  • 7/29/2019 Ppm pre-preventive maintenance of electrical

    1/35

    Title 36pt Times New Romanwith keywordin drive boxSubtitle 24pt Arial Narrow

    Presenters NamePresenters TitleDate

    keyword

  • 7/29/2019 Ppm pre-preventive maintenance of electrical

    2/35

    Topics

    Definition of Preventive Maintenance (PM)

    Reasons for the increased need of PM

    Advantages of a PM system

    Risks of running a PM system

    When to use a PM system

    The law of PM

    Guide to a successful PM system

    Execution process Conclusion

    Readings

  • 7/29/2019 Ppm pre-preventive maintenance of electrical

    3/35

    What is Preventive Maintenance?

    Preventive maintenance is a schedule of

    planned maintenance actions aimed atthe prevention of breakdowns andfailures. The primary goal of preventivemaintenance is to prevent the failure of

    equipment before it actually occurs. It isdesigned to preserve and enhanceequipment reliability by replacing worn

    components before they actually fail.

  • 7/29/2019 Ppm pre-preventive maintenance of electrical

    4/35

    Reasons for the need of a PM system

    Increased Automation

    Business loss due to production delays

    Production of a higher quality product

    Just-in-time manufacturing

    Need for a more organized, planned environment

  • 7/29/2019 Ppm pre-preventive maintenance of electrical

    5/35

    Advantages of a PM system

    Reduced production downtime, resultingin fewer machine breakdowns.

    Better conservation of assets and

    increased life expectancy of assets,thereby eliminating prematurereplacement of machinery andequipment.

    Timely, routine repairs circumvent fewerlarge-scale repairs.

  • 7/29/2019 Ppm pre-preventive maintenance of electrical

    6/35

    Continued -

    Reduced cost of repairs by reducing secondary failures. When partsfail in service, they usually damage other parts.

    Better quality products

    Identification of equipment with excessive maintenance costs

    Improved safety and quality conditions.

  • 7/29/2019 Ppm pre-preventive maintenance of electrical

    7/35

    Brainstorming Exercise

    Are there any risks of running a PM system?

    If there are risks when would it be a good time to use PM?

  • 7/29/2019 Ppm pre-preventive maintenance of electrical

    8/35

    Potential errors or damage

    of a PM system

    Damage to an adjacent equipment during a PM task.

    Reintroducing equipment mortality by installing new parts ormaterials.

    Damage due to an error in reinstalling equipment into its originallocation.

  • 7/29/2019 Ppm pre-preventive maintenance of electrical

    9/35

    When Does Preventive Maintenance Make

    Sense

    This is a logical choice that considers two conditions

    - #1. The component in question has an increasing failure rate.

    - #2. The overall cost of the preventive maintenance action must be less than theoverall cost of a corrective action.

    If both of these conditions are met PM would make sense

  • 7/29/2019 Ppm pre-preventive maintenance of electrical

    10/35

    The Law of PM

    Higher the value of the plant assets andequipment per square foot of plant, thegreater will be the return on a PM program.

    E.g. - downtime in an automobile plant assembly line at one

    time cost $10,000 per minute. Relating this to lost productiontime an automobile manufacturer reported that theestablishment of a PM program in their 16 assembly plantsreduced downtime from 300 hours per year to 25 hours peryear. With results such as this no well-managed plant can

    afford not to develop a PM program.

  • 7/29/2019 Ppm pre-preventive maintenance of electrical

    11/35

    How to determine the optimum age of

    replacement?

  • 7/29/2019 Ppm pre-preventive maintenance of electrical

    12/35

    How to determine the optimum age of

    replacement?

    A more technical approach.

    Where:

    R(t) = reliability at time t.

    CP

    = cost of planned replacement.

    CU= cost of unplanned replacement CPUT(t) = The optimum replacement time

  • 7/29/2019 Ppm pre-preventive maintenance of electrical

    13/35

    The key for a successful PM system

    Scheduling Should be automated to the maximum extentpossible

    Execution Should be done before the actual break downoccurs.

  • 7/29/2019 Ppm pre-preventive maintenance of electrical

    14/35

    Execution

    The Bath Tub Model Three

    stages of new parts1. Infant morality stage

    2. A fairly long run stage

    3. Wear out stage

    Traditional View according toBath Tub Model Replacecomponents just before theyentered wear out stage

  • 7/29/2019 Ppm pre-preventive maintenance of electrical

    15/35

    Execution

    Traditional view says

    Wear out stage = Increased rate of failure.

