7/31/2019 Procedure of Building
1/17
externalw
allc
onstruction
26
5. External Wall Construction
5.1. ERECTION OF EXTERNAL PRECAST WALLS
The erection of precast walls generally involves the following steps:
a) moving the precast wall panels from delivery truck or site storage yard to th e designated locations forinstallation;
b) raising the precast pan els to the required elevation (and rotating to correct orientation if necessary);
c) fixing the precast panels in position; and
d) casting the wet joints and/ or grouting and applying sealant.
Figure 5.1: Erection o f a precast wall
1. Remove precast wall fromdelivery truck
2. Raise the precast wall to requiredheight and orientation
3. Position comp ressiblewaterproofing strip at joint
4. Apply n on -sh rin k grout 5. Lower precast wall in to position 6. Adjust position of precast wall
7. Install strutting 8. Verify plumb(an d ad just if necessary) 9. Remo ve excess grou t infill afterprecast wall is erected
7/31/2019 Procedure of Building
2/17
Figure 5 .3: Wet join ts
5.1.1 CASTING OF WET JOINTS
The use of wet joints is essential in minimising water seepage through the joint areas.
Figure 5.2: Casting of wet joint conn ection s
1. Prepare con tinuity bars of wet joints 2. Set up formwork for casting
Good example of a wet joint Bad example of a wet joint
#
5.1 .2 SEALING OF JOINTS
Precast wall panels should be erected within the
allowable con struction tolerances, with em ph asis
placed o n th e gap size at the joints. This is importan t
to facil i tate proper installation of backer rod
and application of sealant to ensure effective
watertightn ess at these location s.
Concrete surfaces at the joint should be sound,smooth , clean and free from all mortar dust or oth er
contaminants that may affect the adhesion of
sealant to the surfaces. Som e sealants may require
a primer to improve the adhesion. In such cases,
manufacturers advice should be sought to ensure
comp atibility of the sealant an d p rimer. As sho wn
in Figure 5.4, po or surface preparation , resulting
in loose particles and contaminants trapped in
the sealant can lead to premature failure of thesealant system.
27
externalw
allconstruction
7/31/2019 Procedure of Building
3/17
7/31/2019 Procedure of Building
4/17
7/31/2019 Procedure of Building
5/17
externalw
allc
onstruction
30
Figure 5.8: Form tie sleeve ho le (section al view)
RC wall
Form tie sleeve
Wall plugs
Non-shrink grout
Figure 5.7: Patching of form tie holes
1. Remove plastic cone 2. Insert wall plug into sleeve 3. Clean concrete surface
4. App ly slurry of bo nd ing agent,cement water
5. Mix non-shrink grout 6. Press grout mix into recess andfinish b y removing excess grou tfrom concrete surface
7/31/2019 Procedure of Building
6/17
5.3 BRICKLAYING
5.3.1 GENERAL
Qu ality workm ansh ip in bricklaying is essential in
ensuring watertightness of brickwalls.
There should be proper co-ordination between
external brickwork and oth er works. Setting ou t of
all works, including openings, sills and lintels,
should be coordinated. A copy of the approved
brickwall setting out drawings could be displayed
at ap prop riate location for easy reference.
There should be adequate scaffolding provided to
enable workers to work from the outer side of
external walls to achieve a high stan dard of laying
and pointin g works.
5.3.2 BATCHING, MIXING AND USE OF
MORTAR
For enhanced performance, pre-packed mortar mix is
recommended.
For site batching of m ortar mix, standard size containers
should be used to ensure correct proportion of
materials. The u se of shovels to gauge the am ount of
materials cannot be relied upon to give consistent
performance. Additives should only be used upon the
Designers permission, an d with the ad vice from the
m anufacturer. Machine m ixing is recom men ded to
achieve a thorough blend of mortar.
Wide variations in th e mixing time should be avoided.
Insufficient m ixing may result in non-uniformity, poor
workability and low water retention of the m ortar.
Excessive m ixing, on the oth er han d, m ay adversely
affect the strength and bonding of mortar due to air
entrain m ent. It is a goo d practice to regulate thequan tity of mortar being mixed, so that the m ortar
can be used up within th e working time.
5.3.3 CUTTING OF BRICKS
Proper setting out of the brickwork helps to reduce
un necessary cutting of b rick un its. Where cutting of
brick units is needed, it is recommended that
appropriate cutting machine be used to produce clean-
cut edges. Alternatively, bricks could be cut using a
bolster and a h amm er. However, this metho d tend s
to produce less satisfactory results.
