes. This
valve is usually left fully open and is
not used to control flow. The pressure
gauge: The minimum instrumentation is a pressure gauge placed above the master gate valve
before the wing valve. In addition other instruments such as temperature will normally be
fitted.
The wing valve: The wing valve can be a gate valve, or ball valve. When shutting in the well,
the wing gate or valve is normally used so that the tubing pressure can be easily read.
Page 51
Summer Training
Page 51
The swab valve: The swab valve is used to gain access to the well for wire line operations,
intervention and other work over procedures (see below), on top of it is a tree adapter and cap
that will mate with various equipment.
The variable flow choke valve: The variable flow choke valve is typically a large needle
valve. Its calibrated opening is adjustable in 1/64 inch increments (called beans). High-
quality steel is used in order to withstand the high-speed flow of abrasive materials that pass
through the choke, usually for many years, with little damage except to the dart or seat. If a
variable choke is not required, a less expensive positive choke is normally installed on
smaller wells. This has a built in restriction that limits flow when the wing valve is fully
open.
This is a vertical tree. Christmas trees can also be horizontal, where the master, wing and
choke is on a horizontal axis. This reduces the height and may allow easier intervention.
Horizontal trees are especially used on subsea well.
3.5.1Subsea wells
4.Production Separator
Page 52
Summer Training
Page 52
6 SITE VISITED
DTYS, F 6100 Rig, E 760-17 Rig, Workover Operation (ANK # 334)
E- 760- 17
Rig name: E 760-17 BHEL drilling rig at Gandhar field drilling a Directional
well of TD 3200mtrs
Well name:- GNDDH
Field:- Gandhar
Location:- Gandhar
Kick off was at 250mtrs.
L – Profile drilling.
Type of well : Development well
Current onsite drilling depth : 2605m
Type of BOP:- 13 ⅝" annular and double RAM
Mud used: - CLCLS (Chrome lignite – Chrome ligno-sulphate) .
Two triplex pumps were used for mud pumping
H/SIZE Interval(m) Csg. Size Csg. Plan
23‖ 0-150 18 5/8‖ J-55, 87.5 ppf, BTC
17 ½‖ 0-1400 13 3/8‖ N-80, 68 ppf, BTC
12 ¼‖ 0-3206 12 ¼‖ N-80. 47 ppf, BTC
8 ½‖ 0-3236.3 7‖ L-80, 29 ppf, BTC
F-6100
Rig name:- F 6100
Well name:- GNWW (AIG 15)
Field:- Gandhar
Location: - Gandhar. Dist. Bharuch
Page 53
Summer Training
Page 53
Kick off was at 250mtrs.
S – Profile drilling.
Type of well : Development well
Current onsite drilling depth : 3025m
Type of BOP:- 18 ⅝" annular and double RAM
Mud used: - CLCLS (Chrome lignite – Chrome ligno-sulphate) .
Two triplex pumps were used for mud pumping
H/SIZE Interval(m) Csg. Size Csg. Plan
17 ½‖ 0-200 13 3/8‖ J-55, 68 ppf, BTC
12 ¼‖ 0-1800 9 5/8‖ N-80, 43.5 ppf, BTC
8 ½‖ 0-3178 7‖ L-80, 27 ppf, BTC
Page 54
Summer Training
Page 54
7 CASE STUDY
DRILL STRING DESIGN
H/Size Interval(m) D/Collar Weight in Air(tons) D/Pipe
17 ½‖ 0-150 8‖x 3‖=28M (6 T), (6+7.5)T 5‖HWDP+Rest
5‖ D/P ,E-GD 6 ½‖ x 2 13/16‖= 56M (7.5
T)
12 ¼‖ 150-800 8‖x 3‖=28M (6 T), (6 + 15)T 5‖HWDP+Rest
5‖ D/P ,E-GD 6 ½ x 2 13/16‖= 112M (15 T)
8 ½‖ 800-2000 6 ½‖ x 2 13/16‖=
168M(22.5T)
22.5 T 5‖HWDP+Rest
5‖ D/P ,E-GD
Grade Yield strength, (psi)
J 55000
N 80000
N 80000
X 95000
DRILL STRING
SECTION 1
Depth 150m
Hole size 17 1/2‖
Mud Weight 1.06gm/cc = 8.85 ppg
Buoyancy Factor = 1 - (8.85/65.5) = 0.865
Safety Factor Tension 1.8
Collapse 1.125
Drill Collar 1 stand 8‖ × 3‖ 28m
2 stands 6 ½ x 2 13/16‖ 56m
2 stands 5‖HWDP 56m
Page 55
Summer Training
Page 55
Max WOB 8 tonne
Well to be drilled Cos α = 1(vertical)
