8/10/2019 Pmp Processes Pmbokv4.0
1/32
Sub-title (date, name)Arial narrow, 20pt - maximum 2
lines)
Main Title
(Arial narrow, 28pt -Maximum 2 lines)
Main Title
(Arial narrow, 28pt -Maximum 2 lines)
Version 4.0
PMP Examination Preparatory Course
Topic: Project Management Processes
Version 4.0
8/10/2019 Pmp Processes Pmbokv4.0
2/32
PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 1
What is covered
Project Management Processes
Process Groups
Project Management Knowledge Areas
Process Mapping
8/10/2019 Pmp Processes Pmbokv4.0
3/32
PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 2
Project Management Processes
Processset of interrelated actions and activities that areperformed to achieve a pre-specified set of products orresults or services
Project management processesensure the effective
flow of project throughout its existence. Product-oriented processes specify and create the
projects product.
These two processes overlap and interactthroughout the project
8/10/2019 Pmp Processes Pmbokv4.0
4/32
PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 3
Project Management Processes (Contd.)
42 processes are defined and mapped into 5 Process groups
9 Knowledge Management areas
8/10/2019 Pmp Processes Pmbokv4.0
5/32
PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 4
Project Management Processes (Contd.)
Inputs -> Tools/Techniques -> Outputs Each of the 42 processes have inputs, tools & techniques
and outputs
Key inputs tothe process.These are
often outputs
from anotherprocess
Tools andtechniques
used to createthe results or
outputs of theprocess
Key outputs,results anddeliverables
8/10/2019 Pmp Processes Pmbokv4.0
6/32
PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 5
Project Management Processes (Contd.)
Inputs -> Tools/Techniques -> Outputs Example (Perform Quality Assurance Process)
INPUTS
TOOLS / TECHNIQUES
OUTPUTS
8/10/2019 Pmp Processes Pmbokv4.0
7/32
PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 6
Process Groups
5 Process groups
Initiating
Planning
Executing
Monitoring and Controlling
Closing
Logical grouping of PM processes with clear dependencies
Performed in the same sequence on each project / phase Independent of application areas or industry focus
They are not project Phases
8/10/2019 Pmp Processes Pmbokv4.0
8/32
PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 7
Process GroupsInteraction
Commitment to
executing project
Initiating
Processes
Approach to
executing project
Planning
ProcessesCoordinating
people andother resources
Executing
ProcessesControlling
Processes
Closing
ProcessesFormal productacceptance andend of project
Monitoring,
measuring, andtaking correctiveaction
8/10/2019 Pmp Processes Pmbokv4.0
9/32
PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 8
Project Management Knowledge Area
Project Management Knowledge Area: an identifiedarea of project management defined by itsknowledge requirements and described in terms ofits component processes, practices, inputs, outputs,tools and techniques
8/10/2019 Pmp Processes Pmbokv4.0
10/32
PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 9
The Nine Knowledge Areas
Project Integration Management Project Scope Management
Project Time Management
Project Cost Management
Project Quality Management
Project Human Resource Management
Project Communications Management
Project Risk Management
Project Procurement Management
8/10/2019 Pmp Processes Pmbokv4.0
11/32
PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 10
Use of Mnemonics for memorizing knowledge areas
If She Takes Cash, Question Her Current Rent Payment(Knowledge Areas)
8/10/2019 Pmp Processes Pmbokv4.0
12/32
PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 11
Project Integration Management
Develop Project Charter (I)
Develop Project Management Plan (P)
Direct and Manage Project Execution (E)
Monitor and Control Project Work (M)
Perform Integrated Change Control (M)
Close Project or Phase (C)
Project Integration Management includes the processes and activities thatintegratevarious elements of project management which are identified, defined,combined, unified and coordinated within the [five] Project Management Process
Groups
8/10/2019 Pmp Processes Pmbokv4.0
13/32
PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 12
Project Integration Management (Contd.)
