Top Banner

of 32

Pmp Processes Pmbokv4.0

Jun 02, 2018

Download

Documents

asimsquare
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
  • 8/10/2019 Pmp Processes Pmbokv4.0

    1/32

    Sub-title (date, name)Arial narrow, 20pt - maximum 2

    lines)

    Main Title

    (Arial narrow, 28pt -Maximum 2 lines)

    Main Title

    (Arial narrow, 28pt -Maximum 2 lines)

    Version 4.0

    PMP Examination Preparatory Course

    Topic: Project Management Processes

    Version 4.0

  • 8/10/2019 Pmp Processes Pmbokv4.0

    2/32

    PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate

    2009 Capgemini - All rights reserved 1

    What is covered

    Project Management Processes

    Process Groups

    Project Management Knowledge Areas

    Process Mapping

  • 8/10/2019 Pmp Processes Pmbokv4.0

    3/32

    PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate

    2009 Capgemini - All rights reserved 2

    Project Management Processes

    Processset of interrelated actions and activities that areperformed to achieve a pre-specified set of products orresults or services

    Project management processesensure the effective

    flow of project throughout its existence. Product-oriented processes specify and create the

    projects product.

    These two processes overlap and interactthroughout the project

  • 8/10/2019 Pmp Processes Pmbokv4.0

    4/32

    PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate

    2009 Capgemini - All rights reserved 3

    Project Management Processes (Contd.)

    42 processes are defined and mapped into 5 Process groups

    9 Knowledge Management areas

  • 8/10/2019 Pmp Processes Pmbokv4.0

    5/32

    PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate

    2009 Capgemini - All rights reserved 4

    Project Management Processes (Contd.)

    Inputs -> Tools/Techniques -> Outputs Each of the 42 processes have inputs, tools & techniques

    and outputs

    Key inputs tothe process.These are

    often outputs

    from anotherprocess

    Tools andtechniques

    used to createthe results or

    outputs of theprocess

    Key outputs,results anddeliverables

  • 8/10/2019 Pmp Processes Pmbokv4.0

    6/32

    PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate

    2009 Capgemini - All rights reserved 5

    Project Management Processes (Contd.)

    Inputs -> Tools/Techniques -> Outputs Example (Perform Quality Assurance Process)

    INPUTS

    TOOLS / TECHNIQUES

    OUTPUTS

  • 8/10/2019 Pmp Processes Pmbokv4.0

    7/32

    PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate

    2009 Capgemini - All rights reserved 6

    Process Groups

    5 Process groups

    Initiating

    Planning

    Executing

    Monitoring and Controlling

    Closing

    Logical grouping of PM processes with clear dependencies

    Performed in the same sequence on each project / phase Independent of application areas or industry focus

    They are not project Phases

  • 8/10/2019 Pmp Processes Pmbokv4.0

    8/32

    PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate

    2009 Capgemini - All rights reserved 7

    Process GroupsInteraction

    Commitment to

    executing project

    Initiating

    Processes

    Approach to

    executing project

    Planning

    ProcessesCoordinating

    people andother resources

    Executing

    ProcessesControlling

    Processes

    Closing

    ProcessesFormal productacceptance andend of project

    Monitoring,

    measuring, andtaking correctiveaction

  • 8/10/2019 Pmp Processes Pmbokv4.0

    9/32

    PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate

    2009 Capgemini - All rights reserved 8

    Project Management Knowledge Area

    Project Management Knowledge Area: an identifiedarea of project management defined by itsknowledge requirements and described in terms ofits component processes, practices, inputs, outputs,tools and techniques

  • 8/10/2019 Pmp Processes Pmbokv4.0

    10/32

    PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate

    2009 Capgemini - All rights reserved 9

    The Nine Knowledge Areas

    Project Integration Management Project Scope Management

    Project Time Management

    Project Cost Management

    Project Quality Management

    Project Human Resource Management

    Project Communications Management

    Project Risk Management

    Project Procurement Management

  • 8/10/2019 Pmp Processes Pmbokv4.0

    11/32

    PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate

    2009 Capgemini - All rights reserved 10

    Use of Mnemonics for memorizing knowledge areas

    If She Takes Cash, Question Her Current Rent Payment(Knowledge Areas)

  • 8/10/2019 Pmp Processes Pmbokv4.0

    12/32

    PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate

    2009 Capgemini - All rights reserved 11

    Project Integration Management

    Develop Project Charter (I)

    Develop Project Management Plan (P)

    Direct and Manage Project Execution (E)

    Monitor and Control Project Work (M)

    Perform Integrated Change Control (M)

    Close Project or Phase (C)

    Project Integration Management includes the processes and activities thatintegratevarious elements of project management which are identified, defined,combined, unified and coordinated within the [five] Project Management Process

    Groups

  • 8/10/2019 Pmp Processes Pmbokv4.0

    13/32

    PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate

    2009 Capgemini - All rights reserved 12

    Project Integration Management (Contd.)

