PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc. Project Management Professional (PMP)® Exam Prep Course 00 – PMP® Application & Exam PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.
24

Project Management Professional (PMP)® Exam Prep · PDF filePMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc. Project Management Professional (PMP)®

Mar 09, 2018

Download

Documents

voque
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Project Management Professional (PMP)® Exam Prep · PDF filePMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc. Project Management Professional (PMP)®

PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.

Project Management Professional (PMP)®

Exam Prep

Course 00 – PMP® Application & Exam

PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.

Page 2: Project Management Professional (PMP)® Exam Prep · PDF filePMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc. Project Management Professional (PMP)®

PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.

Slide 1

Application & Exam

Types of Questions

PM Basics

Ten Knowledge Areas

Professional Responsibility

Practice Exams

© Copyright and all rights reserved – Looking Glass Development, LLC.

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

Page 3: Project Management Professional (PMP)® Exam Prep · PDF filePMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc. Project Management Professional (PMP)®

PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.

Slide 2

Looking Glass Development, LLC

(303) 663-5402 / (888) 338-7447

4610 S. Ulster St. #150 Denver, CO 80237

[email protected]

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

Page 4: Project Management Professional (PMP)® Exam Prep · PDF filePMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc. Project Management Professional (PMP)®

PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.

Slide 3

What do the letters PMP mean?• Project Management Professional.

What are the benefits of being a PMP?• Higher income potential.

• Shows knowledge of international standards.

• Is required by a growing number of employers.

© Copyright and all rights reserved – Looking Glass Development, LLC.

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

Page 5: Project Management Professional (PMP)® Exam Prep · PDF filePMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc. Project Management Professional (PMP)®

PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.

Slide 4

How Do I Become A PMP?

© Copyright and all rights reserved – Looking Glass Development, LLC.

WorkExperience

ContactHours

ApplicationSubmission

90 Days

ApplicationCompleteness

Review

ApplicantPaymentProcess

Pass Exam(1 year)

ReceiveCertification

PMP

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

Page 6: Project Management Professional (PMP)® Exam Prep · PDF filePMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc. Project Management Professional (PMP)®

PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.

Slide 5

Applying online is the fastest way

https://certification.pmi.orgMailing Address

PMI Certification Department

Fourteen Campus Boulevard

Newtown Square, PA. 19073

© Copyright and all rights reserved – Looking Glass Development, LLC.

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

Page 7: Project Management Professional (PMP)® Exam Prep · PDF filePMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc. Project Management Professional (PMP)®

PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.

Slide 6

DomainPercentage

of QuestionsInitiation 13%

Planning 24%

Executing 31%

Monitoring & Controlling 25%

Closing 7%

Total Number of Scored Questions 175

Total Number of Unscored Questions 25

Total Questions on Exam 200

© Copyright and all rights reserved – Looking Glass Development, LLC.

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

Page 8: Project Management Professional (PMP)® Exam Prep · PDF filePMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc. Project Management Professional (PMP)®

PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.

Slide 7

Task Initiating – 13%Task 1 Perform project assessment based upon available information, lessons

learned from previous projects, & meetings with relevant stakeholders in order to support the evaluation of the feasibility of new products or services within the given assumptions and/or constraints.

Task 2 Identify key deliverables based on the business requirements in order to manage customer expectations & direct the achievement of project goals.

Task 3 Perform stakeholder analysis using appropriate tools & techniques in order to align expectations & gain support for the project.

Task 4 Identify high level risks, assumptions, & constraints based on the current environment, organizational factors, historical data, & expert judgment, in order to propose an implementation strategy.

Task 5 Participate in the development of the project charter by compiling & analyzing gathered information in order to ensure project stakeholders are in agreement on its elements.

© Copyright and all rights reserved – Looking Glass Development, LLC.

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

Page 9: Project Management Professional (PMP)® Exam Prep · PDF filePMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc. Project Management Professional (PMP)®

PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.