Total length of D/C assembly
Wt of D/C in air = WOB/ ( SF x BF x Cos α )
= 8 / (0.8 x 0.865 x 1 ) = 11.56 tonnes
Nominal Weight
Wt of 8‖ × 3‖ D/C = 6 Tonnes
Wt of 6 ½ x 2 13/16‖ D/C = 7.5 Tonnes
Wt of 5‖HWDP = 56 x 73.5 Kg
= 4116 Kg
= 4.12 Tonnes
Total Wt of D/C assembly + HWDP = 17.62 Tonnes
Length of Drill Pipe above Drill collar Assembly
Drill Pipe 5‖ D/P J -55 Grade
19.5 ppf
Length oF D/P = 10 m
L D/P = ( Pt X 0.9 /SF x BF x WD/P ) - (WcLC / WD/P )
= ( 141.8 x 1000 x0.9 / 1.8 x 31.2 x0.865) - ( 17.62 x 1000/ 31.2 )
= 2062.35m
True Ldp = 10 m (feasible)
Margin Of Over Pull
MOP = Pa - P
P = B(WcLD/c + WD/PLD/P/ 1000 )
= 0.865 ( 17.62 + 31.52 x 10/1000 )
= 15.514 Tonnes
Pa = Pt x 0.9 = 141.8 x 0.9 = 127.62 Tonnes
MOP = 127.62 – 15.514
Page 56
Summer Training
Page 56
= 112.11 Tonnes
DRILL STRING
SECTION 2
Depth 800m
Hole size 12 1/4‖
Mud Weight 1.20gm/cc = 10.02 ppg
Buoyancy Factor = 1 - (10.02/65.5) = 0.847
Safety Factor Tension 1.8
Collapse 1.125
Drill Collar 1 stand 8‖ × 3‖ 28m
4 stands 6 ½ x 2 13/16‖ 112m
2 stands 5‖HWDP 56m
Max WOB =10 tonne
Well to be drilled Cos α = 1(vertical)
Total length of D/C assembly
SF = 0.8 (this ensures that only 80% of weight of D/C is used on WOB
BF = 0.853
Cos α = 1
WOB = 10 tonnes
Wt of D/C in Air = 10 / (0.8 x 0.865 x 1 ) = 14.768 tonnes
Nominal Weight
Wt of 8‖ × 3‖ D/C = 6 Tonnes
Page 57
Summer Training
Page 57
Wt of 6 ½ x 2 13/16‖ D/C = 15 Tonnes
Wt of 5‖HWDP = 56 x 73.5 Kg
= 4122 Kg
= 4.12 Tonnes
Total wt of D/C assembly + HWDP = 21 + 4.12 tonnes
= 25.12 tonnes
Length of Drill Pipe above Drill collar Assembly
Drill Pipe 5‖ D/P N -80 Grade
19.5 ppf
Length oF D/P = 604 m
Adjusted wt =31.2 kg/m
Tensile strength =141.8 tonnes
S.F =1.8
L D/P = ( Pt X 0.9 /SF x BF x WD/P ) - (WcLC / WD/P )
= ( 141.8 x 1000 x0.9 / 1.8 x 31.2 x0.847) - ( 25.12 x 1000/ 31.2 )
= 1877.8 m
True Ldp = 604 m (feasible)
Margin Of Over Pull
MOP = Pa - P
P = B(WcLD/c + WD/PLD/P/ 1000 )
= 0.847 ( 25.12 + 31.52 x 604/1000 )
= 37.24 Tonnes
Pa = Pt x 0.9 = 141.8 x 0.9 = 127.62 Tonnes
MOP = 127.62 – 37.24
= 90.38 Tonnes
Page 58
Summer Training
Page 58
DRILL STRING
SECTION-III
Depth 2000m
Hole size 8 ½‖
Mud Weight 1.25gm/cc = 10.44 ppg
Buoyancy Factor = 1 - (10.44/65.5) = 0.841
Safety Factor Tension 1.8
Collapse 1.125
Drill Collar 1 stand 8‖ × 3‖ 28 m
6 stands 6 ½‖ x 2 13/16‖ 168m
2 stands 5‖HWDP 56m
Max WOB =14 tonne
Well to be drilled Cos α = 1(vertical)
Total length of Drill collar assembly
SF = 0.8 (this ensures that only 80% of weight of D/C is used on WOB
BF = 0.841
Cos α = 1
WOB = 14 tonnes
Wt of D/C in Air = 14 / (0.8 x 0.841 x 1 ) = 20.81 tonnes
Nominal Weight
Wt of 6 ½ x 2 13/16‖ D/C = 22.5 Tonnes
Wt of 5‖HWDP = 56 x 73.5 Kg
= 4122 Kg
Page 59
Summer Training
Page 59
= 4.12 Tonnes
Total wt of D/C assembly + HWDP = 22.5 + 4.12 tonnes
= 26.62 tonnes
Length of Drill Pipe above Drill collar Assembly
Drill Pipe 5‖ D/P N -80 Grade
19.5 ppf
Length oF D/P = 1748 m
Adjusted wt =31.2 kg/m
Tensile strength =141.8 tonnes
S.F =1.8
L D/P = ( Pt X 0.9 /SF x BF x WD/P ) - (WcLC / WD/P )
= ( 141.8 x 1000 x0.9 / 1.8 x 31.2 x0.841) - ( 26.62 x 1000/ 31.2 )
= 1848.85m
True Ldp = 1748 m (feasible)
Margin Of Over Pull
MOP = Pa - P
P = B(WcLD/c + WD/PLD/P/ 1000 )
= 0.841 ( 26.62 + 31.52 x 1748/1000 )
= 68.25 Tonnes
Pa = Pt x 0.9 = 141.8 x 0.9 = 127.62 Tonnes
MOP = 127.62 – 68.25
=59.36 Tonnes
Page 60
Summer Training
Page 60
Hydraulics Design
Section I
A) Hole size =17 ½‖
Sp. Gr =1.06
Depth interval from 0 to 150m
Drill collar,
8‖ x 3‖ =28 m
6 1/2‖ x 2 13/16 =56m
5‖ HWDP =56m
D.P 5‖ =10m
Pump available, Oil well Triplex A-850 PT x 2 Nos.