    The Project IntegrationManagement

    Knowledge Areaintegrates the

    processes of the other8 Knowledge Areas

    The Develop Project Charter (I)process (part of the Initiating ProcessGroup) is the first process of the project life cycle

    INTEGRATION

    MANAGEMENT

    PROCUREMENT

    SCOPE

    TIME

    RISK

    MANAGEMENT COST

    COMMUNICATIONS

    HUMAN

    RESOURCES

    QUALITY

  • 8/10/2019 Pmp Processes Pmbokv4.0

    14/32

    PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate

    2009 Capgemini - All rights reserved 13

    Project Scope Management

    Collect Requirements (P)

    Define Scope (P)

    Create WBS (P)

    Verify Scope (M)

    Control Scope (M)

    Project Scope Management includes the processes required to ensurethat the project includes all workrequired and only thework required, to

    complete the project successfully

  • 8/10/2019 Pmp Processes Pmbokv4.0

    15/32

    PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate

    2009 Capgemini - All rights reserved 14

    Project Scope ManagementWBS

    Work Breakdown Structure (WBS)

    A deliverable oriented, hierarchical grouping of projecttasks with increasing detail in each descending level

    It is used to define the project in levels of detail to allow

    the project team to determine the project's complexity andto assist in the process of estimating resourcerequirements, duration of tasks, and project risk

    It is NOT a list of tasks but, rather, a grouping of tasks

    usually by major component (work package),deliverable, or phase

  • 8/10/2019 Pmp Processes Pmbokv4.0

    16/32

    PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate

    2009 Capgemini - All rights reserved 15

    Project Time Management

    Define Activities (P)

    Sequence Activities (P)

    Estimate Activity Resources (P)

    Estimate Activity Durations (P)

    Develop Schedule (P)

    Control Schedule (M)

    Project Time Management includes the processes concerning thetimelycompletion of the project

    Remember: A Gantt chart is

    NOT a project plan

  • 8/10/2019 Pmp Processes Pmbokv4.0

    17/32

    PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate

    2009 Capgemini - All rights reserved 16

    Project Time ManagementQuestions

    1. The critical path in a network is the path that

    a. Has the greatest degree of risk

    b. Will elongate the project if the activities on this pathtakes longer than anticipated

    c. Must be completed before all other paths

    2. The duration of most activities will be significantlyinfluenced by the resources assigned to them

    a. Trueb. False

  • 8/10/2019 Pmp Processes Pmbokv4.0

    18/32

    PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate

    2009 Capgemini - All rights reserved 17

    Project Cost Management

    Estimate Costs (P)

    Determine Budget (P)

    Control Costs (M)

    Project Cost Management is concerned with the processes involvedin planning, estimating, budgeting and controlling costs so that the project can

    be completed within the approvedbudget

  • 8/10/2019 Pmp Processes Pmbokv4.0

    19/32

    PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate

    2009 Capgemini - All rights reserved 18

    Project Quality Management

    Plan Quality (P)

    Perform Quality Assurance (E)

    Perform Quality Control (M)

    Project Quality Management is concerned with the processesrequired to ensure the project will satisfycustomer objectives for

    which it was undertaken

    Quality is PLANNED, not

    inspected in

    Quality is conformance to specifications

    and fitness to use

  • 8/10/2019 Pmp Processes Pmbokv4.0

    20/32

    PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate

    2009 Capgemini - All rights reserved 19

    Project Human Resource Management

    Develop Human Resource Plan (P)

    Acquire Project Team (E)

    Develop Project Team (E)

    Manage Project Team (E)

    Project Human Resource includes processes that organize,manage, and lead the project team

  • 8/10/2019 Pmp Processes Pmbokv4.0

    21/32

    PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate

    2009 Capgemini - All rights reserved 20

    Project Communications Management

    Identify Stakeholders (I)

    Plan Communications (P)

    Distribute Information (E)

    Manage Stakeholder Expectations (E)

    Report Performance (M)

    Project Communications Management is concerned with the process thatensure timely and appropriategeneration, collection, delivery, storage

    and disposition of project information

  • 8/10/2019 Pmp Processes Pmbokv4.0

    22/32

    PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate

    2009 Capgemini - All rights reserved 21

    Project Communication ManagementIdentify Stakeholders

    Positive Stakeholders:

    Will benefit if your project succeeds

    More likely to give you support

    Negative Stakeholders:

    May suffer if your project succeeds

    Unlikely to give you support and may even work againstyou

  • 8/10/2019 Pmp Processes Pmbokv4.0

    23/32

    PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate

    2009 Capgemini - All rights reserved 22

    StakeholdersQuestion ?

