  • Program and Project

    Management with

    mySAP PLM

    Project Management

  • SAP AG 2001, Title of Presentation, Speaker Name 2

    mySAP PLM

    Life-Cycle Data Management

    Program and Project Management

    Asset Life-Cycle Management

    Environment, Health & Safety

    Quality Management

    Life-Cycle Collaboration

    Key Functional Areas of mySAP PLM

  • SAP AG 2001, Title of Presentation, Speaker Name 3

    mySAP Product Lifecycle Management

    Definining Program & Project Management

  • SAP AG 2001, Title of Presentation, Speaker Name 4

    Defining Program & Project Management

    Your

    Products

    DO THINGS RIGHT

    DO THE RIGHT THINGS

    Project Management

    Program Management

    Your

    Products

    DO THINGS RIGHT

    DO THE RIGHT THING

    When presenting to a

    customer put a picture of the

    customers product instead or

    Your Product

  • SAP AG 2001, Title of Presentation, Speaker Name 5

    Defining Program & Project Management

    Strategic Program Management

    Program Management

    Life-Cycle Profitability Management

    Project Management

    Project Management

  • SAP AG 2001, Title of Presentation, Speaker Name 6

    mySAP Product Lifecycle Management

    Project Management

  • SAP AG 2001, Title of Presentation, Speaker Name 7

    Project Structure

    Idea & Concept

    Planning & Approval

    Project Execution

    Closing

    Work Breakdown StructureHierarchically structured elements to

    build up project organization and enable

    top-down/bottom-up scenarios for project

    management (time, costs, resources), as

    well as assignment of all kinds of related

    objects, esp. activities.

    Activities (Network)Chains of activities linked via

    relationships provide network technique

    to model the projects process flow and

    allow typical functions like scheduling,

    capacity planning, or procurement on

    them.

    MilestonesKey dates assigned to the WBS or to

    activities to trigger subsequent functions.

  • SAP AG 2001, Title of Presentation, Speaker Name 8

    Documents

    Idea & Concept

    Planning & Approval

    Project Execution

    Closing

    Life-Cycle Data ManagementFull integration into the Document

    Management System of mySAP Life-

    Cycle Data Management; assignment of

    all various documents supported by all

    DMS functions (i.e. versioning, vaulting)

    Integrated Viewing/Maintenance All originals of assigned document

    masters can be viewed/maintained

    directly from the projects maintenance

    environment.

    Flexible Search/E-PublishingProject documents can be searched by

    various search engines and can also be

    published for external access on the

    Internet.

    Life-Cycle Data

    Management

    Document

    info record

    MS-Office

    CAX-Viewer

    Any file ...

    (i.e. MS-Project)

  • SAP AG 2001, Title of Presentation, Speaker Name 9

    Schedule

    Idea & Concept

    Planning & Approval

    Project Execution

    Closing

    Network-Scheduling according to Project Management StandardsScheduling activities is carried out forwards and backwards. This takes into account

    constraints, calculates their earliest/latest dates, and determines the floats. Based on this,

    you can analyze the critical activities within the network that helps to optimize it. In

    addition, actual and forecast dates will have an impact on the schedule during execution.

    Scheduling does affect Cost- and Resource Planning The projects scheduled dates will be used when calculating costs and resources for

    this, various distribution rules are predefined (i.e. equally, 20/80).

  • SAP AG 2001, Title of Presentation, Speaker Name 10

    Workforce

    Idea & Concept

    Planning & Approval

    Project Execution

    Closing

    Project

    Organisation

    Work Center

    Workforce

    Planning

    Defining a Project Team by Assigning Project OrganizationAlong the Work Breakdown Structure, whole organization units as well as individual

    persons from HR can be assigned to build up a project team.

    Capacity Planning for Activities via Work Centers Available capacities are defined in the work center. By assigning these to an activity,

    scheduling determines the capacity requirement. This enables capacity load analysis.

    Planning Workforce on Individual Persons LevelFurther distribution and evaluation of capacity load on project member level

    Project Team

    Individual

    Persons

  • SAP AG 2001, Title of Presentation, Speaker Name 11

    Procurement

    Idea & Concept

    Planning & Approval

    Project Execution

    Closing

    Project-oriented ProcurementAssignment of components or whole

    BOMs either manually or via an interface

    triggers procurement of the following:

    internal/ external, stock/project stock/non

    stock, via MRP/direct procurement, as

    service order, WBS assigned orders.

    Project-oriented Production Multi-level assembly/production of

    components/products within the project

    Seamless Integration/WorkflowProject planning (i.e. scheduling, release)

    does directly influence the procurement

    process. Costs for components/ procure-

    ment runs into the project calculation.

