7/25/2019 Project Management Professional PMP Exam Prep based on PMBOK guide 5th Free Sample Training Course
1/79
7/25/2019 Project Management Professional PMP Exam Prep based on PMBOK guide 5th Free Sample Training Course
2/79
Chapter 1
Introduction to Project Management
10/11/2017 11:40 AM 2
7/25/2019 Project Management Professional PMP Exam Prep based on PMBOK guide 5th Free Sample Training Course
3/79
What is Project Management?
The application of knowledge, skills, tools and technique to
project activities to meet project requirements
Project Management is accomplished through the application and
integration of the processes such as
Initiating
Planning
Executing
Monitoring and Controlling
Closing
10/11/2017 11:40 AM 3
7/25/2019 Project Management Professional PMP Exam Prep based on PMBOK guide 5th Free Sample Training Course
4/79
The Triple Constraint of Project Management
Scope
10/11/2017 11:40 AM 4
It is the project managers duty to balance and achieve
these three often
-
competing goals.
7/25/2019 Project Management Professional PMP Exam Prep based on PMBOK guide 5th Free Sample Training Course
5/79
Constraint of Project Management
Cost
Customer
Satisfaction
Project
10/11/2017 11:40 AM 5
7/25/2019 Project Management Professional PMP Exam Prep based on PMBOK guide 5th Free Sample Training Course
6/79
10/11/2017 11:40 AM 6
Project, Program, Portfolio
Project E
7/25/2019 Project Management Professional PMP Exam Prep based on PMBOK guide 5th Free Sample Training Course
7/79
Project, Program, Portfolio
10/11/2017 11:40 AM 7
7/25/2019 Project Management Professional PMP Exam Prep based on PMBOK guide 5th Free Sample Training Course
8/79
Project-Based Organizations
Project-based organizations (PBOs) refer to variousorganizational forms that create temporary systems forcarrying out their work. (as in telecommunications, oil andgas, construction, consultancy, and professional Services)
10/11/2017 11:40 AM 8
7/25/2019 Project Management Professional PMP Exam Prep based on PMBOK guide 5th Free Sample Training Course
9/79
Chapter 2
Project Life Cycle and Organization
10/11/2017 11:40 AM 9
7/25/2019 Project Management Professional PMP Exam Prep based on PMBOK guide 5th Free Sample Training Course
10/79
Project Life Cycle (Technical Work)
Project Life Cycle is a collection of generally sequential and
sometimes overlapping project phases.(not black box)
Project Phases are marked by the completion of a deliverable
(Tangible, verifiable work product).
Review of deliverables and approval/denial-phase end
review- are phase exits, stage gates, or kill points???
All projects are divided into phases, and all projects, large or
small, have a similar life cycle structure.
10/11/2017 11:40 AM 10
7/25/2019 Project Management Professional PMP Exam Prep based on PMBOK guide 5th Free Sample Training Course
11/79
Project
Phase 1
Project
Phase 2
Project
Phase 3
Project
Phase 4
Initiation Conclusion
Handoff Handoff Handoff
GatesGatesGates
Deliverables Deliverables Deliverables
10/11/2017 11:40 AM 11
Project Life Cycle
Project phases differ from project to another
Construction: Feasibility-> Planning -> Design -> Production -> Turnover -> StartupIT Project: Requirement -> Design -> Program -> Test -> Implement
7/25/2019 Project Management Professional PMP Exam Prep based on PMBOK guide 5th Free Sample Training Course
12/79
Fast Tracking
There are times when phases are
overlapped to shorten or compress the
project schedule. This is called Fast
Tracking.
Fast tracking means that a later phase is
started prior to completing and approving the
phase, or phases, that come before it.
This technique is used to shorten the overall
duration of the project.
10/11/2017 11:40 AM 12
7/25/2019 Project Management Professional PMP Exam Prep based on PMBOK guide 5th Free Sample Training Course
13/79
Project Stakeholders
10/11/2017 11:40 AM 13
An important part of a project managers responsibility is to manage
stakeholder expectations, which can be difficult because
stakeholders often have very different or conflicting objectives.
Part of the project managers responsibility is to balance these
interests and ensure that the project team interacts with
stakeholders in a professional and cooperative manner.