    Point to Ponder

    Since, wear out stage represents increased rate of failure,wouldnt it be plausible to execute the PM program at this stage?

  • 7/29/2019 Ppm pre-preventive maintenance of electrical

    16/35

    What really should PM focus on?

    Cleaning Found through testing Lubrication and inspection

    And correcting deficiencies

    Predetermined parts replacement

    should be minimal and done onlywhere statistical evidence clearlyindicates wear-out characteristics

  • 7/29/2019 Ppm pre-preventive maintenance of electrical

    17/35

    In the absence of data

    Age exploration programs

    Statistical analysis

    Cost shouldnt be a primary factor in deciding against data collectionfor a PM

  • 7/29/2019 Ppm pre-preventive maintenance of electrical

    18/35

    Motivating Preventive Maintenance

    Workers

    Training programs most effective

    Establish inspection and preventive maintenance as a recognized,

    important part of the overall maintenance program.

    Assign competent, responsible people to the preventive maintenanceprogram.

  • 7/29/2019 Ppm pre-preventive maintenance of electrical

    19/35

    Continued -

    Follow-up to assure quality performance and to show everyone that managementdoes care.

    Provide training in precision maintenance practices and training in the righttechniques and procedures for preventive maintenance on specific equipment.

    Set high standards.

    Publicize reduced costs with improved up-time and revenues, which are the resultof effective preventive maintenance

  • 7/29/2019 Ppm pre-preventive maintenance of electrical

    20/35

    Summary

    PM is not difficult to achieve. It is an essential part for cost reduction

    There is an element of risk involved in PM

    Careful planning and execution will reduce the risk of PM

    The biggest benefits of a PM program occur through painting,lubrication, cleaning and adjusting, and minor componentreplacement to extend the life of equipment and facilities.

  • 7/29/2019 Ppm pre-preventive maintenance of electrical

    21/35

    Why and what has to be maintained

    on breakers ?

    Case

    Mechanism

    Arc chute

    Main contacts Control unit

    Connection systems

    Auxiliary Devices

    Communication system

    Example for Breaker Maintenance

  • 7/29/2019 Ppm pre-preventive maintenance of electrical

    22/35

    Maintenance of case Function of case :

    - isolate the main contacts and protect from arcingeffects

    - support the mechanism, tripping device, auxiliarydevices, terminals

    - Must withstand the stresses during short circuit

    Damaged case is the consequence of

    - shocks,

    - moisture,

    - high short circuit,

    - overheating ( loose connection)

    Preventive maintenance includes :

    - visual inspection of dust, dirt, grease, moisture,cracks, soot,

    - cleaning, ( dust, dirt, soot,) with dry cloth, brush orvacuum cleaner

    - replacement in case of cracks

  • 7/29/2019 Ppm pre-preventive maintenance of electrical

    23/35

    Maintenance of the mechanism

    Breaker mechanism

    - Spring energy on Masterpact- Tumbler on Compact NS

    - operate the contacts to establish and interruptthe circuit

    Chassis mechanism

    - to rack in and out the breaker, test the breaker

  • 7/29/2019 Ppm pre-preventive maintenance of electrical

    24/35

    24

    Jammed mechanism is the consequence of :dust :

    shocks : bending of mechanical partcorrosive atmosphere : rust and corrosionof metallic partNo operation for a long time

    Preventive maintenance includes :dust removal : vacuum cleanerrecommendedcleaning : dry cloth, brush, solventprohibitedgreasing : only Schneider recommendedgreases, in small quantity

    operation of breaker / chassis : to give thespring charged energy and themechanism their original characteristics

    Maintenance of the mechanism Contd.

  • 7/29/2019 Ppm pre-preventive maintenance of electrical

    25/35

    Maintenance of the arc chute (Power breaker only)

    Function of arc chute :- splitters : extinguish the arc and

    absorb the energy under normalcondition and electric fault- filter : blow the pressured gas

    out , cool down the gas

    Arc chute deteriorates- under In : the insulation material

    of the arc chamber can perforate- under Icc : the metal part is

    vaporised

  • 7/29/2019 Ppm pre-preventive maintenance of electrical

    26/35

    26

    Maintenance of main contacts (Power breaker only) Contd.

    Arc chute in bad condition may resultin a non interruption of the arc,

    decrease of the isolating function andultimately destruction in case of highshort circuit current.