    Powerful Progress Tracking

    Purchase

    order

    Service

    order

    Production

    order

    OrderOrderOrder

    BOM

    Components

    Services

  • SAP AG 2001, Title of Presentation, Speaker Name 12

    Costs

    Idea & Concept

    Planning & Approval

    Project Execution

    Closing

    Structural Cost PlanningStrong hierarchy of WBS-Elements can be

    used to plan costs in a top-down- as well as

    in a bottom-up-procedure. For this, the

    detail can vary from overall to periodical

    values, also on a cost element level.

    Easy Cost Planning Predefined calculation templates presented

    in a highly configurable, HTML-based user

    interface provide an end-user focused

    easy-to-understand environment.

    Network CalculationInternal & external work, services, costs

    and procurement planned in the activities

    are automatically calculated.

    Costing through Assigned Orders

    Service

    order

    Invoice

    plan

    Network Calculation

    Duration * Work * Rate/H

    Procurement / Cost Activities

    Easy Cost Planning

    template based calculation

    Structural Cost Planning

    Top Down / Bottom Up

    400 600

    1.200

    200

    Order

    assignment

  • SAP AG 2001, Title of Presentation, Speaker Name 13

    Revenues

    Idea & Concept

    Planning & Approval

    Project Execution

    Closing

    Structural Cost PlanningRevenues, like costs, can be planned direct-

    ly within the WBS hierarchy on various levels.

    Project/Sales Order Billing Plan The billing plan provides revenue planning by

    percentage or as overall values either via the

    project or the sales order.

    Milestone BillingDates and progress of milestones are used

    to trigger the billing procedure.

    Resource-Related Sales Pricing/BillingPlanned resources are used to feed the

    projects sales price calculation. During

    execution, actual costs can be used to derive

    the billing. The flexible and easy-to-use

    Dynamic Items Processor supports this.

    Resource

    related sales

    pricing / billing

    Milestone Billing

    Project progress triggers

    the billing procedure

    400

    200

    30 %

    70 %

    Project Billing Plan

    assigned directly in the WBS

    Structural Revenue Planning

    Top Down / Bottom Up

    400 600

    1.200

    200

    Sales Order

    assignment

    Sales Order

    Billing Plan

  • SAP AG 2001, Title of Presentation, Speaker Name 14

    Budget

    Idea & Concept

    Planning & Approval

    Project Execution

    Closing

    Project Budgeting along the Work Breakdown StructureThe projects cost plan as well as an assigned Investment Program* are the basis for

    deriving the original budget. After the approval, this can be used to control the budget

    availability against the expenditures during the execution phase. Additionally, the original

    budget can be broken down into smaller packages of released budget to allow an even

    more accurate availability control. All budgets can be planned by year or as overall values.

    Budget Updates during Execution Once the budget is approved, changes can be tracked to keep them under control.

    Project Cost Plan

    Original Budget

    + Supplements

    - Returns

    Budget

    Approved

    Yearly

    Budget

    !Budget

    Availability

    Control

    Released Budget

  • SAP AG 2001, Title of Presentation, Speaker Name 15

    Payments

    Idea & Concept

    Planning & Approval

    Project Execution

    Closing

    Project Cash ManagementProject-related payments can be planned either manually, based on project cost plan, or

    supported by various tools like invoice/ billing plans or down payment requests. During

    execution, payment relevant postings - through integration of other mySAP Solutions are

    feeding Project Cash Management and provide the most accurate information possible on

    incoming and outgoing payments.

    Payment Flow Analysis / Interest Calculation Payment information can be used to run various analysis as well as an interest calculation.

    Cash In

    Cash Out

    Interest Calculation

    Payment Flow Analysis

  • SAP AG 2001, Title of Presentation, Speaker Name 16

    Claim

    Idea & Concept

    Planning & Approval

    Project Execution

    Closing

    Claim ManagementCan be used to process any project relevant information like variances or claims from third

    parties who hold your business responsible for a variance that has occurred. In order to trig-

    ger the process, responsible persons can be identified and informed via Workflow.

    Powerful Claim Processing An Easy-Cost Planning calculation is provided to evaluate and plan the process. Necessary

    activities can be planned and tracked together with the claims status. The claim information

    system allows you to keep track of the claims progress.

    Claim

    !

    Customer

    Partner

    Project Team

    Claim Management:

    Cost Calculation

    Document Assignment

    Activity Planning / Task Tracking

    Status / Dates Control

    Workflow Processing

    Start Actions out of Claim

  • SAP AG 2001, Title of Presentation, Speaker Name 17

    Execution (Time)

    Idea & Concept

    Planning & Approval

    Project Execution

    Closing

    Cross Application Time Sheet - CATSOnce a project is released, actual time/cost can be booked against the project. Besides

    using a manual confirmation, CATS offers an ergonomic time entry interface. It allows you

    to book time against many objects within the mySAP Solutions also against WBS

    elements and activities. Before times are transferred to the target applications, entered

    times can be approved and released. The entered times lead to appropriate actual times

    and costs on the projects. Full change and cancellation handling are also provided.