31
externalw
allconstruction
Figure 5.9: Measuring m aterials for mo rtar m ix
Gauging by shovels cann ot b e reliedupo n to give consistent m ortar mix
#
Example of using bu cket batchingfor a 1:3 mix
Sand Cement
+
Example of usin g gauge bo x batchingfor a 1:3 mix
Sand Cement
+
7/31/2019 Procedure of Building
7/17
7/31/2019 Procedure of Building
8/17
33
externalw
allconstruction
The joints should be raked out to a depth of about
10mm while the mortar is still green to form an
adequate key for plaster (Figure 5.12).
As the b rickwall is being erected, emb ed bonding bars
and m esh reinforcement (exmet) in the mortar joints
at every 4 th course of b rickwork. Where 2 p ieces of
reinforcement are joined, an overlapping of minim um
150m m should be provided. Lintels should be installed
for doors and windows open ing.
Figure 5.12: Raking of external mortar joints forplastered brickwalls
INSIDE OUTSIDE
Brick
Mortar joint
~10mm
~10mm
Bonding bars fixed to a concrete column Bonding bars embedded at every 4th course of brickwork
Mesh reinforcemen t emb edded at every 4th courseand tucked into the next course
Steel lintel installed at window opening
Figure 5.13: Installing bon ding b ars, brick reinforcement an d lintels
End of lintel supp orted on afull brick un it with m inimu m100mm bearing
7/31/2019 Procedure of Building
9/17
externalw
allc
onstruction
34
1. Lay DPC on fresh mortar bed 2. Lay fresh mortar over DPC
3 . Lay at least o n e m o re co urse o f b rick o ver DPC 4 . Dam p -p ro of co urse laid with go od ad h esio n
Figure 5.14: Laying damp-proof course (DPC)
RC kerb
Brick cou rse
DPC
5.3.6 OTHER GOOD PRACTICES
As described in Section 2 .4.3, a layer of m etal lathin g
(mesh reinforcement) should be provided at the
following locations to min imise the developm ent
of cracks:
interfaces between brick and RC elements;
around door frames;
around steel lintels; and
around openings for electrical services.
5.3.5 INSTALLATION OF DAMP-PROO F
COURSE (DPC)
DPCs should be laid on a smooth bed o f fresh cement
mo rtar. Care should be taken to ensure that the DPCs
are not dam aged, torn or punctured during the process
of bricklaying. There should be minimum 150mm
lappin g at any joint b etween two sections o f DPC.
The DPC laid sho uld cover the en tire width of the
bricks. After laying the DPC, a fresh layer of mortar
should be laid over the DPC as soon as possible,
followed by the next course of brick. This creates good
adhesion b etween the b rick un its, mo rtar and DPC.
7/31/2019 Procedure of Building
10/17
Rein forcem en t in stalled aroun d door fram e Rein forcem en t in stalled aroun d lin tel
Reinforcement installed around openings forelectrical services
Reinforcement bars in stalled at every 4th course ofbrickwork fo r RC stiffeners
Figure 5.15: Installing mesh reinforcement
M&E services that penetrate the external walls should be housed in trunking boxes, with the surrounding
gaps prop erly sealed to prevent any leakage, as illustrated in Figure 5.16 b elow.
Figure 5 .16: Encasing M&E services in t run king bo xes
1. Routing of pipes in thetrunking box
2. Patching surrounding gaps usingcement mortar
3. Connecting the trunking andfinishing with p aint
35
externalw
allconstruction
7/31/2019 Procedure of Building
11/17
externalw
allc
onstruction
36
5.3.7 COMPLETING WORKS FOR
BRICKLAYING
Mortar infill shou ld be properly compacted b etween
the last course of brickwork and th e beam/ slab soffit.
For better compactness, the use of a han d p um p is
recommended. Joints should be checked after excess
mortar is removed from the b rick face to ensure that
the joints are pro perly filled. Any voids shou ld b e
filled with grout. Where grout is used, avoid excessive
water in the mix which may cause segregation and
un due shrinkage.
Gap between top course of brickwork an d beam soffit Han d pum p for in jection of m ortar
Use hand pump to fill gap with grout Completed grouting work
Figure 5.17: Inject mortar between last course of b rickwork and beam soffit
Duck mouth
7/31/2019 Procedure of Building
12/17
5.4 EXTERNAL PLASTERING AND SKIM COAT
Typical cross section al details of finishes for external wall are shown b elow:
Figure 5.18: Typical cross section al deta ils of external finish es
Typical cross section of a p recast wall (or a cast
in-situ RC wall) requ iring skim coat o nly
External finishes for p recast walls consisting:
1. a thin layer of skim coat to fill out m inor voids/
surface imperfections.
Typical cross section of a cast in -situ RC wall
requiring plastering
External finishes for cast in-situ reinforced con crete
(RC) walls consisting:
1. a spatterdash coat for better keying of the
subsequent rendering coats;
2. an undercoat (scratched);
3. a second coat; and
4. a finishing coat.