Slide 8

Task Initiating – 13%Task 6 Obtain project charter approval from the sponsor, in order to

formalize the authority assigned to the project manager & gain commitment & acceptance for the project.

Task 7 Conduct benefit analysis with relevant stakeholders to validate project alignment with organizational strategy & expected business value.

Task 8 Inform stakeholders of the approved project charter to ensure common understanding of the key deliverables, milestones & their roles & responsibilities.

© Copyright and all rights reserved – Looking Glass Development, LLC.

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

Page 10: Project Management Professional (PMP)® Exam Prep · PDF filePMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc. Project Management Professional (PMP)®

PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.

Slide 9

Task Planning – 24%Task 1 Review & assess detailed project requirements, constraints, &

assumptions with stakeholders based on the project charter, lessons learned, & by using requirements gathering techniques in order to establish detailed project deliverables.

Task 2 Develop a scope management plan, based on the approved project scope & using scope management techniques, in order to define, maintain, & manage the scope of the project.

Task 3 Develop the cost management plan based on the project scope, schedule, resources, approved project charter & other information, using estimating techniques, in order to manage project costs.

Task 4 Develop the project schedule based on the approved project deliverables & milestones, scope & resource management plans in order to manage timely completion of the project.

© Copyright and all rights reserved – Looking Glass Development, LLC.

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

Page 11: Project Management Professional (PMP)® Exam Prep · PDF filePMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc. Project Management Professional (PMP)®

PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.

Slide 10

Task Planning – 24%Task 5 Develop the human resource management plan by defining the

roles & responsibilities of the project team members in order to create a project organizational structure & provide guidance regarding how resources will be assigned & managed.

Task 6 Develop the communications management plan based on the project organizational structure & stakeholder requirements, in to define & manage the flow of project information.

Task 7 Develop the procurement management plan based on the projectscope, budget, & schedule, in order to ensure that the required project resources will be available.

Task 8 Develop the quality management plan & define the quality standards for the project and its products, based on the project scope, risks & requirements, in order to prevent the occurrence of defects & control the cost of quality.

© Copyright and all rights reserved – Looking Glass Development, LLC.

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

Page 12: Project Management Professional (PMP)® Exam Prep · PDF filePMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc. Project Management Professional (PMP)®

PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.

Slide 11

Task Planning – 24%Task 9 Develop the change management plan by defining how changes will be

addressed & controlled in order to track & manage change.

Task 10 Plan for risk management by developing a risk management plan; identifying, analyzing, & prioritizing project risk; creating the risk register; & defining risk response strategies in order to manage uncertainty & opportunity throughout the project life cycle.

Task 11 Present the project management plan to the relevant stakeholders according to applicable policies & procedures in order to obtain approval to proceed with project execution.

Task 12 Conduct kick-off meeting communicating the start of the project, key milestones, & other relevant information in order to inform & engage stakeholders & gain commitment.

Task 13 Develop the stakeholder management plan by analyzing needs, interests, & potential impact in order to effectively manage stakeholders’ expectations & engage them in project decisions.

© Copyright and all rights reserved – Looking Glass Development, LLC.

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

Page 13: Project Management Professional (PMP)® Exam Prep · PDF filePMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc. Project Management Professional (PMP)®

PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.

Slide 12

Task Executing – 31%Task 1 Acquire & manage project resources by following the human resource &

procurement management plans in order to meet project requirements.

Task 2 Manage task execution based on the project management plan by leading & developing the project team in order to achieve project deliverables.

Task 3 Implement the quality management plan using the appropriate tools & techniques in order to ensure that work is performed in accordance with required quality standards.

Task 4 Implement approved changes & corrective actions by following the change management plan in order to meet project requirements.

Task 5 Implement approved actions by following the risk management plan in order to minimize the impact of the risks & take advantage of opportunities on the project.

Task 6 Manage the flow of information by following the communications plan in order to keep stakeholders engaged & informed.

