Project Management. Projects „Unique, one-time operations designed to accomplish a specific set of objectives in a limited time frame.”

Dec 26, 2015

Download

Documents

Collin Stephens
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Project Management. Projects „Unique, one-time operations designed to accomplish a specific set of objectives in a limited time frame.”

Project Management

Page 2: Project Management. Projects „Unique, one-time operations designed to accomplish a specific set of objectives in a limited time frame.”

Projects

„„Unique, one-time operations designed to Unique, one-time operations designed to accomplish a specific set of objectives in a accomplish a specific set of objectives in a limited time frame.limited time frame.””

Page 3: Project Management. Projects „Unique, one-time operations designed to accomplish a specific set of objectives in a limited time frame.”

Processes in an organization

Usual business

processes

Projects

Changes &Uncertainty

Routines &regular tasks

Page 4: Project Management. Projects „Unique, one-time operations designed to accomplish a specific set of objectives in a limited time frame.”

Main characteristics of projects

• Uniqe set of tasks and processes• Narrow focus, specific performance objectives• The end of the project is definite:

– Limited time-frame– Objectives reached or – it is proven, that objectives cannot be reached

anymore

• Budget is limited• It can be planned• It is always risky

Page 5: Project Management. Projects „Unique, one-time operations designed to accomplish a specific set of objectives in a limited time frame.”

Project management

• Project management is the discipline of planning, organizing, and managing resources to bring about the successful completion of specific project goals and objectives.

• Project-like management: managing non-project processes as projects

Page 6: Project Management. Projects „Unique, one-time operations designed to accomplish a specific set of objectives in a limited time frame.”

Project Manager (Stevenson)

Responsible for:

Work (tasks) QualityHuman Resources TimeCommunications Costs

Page 7: Project Management. Projects „Unique, one-time operations designed to accomplish a specific set of objectives in a limited time frame.”

Other roles in the project

• Project-coordinator: negotiate with the functional leaders, report to the project manager

• Project champion: strong person who promotes and supports the project

• Projectmanagement-team members

• Project-workers: deliver the tasks

Page 8: Project Management. Projects „Unique, one-time operations designed to accomplish a specific set of objectives in a limited time frame.”

Project Life Cycle (Stevenson)

Concept

FeasibilityFeasibility

PlanningPlanning

ExecutionExecution

TerminationTermination

Man

agem

ent

Page 9: Project Management. Projects „Unique, one-time operations designed to accomplish a specific set of objectives in a limited time frame.”

Project life cycle

Page 10: Project Management. Projects „Unique, one-time operations designed to accomplish a specific set of objectives in a limited time frame.”
Page 11: Project Management. Projects „Unique, one-time operations designed to accomplish a specific set of objectives in a limited time frame.”

Cost of changing in the life cycle

Planning, preparation

Definintion Implementation, execution

Closing the

project

Time

Costs

Influence of the stakeholders

Cost of changing

Page 12: Project Management. Projects „Unique, one-time operations designed to accomplish a specific set of objectives in a limited time frame.”

Project-management tools

Page 13: Project Management. Projects „Unique, one-time operations designed to accomplish a specific set of objectives in a limited time frame.”

Problem tree diagramA problem tree is a problem analysis tool that illustrates the cause and effect

relationship of problems using a hierarchical tree diagram. • by arranging the problem statements in hierarchical order • and depicting the problem statements in a boxed article.

Page 14: Project Management. Projects „Unique, one-time operations designed to accomplish a specific set of objectives in a limited time frame.”

Problem-tree

Page 15: Project Management. Projects „Unique, one-time operations designed to accomplish a specific set of objectives in a limited time frame.”

Fishbone (Ishikawa) diagram• A Fishbone Diagram is a problem analysis tool that

illustrates the cause and effect relationships of problems and is often use in the quality management discipline.

Page 16: Project Management. Projects „Unique, one-time operations designed to accomplish a specific set of objectives in a limited time frame.”

Objective tree• An objective tree is an objective formulation tool that depicts

graphically the hierarchy of objectives. It is formulated by initially inverting the statements found in the problem tree (often used in tandem).

Page 17: Project Management. Projects „Unique, one-time operations designed to accomplish a specific set of objectives in a limited time frame.”

Logical Framework Matrix

Pre-conditions 

 

 4. Activities (inputs)

   3. Outputs (results)

   

2. Immediate objective

   1. Startegic goal

4. Risks and assumptions

3. Means of verifi-cation2. Indicators

1. Objectives-structure

Page 18: Project Management. Projects „Unique, one-time operations designed to accomplish a specific set of objectives in a limited time frame.”

Work Breakdown Structure

• a tool used to define and group a project's discrete work elements (or tasks) in a way that helps organize and define the total work scope of the project

Page 19: Project Management. Projects „Unique, one-time operations designed to accomplish a specific set of objectives in a limited time frame.”

GANTT charts

• A Gantt chart is a type of bar chart that illustrates a project schedule.

• Gantt charts illustrate the start and finish dates of the terminal elements and summary elements of a project.

• Some Gantt charts also show the dependency relationships between activities.

• Gantt charts can be used to show current schedule status using percent-complete shadings, or colored lines and a vertical "TODAY" line.

Page 20: Project Management. Projects „Unique, one-time operations designed to accomplish a specific set of objectives in a limited time frame.”

GANTT charts

ID Activities Who is responsible?

Time intervals

1. 2. 3. 4. 5. 6. 7. 8.

1.

2.

3.

4.

5.

6.

7.

8

9

10.

11.