B) Operating pressure limit = 160 kg/cm2
C) Surface equipment =Type 3
Step I: Annulus velocities 60-100 ft/min, 18-30 m/min
Circulation rate (5‖ DP) = 4340 lit/min.
Step II: liner size selected = 7‖ = 177mm
No. Of pumps =2 Nos
Operating pressure = 160 kg/cm2
Step III: SPM = ((circulation rate lit/min)/(No. Of pumps x lit/stroke))
= 4340/(2 x 36.7) = 59.13 spm.
Step IV: From Table- D4
St pipe - 45 ft
ID - 4‖
Hose - 55 ft
Page 61
Summer Training
Page 61
ID - 3‖
Swivel - 5 ft
ID - 2 1/4‖
Kelly - 40 ft
OD - 3 ¼‖
Step V: Assume Pressure losses through surface equipment = 10.2 kg/cm2
Step VI: Pressure loss = (pressure loss from table D-6)/1000 x length of D.P
Assuming loss through drill pipe bore = 39.3 kg/cm2/1000
Pressure loss = (39.3/ 1000) x 10
= 0.393 kg/cm2
Step VII: Assuming for 17 ½‖ hole size 5‖ drill pipe, Pressure loss through D/P
Annulus = 0.2 Kg/cm2/1000m.
Pressure Loss = (0.2/1000) x 10 Kg/cm2 = 0.002 Kg/cm
2
Step VIII: (i) Drill collar 8‖ x 3‖ = 28m
Assume Pressure loss through Drill collar bore3’’ = (23.5/100) x 28 Kg/cm2
= 6.58 Kg/cm2
(ii) Drill Collar 6 ½‖ x 2 13/16‖ = 56 m
Assuming pressure through D/C bore (2 13/16)‖ = 32.1 kg/ cm2
Pressure losing (32.1/100)x 56 = 17.64 kg/cm2
(iii)HWDP 5‖ = 56 m
Pressure loss = (39.3/1000) x 56 kg/cm2 = 2.2008 kg/cm
2
Total pressure loss through D/C = (6.58+17.64+2.2008) = 26.4208 kg/cm2
Step IX: Circulation rate, hole size and drill collar size,
Pressure loss = (pressure loss from table D-9)/100) x length of collar
Hole Size 17 ½‖, D/C size
8‖ x 3‖ = 28 m, 0.23 kg/cm2/100
Page 62
Summer Training
Page 62
6 ½‖ x 2 13/16 = 56 m, 0.23 kg/cm2/100
For 8‖ x 3‖ casing (0.23/100) x 28 = 0.0644 kg/cm2
For 6 ½‖ x 2 13/16 (0.23/100) x 56 = 0.1288 kg/cm2
Annulus loss,
HWDP -> 5‖
P.D = (0.2/1000) x 56 =0.0112 kg/cm2
Total Pr. Loss around collar annulus = 0.205 kg/cm2
Step X: Adding steps 5, 6, 7, 8, 9
Sp.gr = 1.06
System Pressure Loss x (1.06/1.2) = Actual Pressure loss
Applied pr. Loss = 37.2208 x (1.06/1.2)
APL = 32.8784 kg/cm2
Step XI: Pressure available for nozzle selection = (160- 32.8784) x (1.2/1.06)
= 143.91 kg/cm2
Step XII: Nozzle size - 20-20-20
Pressure loss - 100.9 kg/cm2
Mud wt = 1.06 gm/cc
Actual Pr loss through nozzles
= 100.9 x (1.06/1.2)
= 89.13 kg/cm2
Step XIII: Stand pipe Pr = 100.9 +89.13
= 190.03kg/cm2
Step XIV: %age BHP = (100.9 x 100)/ 190.03 =53.1 %
Step XV: Jet velocity = (1.55 x circulation rate) / Area of Nozzles
= (1.55 x 4340) / (0.9204 x 60)
= 121.81 kg/cm2
Step XVI: Calculate BHHP/ sq inch hole size
Page 63
Summer Training
Page 63
BHHP/ Sq. Inch hole size = ((Actual Pr loss through bit) x (Circulation rate))/
(5.97 x (hole Dia. inch) 2
)
= (100.9 x 4340/60)/ (5.97 x (17.5)2) = 3.992
Section 2
A) Hole size =12 ¼‖
Sp. Gr =1.20
Depth interval from 0 to 800m
Drill collar,
8‖ x 3‖ =28 m
6 1/2‖ x 2 13/16 =112 m
5‖ HWDP =56 m
D.P 5‖ =604 m
Pump available, Oil well Triplex A-850 PT x 2 Nos.
