MS PROJECT HW Prof Ralph V. Locurcio, PE CON 2001 CVE 4070
8

Prof Ralph V. Locurcio, PE CON 2001 CVE 4070. Sequence Single Family House - 3,000 square feet Duration 1 General Conditions 21 2 Apply for Permits.

Jan 18, 2016

Download

Documents

Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Prof Ralph V. Locurcio, PE CON 2001 CVE 4070. Sequence Single Family House - 3,000 square feet Duration 1 General Conditions 21 2 Apply for Permits.

MS PROJECT HW

Prof Ralph V. Locurcio, PECON 2001CVE 4070

Page 2: Prof Ralph V. Locurcio, PE CON 2001 CVE 4070. Sequence Single Family House - 3,000 square feet Duration 1 General Conditions 21 2 Apply for Permits.

WBS Instructions

Page 3: Prof Ralph V. Locurcio, PE CON 2001 CVE 4070. Sequence Single Family House - 3,000 square feet Duration 1 General Conditions 21 2 Apply for Permits.

Project TaskSequence

SequenceSingle Family House - 3,000 square feet

Duration

1 General Conditions 21

2 Apply for Permits 1

3 Site Work 3

4 Pour Foundation 19

5 Pour floor slab 8

6 Framing or masonry for walls 22

7 Construct roof & dry in 16

8 Complete exterior finishes 15

9 Rough-in plumbing & electrical& tel 14

10 Rough-in HVAC 4

11 Install insulation 4

12 Install drywall 5

13 Paint and wallpaper interior 10

14 Install kitchen & cabinets & trim 5

15 Install plumbing fixtures 4

16 Install electrical fixtures 4

17 Install HVAC equipment 3

18 Install carpet, tile and appliances 6

19 Install landscaping 3

20 Install driveway 2

21 Final inspection for CO 1

22 Make final repairs 2

23 Cleanup for occupancy 1

Total 173

Actual 140

Page 4: Prof Ralph V. Locurcio, PE CON 2001 CVE 4070. Sequence Single Family House - 3,000 square feet Duration 1 General Conditions 21 2 Apply for Permits.

House WBSWBS for Senior Design

Activity or Task   Assigned   Planned Actual Planned Actual Float % Done

    person)   Start Start Finish Finish Lag Comp  

Phase-1 (5%)                    

  General Conditions Engineer-1 21 23-Aug   3-Sep   0    

  Apply for Permits Engineer-2 1 23-Aug   29-Aug   -5    

Phase-2 (15%)                    

  Site Work   3              

  Pour Foundation   19              

  Pour floor slab   8              

 Framing or masonry for walls   22              

  Construct roof & dry in   16              

Phase-3 (50%)                    

 Complete exterior finishes

  15              

 Rough-in plumbing & electrical& tel   14              

  Rough-in HVAC   4              

  Install insulation   4              

  Install drywall   5              

Phase-4 (95%)                    

 Paint and wallpaper interior   10              

 Install kitchen & cabinets & trim   5              

  Install plumbing fixtures   4              

  Install electrical fixtures   4              

  Install HVAC equipment   3              

 Install carpet, tile and appliances   6              

Phase-5 (100%)                    

  Install landscaping   3              

  Install driveway   2              

  Final inspection for CO   1              

  Make final repairs   2              

  Cleanup for occupancy   1              

                     

Page 5: Prof Ralph V. Locurcio, PE CON 2001 CVE 4070. Sequence Single Family House - 3,000 square feet Duration 1 General Conditions 21 2 Apply for Permits.

Flow Chart

Page 6: Prof Ralph V. Locurcio, PE CON 2001 CVE 4070. Sequence Single Family House - 3,000 square feet Duration 1 General Conditions 21 2 Apply for Permits.

Schedule Instructions

Note: The following items are required for full credit:1. Schedule must use MS Project    

2. Use Septemnber 1 as your starting date for the construction3. Calculate start & finish dates based on your flow chart & Sept 1 start4. Schedule must be on one page; landscape format5. Be sure to arrange the tasks in "logical" construction order6. Must use task sequencing & overlap per your Flow Diagram7. Add lead or lag to separate or overlap a task or sequence of tasks8. All activities must be labeled with activity names to the right of the bar9. All activities must show % complete to left of bar  

10. Show % complete in the activity bar for all tasks11. All activities must be completed in less than 173 days12. All activity bars must be colored blue & use cross hatch pattern 13. Include the 3 "phase" activities with black bars as: (1) Planning (2) Foundation & Site (3) Vertical (4) Exterior & Finish14. Include a title & your name in the heading                   

Page 7: Prof Ralph V. Locurcio, PE CON 2001 CVE 4070. Sequence Single Family House - 3,000 square feet Duration 1 General Conditions 21 2 Apply for Permits.

MS Project Schedule

Page 8: Prof Ralph V. Locurcio, PE CON 2001 CVE 4070. Sequence Single Family House - 3,000 square feet Duration 1 General Conditions 21 2 Apply for Permits.