Page 21: Project Management. Projects „Unique, one-time operations designed to accomplish a specific set of objectives in a limited time frame.”

GANTT charts

6.

5.

4.

3.

2.

1.

timeactivities

Page 22: Project Management. Projects „Unique, one-time operations designed to accomplish a specific set of objectives in a limited time frame.”

GANTT charts

Page 23: Project Management. Projects „Unique, one-time operations designed to accomplish a specific set of objectives in a limited time frame.”

GANTT charts

6.

5.

4.

3.

2.

1.

timeActivities

today

Page 24: Project Management. Projects „Unique, one-time operations designed to accomplish a specific set of objectives in a limited time frame.”

The Network Diagram

• Network (precedence) diagram

• Activity-on-arrow (AOA)

• Activity-on-node (AON)

• Activities

• Events

Page 25: Project Management. Projects „Unique, one-time operations designed to accomplish a specific set of objectives in a limited time frame.”

The Network Diagram• Path

– Sequence of activities that leads from the starting node to the finishing node

• Critical path– The longest path; determines expected project

duration

• Critical activities– Activities on the critical path

• Slack– Allowable slippage for path; the difference the

length of path and the length of critical path

Page 26: Project Management. Projects „Unique, one-time operations designed to accomplish a specific set of objectives in a limited time frame.”

Project Network – Activity on Arrow

1

2

3

4

5 6

Locatefacilities

Orderfurniture

Furnituresetup

InterviewHire andtrain

Remodel

Move in

AOA

Page 27: Project Management. Projects „Unique, one-time operations designed to accomplish a specific set of objectives in a limited time frame.”

Project Network – Activity on Node

a

b

c

e

f

Locatefacilities

Orderfurniture

Furnituresetup

Interview

RemodelMove in

d

Hire andtrain

g

AON

FINISHSTART

Page 28: Project Management. Projects „Unique, one-time operations designed to accomplish a specific set of objectives in a limited time frame.”

Network Conventions

a

b

c a

b

c

a

b

c

d

a

b

c

Dummyactivity

Page 29: Project Management. Projects „Unique, one-time operations designed to accomplish a specific set of objectives in a limited time frame.”

Time Estimates

• Deterministic

– Time estimates that are fairly certain

• Probabilistic

– Estimates of times that allow for variation

Page 30: Project Management. Projects „Unique, one-time operations designed to accomplish a specific set of objectives in a limited time frame.”

Deterministic time estimates

1

2

3

4

5 6

8 weeks

6 weeks

3 weeks

4 weeks9 weeks

11 weeks

1 week

Locate

facilities

Order

furniture Fu

rnitu

re

setup

InterviewHire

and train

Remodel Move in

Page 31: Project Management. Projects „Unique, one-time operations designed to accomplish a specific set of objectives in a limited time frame.”

Solution

P a t h L e n g t h( w e e k s )

S l a c k

1 - 2 - 3 - 4 - 5 - 61 - 2 - 5 - 61 - 3 - 5 - 6

1 82 01 4

206

Critical PathCritical Path

Page 32: Project Management. Projects „Unique, one-time operations designed to accomplish a specific set of objectives in a limited time frame.”

Probabilistic Time Estimates

• Optimistic time

– Time required under optimal conditions

• Pessimistic time

– Time required under worst conditions

• Most likely time

– Most probable length of time that will be required

Page 33: Project Management. Projects „Unique, one-time operations designed to accomplish a specific set of objectives in a limited time frame.”

1-3-4a

3-4-5d

3-5-7e

5-7-9f

2-4-6b

4-6-8h

2-3-6g 3-4-6

i

2-3-5c

Optimistictime

Most likelytime

Pessimistictime

Page 34: Project Management. Projects „Unique, one-time operations designed to accomplish a specific set of objectives in a limited time frame.”

Sample: a research-projectSurvey on students• Task 1: literature overview• Task 2: design questionaire• Task 3: collect a sample of subjects• Task 4: printing questionaires• Task 5: fieldwork• Task 6: analyse data• Task 7: writing up• Task 8: prepare a presentation• Task 9: presenting to the customer

Page 35: Project Management. Projects „Unique, one-time operations designed to accomplish a specific set of objectives in a limited time frame.”

AOA Network diagramWhat is its AON version?

a

c

d

b

e

f

6

5

10

4

9

2

Page 36: Project Management. Projects „Unique, one-time operations designed to accomplish a specific set of objectives in a limited time frame.”

Solution?

Page 37: Project Management. Projects „Unique, one-time operations designed to accomplish a specific set of objectives in a limited time frame.”

Problem: converting table data to AoA and AoN

Activity

Immediatepredecessor

Duration

a - 2

b a 3

c b 2

d b 1

TPT = ? Float = ?

Page 38: Project Management. Projects „Unique, one-time operations designed to accomplish a specific set of objectives in a limited time frame.”

Solution (AoN)

Solution (AoA)

a2

b3

c2

d1

finishstar

t

1 22a 3

2c

4

53b

1d

Page 39: Project Management. Projects „Unique, one-time operations designed to accomplish a specific set of objectives in a limited time frame.”

Solution: TPT from critical path analysis

• Identify all the paths and their duration:a-b-c = 7

a-b-d = 6

• The path with the longest duration is the critical path, and it sets the TPT = 7

• Identify the floats:The non-critical activities have floats. Here the only non-

critical is the d. Its float is the time that it can use up without increasing the TPT. This time it is: 7 – 6 = 1

Page 40: Project Management. Projects „Unique, one-time operations designed to accomplish a specific set of objectives in a limited time frame.”