dunmaglassWind farm

Page 2: Project leaflet - June 2013

What Will the enabling Works comprise of?

• Theupgradeof11kmofexistingtrackfrom3mwideto6mwide(includingsloperetentionworks);

• Associateddrainageworks;• Developmentofborrowpit;• Constructionoftwotimberdeckbridges

spanning16mand18mrespectively;• Constructionof132/33kVsub-station

platform;• Constructionofmainsitecompoundfor

theentireworks;and• DismantlingofMarkhamturbine.What Will the the main Works comprise of?

• Constructionof33turbinebaseswithassociatedtrackanddrainageconstruction;

• Cableinstallationworks;• Delivery,erection,commissioningof

turbines;and• Constructionof132/33kVsub-station,

controlbuildingandwelfarebuilding.

Will there be a drivers code of conduct in place for the project?

Yes,RJMcLeodwillproduceadriverscodeofconductwhichwillreinforceourexpectationsfromalldeliverydrivers.

Will there be an increase in the number of vehicles on the local roads during the enabling Works?

Wehadpreviouslylookedatimportingallstonefortheenablingworksandwearenowlookingtodothisslightlydifferentlybyoperatingtheborrowpitonthesiteearlierthanplanned.Thismeansthattherewillbeanincreaseinthenumberofvehiclesontheroadstobeginwith,asHeavyGoodsVehicles(HGVs)willbedeliveringmaterialstothesiteincludingaggregatesfortheroadworksonthesite,andthisislikelytolastuntillaterthisyear.ThesetrafficmovementswillbesubjecttoourTrafficManagementPlanwhichhasbeenagreedwithHighlandCouncil.Oncetheborrowpitisfunctioningthesevehiclenumberswillreduce.

Activity Indicative Dates**Please note that these may be subject to change

Enabling works contract (RJ McLeod) - UptoPlateau

Mid July 2013 - Dec 2013

Main works (contractor TBC) April 2014 - July 2016

Build 132/33kV substation (on site) - By SHE Transmission

July 2014 - October 2015

Delivery of turbines to site July 2015 - Oct 2015 and April 2016 - July 2016

Completion October 2016

What are the plans for the grid connection for the project?

WecurrentlyhaveagridconnectiondatefortheprojectinOctober2015,andthedetailofthisiscurrentlybeingfinalisedbytheprojectteamfromScottishHydroElectricTransmissionPlc.

Will there be any local job opportunities for the local area?

SSEiscommittedtomaximisingthebenefitfromourprojectstothelocalcommunity,andweseeourHighlandportalasonewayofdoingthisasitwillhelptofacilitateengagementbetweenSSEandlocalbusinesses.Wearekeentohearfromanylocalbusinesses,anditwouldbeusefulforyoutoregisterontheportalwhichcanbedoneatwww.sseopen4business-highlands.com.

Will the community benefit for the project remain as it has been agreed previously With res?

RESareintheprocessoffinalisingthearrangementswiththecommunitiesinvolvedinthecommunitybenefitfundforDunmaglasswindfarm,andtheseagreementswillbereassignedtoSSEinduecourse.SSEwillarrangetomeetwiththecommunitiestodiscussthearrangementsforthefundsoncetheseagreementshavebeensignedovertous,andwearecommittedtohonouringthecommitmentsthatREShavemadeinrelationtothesefunds.

hoW Will sse engage With the local community about the Works?

WearecommittedtocontinuingwiththelocalliaisongroupthatREShassetuptodiscusstheroadimprovementsworks.Inaddition,wewillprovideregularupdatesandnewsletterstothosewhohavesigneduptothisfromRES,andifyouwouldliketosignuptothislist,pleasecontactMarianneTownsleywhocanaddyoutothecirculationlist.Inaddition,wewillholdanotherinformationdayaheadoftheturbinedeliveriesstartingtoensurethatthelocalcommunityarekeptuptodate.

SSEwillalsocreateawebsiteaddressfortheprojectinduecourseandthewebaddressforthiswillbewww.sse.com/dunmaglass.Inaddition,theRESsite(www.dunmaglass-windfarm.co.uk)willredirecttothissitewhentheRESworkshavebeencompleted.

Who should i contact With any queries about the project?

IfyouhaveanyqueriesabouttheB851publicroadimprovementworks,pleasecontactRachelAndersonofRESviae-mail([email protected])orviaphone(01414045531).

Foranyqueriesrelatingtotheproject,pleasecontactSSE’sLiaisonManager,MarianneTownsleyviae-mail([email protected])orviaphone(01463728069).

What is the current programme for the project?