B) Operating pressure limit = 70 x 2 = 140 kg/cm2
C) Surface equipment =Type 3
Step I: Annulus velocities 70-110 ft/min, 21-33 m/min
Circulation rate (5‖ DP) = 4777 lit/min.
Step II: liner size selected = 6 ½‖ = 165mm
No. Of pumps =2 Nos
Operating pressure = 140 kg/cm2
Step III: SPM = ((circulation rate lit/min)/(No. Of pumps x lit/stroke))
= 4777/ (2 x 32.2) = 74.18 spm.
Step IV: From Table- D4
St pipe - 45 ft
ID - 4‖
Hose - 55 ft
ID - 3‖
Page 64
Summer Training
Page 64
Swivel - 5 ft
ID - 2 1/4‖
Kelly - 40 ft
ID - 3 ¼‖
Step V: Assume Pressure losses through surface equipment = 10.2 kg/cm2
Step VI: Pressure loss = (pressure loss from table D-6)/1000 x length of D.P
Assuming loss through drill pipe bore = 39.3 kg/cm2/1000
Pressure loss = (39.3/ 1000) x 604
= 23.74 kg/cm2
Step VII: Assuming for 12 ¼‖ hole size 5‖ drill pipe, Pressure loss through D/P
Annulus = 0.2 Kg/cm2/1000m.
Pressure Loss = (0.2/1000) x 604 Kg/cm2 = 0.1208 Kg/cm
2
Step VIII: (i) Drill collar 8‖ x 3‖ = 28m
Assume Pressure loss through Drill collar bore3’’ = (23.5/100) x 28 Kg/cm2
= 6.58 Kg/cm2
(ii) Drill Collar 6 ½‖ x 2 13/16‖ = 112 m
Assuming pressure through D/C bore (2 13/16)‖ = 32.1 kg/ cm2
Pressure losing (32.1/100) x 112 = 35.952 kg/cm2
(iii)HWDP 5‖ = 56 m
Pressure loss = (39.3/1000) x 56 kg/cm2 = 2.2008 kg/cm
2
Total pressure loss through D/C = (6.58+35.952+2.2008) = 44.7328 kg/cm2
Step IX: Pressure Loss in annulus around the collar
Pressure loss = (pressure loss from table D-9)/100) x length of collar
Hole Size 12 ¼‖, D/C size are
8‖ x 3‖ = 28 m, 0.23 kg/cm2/100
6 ½‖ x 2 13/16 = 56 m, 0.23 kg/cm2/100
Page 65
Summer Training
Page 65
For 8‖ x 3‖ casing (0.23/100) x 28 = 0.0644 kg/cm2
For 6 ½‖ x 2 13/16 (0.23/100) x 112 = 0.2576 kg/cm2
Annulus loss,
HWDP of size 5‖
Pr. loss = (0.2/1000) x 56 =0.0112 kg/cm2
Total Pr. Loss around the drill collar annulus = 0.3332 kg/cm2
Step X: Adding steps 5, 6, 7, 8, 9
Sp.gr = 1.20
System Pressure Loss x (1.2/1.2) = Actual Pressure loss
Actual System Pr. Loss = 79.1268 x (1.2/1.2) kg/cm2
ASPL = 79.1268 kg/cm2
Step XI: Pressure available for nozzle selection = (140 - 79.1268) x (1.2/1.2)
= 68.8732 kg/cm2
Step XII: Nozzle size - 24-24-24
Pressure loss - 48.7 kg/cm2
Mud wt = 1.2 gm/cc
Actual Pr loss through nozzles
= 48.7 x (1.2/1.2)
= 48.7 kg/cm2
Step XIII: Stand pipe Pr = 48.7 + 48.7
= 97.4 kg/cm2
Step XIV: %age BHP = (48.7 x 100)/ 97.4 =50 %
Step XV: Jet velocity = (1.55 x circulation rate) / Area of Nozzles
= (1.55 x 4777)/ (1.3254 x 60)
= 93.1365 kg/cm2
Step XVI: Calculate BHHP/ sq inch hole size
BHHP/ Sq. Inch hole size = ((Actual Pr loss through bit) x (Circulation rate))/
Page 66
Summer Training
Page 66
(5.97 x (hole Dia. inch) 2
)
= (48.7 x 4777/60)/ (5.97 x (12.25)2) = 4.328
Section 3
A) Hole size =8 ½‖
Sp. Gr =1.25
Depth interval from 0 to 2000m
Drill collar,
6 1/2‖ x 2 13/16 =168 m
5‖ HWDP =56 m
D.P 5‖ =1776 m
Pump available, Oil well Triplex A-850 PT x 2 Nos.