7/25/2019 Project Management Professional PMP Exam Prep based on PMBOK guide 5th Free Sample Training Course
14/79
Co
standstaffingle
vel
Time
Initial Phase Intermediate Phase(s) Final Phase
cost of changes
influence of stakeholders
Stakeholders Influence Over Time
10/11/2017 11:40 AM 14
7/25/2019 Project Management Professional PMP Exam Prep based on PMBOK guide 5th Free Sample Training Course
15/79
Project Success
The success of the project should be measured in terms ofcompleting the project within the constraints of scope, time,cost, quality, resources, and risk as approved between theproject managers and senior management.
10/11/2017 11:40 AM 15
7/25/2019 Project Management Professional PMP Exam Prep based on PMBOK guide 5th Free Sample Training Course
16/79
Organizational Structure- FunctionalOrganization
The organization is grouped by areas of specialization within differentfunctional areas.
Projects generally occur within a single department.
Information required from other department will be routed through
departmental heads.
Team members complete project work in addition to normal department
work.10/11/2017 11:40 AM 16
7/25/2019 Project Management Professional PMP Exam Prep based on PMBOK guide 5th Free Sample Training Course
17/79
Organizational Structure- BalancedMatrix Organization
Two Bosses
Team members reports to
Project Manager and Functional
Manager
Team members do project work
in addition to normal
departmental work
Power is shared between thefunctional and project manager
10/11/2017 11:40 AM 17
7/25/2019 Project Management Professional PMP Exam Prep based on PMBOK guide 5th Free Sample Training Course
18/79
Iterative and Incremental Life Cycles
Ones in which project phases (also called iterations)intentionally repeat one or more project activities as the
project teams understanding of the product increases,while increments successively add to the functionality ofthe product.
10/11/2017 11:40 AM 18
7/25/2019 Project Management Professional PMP Exam Prep based on PMBOK guide 5th Free Sample Training Course
19/79
Chapter 4
Project Integration Management
10/11/2017 11:40 AM 19
7/25/2019 Project Management Professional PMP Exam Prep based on PMBOK guide 5th Free Sample Training Course
20/79
Project Integration Management
Project Integration Management includes the processesand activities to identify, define, combine, unify, andcoordinate the various processes and project managementactivities within the Project Management Process Groups.
10/11/2017 11:40 AM 20
7/25/2019 Project Management Professional PMP Exam Prep based on PMBOK guide 5th Free Sample Training Course
21/79
Develop Project Charter
Project Charter is the process of developing adocument that formally authorizes the existence of a
project and provides the project manager with the
authority to apply organizational resources to project
activities.
The Project Managershould always be assigned prior
to the start of planning, and preferably while the project
charter is being developed.
The Project Charter is Issued by a sponsor, not the
project manager, but preferred to be participated in
developing it.
10/11/2017 11:40 AM 21
7/25/2019 Project Management Professional PMP Exam Prep based on PMBOK guide 5th Free Sample Training Course
22/79
Project Selection Methods
Project selection is generally the responsibility of Portfolio Managers,
Steering Committees. In smaller companies, Presidents and Vice- Presidents.
These methods generally fall into one of two broad categories:
Benefit measurement methods (comparative approach) that are
comparative approaches:murder board, peer review, scoring models,
benefit contribution, or Economic models.
Constrained optimization methods (Mathematical approach) that useprograms; linear, nonlinear, dynamic, integer, or multi-objective
programming algorithms
10/11/2017 11:40 AM 22
7/25/2019 Project Management Professional PMP Exam Prep based on PMBOK guide 5th Free Sample Training Course
23/79
1. Present valuePresent value :PV = FV/(1 + r)n
FV = amount of money t years from now
r = interest rate (also called discount rate)
n = time period
Assume a 10% interest (or discount) rate
PV (Year 1) = FV / (1 + r)t =$35,000/(1 + 0.1)1= $31,819
Economic Model
Year FV PV
0 $50,000 $50,000
1 $35,000 $31,819
2 $15,000 $12,397
10/11/2017 11:40 AM 23
7/25/2019 Project Management Professional PMP Exam Prep based on PMBOK guide 5th Free Sample Training Course
24/79
2. Net present value: This Means the total benefits (income or revenue) less
the cost. To calculate NPV you need to calculate the present value of each
of the income and revenue figures then add up the present values.
Time
Period
Income or
revenue
Present Value
at 10% interest
rate
Costs Present Value
at Costs 10%
interest rate
0 0 0 200 200
1 50 45 100 91
2 100 83 0 0
3 300 225 0 0
Total 353 291
NPV=353-291=6210/11/2017 11:40 AM 24
Economic Model
7/25/2019 Project Management Professional PMP Exam Prep based on PMBOK guide 5th Free Sample Training Course
25/79
Requirements Traceability Matrix
A grid that links product requirements from their origin to the deliverables that satisfythem.It provides a mean to track requirements throughout the project life cycle.