    1. How do you work with negative stakeholders?

    a. Keep your friends close and your stakeholders closer

    b. Identify what this stakeholder's goals really are; seeif there are any of this persons goals that you can

    satisfy without negatively impacting your projectc. Open up a dialog; keep the communication

    channels open

    d. Always be honest and play straight; even if a win/win

    situation is not possible, you give the stakeholder anincentive to play straight in return

  • 8/10/2019 Pmp Processes Pmbokv4.0

    24/32

    PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate

    2009 Capgemini - All rights reserved 23

    Project Risk Management

    Plan Risk Management (P)

    Identify Risks (P)

    Perform Qualitative Risk Analysis (P)

    Perform Quantitative Risk Analysis (P)

    Plan Risk Responses (P)

    Monitor and Control Risks (M)

    Project Risk Management is concerned with the identification andplanningfor potential risksthat may impact the project (both positive

    and negative impacts)

  • 8/10/2019 Pmp Processes Pmbokv4.0

    25/32

  • 8/10/2019 Pmp Processes Pmbokv4.0

    26/32

    PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate

    2009 Capgemini - All rights reserved 25

    Professional Responsibility

    Always take the high road

    Follow the law

    Follow the regulations of your company

    When is it OK to offer a bribe to an official in order to get the

    permits you need to proceed with your project?

    Discussion Topic

  • 8/10/2019 Pmp Processes Pmbokv4.0

    27/32

    PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate

    2009 Capgemini - All rights reserved 26

    Professional ResponsibilityQuestions

    1. During an informal meeting with your project client you are offered

    a substantial monetary incentive to alter the configuration of theproduct to meet the client's personal need. This change may result inadditional project costs and schedule delays. The appropriate actionto take would be:

    a. Refrain from accepting the offer and advise the customer tosubmit a request to the change control board

    b. Accept the offer and issue an internal configuration changerequest to the design group

    c. Obtain additional information about the request and thecustomer's personal need before accepting the offer

    d. Delay acceptance of the offer until you can ensure that you canprotect yourself from any legal liabilities

  • 8/10/2019 Pmp Processes Pmbokv4.0

    28/32

    PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate

    2009 Capgemini - All rights reserved 27

    Professional ResponsibilityQuestions (Contd.)

    2. Your project is running out of cash and significant work remains. You are directed

    by senior management to instruct your people to use another project's chargenumbers while working on your project. You should:

    a. Follow instructions

    b. Inform the corporate auditors

    c. Understand the background of management's instructions before taking any action

    d. Shut down the project, if possible

    3. Your executives, in appreciation for the success of your project, have given you a$10,000 bonus to be disbursed among your five-team members. One of the five, whois a substandard worker and accomplished very little on your project, is in your carpool. You should:

    a. Provide everyone with an equal share

    b. Provide everyone a share based upon their performance

    c. Ask the workers to decide among themselves how the bonus should be subdivided

    d. Ask the sponsor to make the decision

  • 8/10/2019 Pmp Processes Pmbokv4.0

    29/32

    PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate

    2009 Capgemini - All rights reserved 28

    Process Mapping

  • 8/10/2019 Pmp Processes Pmbokv4.0

    30/32

    PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate

    2009 Capgemini - All rights reserved 29

    Recap

    Knowledge Areas

    Scope Management

    Integration Management

    Monitoring & Controlling

    Closing

    WBS

    Initiating

    Process Groups

    Risk Management

  • 8/10/2019 Pmp Processes Pmbokv4.0

    31/32

    PMP Workshop | Financial ServicesAll work described was performed by Capgemini or a Capgemini affiliate

    2009 Capgemini - All rights reserved 30

    Summary

    Questions

  • 8/10/2019 Pmp Processes Pmbokv4.0

    32/32

    www.capgemini.com/financialservices

    Thank You