    Filters : avoid compound (made ofdust + grease) covering the filter

    Preventive maintenance includes :periodic inspection after a fault :splitters should not present holesand be too thin, plastic part shouldnot have holes ( decrease of

    insulation level)replacementcleaning of filter

  • 7/29/2019 Ppm pre-preventive maintenance of electrical

    27/35

    Maintenance of main contacts (Power breaker only) Function of main contacts :

    - To make or break the circuit under normal (

    In) or fault conditions (overload and Short-circuit )

    Contacts get worn during each mechanicaland electrical open / close operation andafter short circuit ( maxi 2 cycles at Icu)

    Worn contacts will result in :

    - over heating of the breaker ( increase ofcontact resistance)

    - decrease of life expectancy

    - measurement of individual pole resistance- replacement

  • 7/29/2019 Ppm pre-preventive maintenance of electrical

    28/35

    28

    Worn contacts will result in :over heating of the breaker ( increase of

    contact resistance)decrease of life expectancy

    Preventive maintenance includes :periodic visual check, control of themechanical contact wear indicator and

    electronic wear indicator on Micrologic P &Hmeasurement of individual pole resistancereplacement

    Preventive maintenance includes :periodic visual check, control of the

    mechanical contact wear indicator andelectronic wear indicator on Micrologic P &H

  • 7/29/2019 Ppm pre-preventive maintenance of electrical

    29/35

    Maintenance of electronic control unit

    Function of control unit :

    - permanently analyse the phase current compare it to the protection set and in case of fault

    trips the breaker

    Control unit is sensitive to :

    - environment : ambient temperature, humidity, corrosive atmosphere,

    - operating conditions : vibration, electro-magnetic field,

    A malfunctioning of the trip unit will result in :

    - a non interruption of the fault current

    - damage of equipment and breaker

    Preventive maintenance includes :

    - periodic push to trip test or trip test- control of the complete tripping channel

    - curve adjustment

    - saving of log event, settings ( Micrologic P & H)

  • 7/29/2019 Ppm pre-preventive maintenance of electrical

    30/35

    Maintenance of thermal-magnetic trip unit

    Function of thermal-magnetic trip unit :

    - Connected permanently in series with the phase currents

    - based on the bending of a bimetal for overload and the movement of a magnet in a strongmagnetic field

    Thermal -magnetic trip unit is sensitive to :

    - ambient temperature, corrosive atmosphere

    A malfunctioning of the trip unit will result in :

    - a non interruption of the fault current

    - damage of equipment and breaker

    Preventive maintenance includes :

    - primary injection test to trip the breaker

    M i t f ti t

  • 7/29/2019 Ppm pre-preventive maintenance of electrical

    31/35

    Maintenance of connection systems Function of connection systems :

    - Link together various types of devices by mean of electricaldistribution systems (bus bars, cables, auxiliary wires, ).

    Bad connection ( too tight or too loose) will result in :

    - Thermal effect leading to destruction of devices

    - short circuit or fire

    Preventive maintenance includes :

    - For fixed connectors : No need of control if done with Schneiderrecommendation . otherwise : check temperature rise, if loose,dismantle and tighten with new screws, bolts & washers

    - For sliding connectors : (mainly chassis)

    - periodic cleaning and greasing with Schneider

    recommended grease

    - if corrosive atmosphere ( SO2 / H2S) : clean withspecial solution ( Thioure) and re grease

    - Wires : check tightening and the insulation material

    i f ili d i

  • 7/29/2019 Ppm pre-preventive maintenance of electrical

    32/35

    Maintenance of auxiliary devices

    Function of auxiliary devices :

    - Shunt trip release, under voltage release, OF contacts,

    SD/SDE alarm contacts , electrical motor MCH Malfunctioning of the auxiliary device will result in a wrong

    operation of the breaker

    the consequences can be :- no safety operation ( emergency)

    - wrong operation in the circuit

    Preventive maintenance includes :- functional test of auxiliary device at nominal voltage

    - replacement

    PPM S h d l F T hi (M i P l)

  • 7/29/2019 Ppm pre-preventive maintenance of electrical

    33/35

    PPM Schedule For Township(Metering Panel)