Matrix helps to ensure that requirements approved in requirements documentation
are delivered at the end of the project.
Attributes associated with each requirement can be recorded in the requirements
traceability matrix.
Collect Requirements Outputs
10/11/2017 11:40 AM 25
7/25/2019 Project Management Professional PMP Exam Prep based on PMBOK guide 5th Free Sample Training Course
26/79
Create WBS
The WBS is a deliverables-orientateddecomposition of the work to be executed by
project team to accomplish the project
objectives and create the required
deliverables.
The planned work is contained within the
lowest level WBS components (work
packages) which can be scheduled, cost
estimated, monitored and controlled.
The top most level of each WBS is the total
project itself
10/11/2017 11:40 AM 26
7/25/2019 Project Management Professional PMP Exam Prep based on PMBOK guide 5th Free Sample Training Course
27/79
Question
You're the project manager for an advertising campaign. The stakeholders,
including the client, approved your completed WBS. Later, after some of the
artwork has been printed, the client wants to add a registered trademark
symbol, which will cost a considerable amount of money. The client says that
your company's salesperson, prior to signoff on the WBS, promised this
feature would be included. Who should pay for the change?
A. Your company managing the project
B. Both the client and your company should pay part of the cost
C. The change should not be implemented
D. The client
10/11/2017 11:40 AM 27
7/25/2019 Project Management Professional PMP Exam Prep based on PMBOK guide 5th Free Sample Training Course
28/79
Create WBS Outputs
A WBS structure may be created through various approaches. Some of
the popular methods include the top down approach, the use of
organization-specific guidelines, and the use of WBS templates. A bottom-
up approach can be used during the integration of subcomponents
The WBS is a hierarchical decomposition of the total scope of work to be
carried out by the project team to accomplish the project objectives and
create the required deliverables.
10/11/2017 11:40 AM 28
7/25/2019 Project Management Professional PMP Exam Prep based on PMBOK guide 5th Free Sample Training Course
29/79
Validate Scope
Validate Scope is the process of formalizing acceptance of the completedproject.
The Validate Scope process differs from the Control Quality process in that
the former is primarily concerned with acceptance of the deliverables, while
quality control is primarily concerned with correctness of the deliverables
and meeting the quality requirements specified for the deliverables.
Control Quality is generally performed before Validate Scope, although the
two processes may be performed in parallel.
10/11/2017 11:40 AM 29
7/25/2019 Project Management Professional PMP Exam Prep based on PMBOK guide 5th Free Sample Training Course
30/79
Three Point Estimates (PERT)
10/11/2017 11:40 AM 30
7/25/2019 Project Management Professional PMP Exam Prep based on PMBOK guide 5th Free Sample Training Course
31/79
PERT Calculations
If all activities are on critical, then total estimated project duration = sum of
PERT values for each activities.
Standard Deviation shall not be added. Add variance of each activities and
take square root of sum to get standard deviation for total project.
In the example above, range will be 170.167 +/-10.060
Estimate Activity Durations : Tools &Techniques
Activity O M P PERT SD Variance Range
A 14 27 47
B 41 60 89
C 39 44 48
D 29 37 42
10/11/2017 11:40 AM 31
7/25/2019 Project Management Professional PMP Exam Prep based on PMBOK guide 5th Free Sample Training Course
32/79
PERT Calculations
If all activities are on critical, then total estimated project duration = sum of
PERT values for each activities.
Standard Deviation shall not be added. Add variance of each activities and
take square root of sum to get standard deviation for total project.
In the example above, range will be 170.167 +/-10.060
Estimate Activity Durations : Tools &Techniques
Activity O M P PERT SD Variance Range
A 14 27 47 28,167 5.5 30,25 28.167+/-5.5
B 41 60 89 61,667 8 64 61.667+/-8
C 39 44 48 43,833 1.5 2.25 43.833+/-1.5
D 29 37 42 36,500 2.167 4.694 336,5+/-2.167
10/11/2017 11:40 AM 32
7/25/2019 Project Management Professional PMP Exam Prep based on PMBOK guide 5th Free Sample Training Course
33/79
Group Decision-Making Techniques
Team-based approaches, such as brainstorming, the Delphi or nominal
group techniques, are useful for engaging team members to improve
estimate accuracy and commitment to the emerging estimates. By involving
a structured group of people who are close to the technical execution of
work in the estimation process, additional information is gained and more
accurate estimates obtained.