Typical cross section of a plastered brickwall
External finishes for b rickwalls consisting:
1. an undercoat (scratched);
2. a second coat; and
3. a finishing coat.
Skim Co at
PrecastWall
CastIn-situRC Wall
Spatterdash
Finishing Coat
Second Coat
Undercoat
Finishing Coat
Second Coat
Undercoat
Figure 5.18 shows that external wall construction with precast walls involve the least work for external finishes.
The process is, hence, less workmanship-dependent and more efficient.
37
externalw
allconstruction
Brickwall
7/31/2019 Procedure of Building
13/17
externalw
allc
onstruction
38
Figure 5.19: Sealing gap between window frame and external wall
Using hand p um p to fill gap between frame andwall with waterproo fing mortar before plastering
Gunn ing sealant in to groove lineafter plastering is com pleted
External RC mem bers with poor alignm ent and p lumb,
poor construction joint, honeycombed and badly
formed surfaces should be rectified accordingly. All
protrusions, fins, imperfections and blemishes should
be rem oved from the RC surfaces.
Cleaning
All brick, concrete and o ther surfaces should be cleaned
of dust, dirt, d ebris, grease, form release agents (for
concrete surfaces), laitance and any other detrimental
m aterials that m ay affect the bo nd ing of plaster or
skim coat.
Active biological growth, such as algae, fungus and
mould, should be removed as they may result in theformation of poorly laminated finishes, creating
undesirable cavities or even cracks, thereby reducing
the watertightn ess of the finishin g coats. Appropriate
cleaning solution can be used for th is purpose.
Figure 5.20: General cleaning p rior to app lication of finishes
Cleaning prior to application of fin ishes Use of high pressure water jet
5.4.1 PREPARATORY WORK
There should be proper co-ordination between external
finishin g works and works of o ther trades.
Gaps between the external walls and window/ door
open ings should be fully grouted with waterproofing
mo rtar before the comm encement of finishing work.
7/31/2019 Procedure of Building
14/17
Figure 5.21: Use of appro priate cleanin g solution s prior to app lication of finishes
Presen ce o f fo rm oils with efflo rescen ce Ap plicatio n o f clean in g so lu tio n to rem ove resid ualform release agents on concrete surfaces
#
Treatm ent At Joints Between Dissim ilar Materials
A layer of approved waterproofing compound should
be applied at locations where there are potential risks
of water seepage, for example, at brick-RC joints or
around embedded M&E services.
A layer of render should be applied over the joint
area prior to the application of the waterproofing
mem brane. The width of the ap plied waterproofing
compo und should be minimum 200mm (i.e. 100mm
on each side of the joint). Once the waterproofing
membrane has cured sufficiently, install a layer of
metal lathing over the waterproofing m embran e to
prevent cracks at these in terfaces.
Figure 5.22: Treatment at join ts between d issimilar materials
1. Ap ply ren der to b rick-RC jo in ts 2 . Ap ply waterp ro ofin g m em bran e 3 . In stall m etal lath at brick-RC jo in ts
39
externalw
allconstruction
7/31/2019 Procedure of Building
15/17
externalw
allc
onstruction
40
Figure 5.23: Apply waterproofing membrane toperimeter walls with 300mm uptu rn
Figure 5.24: Spatterdash coat o n RC surfaces for better
bon ding with plaster
Waterproofing Application along Perimeter Walls
and Planters
There shou ld b e prop er surface preparation before
application of waterproofing membrane to the
surrounding perimeter walls and planters as discussed
in section 2.5.3. Refer to manufacturers instructions
on the surface preparation required, as well as coverageand number of coats to be applied. The membrane
should be applied with a m inimum 300mm upturn
along the external wall (Figure 2.30 in Chapter 2) .
App lication of Spatterdash Coat
For cast in-situ RC walls that requ ire plastering, proper
bonding and keying are important in ensuring goodadhesion of the plaster to the RC substrate. The
substrate surfaces should be dampened before
commencing application of spatterdash coat. A
spatterdash coat of 3-5mm thick sho uld b e applied
to give effective keying action. For b etter performance,
a thin layer of bond ing agent can be applied on the
RC surfaces before the app lication o f the spatterdash
coat. The app lication of the spatterdash coat shou ld
comm ence when the bon ding agent is still damp .
5.4.2 APPLICATION O F PLASTER
Plastering can substantially increase the rain resistance
of external walls. However, cracks in th e plaster m ay
develop over time an d redu ce the level of protection
against rain. Cracks in the plaster are usually caused
by shrinkage of the plaster and/ or inadequate bonding
between the p laster and the substrate.
For better performance, pre-packed plaster mixes are
recom men ded. Approved waterproofing com poun d
or bo ndin g agent could be added to th e plaster mix
to improve its waterproofing ability.