Task 7 Maintain stakeholder relationships by following the stakeholder management plan in order to receive continued support & management expectations.

© Copyright and all rights reserved – Looking Glass Development, LLC.

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

Page 14: Project Management Professional (PMP)® Exam Prep · PDF filePMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc. Project Management Professional (PMP)®

PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.

Slide 13

Task Monitoring & Controlling – 25%Task 1 Measure project performance using appropriate tools & techniques in

order to identify & quantify any variances & corrective actions.

Task 2 Manage changes to the project by following the change management plan in order to ensure that project goals remain aligned with business needs.

Task 3 Verify that project deliverables conform to the quality standards established in the quality management plan by using appropriate tools and techniques to meet project requirements and business needs.

Task 4 Monitor & assess risk by determining whether exposure has changed & evaluating the effectiveness of response strategies in order to manage the impact of risks & opportunities on the project.

Task 5 Review the issue log,, update if necessary, & determine corrective actions by using appropriate tools & techniques in order to minimize the impact on the project.

Task 6 Capture, analyze, & manage lessons learned, using lessons learned management techniques in order to enable continuous improvement.

Task 7 Monitor procurement activities according to the procurement plan in order to verify compliance with project objectives.

© Copyright and all rights reserved – Looking Glass Development, LLC.

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

Page 15: Project Management Professional (PMP)® Exam Prep · PDF filePMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc. Project Management Professional (PMP)®

PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.

Slide 14

Task Closing – 7%Task 1 Obtain final acceptance of the project deliverables from relevant

stakeholders in order to confirm that project scope & deliverables were achieved.

Task 2 Transfer the ownership of deliverables to the assigned stakeholders in accordance with the project plan in order to facilitate project closure.

Task 3 Obtain financial, legal, & administrative closure using generally accepted practices & policies in order to communicate formal project closure & ensure transfer of liability.

Task 4 Prepare & share the final project report according to the communications management plan in order to document & convey project performance & assist in project evaluation.

© Copyright and all rights reserved – Looking Glass Development, LLC.

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

Page 16: Project Management Professional (PMP)® Exam Prep · PDF filePMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc. Project Management Professional (PMP)®

PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.

Slide 15

Task Closing – 7%Task 5 Collate lessons learned that were documented throughout the

project & conduct a comprehensive project review in order to update the organization’s knowledge base.

Task 6 Archive project documents & materials using generally accepted practices in order to comply with statutory requirements & for potential use in future projects & audits.

Task 7 Obtain feedback from relevant stakeholders using appropriate tools & Techniques & based on the stakeholder management plan in order to evaluate their satisfaction.

© Copyright and all rights reserved – Looking Glass Development, LLC.

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

Page 17: Project Management Professional (PMP)® Exam Prep · PDF filePMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc. Project Management Professional (PMP)®

PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.

Slide 16

Must get 61% or better

There is no penalty for wrong answers

Fees:PMI members pay $405Non-members pay $555

Each applicant has one (1) year to take exam

© Copyright and all rights reserved – Looking Glass Development, LLC.

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

Page 18: Project Management Professional (PMP)® Exam Prep · PDF filePMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc. Project Management Professional (PMP)®

PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.

Slide 17

The exam is NOT based on the PMBOK Guide®.

The exam requires more than memorization.

Almost half of the exam requires you to identify what you would do in a given situation.

The exam emphasizes the five (5) process groups, ten (10) knowledge areas and 47 processes.

Exam requires you to answer the questions from PMI’s perspective based on the RDS.

© Copyright and all rights reserved – Looking Glass Development, LLC.

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

Page 19: Project Management Professional (PMP)® Exam Prep · PDF filePMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc. Project Management Professional (PMP)®

PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.

Slide 18

Rarely will the answer be a direct quote from the PMBOK Guide.

Questions can be series based, i.e. you must answer the first question correctly to answer the next three (3) or four (4) questions.