Estimate Activity Durations : Tools &Techniques
10/11/2017 11:40 AM 33
7/25/2019 Project Management Professional PMP Exam Prep based on PMBOK guide 5th Free Sample Training Course
34/79
Reserve Analysis
Contingency Reserve time also called buffer or time reserves
Reserve is added to account for schedule risk.
You might choose to add a percentage of time or a set number of work
periods to the activity or the overall schedule.
If not done properly can lead to padding
Contingency reserve shall be clearly identified and documented for future
analysis
Estimate Activity Durations : Tools &Techniques
10/11/2017 11:40 AM 34
7/25/2019 Project Management Professional PMP Exam Prep based on PMBOK guide 5th Free Sample Training Course
35/79
Develop Schedule-Tools & Techniques
Schedule Network Analysis
Schedule network analysis is a technique that generates the project
schedule.
It employs a schedule model and various analytical techniques, such as
critical path method, critical chain method, what-if analysis, and resource
levelling to calculate the early and late start and finish dates for the
uncompleted portions of project activities.
Critical Path Method A method used to estimate the minimum project duration and determine the
amount of scheduling flexibility on the logical network paths within the
schedule model
10/11/2017 11:40 AM 35
7/25/2019 Project Management Professional PMP Exam Prep based on PMBOK guide 5th Free Sample Training Course
36/79
Example of Critical Path Method
10/11/2017 11:40 AM 36
7/25/2019 Project Management Professional PMP Exam Prep based on PMBOK guide 5th Free Sample Training Course
37/79
Network Diagram Nodes
ES = Earliest date an activity can be started EF = Earliest date an activity can be completed LS = Latest date an activity can start LF = Latest date an activity can be completed
ES
LS LF
EF
Duration
Forward pass
Backward pass
10/11/2017 11:40 AM 37
7/25/2019 Project Management Professional PMP Exam Prep based on PMBOK guide 5th Free Sample Training Course
38/79
7/25/2019 Project Management Professional PMP Exam Prep based on PMBOK guide 5th Free Sample Training Course
39/79
Develop Schedule: Tools and TechniquesResource Optimization Techniques
1. Resourceleveling.Atechnique in whichstart and finishdates are adjusted
based on resourceconstraints with thegoal of balancingdemand forresources with theavailable supply.
10/11/2017 11:40 AM 39
7/25/2019 Project Management Professional PMP Exam Prep based on PMBOK guide 5th Free Sample Training Course
40/79
Develop Schedule: Tools and TechniquesModeling Techniques
1. What-If Scenario Analysis. is the process of evaluating scenarios
in order to predict their effect, positively or negatively, on project
objectives.
2. Simulation. involves calculating multiple project durations withdifferent sets of activity assumptions, usually using probability
distributions constructed from the three-point estimates
10/11/2017 11:40 AM 40
7/25/2019 Project Management Professional PMP Exam Prep based on PMBOK guide 5th Free Sample Training Course
41/79
Develop Schedule: Tools and TechniquesSchedule Compression
Fast Tracking Performing critical path tasks in parallel and
riskier than crashing Eg,.Design is half finished and start coding
Crashing
Analyze cost and schedule trade-offs Determine most compression for least cost Crash the tasks that cost the least first,
focusing on minimizing project cost
10/11/2017 11:40 AM 41
7/25/2019 Project Management Professional PMP Exam Prep based on PMBOK guide 5th Free Sample Training Course
42/79
Milestone Chart
10/11/2017 11:40 AM 42
7/25/2019 Project Management Professional PMP Exam Prep based on PMBOK guide 5th Free Sample Training Course
43/79
Project Calendars
project calendar identifies working days and shifts that are available
for scheduled activities. It distinguishes time periods in days or parts
of days that are available to complete scheduled activities from time
periods that are not available. A schedule model may require more
than one project calendar to allow for different work periods for
some activities to calculate the project schedule. The project
calendars may be updated.
10/11/2017 11:40 AM 43
7/25/2019 Project Management Professional PMP Exam Prep based on PMBOK guide 5th Free Sample Training Course
44/79
Sample PMP
CertificationQuestions
7/25/2019 Project Management Professional PMP Exam Prep based on PMBOK guide 5th Free Sample Training Course
45/79
Exercise
Q1. The estimate for a task is O = 3 days, P = 7 days, M = 4 days. What is the standarddeviation of the task?
