Pre-Feasibility Report Page 1 of 10 PRE-FEASIBILITY REPORT For PRIOR ENVIRONMENTAL CLEARANCE STORAGE CAPACITY ENHANCEMENT OF IOCL, LPG BOTTLING PLANT Capacity: 2 X 1200 MT At Plot No. 2649 & 2655 Tabiji, Beawer Bypass Road, NH-8, Ajmer (Raj.)-305001 Project Proponent: M/s. Indian Oil Corporation Limited, Ajmer Environmental Consultant: ENVIRO INFRA SOLUTIONS PVT. LTD. Accredited by NABET (Quality Council of India) for EIA studies as ‘A’ Category Consultant (S. No. 48 th , List of Accredited Consultant Organizations August 08, 2017) Address: - 301, 302 & 305, SRBC, Sec.-9, Vasundhara, GZB-201012 Ph.: 0120-4151183 Email: [email protected]Website: www.enviroinfrasolutions.com August 2017
10
Embed
Pre-Feasibility Report PRE-FEASIBILITY REPORTPFR).pdf · for EIA studies as ‘A’ Category Consultant (S. No. 48th, List of Accredited Consultant Organizations August 08, ... Pre-Feasibility
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Pre-Feasibility Report
Page 1 of 10
PRE-FEASIBILITY REPORTFor
PRIOR ENVIRONMENTAL CLEARANCESTORAGE CAPACITY ENHANCEMENT OF
Loading/Unloading shed, Cold Repair Shed and Connecting platforms.
Fire Detection & Alarm System covering the entire plant area.
Portable Fire Extinguishers.
Personnel protective equipment.
3.8 Power Supply
For the existing project, power is received from Ajmer vidyut vitran nigam limited. The power
demand is 11 KV, 800 KVA. The power requirement shall be remain same after the proposed
capacity expansion. DG sets are available for emergency
Generators Capacity: 500 KVA - 1 No.
250 KVA - 2 No.750 KVA- 1 No.
3.9 Water Requirement
Since the plant is based on the filling of LPG bottle and whole process is automatic and require
water only for Washing and in Domestic section. Maximum quantity of water requires would be for
the washing of bottle and domestic use in housekeeping, toilets and in Gardening. Unit requires
after expansion total 42 KL/D water (Fresh Water 22KLD) which shall be used for Process &
Domestic purpose and that shall be met by supply of surface water purchase through tankers. No
ground water shall be used.
3.10 Man Power Requirement
Total manpower required during construction is 35. Total 43 numbers of permanent employeesand 115 numbers of temporary workers engaged in current operation. After expansion totalrequirement of permanent employees will be 50 numbers and temporary workers will be 130numbers.
3.11 Communication System
Communication facility available at plant for internal and external communication purpose is as
follows
Telephones/mobile - 6 Nos.
VHF - 14 Nos.
PA Page phone - 14 Nos.
Electric siren - 2
Pre-Feasibility Report
Page 10 of 10
Hand siren - 09
4. SITE ANALYSIS
4.1 Connectivity
The Plant site located around 10.50 Km away from Ajmer City. The connectivity of the site to
airport, railway and road is as follows:
a. Airport connectivity- The nearest domestic and international airport is Jaipur which is
about 136 Kilometers.
b. Upcoming domestic airport at Kishangarh is 25 kms away.
c. Rail connectivity- The nearest railway station is Adarsh Nagar, which is about 7
kilometers from the site
d. Road connectivity- Nearest highway is NH-8.
e. Police Station – Mangliyawas Ajmer Police Station.
f. Hospital- Satellite Hospital Adarsh nagar
5.0 PROJECT SCHEDULE AND COST ESTIMATES
5.1 Project schedule
The company has proposed to enhance the storage capacity of the LPG in the plant by 2 X 1200
MT Mounded storage vessels to increase the storage capacity to 4400 MT. This will improve the
storage cover from existing 3.5 days to 5.5 days.
However, this increase in storage capacity will in no way increase the filling capacity of LPG
cylinders at present.
5.2 Cost estimates
The total cost of the project is estimated to be 30.74 crores.
5.3 Corporate Social Responsibility (CSR) PolicyThe company is actively involved in CSR related activities, budgetary provisions have been made
in the financial year 2017-2018 to spend on Corporate Social Responsibility (CSR) by IOCL head
office.
Classrooms and toilets have been constructed and donated for the Higher secondary school at
Tabiji.
As part of CSR, location has provided Kota stone flooring at Makupura higher secondary school.