B) Operating pressure limit = 2 x 100 kg/cm2
C) Surface equipment =Type 3
Step I: Annulus velocities 120-180 ft/min, 36-54 m/min
Circulation rate (5‖ DP) = 5644 lit/min.
Step II: liner size selected = 6 ½‖ = 165mm
No. Of pumps =1 Nos
Operating pressure = 200 kg/cm2
Step III: SPM = ((circulation rate lit/min) / (No. Of pumps x lit/stroke))
= 5644/ (2 x 32.2) = 87.64 spm.
Step IV: From Table- D4
St pipe - 45 ft
ID - 4‖
Hose - 55 ft
ID - 3‖
Swivel - 5 ft
ID - 2 1/4‖
Page 67
Summer Training
Page 67
Kelly - 40 ft
ID - 3 ¼‖
Step V: Assume Pressure losses through surface equipment = 10.2 kg/cm2
Step VI: Pressure loss = (pressure loss from table D-6) / 1000 x length of D.P
Assuming loss through drill pipe bore = 39.3 kg/cm2/1000
Pressure loss = (39.3 / 1000) x 1776
= 69.796 kg/cm2
Step VII: Assuming for 8 ½‖ hole size 5‖ drill pipe, Pressure loss through D/P
Annulus = 0.2 Kg/cm2/1000m.
Pressure Loss = (0.2/1000) x 1776 Kg/cm2 = 0.3552 Kg/cm
2
Step VIII: (i) Drill Collar 6 ½‖ x 2 13/16‖ = 168 m
Assuming pressure through D/C bore (2 13/16)‖ = 32.1 kg/ cm2
Pressure losing (32.1/100) x 168 = 53.928 kg/cm2
(ii)HWDP 5‖ = 56 m
Pressure loss = (39.3/1000) x 56 kg/cm2 = 2.2008 kg/cm
2
Total pressure loss through D/C = (53.928+2.2008) = 56.1288 kg/cm2
Step IX: Pressure Loss in annulus around the collar
Pressure loss = (pressure loss from table D-9)/100) x length of collar
Hole Size 8 ½‖, D/C size are
6 ½‖ x 2 13/16 = 168 m, 0.23 kg/cm2/100
For 6 ½‖ x 2 13/16 (0.23/100) x 168 = 0.3864 kg/cm2
Annulus loss for,
HWDP of size 5‖
Pr. loss = (0.2/1000) x 56 =0.0112 kg/cm2
Total Pr. Loss around the drill collar annulus = 0.3976 kg/cm2
Step X: Adding steps 5, 6, 7, 8, 9
Page 68
Summer Training
Page 68
Sp.gr = 1.20
System Pressure Loss x (1.2/1.2) = Actual Pressure loss
Actual System Pr. Loss = 136.8776 x (1.25/1.2) kg/cm2
ASPL = 142.58 kg/cm2
Step XI: Pressure available for nozzle selection = (200- 142.58) x (1.2/1.25)
= 55.1232 kg/cm2
Step XII: Nozzle size - 27-27-27
Pressure loss - 44.3 kg/cm2
Mud wt = 1.25 gm/cc
Actual Pr loss through nozzles
= 44.3 x (1.25/1.2)
= 46.15 kg/cm2
Step XIII: Stand pipe Pr = 44.3 + 46.15
=90.45 kg/cm2
Step XIV: %age BHP = (44.3 x 100)/ 90.45 =48.98 %
Step XV: Jet velocity = (1.55 x circulation rate) / Area of Nozzles
= (1.55 x 5644)/ (1.5555 x 60)
= 94.066 kg/cm2
Step XVI: Calculate BHHP/ sq inch hole size
BHHP/ Sq. Inch hole size = ((Actual Pr loss through bit) x (Circulation rate))/
(5.97 x (hole Dia. inch) 2
)
= (44.3 x 5644/60)/ (5.97(8.5)2) = 9.66
Page 69
Summer Training
Page 69
CASING DESIGN Factors Influencing Casing Design:
Casing design involves the determination of factors which influence the failure of casing andthe selection of the most suitable casing grades and weights for a specific operation, bothsafely and economically. The casing programme should also reflect the completion andproduction requirements.
A good knowledge of stress analysis and the ability to apply it are necessary for the design ofcasing strings. The end product of such a design is a 'pressure vessel' capable of withstandingthe expected internal and external pressures and axial loading. Hole irregularities furthersubject the casing to bending forces which must be considered during the selection of casinggrades.
A safety margin is always included in casing design, to allow for future deterioration of thecasing and for other unknown forces which may be encountered, including corrosion, wearand thermal effects. Casing design is also influenced by: a. Loading conditions during drilling and production; b. The strength properties of the casing seat (i.e. formation strength at casing shoe); c. The degree of deterioration the pipe will be subjected to during the entire life of the
well; d. The availability of casing.