A. 5/6 of a day -B. 2/3 of a day -C. 1 days -D. 5 2/3 days
Solution: SD = (P-O)/6 = (7-3)/6 = 2/3
Q2. You are the project manager for a new project and have figured out the following
dependencies: Task 1 can start immediately and has an estimated duration of 3 weeks
Task 2 can start after Task1 is completed and has an estimated duration of 3 weeks
Task 3 can start after Task 1 is completed and has an estimated duration of 6 weeks
Task 4 can start after Task 2 is completed and has an estimated duration of 8 weeks
Task 5 can start after task 4 is completed and after Task 3 is completed . This tasktakes 4 weeks.
What is the duration of the critical path?
A. 18.5 weeks -B. 19 weeks -C. 20 weeks -D. 18 weeks
10/11/2017 11:40 AM 45
7/25/2019 Project Management Professional PMP Exam Prep based on PMBOK guide 5th Free Sample Training Course
46/79
You are the project manager fora project with the followingnetwork diagram. Studying thediagram, which path is thecritical path?
A. ABCDB. EBCD
C. EFH
D. EGH
10/11/2017 11:40 AM 46
Exercise
7/25/2019 Project Management Professional PMP Exam Prep based on PMBOK guide 5th Free Sample Training Course
47/79
Chapter 7
Project Cost Management
10/11/2017 11:40 AM 47
7/25/2019 Project Management Professional PMP Exam Prep based on PMBOK guide 5th Free Sample Training Course
48/79
Forecasting
Using the earned value analysis, team can now forecast the project
performance.
Estimate at completion (EAC) may differ from Budget at Completion (BAC)
Estimate to complete (ETC) is the estimate of remaining work. Now
Estimate at completion = AC + ETC.
Control Costs- Tools and Techniques
10/11/2017 11:40 AM 48
7/25/2019 Project Management Professional PMP Exam Prep based on PMBOK guide 5th Free Sample Training Course
49/79
Plan Human Resource Management:Outputs
Human Resource Management Plan - which includes:
Roles and Responsibilities
Role. The function assumed by or assigned to a person in the project.
Authority. The right to apply project resources, make decisions, sign
approvals, accept deliverables, and influence others to carry out the work of
the project.
Responsibility. The assigned duties and work that a project team member is
expected to perform in order to complete the projects activities.
Competency. The skill and capacity required to complete assigned activities
within the project constraints.10/11/2017 11:40 AM 49
7/25/2019 Project Management Professional PMP Exam Prep based on PMBOK guide 5th Free Sample Training Course
50/79
Acquire Project Team
The process of confirming human resource availability and obtaining the team
necessary to complete project activities.
10/11/2017 11:40 AM 50
http://wendyjacobs.com.au/http://wendyjacobs.com.au/7/25/2019 Project Management Professional PMP Exam Prep based on PMBOK guide 5th Free Sample Training Course
51/79
Multi-Criteria Decision Analysis
Knowledge. Consider if the team member has relevant knowledge of the customer,
similar implemented projects, and nuances of the project environment.
Skills. Determine whether the member has the relevant skills to use a project tool,
implementation, or training.
Attitude. Determine whether the member has the ability to work with others as a
cohesive team.
International factors. Consider team member location, time zone and
communication capabilities.
10/11/2017 11:40 AM 51
Acquire Project Team: Tools &Techniques
7/25/2019 Project Management Professional PMP Exam Prep based on PMBOK guide 5th Free Sample Training Course
52/79
Develop Project Team
Develop Project Team is the process of improving competencies,team member interaction, and overall team environment to enhanceproject performance.
10/11/2017 11:40 AM 52
7/25/2019 Project Management Professional PMP Exam Prep based on PMBOK guide 5th Free Sample Training Course
53/79
Motivation Theory: McGregors X & Y Theory
Theory X
People tends to be negative, passive e.g. Avoid responsibility,
need to be watched
Extrinsic Motivation
Theory Y
People tends to be positive e.g. Want to achieve, willing to work
without supervision, can direct their own effort
Intrinsic Motivation
10/11/2017 11:40 AM 53
7/25/2019 Project Management Professional PMP Exam Prep based on PMBOK guide 5th Free Sample Training Course
54/79
Herzbergs Theory
Job Satisfaction due to lack of hygiene factors
Job satisfaction due to motivation factors
Hygiene Factors
Working conditionSalaryPersonal life
Relationship at workSecuritystatus
Motivations Factors
ResponsibilitySelf actualizationProfessional growthrecognitionPersonal lifeRelationship at workSecurity
status10/11/2017 11:40 AM 54
Develop Project Team: Tools &
7/25/2019 Project Management Professional PMP Exam Prep based on PMBOK guide 5th Free Sample Training Course
55/79
Team Building Activities: Such
activities can vary from a five minute
agenda item in a status review
meeting to an off-site, professionally
facilitated experienced designed to
improve interpersonal relationships.
