MS PROJECT HW Prof Ralph V. Locurcio, PE CON 2001 CVE 4070
Jan 18, 2016
MS PROJECT HW
Prof Ralph V. Locurcio, PECON 2001CVE 4070
WBS Instructions
Project TaskSequence
SequenceSingle Family House - 3,000 square feet
Duration
1 General Conditions 21
2 Apply for Permits 1
3 Site Work 3
4 Pour Foundation 19
5 Pour floor slab 8
6 Framing or masonry for walls 22
7 Construct roof & dry in 16
8 Complete exterior finishes 15
9 Rough-in plumbing & electrical& tel 14
10 Rough-in HVAC 4
11 Install insulation 4
12 Install drywall 5
13 Paint and wallpaper interior 10
14 Install kitchen & cabinets & trim 5
15 Install plumbing fixtures 4
16 Install electrical fixtures 4
17 Install HVAC equipment 3
18 Install carpet, tile and appliances 6
19 Install landscaping 3
20 Install driveway 2
21 Final inspection for CO 1
22 Make final repairs 2
23 Cleanup for occupancy 1
Total 173
Actual 140
House WBSWBS for Senior Design
Activity or Task Assigned Planned Actual Planned Actual Float % Done
person) Start Start Finish Finish Lag Comp
Phase-1 (5%)
General Conditions Engineer-1 21 23-Aug 3-Sep 0
Apply for Permits Engineer-2 1 23-Aug 29-Aug -5
Phase-2 (15%)
Site Work 3
Pour Foundation 19
Pour floor slab 8
Framing or masonry for walls 22
Construct roof & dry in 16
Phase-3 (50%)
Complete exterior finishes
15
Rough-in plumbing & electrical& tel 14
Rough-in HVAC 4
Install insulation 4
Install drywall 5
Phase-4 (95%)
Paint and wallpaper interior 10
Install kitchen & cabinets & trim 5
Install plumbing fixtures 4
Install electrical fixtures 4
Install HVAC equipment 3
Install carpet, tile and appliances 6
Phase-5 (100%)
Install landscaping 3
Install driveway 2
Final inspection for CO 1
Make final repairs 2
Cleanup for occupancy 1
Flow Chart
Schedule Instructions
Note: The following items are required for full credit:1. Schedule must use MS Project
2. Use Septemnber 1 as your starting date for the construction3. Calculate start & finish dates based on your flow chart & Sept 1 start4. Schedule must be on one page; landscape format5. Be sure to arrange the tasks in "logical" construction order6. Must use task sequencing & overlap per your Flow Diagram7. Add lead or lag to separate or overlap a task or sequence of tasks8. All activities must be labeled with activity names to the right of the bar9. All activities must show % complete to left of bar
10. Show % complete in the activity bar for all tasks11. All activities must be completed in less than 173 days12. All activity bars must be colored blue & use cross hatch pattern 13. Include the 3 "phase" activities with black bars as: (1) Planning (2) Foundation & Site (3) Vertical (4) Exterior & Finish14. Include a title & your name in the heading
MS Project Schedule