A casing string incorrectly designed can result in disastrous consequences, placing humanlives at risk and causing damage and loss of expensive equipment. The entire oil reservoir may be placed at risk if the casing cannot contain a kick which may develop into a blowout resulting in a large financial loss to the operating company and a large depletion of the reservoir potential. Design Criteria: There are three basic forces which the casing is subjected to: collapse, burst and tension. These are the actual forces that exist in the wellbore. They must first be calculated and mustbe maintained below the casing strength properties. In other words, the collapse pressuremust be less than the collapse strength of the casing and so on.
Casing should initially be designed for collapse, burst and tension. Refinements to the selected grades and weights should only be attempted after the initial selection is made.
For directional wells a correct well profile is required to determine the true vertical depth(TVD). All wellbore pressures and tensile forces should be calculated using true verticaldepth only. The casing lengths are first calculated as if the well is a vertical well and thenthese t lengths are corrected for the appropriate hole angle.
Page 70
Summer Training
Page 70
Collapse criteria:
Collapse pressure originates from the column of mud used to drill the hole, and acts on theoutside of the casing. Since the hydrostatic pressure of a column of mud increases withdepth, collapse pressure is highest at the bottom and zero at the top.This is a simplified assumption and does not consider the effects of internal pressure. For practical purposes, collapse pressure should be calculated as follows: Collapse pressure = External pressure – Internal pressure
The actual calculations involved in evaluating collapse
and burst pressures are usually straight forward. However, knowing which factors to use for calculating external an internal pressure is not easy and requires knowledge of current and future operations in the wellbore.
The following procedure was used for collapse design: Assumptions 1. Casing is assumed empty due to lost circulation at casing
setting depth (CSD) or at TD of next hole 2. Internal pressure inside casing is zero 3. External pressure is caused by mud
in which casing was run in 4. No cement outside casing The equation could be written as Collapse pressure (C) = mud density x depth x acceleration due to gravity
=0.052 x x CSD….psi
=
…………..Kg/sq.cm Where is in ppg CSD is in ft. W is mud weight in gm. /cc D is depth in cm LOST CIRCULATION
If collapse calculations are based on 100% evacuation then the internal pressure (or back up load) is to zero. The 100% evacuation condition can only occur when a. The casing is run empty b. There is complete loss of fluid into a thief zone (say into a cavernous formation), c. There is complete loss of fluid due to a gas blowout which subsequently subsides
Page 71
Summer Training
Page 71
None of these conditions should be allowed to occur in practice with the exception of encountering cavernous formations.
During lost circulation, the mud level in the well drops to a height such that the remaining hydrostatic pressure of mud is equal to the formation pressure of the thief zone. In this case the mud pressure exactly balances the formation pressure of the thief zone and fluid loss into the formation will cease. If the formation pressure of the thief is not known, it is usual to assume the pressure of the thief zone to be equal to 0.465 psi/ft. or 0.0075gm/cm. Burst criterion In oil well casings, burst occurs when the effective internal pressure inside the casing(internal pressure minus external pressure) exceeds the casing burst strength. Like collapse, the burst calculations are straightforward. The difficulty arises when oneattempts to determine realistic values for internal and external pressures.
In development wells, where pressures are well known the task is straight forward. Inexploration wells, there are many problems when one attempts to estimate the actualformation pressure including: a. The exact depth of the zone (formation pressure increases with depth) b. Type of fluid (oil or gas) c. Porosity, permeability d. Temperature
The above factors determine the severity of the kick in terms of pressure and ease ofDetection Clearly; one must design exploration wells for a greater degree of uncertainty thandevelopment wells. Indeed, some operator’s manuals detail separate design methods fordevelopment and exploration wells BURST CALCULATIONS Burst Pressure, B is given by:
B = internal pressure – external pressure DESIGN & SAFETY FACTORS Safety factor uses a rating based on catastrophic failure of the casing.
Safety Factor =
Design factor uses a rating based on the minimum yield strength of casing.
The burst design factor (DF-B) is given by:
Similarly, the collapse design factor is given by:
Page 72
Summer Training
Page 72
RECOMMENDED DESIGN FACTORS
SI.no Type of Design Recommended DF Industry Recommended DF 1 Collapse 1.0 1.0-1.1 2 Burst 1.1 1.1-1.25 3 Tension 1.6-1.8 1.3-1.8 4 Compression 1.0 1.0 5 Triaxile design 1.1 1.1-1.2
CASING SELECTION- BURST AND COLLAPSE
However before a load case is applied, the casing grades/weights should initially be selected on the basis of burst and collapse pressures, then load cases should be applied. If only one grade or one weight of casing is available, and then the task of selecting casing is easy. The strength properties of the casings available are compared with the collapse and burst pressures in the wellbore. If the design factors in collapse and burst are acceptable then all that remains is to check the casing for tension.