Informal communication and activities
supported building trust and
establishing good working
relationships.
Develop Project Team: Tools &Techniques
10/11/2017 11:40 AM 55
7/25/2019 Project Management Professional PMP Exam Prep based on PMBOK guide 5th Free Sample Training Course
56/79
Develop Project Team: Tools andTechniques
Team Building Activities
One theory states that there are 5 stages of development that the teams may
go through. Usually these stages occur in an order .
1. Forming : this phase is where the team meets and learns about the project
and what their formal roles and responsibilities are . Team members tend to
be independent and not as open in this phase
2. Storming : During this phase , the team begins to address the project work,
technical decisions , and the project management approach . If team
members are not collaborative and open to differing ideas and perspectives
the environment can become destructive.
.
10/11/2017 11:40 AM 56
Pl C i ti M t T l d
7/25/2019 Project Management Professional PMP Exam Prep based on PMBOK guide 5th Free Sample Training Course
57/79
Plan Communications Management: Tools andTechniques
Communication Requirements AnalysisThe total number of potentialcommunication channels is n(n 1)/2,where n represents the number of
stakeholders
10/11/2017 11:40 AM 57
2)1(
NN
7/25/2019 Project Management Professional PMP Exam Prep based on PMBOK guide 5th Free Sample Training Course
58/79
Communication Methods:
Interactive communication - Between two or more parties in
multidirectional (Phone calls, meetings, interviews). Most effective way.
Push communication - Sent a specific information to specific recipients.
Examples are letters, memos, e-mails, faxes etc. This ensures that
message is sent but will but will not certify that it is actually received or
understood. (Push the message to recipient)
Pull communication Used for large volume of information and large
audiences. Examples are internet sites, company data bases, e-learning
etc. Recipients has to access the communication content (Pull out
information) at their own discretion.
Plan Communication : Tools & Techniques
10/11/2017 11:40 AM 58
7/25/2019 Project Management Professional PMP Exam Prep based on PMBOK guide 5th Free Sample Training Course
59/79
Chapter 11
Project Risk Management
10/11/2017 11:40 AM 59
Perform Quantitative Risk Analysis Tools &
7/25/2019 Project Management Professional PMP Exam Prep based on PMBOK guide 5th Free Sample Training Course
60/79
Modelling and Simulation: Project simulations allow the project team to
play what-if games without affecting any areas of production. The Monte
Carlo technique is the most common simulation.
Monte Carlo, typically completed through a computer software program,
completely simulates a project with values for all possible variables topredict the most likely model.
Perform Quantitative Risk Analysis Tools &Techniques
10/11/2017 11:40 AM 60
7/25/2019 Project Management Professional PMP Exam Prep based on PMBOK guide 5th Free Sample Training Course
61/79
Control Risks
Control Risks is the process of implementing risk response plans, trackingidentified risks, monitoring residual risks, identifying new risks, and evaluating
risk process effectiveness throughout the project.
Control Risks Tools & Techniques
Reserve Analysis: it compared the amount of the contingency reserves
remaining to the amount of risk remaining at any time in the project
10/11/2017 11:40 AM 61
7/25/2019 Project Management Professional PMP Exam Prep based on PMBOK guide 5th Free Sample Training Course
62/79
Chapter 12
Project Procurement Management
10/11/2017 11:40 AM 62
7/25/2019 Project Management Professional PMP Exam Prep based on PMBOK guide 5th Free Sample Training Course
63/79
Project Procurement Management
Plan Procurement Management is the process of documenting project
procurement decisions, specifying the approach, and identifying potential
sellers.
PM must be involved in the creation of the contracts
10/11/2017 11:40 AM 63
P j P M T l &
7/25/2019 Project Management Professional PMP Exam Prep based on PMBOK guide 5th Free Sample Training Course
64/79
Project Procurement Management Tools &Techniques
Make-or-Buy AnalysisIt is a general management technique used to determine whether particularwork can best be accomplished by the project team or must be purchasedfrom outside sources.