    33

    Sl No

    Name of the

    Cluster

    Name of

    the block

    Date of PPM to

    be carried outPPM start time PPM end time

    Activity to be carried out

    1 A & B 11/5/2012 9:00 15:00

    All eletrical panel( Metering Panel, Utility Panel )

    cleanning & all Basbas & cable conection check &

    tightness

    2 C & D 11/6/2012 9:00 15:00

    All eletrical panel( Metering Panel, Utility Panel )

    cleanning & all Basbas & cable conection check &

    tightness

    3 E & F 11/7/2012 9:00 15:00

    All eletrical panel( Metering Panel, Utility Panel )

    cleanning & all Basbas & cable conection check &

    tightness

    4 G & H 11/8/2012 9:00 15:00

    All eletrical panel( Metering Panel, Utility Panel )

    cleanning & all Basbas & cable conection check &

    tightness

    5 J ,K & L 11/9/2012 9:00 15:00

    All eletrical panel( Metering Panel, Utility Panel )

    cleanning & all Basbas & cable conection check &

    tightness

    6 M & N 11/10/2012 9:00 15:00

    All eletrical panel( Metering Panel, Utility Panel )

    cleanning & all Basbas & cable conection check &

    tightness

    7 O & P 11/12/2012 9:00 15:00

    All eletrical panel( Metering Panel, Utility Panel )

    cleanning & all Basbas & cable conection check &

    tightness

    8 Aminety 11/15/2012 9:00 15:00

    Electrical Panel Cleaning & all busbar & cable connection

    check & tightness

    9 A & B 11/16/2012 9:00 15:00

    All eletrical panel( Metering Panel, Utility Panel)

    cleanning & all Basbas & cable conection check &

    tightness

    10 C , D & E 11/17/2012 9:00 15:00

    All eletrical panel( Metering Panel, Utility Panel)

    cleanning & all Basbas & cable conection check &

    tightness

    11 F & G 11/19/2012 9:00 15:00

    All eletrical panel( Metering Panel, Utility Panel)

    cleanning & all Basbas & cable conection check &

    tightness

    12 J & K 11/20/2012 9:00 15:00

    All eletrical panel( Metering Panel, Utility Panel)

    cleanning & all Basbas & cable conection check &

    tightness

    13 Aminety 11/21/2012 9:00 15:00

    Electrical Panel Cleaning & all busbar & cable connection

    check & tightness

    Koel

    Sankha

    PPM Schedule For Township(Substations)

  • 7/29/2019 Ppm pre-preventive maintenance of electrical

    34/35

    34

    Sl No

    Name of the

    Cluster

    Name of the

    block

    Date of PPM to be

    carried outPPM start t ime PPM end time

    Activity to be carried out Efected Area

    1 LT Panel # 6 1-Mar-13 9:00 15:00

    Eletrical Feeder panel cleanning , Breaker Rackout,Rackin

    check, Breaker Contact check. All Busbar & cable conection

    check & tightness

    SA/SB,SC/SD,WTP,PROJECT

    OFFICE,KA/KB,KC/KD/KE,

    KF/KG,KH/KJ,KF/KG

    2 LT Panel # 7 2-Mar-13 9:00 15:00

    Eletrical Feeder panel cleanning , Breaker Rackout,Rackin

    check, Breaker Contact check. All Busbar & cable conection

    check & tightness

    SE/SF,SG/SH,SJ/SK/SL,

    SM/SN,SO/SP,COMMERCIAL

    LT Panel # 5 3-Mar-13 9:00 15:00

    Eletrical Feeder panel cleanning , Breaker Rackout,Rackin

    check, Breaker Contact check. All Busbar & cable conection

    check & tightness SPARE

    3 LT Panel # 3 4-Mar-13 9:00 15:00

    Eletrical Feeder panel cleanning , Breaker Rackout,Rackin

    check, Breaker Contact check. All Busbar & cable conection

    check & tightness

    STUDIO/MA/MB,MC/MD/ME,

    MF/MG

    4 LT Panel # 4 5-Mar-13 9:00 15:00

    Eletrical Feeder panel cleanning , Breaker Rackout,Rackin

    check, Breaker Contact check. All Busbar & cable conection

    check & tightness

    MAINGATE/BANGALOW/

    HOSTEL

    5 LT Panel # 1 6-Mar-13 9:00 15:00

    Eletrical Feeder panel cleanning , Breaker Rackout,Rackin

    check, Breaker Contact check. All Busbar & cable conection

    check & tightness

    HATI BLOCK/COMMUNITY

    CENTER,TEMPLE,APPOLO

    6 LT Panel # 2 7-Mar-13 9:00 15:00

    Eletrical Feeder panel cleanning , Breaker Rackout,Rackin

    check, Breaker Contact check. All Busbar & cable conection

    check & tightness BRAHMANI BLOCK

    Substation # 3

    Substation # 1

    Substation # 2

    PPM Schedule For Township(Substations)