For deep wells or where more than one grade and weight are used, a graphical method of selecting casing is used as follows: 1. Plot a graph of pressure against depth, as shown in Figure 5.5, starting the depth and
pressure scales at zero. Mark the CSD on this graph. 2. Collapse Line: Mark point C1 at zero depth and point C2 at CSD. 3. Draw a straight line through points C1 and C2.For partial loss circulation, there will
be three collapse points. Mark C1 at zero depth, C2 at depth (CSD-L) and C3 at CSD. Draw two straight lines through these points.
4. Burst Line: Plot pointB1 at zero depth and point B2 at CSD. Draw a straight line through point B1 and B2 For production casing, the highest pressure will be at casing shoe.
5. Plot the collapse and burst strength of the available casing, as shown in above Figure. In this figure, two grades, N80 and K55 are plotted to represent the available casing.
Page 73
Summer Training
Page 73
6. Select a casing string that satisfies both collapse and burst. Figure provides the initial selection and in many cases this selection differs very little from the final selection. Hence, great care must be exercised when producing Figure.
Page 74
Summer Training
Page 74
Page 75
Summer Training
Page 75
Tension Criteria:
Tension loadings canarise due to: bending, drag, shock loading and during pressure testing of casingin casing design, the uppermost joint of the string is considered the weakest in tension, as ithas to carry the total weight of the casing string. Selection is based on a design factor of 1.6to 1.8 for the top joint. Tensile forces are determined as follows: 1. Calculate weight of casing in air (positive value)
using true vertical depth; 2. Calculate buoyancy force (negative value); 3. Calculate bending force in deviated wells (positive
value); 4. Calculate drag force in deviated wells (this force is
only applicable if casing ispulled out of hole); 5. Calculate shock loads due to arresting casing in slips;
and 6. Calculate pressure testing forces
Forces (1) to (3) always exist, whether the pipe is static or in motion. Forces (4) and (5) exist only when the pipe is in motion
TENSION CALCULATIONS:
Buoyant Weight of Casing (Positive Force):
The buoyant weight is determined as the difference between casing air weight and buoyancy force. Casing air weight = casing weight (lb/ft) x hole TVD (5.20) For open-ended casing, see Figure Buoyancy force = Pe (Ae – Ai) (5.21) For closed casing, see Figure Buoyancy force = Pe Ae – Pi Ai (5.22) Where Pe = external hydrostatic pressure, psi Pi = internal hydrostatic pressure, psi Ae and Ai are external and internal areas of the casing Since the mud inside and outside the casing is invariably the same, the buoyancy force is almost always given by
Buoyancy force = Pe (Ae – Ai)
Page 76
Summer Training
Page 76
If a tapered casing string is used then the buoyancy
force at TD is calculated as above. At across-sectional
change, the buoyancy force is calculated as follows:
Buoyancy force = Pe2 (Ae2 – Ae1) – Pi2 (Ai2- Ai1)
For most applications, the author recommends calculating the buoyant weight as follows:
Buoyant weight = air weight x buoyancy factor
Bending Force:
The bending force is given by:
Bending force = 63 Wn x OD x θ (5.26) Where Wn = weight of casing lb/ft (positive force)
θ= dogleg severity, degrees/100 ft
Shock Load Shock loading in casing operations results when: Sudden decelerations are applied Casing is picked off the slips Slips are kicked in while pipe is moving
Casing hits a bridge or jumps off an edge down hole Shock loading is a dynamic force with a very short duration: approximately one second. It can be shown that the shock is
given by 1: Fshock = 1780 V As (5.27) where As = cross-sectional area V = pipe running velocity in ft/s, usually taken as the Instantaneous velocity (some operators use V = 5 ft/s as the instantaneous velocity) After some observations the above shock load equation could be w rewritten as
Shock load (max) = 1500 x Wn
Drag Force This force is usually of the order of 100,000 lbf (positive force). Because the calculation of drag force is complex and requires an accurate knowledge of the friction factor between the casing and hole, shock load calculations will in most cases suffice. The effect of the drag force lasts for the duration of running a joint of casing; shock loading lasts for only 1 second or so. Hence shock loading and drag forces cannot exist simultaneously. In most cases the magnitude of shock and drag forces are approximately the same
Page 77
Summer Training
Page 77
Pressure Testing The casing should be tested to the maximum pressure which it sees during drilling and production operations (together with a suitable rounding margin). PRESSURE TESTING ISSUES When deciding on a pressure test value, the resulting force must not be allowed to exceed: 80% of the rated burst strength The connection pressure rating 75% of the connection tensile rating Triaxile stress rating of the casing Load cases:
There are three load cases for which the total tensile force should be calculated for: running conditions, pressure testing and static conditions. These load cases are sometimes described as Installation Load cases. Other load cases will be discussed later. Load Case 1: Running Conditions This applies to the case when the casing is run in hole and prior to pumping cement:
Total tensile force = buoyant weight + shock load +bending force
Load Case 2: Pressure Testing Conditions
This condition applies when the casing is run to TD, the cement is displaced behind the
casing and mud is used to apply pressure on the top plug. This is usually the best time to
test the casing while the cement is still wet. In the past, some operators tested casing
after the cement was set. This practice created micro channels between the casing and
the cement and allowed pressure communication between various zones through these
open channels.