You are trying to decide whether to lease or buy an item for your project.The daily lease cost is Dhs. 120. To purchase the item investment cost isDhs. 1000 and the daily cost is Dhs. 20. How long will it take for the leasecost to be the same as the purchase cost?
Let D equal the number of days when the purchase and lease costs areequal.
QR 120 D = QR 1000 + QR 20 D
QR 120 D - QR 20 D = QR 1000 QR 100 D = QR 1000
D = QR 1000 / QR 100
D = 10
The least cost will be the same as the purchase cost after ten days.
10/11/2017 11:40 AM 64
7/25/2019 Project Management Professional PMP Exam Prep based on PMBOK guide 5th Free Sample Training Course
65/79
Contract Types:
Contract is a mutually binding legal agreement that
obligates the seller to provide the specified products,
services or results, and obligates the buyer to
compensate the seller.
The contract may includes the following: An offer,
Acceptance, Pricing, roles and responsibilities,
penalties, warranty,
1. Purchase Order: Contract to purchase 30 linear
meters of wood at Dhs. 40 per meter
Legal Contractual Relationships
10/11/2017 11:40 AM 65
7/25/2019 Project Management Professional PMP Exam Prep based on PMBOK guide 5th Free Sample Training Course
66/79
Chapter 13
Project Stakeholder Management
10/11/2017 11:40 AM 66
7/25/2019 Project Management Professional PMP Exam Prep based on PMBOK guide 5th Free Sample Training Course
67/79
Identify Stakeholders
Identify Stakeholders is the process of identifying the people,groups, or organizations that could impact or be impacted by adecision, activity, or outcome of the project, analyzing anddocumenting relevant information regarding their interests,involvement, interdependencies, influence, and potential impact onproject success.
It is critical for project success to identify the stakeholders early inthe project or phase and to analyze their levels of interest, their
individual expectations, as well as their importance and influence.
10/11/2017 11:40 AM 67
7/25/2019 Project Management Professional PMP Exam Prep based on PMBOK guide 5th Free Sample Training Course
68/79
Identify Stakeholders: Tools and Techniques
Stakeholder Analysis: is a technique of systematicallygathering and analyzing quantitative and qualitativeinformation to determine whose interests should betaken into account throughout the project.
10/11/2017 11:40 AM 68
Identify Stakeholders : Tools &
7/25/2019 Project Management Professional PMP Exam Prep based on PMBOK guide 5th Free Sample Training Course
69/79
Identify Stakeholders : Tools &Techniques
Step 1:Identify all potential project stakeholders andrelevant information such as their roles, departments,
interest, knowledge levels, expectations and influence
levels .
Step 2 :Identify the potential impact or support each
stakeholder could generate and classify them so as to
define an approach strategy.
Step 3 :Access how key stakeholders are likely to react
in various situations and plan how to influence them for
their support and mitigate potential negative impact
10/11/2017 11:40 AM 69
Plan Stakeholder Management: Tools
7/25/2019 Project Management Professional PMP Exam Prep based on PMBOK guide 5th Free Sample Training Course
70/79
Plan Stakeholder Management: Toolsand Techniques
Analytical Techniques:The engagement level of the stakeholders can be classified as follows:
Unaware. Unaware of project and potential impacts.
Resistant.Aware of project and potential impacts and resistant to
change.
Neutral.Aware of project yet neither supportive nor resistant.
Supportive.Aware of project and potential impacts and supportive
to change.
Leading.Aware of project and potential impacts and actively
engaged in ensuring the project is a success.
10/11/2017 11:40 AM 70
7/25/2019 Project Management Professional PMP Exam Prep based on PMBOK guide 5th Free Sample Training Course
71/79
Chapter 13Professional Responsibility
10/11/2017 11:40 AM 71
7/25/2019 Project Management Professional PMP Exam Prep based on PMBOK guide 5th Free Sample Training Course
72/79
Professional Responsibility
About 18 questions on the exam cover this part.
The PMP must adhere to a high set of principles, rules, and policies.
On the PMP exam, always choose the answer which best supports the PMP
profession and the higher set of principles the PMP is expected to adhere to.
Did you realize that it is unethical to manage a project if you have not been
trained in project management? Did you know that it is unethical to provide a
project schedule that you do not believe to be accurate?
10/11/2017 11:40 AM 72
Responsibility
Fairness
Respect
Honesty
Responsibility- ownership of decisions
7/25/2019 Project Management Professional PMP Exam Prep based on PMBOK guide 5th Free Sample Training Course
73/79
Responsibility ownership of decisionsand actions
Make decisions based on the best interests of the company and the team,
as well as society, rather than your own interest.
Inform the sponsor of your real qualifications if its not matching the project
before accepting the assignment
Do what you say you will do
Acknowledge your own errors
Respect confidentiality requirements
Uphold laws
Report unethical behaviour to the management
Report violations of PMIs code of ethics and professional conduct
10/11/2017 11:40 AM 73
Respect- the appropriate treatment of
7/25/2019 Project Management Professional PMP Exam Prep based on PMBOK guide 5th Free Sample Training Course
74/79
Respect the appropriate treatment ofpeople and resources
Maintain an attitude of mutual cooperation
Respect cultural differences
Don't gossip or saying things that could damage another persons reputation
Engage in good faith negotiations
Respect others
Be direct in dealing with conflict
Do not use your power or position to influence others for your own [personal
benefit
10/11/2017 11:40 AM 74
Q4
7/25/2019 Project Management Professional PMP Exam Prep based on PMBOK guide 5th Free Sample Training Course
75/79
Q4
You are the project manager of the LKH Project. This project must be
completed within six months, but after two months the schedule has begun to
slip. As of now, the project is one week behind schedule. Based on your
findings, you believe you can make some corrective actions and recover the
lost time over the next month to get the project back on schedule for its
completion date. Management, however, requires weekly status reports on
cost and schedule. Which of the following should you do?
A. Report that the project is one week behind schedule, but will finish on
schedule based on cited corrective actions.
B. Report that the project is on schedule and will finish on schedule.
C. Report that the project is off schedule by a few days, but will finish on
schedule.
D. Report that the project is running late.10/11/2017 11:40 AM 75
Q5
7/25/2019 Project Management Professional PMP Exam Prep based on PMBOK guide 5th Free Sample Training Course
76/79
Q5
You are a project manager within an organization that completes technical
projects for other entities. You have plans to leave your company within the
next month to launch your own consulting businesswhich will compete with
your current employer. Your company is currently working on a large proposal
for a government contract that your new company could also benefit from.
What should you do?
A. Resign from your current job and bid against your employer to get the
contract.
B. Decline to participate due to a conflict of interest.
C. Help your employer prepare the proposal.
D. Inform your employer that you will be leaving their company within a month
and it would be inappropriate for you to work on the current proposal.
10/11/2017 11:40 AM 76
Q6
7/25/2019 Project Management Professional PMP Exam Prep based on PMBOK guide 5th Free Sample Training Course
77/79
Q6
Your company does not allow project managers to accept gifts from vendorsof any kind. A friend that you have known for years now works for a vendor
that your company may be doing business with. Your friend from the vendor
asks you to lunch to discuss an upcoming project and you accept. When the
check arrives at the lunch table, your friend insists on paying. You should:
A. Allow the friend to buy because youve been friends for years.
B. Allow the friend to buy because lunch isnt really a gift.
C. Dont allow the friend to buy because your company does not allow any gifts
from vendors.
D. Insist that you purchase your friends lunch and your friend buys yours.
10/11/2017 11:40 AM 77
Q7
7/25/2019 Project Management Professional PMP Exam Prep based on PMBOK guide 5th Free Sample Training Course
78/79
Q7
You are the project manager of the AAA Project. Due to the nature of theproject, much of the work will require overtime between Christmas and New
Years Day. Many of the project team members, however, have requested
vacation during that week. What is the best way to continue?
A. Refuse all vacation requests and require all team members to work.
B. Only allow vacation requests for those team members who are not needed
during that week.
C. Divide tasks equally among the team members so each works the same
amount of time.
D. Allow team members to volunteer for the overtime work.
10/11/2017 11:40 AM 78
7/25/2019 Project Management Professional PMP Exam Prep based on PMBOK guide 5th Free Sample Training Course
79/79
Tricks for the PMP Exam
Bring the authorization letter from PMI to the test site
Bring snacks, you can not eat in the test room, but you can out of
the room.
The exam will not be adapted according to you, 200 Qs will beselected in the beginning and it will not be changed
You can mark questions in order to return to it back
Most of the questions are situational
You can re-take the exam for 2 times only.