    Integration into Material and Travel Cost Management

    HR CO

    MM

    CS

    PS

    Time Tracking

    Time Release

    Time Approval Tra

    nsfe

    r

    M T W T FTarget

    6 3 8 4Project / HR

    8 2 5 4Cost Center / HRCATS

    Internal &

    External

    Persons

  • SAP AG 2001, Title of Presentation, Speaker Name 18

    Project Information System

    Workforce

    Structures Logistical Infosystem

    Structures/Dates/Procurement

    PS Infosystem Finance

    Controlling/Finance/Payment

    Capacity Information System

    Workload/Workforce Planning

    Business Information Warehouse

    Predefined PS Info Cubes

    Controlling

    Hierarchy &

    Cost Element

    Reporting

    Business Information

    Warehouse

    Project Information System

    Multi Project Reporting

    Alternative Hierarchies

    Data Warehouse

    Profitability Analysis

  • SAP AG 2001, Title of Presentation, Speaker Name 19

    Progress

    Progress Analysis/ Earned Value

    Cost-to-Complete

    Milestone Trend Analysis

    Progress Tracking

    Project Information System

    Multi Project Reporting

    Alternative Hierarchies

    Data Warehouse

    Profitability Analysis

    Cost-to-Complete

    Progress Analysis

    Milestond

    Trend

    Analysis

    Progress Tracking

    X

    X

  • SAP AG 2001, Title of Presentation, Speaker Name 20

    Multi Project Reporting / Alternative Hierarchies

    Multi Project ReportingThe Information System within the Project

    System is also tailored to the special needs

    of analyzing many projects. Flexible

    selection methods allow accurate reporting.

    Alternative Hierarchy A hierarchy can be built accordingly using

    project characteristics (i.e. Product Line,

    Project Category).

    SummarizationProject information can be aggregated

    using the alternative hierarchy.

    Project ViewsAlternative hierarchies can be applied as

    special views in project reports.

    Project Information System

    Multi Project Reporting

    Alternative Hierarchies

    Data Warehouse

    Profitability Analysis

    Alternative Hierarchy

    Product Line

    Project Category

    Professional Line

    R&D Projects

    Economic Line

    R&D Projects

    Customer Projects

  • SAP AG 2001, Title of Presentation, Speaker Name 21

    Baselining & Simulation

    BaseliningA project version can be created manually or by reaching a particular status. Then all

    relevant data are stored aside the operative project and cannot be changed. Project

    changes can be monitored based on this.

    Simulation Using a simulation allows you to hold a complete project with an operative project. A

    simulation can be changed to carry out What-If-Analyses. A transfer back into the

    operative project does provide an update of the dates changed during the simulation.

    Project Version:

    Complete Snapshot of a Project

    Can also be created automatically

    Provides tracking of all Project Changes

    Project Simulation:

    Stores a project parallel to the operative one

    Can be changed and transferred back

    Provides What-If-Analyses

    Project Information System

    Multi Project Reporting

    Alternative Hierarchies

    Data Warehouse

    Profitability Analysis

  • SAP AG 2001, Title of Presentation, Speaker Name 22

    Employeegroup

    Order type

    Reg

    ion

    Junior consultant

    Senior consultant

    Management consultant

    Business IT Feasibility

    audit Cons. study

    No

    rth

    So

    uth

    East

    Report list

    Profitability Analysis

    Project Information System

    Multi Project Reporting

    Alternative Hierarchies

    Data Warehouse

    Profitability Analysis

    Controlling:

    Profitability AnalysisEnables you to evaluate market segments,

    which can be classified according to

    products, customers, orders or any

    combination of these, or strategic business

    units, such as sales organizations or

    business areas, with respect to your

    company's profit or contribution margin.

    Integration of Project Results The costs and revenues of a project can be

    transferred periodically by using the

    powerful settlement functionality which is

    directly integrated into the Profitability

    Analysis in Controlling.

    Profitability

    Analysis

  • SAP AG 2001, Title of Presentation, Speaker Name 23

    External Project System Interface (EPS)

    BAPI

    mySAP Program and

    Project Management

    mySAP

    OpenPS

    MS Project

    External Project System Interface

    (EPS) based on Business

    Application Programming

    Interface (BAPI)

    SAP delivers an EPS

    Solution for MS Project

    called OpenPS. Other

    Certified Solutions exist.

    Like Microsoft Project,

    Artemis, Primavera ...

    mySAP Project Management EPS InterfaceExternal

    Project System