Total tensile force = buoyant weight + pressure testing force +bending force Load Case 3: Static Conditions
This condition applies when the casing is in the ground, cemented and the well head installed. The casing is now effectively a pressure vessel fixed at top and bottom. One canargue that other forces should be considered for this case such as production forces, injectionforces, temperature induced forces etc.
Total tensile force = buoyant weight + bending force + (miscellaneous forces) It is usually sufficient to calculate the total force at the top joint, but it may be
necessary tocalculate this force at other joints with marginal safety factors in tension.Once again, ensure that the design factor in tension during pressure testing is greater than1.6, i.e.
Page 78
Summer Training
Page 78
Load calculations:
Collapse Pressure:
Surface casing (13 3/8‟‟, J-55, 61ppf, BTC)
Intermediate Casing (9 5/8‟‟, N-80, 40ppf, BTC)
Production Casing (5 ½‟‟, N-80, 17ppf, BTC)
Page 79
Summer Training
Page 79
Burst Calculations:
Surface Casing: (13 3/8‟‟, J-55, 61ppf, BTC)
Case 1: By using Formation Pressure
Expected formation pressure = Hydrostatic Pressure + (10%Hydrostatic Pressure)
=110% Hydrostatic Pressure (of next Casing)
Hydrostatic Pressure = M x D/10 kg/sq.cm
= 1.20x800/10
= 96 kg/sq.cm
Formation Pressure = 1.1x96=105.6 kg/sq.cm
=99.53 kg/sq.cm
Case2: By using Fracture Pressure
Fracture Gradient of Gandhar field is = 0.8-0.9 psi/ft.
= 1.8476-2.075 gm./cc.
Taking minimum Fracture Gradient=1.85 gm/cc
=27.44 kg/sq.cm
Take minimum Value=27.44 kg/sq.cm
Page 80
Summer Training
Page 80
Intermediate Casing: (9 5/8‟‟,N-80,40ppf,BTC)
Case 1: By using Formation Pressure
Expected formation pressure = Hydrostatic Pressure + (10%Hydrostatic Pressure)
=110% Hydrostatic Pressure (of next Casing)
Hydrostatic Pressure=MxD/10 kg/sq.cm
=1.25x2000/10
=250 kg/sq.cm
Formation Pressure=1.1x250=275 kg/sq.cm
=237.18kg/sq.cm
Case2: By using Fracture Pressure
Fracture Gradient of Gandhar field is =0.8-0.9 psi/ft.
=1.8476-2.075 gm./cc.
Taking minimum Fracture Gradient=1.85 gm/cc
Take Minimum Value =139.496 kg/sq.cm
Production Casing:
By using Fracture Pressure
Fracture Gradient of Gandhar field is =0.8-0.9 psi/ft.
=1.8476-2.075 gm./cc.
Taking minimum Fracture Gradient=1.85 gm/cc
Page 81
Summer Training
Page 81
=319.12 kg/sq.cm
Tensile Load Calculations:
Surface Casing: (13 3/8‟‟, J-55, 61ppf, BTC)
W=1.06
=0.865
(
)
=11.777Tonnes
Intermediate Casing: Combination Casing String
W=1.20
= 0.847
Page 82
Summer Training
Page 82
(
)
( )
= 44.30 Tonnes
Production Casing: (Combination Casing)
W=1.25
= 0.841
(
)
=69.41Tonnes
Casing Performance Properties:
Grade Size Weight
(ppf)
Collapse
Resistance
(kg/cm2)
Pipe Yield
(in Tonnes)
Joint
Strength(BTC)
(in Tonnes)
Burst
Resistance
(kg/cm2)
J-55,13 3/8’’ 61 108 436.35 464.35 217
N-80,9 5/8’’ 40 217 415.5 444 404
N-80,5 ½’’ 17 442 180 202.3 544
Design Factors Calculations:
Casing
Loads
Surface
Casing
Intermediate
Casing
Production
Casing
Design Factors
Collapse Pressure 15.9kg/sq.cm 96 kg/sq.cm 250kg/sq.cm 6.67,2.26,1.768,
Burst Pressure
27.44
kg/sq.cm
139.496
kg/sq.cm
319.12kg/sq.cm 7.91,2.89,1.70
Tensile Load 11.777Tonnes 44.30Tonnes 69.41 Tonnes 39.47,10.02,2.91
Page 83
Summer Training
Page 83
REFERENCES:
Institute of Drilling Technology, ONGC, Dehradun -- Drilling Operations Manual;
First Edition 1994
Drilling & Well Completion, Gatlin, Carl
Baker Hughes INTEQ - Oil Field Familiarization Training Guide
Baker Hughes INTEQ (1995) - Drilling Engineering Workbook
Herriot-Watt University – Drilling Engineering book
Mud Engineering by Prof. Abdel-Alim Hashem
Well Engineering & Construction, Rabia, H