A small percentage of the questions will be based on the inputs and outputs from the PMBOK Guide.

Earned Value, Critical Chain, PERT, EMV, and CPM will almost certainly be on the test.

Approximately 10%-15% of the exam will require the use of other formulas.

© Copyright and all rights reserved – Looking Glass Development, LLC.

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

_____________________________________________________________________________________

Page 20: Project Management Professional (PMP)® Exam Prep · PDF filePMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc. Project Management Professional (PMP)®

PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.

Page 21: Project Management Professional (PMP)® Exam Prep · PDF filePMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc. Project Management Professional (PMP)®

PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.

Review Questions:

1. Which of the following correctly represents the acronym PMP®?

A. Project Mentoring Professional

B. Project Management Professional

C. Program Management Professional

D. Portfolio Management Professional

2. Which of the following is a benefit to holding the PMP® credential?

A. Higher income potential

B. Shows knowledge of a global standard

C. It is required by a growing number of companies

D. All of the above

3. If you have a four year baccalaureate degree how many hours of professional

experience leading projects do you need?

A. 3,600

B. 4,500

C. 7,500

D. None of the above

4. If a candidate is attempting to qualify to sit for the PMP® exam how many contact

hours must be completed?

A. 35

B. None, PDUs are required

C. 45

D. 21

5. If you do not have a four year baccalaureate degree how many hours of

professional experience leading project do you need?

A. 6,000

B. 4,500

C. 9,000

D. 7,500

Page 22: Project Management Professional (PMP)® Exam Prep · PDF filePMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc. Project Management Professional (PMP)®

PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.

6. Which of the following best describes a contact hours?

A. Contact hours are the same as PDUs

B. Contact hours represent hours of formal instruction or education in the

field of project management

C. Contact hours represent hours spent reading about or training in the field

of project management

D. None of the above

7. How many questions are in the PMP® exam?

A. 175

B. 250

C. 200

D. 150

8. Which of the following PMBOK® Guide knowledge areas represents the largest

percentage of test questions:

A. Executing

B. Monitoring & Controlling

C. Planning

D. Initiating

9. What is the required passing score for the PMP® exam?

A. 68%

B. 80%

C. 61%

D. 75%

10. Approximately what percentage of test questions will be a direct quote from the

PMBOK® Guide?

A. 15%

B. 21%

C. 5%-10%

D. 0%

Page 23: Project Management Professional (PMP)® Exam Prep · PDF filePMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc. Project Management Professional (PMP)®

PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.

Answer Key:

1. B

The PMP® is the most popular project management certification in the world. It

stands for Project Management Professional.

2. D

All of the above are true according to PMI®.

3. B

Under PMI®'s Category I qualifications for people who hold a baccalaureate

degree, each candidate must possess at least 4,500 hours of professional

experience leading projects and 36 months of experience.

4. A

For all PMP® candidates 35 contact hours must be obtained. A contact hour is

the same as an hour of face time with an instructor.

5. D

Under PMI®'s Category II qualifications for people who hold a baccalaureate

degree, each candidate must possess at least 7,500 hours of professional

experience leading projects and 60 months of experience.

6. B

Contact hours represent hours of formal instruction or education in the field of

project management. Contact hours are the same as PDU categories 1, 3 and/or

5.

7. C

The PMP® exam contains 200 questions of which only 175 are actually graded.

25 questions are being evaluated for future addition to the testbank.

8. A

The executing process group represents 27% of the PMP® exam. The planning

process group represents 23%.

9. C

61% is the required passing score for the PMP® exam. Approximately 68% of all

exams receive this score or better.

Page 24: Project Management Professional (PMP)® Exam Prep · PDF filePMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc. Project Management Professional (PMP)®

PMI, PMBOK and PMP are registered marks of the Project Management Institute, Inc.

10. D

You should expect no correct answers on the exam to be exact quotes from the

PMBOK® Guide because of the focus on situational questions.