The Project IntegrationManagement
Knowledge Areaintegrates the
processes of the other8 Knowledge Areas
The Develop Project Charter (I)process (part of the Initiating ProcessGroup) is the first process of the project life cycle
INTEGRATION
MANAGEMENT
PROCUREMENT
SCOPE
TIME
RISK
MANAGEMENT COST
COMMUNICATIONS
HUMAN
RESOURCES
QUALITY
8/10/2019 Pmp Processes Pmbokv4.0
14/32
PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 13
Project Scope Management
Collect Requirements (P)
Define Scope (P)
Create WBS (P)
Verify Scope (M)
Control Scope (M)
Project Scope Management includes the processes required to ensurethat the project includes all workrequired and only thework required, to
complete the project successfully
8/10/2019 Pmp Processes Pmbokv4.0
15/32
PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 14
Project Scope ManagementWBS
Work Breakdown Structure (WBS)
A deliverable oriented, hierarchical grouping of projecttasks with increasing detail in each descending level
It is used to define the project in levels of detail to allow
the project team to determine the project's complexity andto assist in the process of estimating resourcerequirements, duration of tasks, and project risk
It is NOT a list of tasks but, rather, a grouping of tasks
usually by major component (work package),deliverable, or phase
8/10/2019 Pmp Processes Pmbokv4.0
16/32
PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 15
Project Time Management
Define Activities (P)
Sequence Activities (P)
Estimate Activity Resources (P)
Estimate Activity Durations (P)
Develop Schedule (P)
Control Schedule (M)
Project Time Management includes the processes concerning thetimelycompletion of the project
Remember: A Gantt chart is
NOT a project plan
8/10/2019 Pmp Processes Pmbokv4.0
17/32
PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 16
Project Time ManagementQuestions
1. The critical path in a network is the path that
a. Has the greatest degree of risk
b. Will elongate the project if the activities on this pathtakes longer than anticipated
c. Must be completed before all other paths
2. The duration of most activities will be significantlyinfluenced by the resources assigned to them
a. Trueb. False
8/10/2019 Pmp Processes Pmbokv4.0
18/32
PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 17
Project Cost Management
Estimate Costs (P)
Determine Budget (P)
Control Costs (M)
Project Cost Management is concerned with the processes involvedin planning, estimating, budgeting and controlling costs so that the project can
be completed within the approvedbudget
8/10/2019 Pmp Processes Pmbokv4.0
19/32
PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 18
Project Quality Management
Plan Quality (P)
Perform Quality Assurance (E)
Perform Quality Control (M)
Project Quality Management is concerned with the processesrequired to ensure the project will satisfycustomer objectives for
which it was undertaken
Quality is PLANNED, not
inspected in
Quality is conformance to specifications
and fitness to use
8/10/2019 Pmp Processes Pmbokv4.0
20/32
PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 19
Project Human Resource Management
Develop Human Resource Plan (P)
Acquire Project Team (E)
Develop Project Team (E)
Manage Project Team (E)
Project Human Resource includes processes that organize,manage, and lead the project team
8/10/2019 Pmp Processes Pmbokv4.0
21/32
PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 20
Project Communications Management
Identify Stakeholders (I)
Plan Communications (P)
Distribute Information (E)
Manage Stakeholder Expectations (E)
Report Performance (M)
Project Communications Management is concerned with the process thatensure timely and appropriategeneration, collection, delivery, storage
and disposition of project information
8/10/2019 Pmp Processes Pmbokv4.0
22/32
PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 21
Project Communication ManagementIdentify Stakeholders
Positive Stakeholders:
Will benefit if your project succeeds
More likely to give you support
Negative Stakeholders:
May suffer if your project succeeds
Unlikely to give you support and may even work againstyou
8/10/2019 Pmp Processes Pmbokv4.0
23/32
PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 22
StakeholdersQuestion ?
1. How do you work with negative stakeholders?
a. Keep your friends close and your stakeholders closer
b. Identify what this stakeholder's goals really are; seeif there are any of this persons goals that you can
satisfy without negatively impacting your projectc. Open up a dialog; keep the communication
channels open
d. Always be honest and play straight; even if a win/win
situation is not possible, you give the stakeholder anincentive to play straight in return
8/10/2019 Pmp Processes Pmbokv4.0
24/32
PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 23
Project Risk Management
Plan Risk Management (P)
Identify Risks (P)
Perform Qualitative Risk Analysis (P)
Perform Quantitative Risk Analysis (P)
Plan Risk Responses (P)
Monitor and Control Risks (M)
Project Risk Management is concerned with the identification andplanningfor potential risksthat may impact the project (both positive
and negative impacts)
8/10/2019 Pmp Processes Pmbokv4.0
25/32
8/10/2019 Pmp Processes Pmbokv4.0
26/32
PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 25
Professional Responsibility
Always take the high road
Follow the law
Follow the regulations of your company
When is it OK to offer a bribe to an official in order to get the
permits you need to proceed with your project?
Discussion Topic
8/10/2019 Pmp Processes Pmbokv4.0
27/32
PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 26
Professional ResponsibilityQuestions
1. During an informal meeting with your project client you are offered
a substantial monetary incentive to alter the configuration of theproduct to meet the client's personal need. This change may result inadditional project costs and schedule delays. The appropriate actionto take would be:
a. Refrain from accepting the offer and advise the customer tosubmit a request to the change control board
b. Accept the offer and issue an internal configuration changerequest to the design group
c. Obtain additional information about the request and thecustomer's personal need before accepting the offer
d. Delay acceptance of the offer until you can ensure that you canprotect yourself from any legal liabilities
8/10/2019 Pmp Processes Pmbokv4.0
28/32
PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 27
Professional ResponsibilityQuestions (Contd.)
2. Your project is running out of cash and significant work remains. You are directed
by senior management to instruct your people to use another project's chargenumbers while working on your project. You should:
a. Follow instructions
b. Inform the corporate auditors
c. Understand the background of management's instructions before taking any action
d. Shut down the project, if possible
3. Your executives, in appreciation for the success of your project, have given you a$10,000 bonus to be disbursed among your five-team members. One of the five, whois a substandard worker and accomplished very little on your project, is in your carpool. You should:
a. Provide everyone with an equal share
b. Provide everyone a share based upon their performance
c. Ask the workers to decide among themselves how the bonus should be subdivided
d. Ask the sponsor to make the decision
8/10/2019 Pmp Processes Pmbokv4.0
29/32
PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 28
Process Mapping
8/10/2019 Pmp Processes Pmbokv4.0
30/32
PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 29
Recap
Knowledge Areas
Scope Management
Integration Management
Monitoring & Controlling
Closing
WBS
Initiating
Process Groups
Risk Management
8/10/2019 Pmp Processes Pmbokv4.0
31/32
PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 30
Summary
Questions
8/10/2019 Pmp Processes Pmbokv4.0
32/32
www.capgemini.com/financialservices
Thank You