Brick surfaces should be m oistened prior to application
of the undercoat to obtain good adhesion and prevent
excessive absorption of water from the u nd ercoat by
the brickworks. Plastering on brick surfaces is usually
applied in two coats (excluding the finishing coat).
The th ickness may vary depending on the evenness of
the wall surface. Usually, the u nd ercoat is between 8-
10mm thick (scratched), and the second coat is 6-
10mm thick. Som e pre-packed plastering m ortars may
allow thinner layers of application. For such cases,
refer to specifications of the manufacturer. The total
th ickness allowed for th e plaster (includ ing all coats)
shou ld generally be limited to 25m m.
For plastered RC surfaces, the thickness of plaster
should be between 5-18mm. If the structural works
are constructed with good alignment and surfacecondition, a th inner coat of plaster or skimm ing may
be applied.
Each plaster coat should be sufficiently cured by mist
spraying before applying the subsequent coat. Rapid
drying of the plaster sho uld be avoided to achieve
better shrinkage control.
Where applicable, all plastering works should be
terminated at groove lines, casing beads, corners,
openings, or other acceptable intersection of surfaces
to achieve a better finish ing without any visible lines
at th e termin ating plaster. To reduce the risks of water
seepage at th e joints b etween two ad jacent groove
lines, a suitable sealant shou ld be ap plied to these
join ts, includin g the turn ing corners of the groove line
after plastering.
7/31/2019 Procedure of Building
16/17
Figure 5.25: Terminating plastering works at groove lines
1 2 3
All defective plaster, including hairline cracks, pits,
blisters, and other defects, should be rectified. When
carrying out rectification works, a suitable bonding
agent should be app lied to th e existing plaster edgesor surfaces where the new plaster will be applied over.
5.4.3 APPLICATION OF SKIM COAT
The surface of RC memb ers (includin g precast walls)
should be constructed to good alignment and plumb
so that plastering is not required. Where there are
min or surface un evenn ess or blemishes, the RC
surfaces could be skim coated with approved
skimm ing m aterials. In such cases, the skimm ing
can be app lied in two coats, steel trowelled un til asmooth and un iform surface is achieved. As a general
guide, thickness of skim coat to RC walls should
not exceed 5m m.
Skim coats should be cured for 48 hours by fog spraying
to prevent rapid drying. For the first 12 hours, a very
light fog spraying is recommended.
Figure 5.26: Application of skim coat
2. Scoop skimming mortar onto p lasteringhawk
3. App ly skim coat on to prepared RC surface,trowel until smooth and u niform
1. Prepare skimmin g too ls
Steel trowel forskimming
Plastering h awk forhandling mortar
41
externalw
allconstruction
7/31/2019 Procedure of Building
17/17
externalwallconstruction/testing
42
5.4.4 APPLICATION O F SEALER
Subsequen t to th e com pletion o f plastering works or
skim coating, it is recommended to apply a water
repelling sealer, either film forming or im pregnating
in n ature, over the external wall before com mencing
painting works. In particular, water-based impregnating
sealers can form a h ydrop ho bic zone which p rotectsthe sub strate against water ingress. Prior to application
of the sealer, the receiving surface should be d ry, clean
and free from dust, dirt, grease and any loose foreign
matter. Refer to manufacturers instructions on the
selection and usage of the sealer.
Figure 5.27: Application of sealer prior topainting works
6. Testing
Figure 6.1: Conduct of field watertightness testfor joints between external wall andwindow frame
No sign of seepage should be detected th roughou t
the test.
Water intensity
Wind Pressure
Nozzle inclination
Distance of nozzle
from wall
Sample
Spray duration
: 300mm/h r
: 1 litre/m in/m of joint
: 240 Pa
: 90 to wall
: 200mm
: 1 samp le = 2m length of joint
: 10m ins
6.1. WATERTIGHTNESS TESTS
Extern al Wall Panels
To verify the watertightness performance of the
completed external walls, field watertightness test
could be carried out on m inimum 10% of the external
walls. The conduct of field watertightness test is
especially critical for external brickwalls where
waterproofing performance is highly workmanship-
dependent.
For con duct of the watertightness test, water shou ld
be sprayed o n the wall surface at a d istance of 1800
2000 mm from the wall, with the nozzle fixed at an
inclined an gle of 30 degree to the external wall. 300
litres of water shou ld b e delivered to the test wall
panel for 2 hours.
The t est wall pan el is con sidered to h ave passed thetest if no damp ness or seepage appears on th e internal
surface of the wall panel or the adjacent areas during
the test and within half an h our after the comp letion
of test.
Join ts Between Extern al Wall an d Wind ow Frame
Field tests should be conducted to verify the
watertightness performance of the joints between the
external wall and window frame.
The following parameters are used in the CONQUAS
21 field watertightness test: