PMP Lecture 4: Project Integration Management

Mar 22, 2017

Download

Education

Mohamed Loey
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: PMP Lecture 4: Project Integration Management

Project Integration Management

Project Integration Management

Page 2: PMP Lecture 4: Project Integration Management

Project Integration Management

Knowledge Areas

Project Management Process

Initiating Planning ExecutingMonitoring& Control

Closing

4. Integration 4.1 DevelopProject Charter

4.2 Develop ProjectManagement Plan

4.3 Direct andManage ProjectWork

4.4 Monitor andControl ProjectWork4.5 PerformIntegrated ChangeControl

4.6 Close Projector Phase

Page 3: PMP Lecture 4: Project Integration Management

Project Integration Management

Project Integration Management includes the processes and

activities to identify, define, combine, unify, and coordinate the

various processes and project management activities within the

Project Management Process.

Page 4: PMP Lecture 4: Project Integration Management

Project Integration Management

Page 5: PMP Lecture 4: Project Integration Management

Project Integration Management

Process Knowledge AreasInitiating 4.1 Develop Project Charter

Planning 4.2 Develop Project Management Plan

Executing 4.3 Direct and Manage Project Work

Monitoring & Control4.4 Monitor and Control Project Work

4.5 Perform Integrated Change Control

Closing 4.6 Close Project or Phase

Page 6: PMP Lecture 4: Project Integration Management

Project Integration Management

Process Knowledge AreasInitiating 4.1 Develop Project Charter

Planning 4.2 Develop Project Management Plan

Executing 4.3 Direct and Manage Project Work

Monitoring & Control4.4 Monitor and Control Project Work

4.5 Perform Integrated Change Control

Closing 4.6 Close Project or Phase

Page 7: PMP Lecture 4: Project Integration Management

Project Integration Management

Develop Project Charter is the process of developing a document

that formally authorizes the existence of a project and provides the

project manager with the authority to apply organizational

resources to project activities.

Page 8: PMP Lecture 4: Project Integration Management

Project Integration Management

Project Name

Project purpose

Summary budget

Cost

Project Duration

Project Manager/ Authorities

High level Risk

Stakeholders

Project success criteria

Assumptions and constraints

Page 9: PMP Lecture 4: Project Integration Management

Project Integration Management

The key benefit of this process is a well-defied project start and

project boundaries, creation of a formal record of the project, and a

direct way for senior management to formally accept and commit to

the project.

Page 10: PMP Lecture 4: Project Integration Management

Project Integration Management

• Business case

• Project Statement of Work

• Agreements

• Enterprise environmental factors

• Organizational process assets

Inputs

• Expert judgment

• Facilitation techniques

Tools and

Techniques • Project charter

Outputs

Page 11: PMP Lecture 4: Project Integration Management

Project Integration Management

• Business case

• Project Statement of Work

• Agreements

• Enterprise environmental factors

• Organizational process assets

Inputs

• Expert judgment

• Facilitation techniques

Tools and

Techniques • Project charter

Outputs

Page 12: PMP Lecture 4: Project Integration Management

Project Integration Management

1) Business Case is a document that describes the necessary

information from a business standpoint to determine whether or not

the project is worth the required investment.

It is commonly used for decision making by managers

Page 13: PMP Lecture 4: Project Integration Management

Project Integration Management

The business case is created as a result of market demand (e.g., a

car company authorizing a project to build more fuel-efficient cars

in response to gasoline shortages)

Page 14: PMP Lecture 4: Project Integration Management

Project Integration Management

2) Project Statement of Work (or SOW)

is a formal document that defines

the entire scope of the project.

SOW written by sponsor or customer

Page 15: PMP Lecture 4: Project Integration Management

Project Integration Management

SOW

Business Need

Product Scope Description

Strategic Plan

Page 16: PMP Lecture 4: Project Integration Management

Project Integration Management

3) Agreements may take the form of contracts, memorandums of

understanding (MOUs), service level agreements (SLA), letter of

agreements, letters of intent, verbal agreements, email, or other

written agreements.

Page 17: PMP Lecture 4: Project Integration Management

Project Integration Management

4) Enterprise Environmental Factors:

o Governmental standards

o Industry standards

o Marketplace conditions

o Quality standards

Page 18: PMP Lecture 4: Project Integration Management

Project Integration Management

5) Organizational Process Assets:

• Templates (e.g., project charter template)

• Historical information and lessons learned knowledge base

Page 19: PMP Lecture 4: Project Integration Management

Project Integration Management

• Business case

• Project Statement of Work

• Agreements

• Enterprise environmental factors

• Organizational process assets

Inputs

• Expert judgment

• Facilitation techniques

Tools and

Techniques • Project charter

Outputs

Page 20: PMP Lecture 4: Project Integration Management

Project Integration Management

1) Expert Judgment: is often used to assess the inputs used to develop

the project charter.

2) Facilitation techniques:

Brainstorming, problem solving, and meeting management are

examples of key techniques used by facilitators

Page 21: PMP Lecture 4: Project Integration Management

Project Integration Management

• Business case

• Project Statement of Work

• Agreements

• Enterprise environmental factors

• Organizational process assets

Inputs

• Expert judgment

• Facilitation techniques

Tools and

Techniques • Project charter

Outputs

Page 22: PMP Lecture 4: Project Integration Management

Project Integration Management

1) Project Charter

Page 23: PMP Lecture 4: Project Integration Management

Project Integration Management

Page 24: PMP Lecture 4: Project Integration Management

Project Integration Management

Process Knowledge AreasInitiating 4.1 Develop Project Charter

Planning 4.2 Develop Project Management Plan

Executing 4.3 Direct and Manage Project Work

Monitoring & Control4.4 Monitor and Control Project Work

4.5 Perform Integrated Change Control

Closing 4.6 Close Project or Phase

Page 25: PMP Lecture 4: Project Integration Management

Project Integration Management

Develop Project Management Plan is the process of defining,

preparing, and coordinating all subsidiary plans and integrating

them into a comprehensive project management plan.

The key benefit of this process is a central document that defines the

basis of all project work.

Page 26: PMP Lecture 4: Project Integration Management

Project Integration Management

4.2 Develop Project

Management Plan

5.1 Plan Scope

Management

5.6 Control Scope

6.1 Plan Schedule

Management

6.7 Control Schedule

7.1 Plan Cost Management

7.4 Control Costs

8.1 Plan Quality

Management

9.1 Plan Human

Resource Management

4.2 Develop Project

Management Plan

10.1 Plan Communications

Management

10.3 Control Communications

11.1 Plan Risk Management

11.6 Control Risks

12.1 Plan Procurement Management

12.3 Control Procurements

12.4 Close Procurements

13.2 Plan Stakeholder

Management

13.4 Control Stakeholder Engagement

Page 27: PMP Lecture 4: Project Integration Management

Project Integration Management

1- Project charter

2- Outputs from other processes

3- Enterprise environmental factors

4- Organizational process assets

Inputs1- Expert judgment

2- Facilitation techniques

Tools and

Techniques1- Project management plan

Outputs

Page 28: PMP Lecture 4: Project Integration Management

Project Integration Management

1- Project charter

2- Outputs from other processes

3- Enterprise environmental factors

4- Organizational process assets

Inputs1- Expert judgment

2- Facilitation techniques

Tools and

Techniques1- Project management plan

Outputs

Page 29: PMP Lecture 4: Project Integration Management

Project Integration Management

1) Project Charter: Described in Section 4.1.3

Page 30: PMP Lecture 4: Project Integration Management

Project Integration Management

The project manager uses project charter as the

starting point for his initial planning

Project Charter Example

Time = 3 Years + 2 Months

Cost = 1 Million EGP +/- 25%

Page 31: PMP Lecture 4: Project Integration Management

Project Integration Management

2) Outputs from other processes

3) Enterprise environmental factors

o Governmental standards

o Industry standards

4) Organizational process assets

• Templates (e.g., project charter template)

• Historical information and lessons learned knowledge base

Page 32: PMP Lecture 4: Project Integration Management

Project Integration Management

1- Project charter

2- Outputs from other processes

3- Enterprise environmental factors

4- Organizational process assets

Inputs1- Expert judgment

2- Facilitation techniques

Tools and

Techniques1- Project management plan

Outputs

Page 33: PMP Lecture 4: Project Integration Management

Project Integration Management

1) Expert Judgment: is often used to assess the inputs used to develop

the project charter.

2) Facilitation techniques:

Brainstorming, problem solving, and meeting management are

examples of key techniques used by facilitators

Page 34: PMP Lecture 4: Project Integration Management

Project Integration Management

1- Project charter

2- Outputs from other processes

3- Enterprise environmental factors

4- Organizational process assets

Inputs1- Expert judgment

2- Facilitation techniques

Tools and

Techniques1- Project management plan

Outputs

Page 35: PMP Lecture 4: Project Integration Management

Project Integration Management

Page 36: PMP Lecture 4: Project Integration Management

Project Integration Management

Process Knowledge AreasInitiating 4.1 Develop Project Charter

Planning 4.2 Develop Project Management Plan

Executing 4.3 Direct and Manage Project Work

Monitoring & Control4.4 Monitor and Control Project Work

4.5 Perform Integrated Change Control

Closing 4.6 Close Project or Phase

Page 37: PMP Lecture 4: Project Integration Management

Project Integration Management

Direct and Manage Project Work is the process of leading and

performing the work defined in the project management plan and

implementing approved changes to achieve the project’s objectives.

The key benefit of this process is that it provides overall

management of the project work.

Page 38: PMP Lecture 4: Project Integration Management

Project Integration Management

• Project management plan

• Approved change requests

• Enterprise environmentalfactors

• Organizational process assets

Inputs

• Expert judgment

• Project managementinformation system

• Meetings

Tools and

Techniques • Deliverables

• Work performance data

• Change requests

• Project management plan updates

• Project documents updates

Outputs

Page 39: PMP Lecture 4: Project Integration Management

Project Integration Management

• Project management plan

• Approved change requests

• Enterprise environmentalfactors

• Organizational process assets

Inputs

• Expert judgment

• Project managementinformation system

• Meetings

Tools and

Techniques • Deliverables

• Work performance data

• Change requests

• Project management plan updates

• Project documents updates

Outputs

Page 40: PMP Lecture 4: Project Integration Management

Project Integration Management

1) Project management plan: Described in Section 4.2.3

2) Approved change requests are an output of the Perform Integrated

Change Control process, and include those requests reviewed and

approved for implementation by the change control board (CCB).

3) Enterprise environmental factors

4) Organizational process assets

Page 41: PMP Lecture 4: Project Integration Management

Project Integration Management

• Project management plan

• Approved change requests

• Enterprise environmentalfactors

• Organizational process assets

Inputs

• Expert judgment

• Project managementinformation system

• Meetings

Tools and

Techniques • Deliverables

• Work performance data

• Change requests

• Project management plan updates

• Project documents updates

Outputs

Page 42: PMP Lecture 4: Project Integration Management

Project Integration Management

1) Expert judgment is used to assess the inputs needed to direct and

manage execution of the project management plan.

2) Project management information system is a tools and techniques

used to gather and integrate the output of project management

system.

3) Meetings are used to discuss and address pertinent topics of the

project.

Page 43: PMP Lecture 4: Project Integration Management

Project Integration Management

Meeting

Well define agenda

meeting documented

Each attendance should have define function (role)

Page 44: PMP Lecture 4: Project Integration Management

Project Integration Management

• Project management plan

• Approved change requests

• Enterprise environmentalfactors

• Organizational process assets

Inputs

• Expert judgment

• Project managementinformation system

• Meetings

Tools and

Techniques • Deliverables

• Work performance data

• Change requests

• Project management plan updates

• Project documents updates

Outputs

Page 45: PMP Lecture 4: Project Integration Management

Project Integration Management

1) Deliverable is any unique and verifiable product, result or

capability to perform a service that is required to be produced to

complete a process.

Page 46: PMP Lecture 4: Project Integration Management

Project Integration Management

2) Work performance data are the raw observations and

measurements identified during activities being performed to carry

out the project work.

Examples of work performance data include work completed, key

performance indicators, technical performance measures, start and

finish dates of schedule activities, number of change requests,

number of defects, actual costs, and actual durations

Page 47: PMP Lecture 4: Project Integration Management

Project Integration Management

3) Change requests is a formal proposal to modify any document,

deliverable, or baseline.

Change requests

Corrective action

Preventive action

Defect repair

Updates

Page 48: PMP Lecture 4: Project Integration Management

Project Integration Management

4) Project management plan updates

5) Project documents updates:

Requirements documentation

Stakeholder register

Risk

Page 49: PMP Lecture 4: Project Integration Management

Project Integration Management

Page 50: PMP Lecture 4: Project Integration Management

Project Integration Management

Process Knowledge AreasInitiating 4.1 Develop Project Charter

Planning 4.2 Develop Project Management Plan

Executing 4.3 Direct and Manage Project Work

Monitoring & Control4.4 Monitor and Control Project Work

4.5 Perform Integrated Change Control

Closing 4.6 Close Project or Phase

Page 51: PMP Lecture 4: Project Integration Management

Project Integration Management

Monitor and Control Project Work is the process of tracking,

reviewing, and reporting the progress to meet the performance

objectives defied in the project management plan.

The key benefit of this process is that it allows stakeholders to

understand the current state of the project, the steps taken, and

budget, schedule, and scope forecasts.

Page 52: PMP Lecture 4: Project Integration Management

Project Integration Management

Inputs

Project management plan

Schedule forecasts

Cost forecasts

Validated changes

Work performance information

Enterprise environmental factors

Organizational process assets

Tools and

Techniques

Expert judgment

Analytical techniques

Project managementinformation system

Meetings

Outputs

Change requests

Work performance reports

Project management plan updates

Project documents updates

Page 53: PMP Lecture 4: Project Integration Management

Project Integration Management

Inputs

Project management plan

Schedule forecasts

Cost forecasts

Validated changes

Work performance information

Enterprise environmental factors

Organizational process assets

Tools and

Techniques

Expert judgment

Analytical techniques

Project managementinformation system

Meetings

Outputs

Change requests

Work performance reports

Project management plan updates

Project documents updates

Page 54: PMP Lecture 4: Project Integration Management

Project Integration Management

1) Project Management Plan Described in Section 4.2.3

2) Schedule Forecasts are derived from progress against the schedule

baseline and computed time estimate to complete (ETC).

3) Cost Forecasts are derived from progress against the cost baseline and

computed estimates to complete (ETC)

4) Validated changes Approved changes that result from the Perform

Integrated Change Control process require validation to ensure that the

change was appropriately implemented

Page 55: PMP Lecture 4: Project Integration Management

Project Integration Management

5) Work performance information is the performance data collected

from various controlling processes, analyzed in context, and

integrated based on relationships across areas.

6) Enterprise Environmental Factors

7) Organizational Process Assets

Page 56: PMP Lecture 4: Project Integration Management

Project Integration Management

Inputs

Project management plan

Schedule forecasts

Cost forecasts

Validated changes

Work performance information

Enterprise environmental factors

Organizational process assets

Tools and

Techniques

Expert judgment

Analytical techniques

Project managementinformation system

Meetings

Outputs

Change requests

Work performance reports

Project management plan updates

Project documents updates

Page 57: PMP Lecture 4: Project Integration Management

Project Integration Management

1) Expert Judgment

2) Analytical techniques are applied in project management to

forecast potential outcomes, ex: Regression analysis

3) Project Management Information System is tools that gather and

provides access to automated tools, such as scheduling, cost, and

resourcing tools

4) Meetings

Page 58: PMP Lecture 4: Project Integration Management

Project Integration Management

Inputs

Project management plan

Schedule forecasts

Cost forecasts

Validated changes

Work performance information

Enterprise environmental factors

Organizational process assets

Tools and

Techniques

Expert judgment

Analytical techniques

Project managementinformation system

Meetings

Outputs

Change requests

Work performance reports

Project management plan updates

Project documents updates

Page 59: PMP Lecture 4: Project Integration Management

Project Integration Management

1) Change requests

2) Work performance reports

3) Project management plan updates

4) Project documents updates

Page 60: PMP Lecture 4: Project Integration Management

Project Integration Management

Page 61: PMP Lecture 4: Project Integration Management

Project Integration Management

Process Knowledge AreasInitiating 4.1 Develop Project Charter

Planning 4.2 Develop Project Management Plan

Executing 4.3 Direct and Manage Project Work

Monitoring & Control4.4 Monitor and Control Project Work

4.5 Perform Integrated Change Control

Closing 4.6 Close Project or Phase

Page 62: PMP Lecture 4: Project Integration Management

Project Integration Management

Perform Integrated Change Control is the process of reviewing all

change requests; approving changes and managing changes to

deliverables, organizational process assets, project documents, and the

project management plan; and communicating their disposition.

The key benefit of this process is that it allows for documented changes

within the project to be considered in an integrated fashion while

reducing project risk, which often arises from changes made without

consideration to the overall project objectives or plans.

Page 63: PMP Lecture 4: Project Integration Management

Project Integration Management

Inputs

• Project management plan

• Work performancereports

• Change requests

• Enterprise environmental factors

• Organizational process assets

Tools and

Techniques

• Expert judgment

• Meetings

• Change control tools

Outputs

• Approved change requests

• Change log

• Project management plan updates

• Project documents updates

Page 64: PMP Lecture 4: Project Integration Management

Project Integration Management

Inputs

• Project management plan

• Work performancereports

• Change requests

• Enterprise environmental factors

• Organizational process assets

Tools and

Techniques

• Expert judgment

• Meetings

• Change control tools

Outputs

• Approved change requests

• Change log

• Project management plan updates

• Project documents updates

Page 65: PMP Lecture 4: Project Integration Management

Project Integration Management

1) Project management plan Described in Section 4.2.3

2) Work performance reports

3) Change requests

4) Enterprise environmental factors

5) Organizational process assets

Page 66: PMP Lecture 4: Project Integration Management

Project Integration Management

Inputs

• Project management plan

• Work performancereports

• Change requests

• Enterprise environmental factors

• Organizational process assets

Tools and

Techniques

• Expert judgment

• Meetings

• Change control tools

Outputs

• Approved change requests

• Change log

• Project management plan updates

• Project documents updates

Page 67: PMP Lecture 4: Project Integration Management

Project Integration Management

1) Expert judgment

2) Meetings

3) Change control tools

Page 68: PMP Lecture 4: Project Integration Management

Project Integration Management

Inputs

• Project management plan

• Work performancereports

• Change requests

• Enterprise environmental factors

• Organizational process assets

Tools and

Techniques

• Expert judgment

• Meetings

• Change control tools

Outputs

• Approved change requests

• Change log

• Project management plan updates

• Project documents updates

Page 69: PMP Lecture 4: Project Integration Management

Project Integration Management

1) Approved change requests

2) Change log

3) Project management plan updates

4) Project documents updates

Page 70: PMP Lecture 4: Project Integration Management

Project Integration Management

Page 71: PMP Lecture 4: Project Integration Management

Project Integration Management

Process Knowledge AreasInitiating 4.1 Develop Project Charter

Planning 4.2 Develop Project Management Plan

Executing 4.3 Direct and Manage Project Work

Monitoring & Control4.4 Monitor and Control Project Work

4.5 Perform Integrated Change Control

Closing 4.6 Close Project or Phase

Page 72: PMP Lecture 4: Project Integration Management

Project Integration Management

Close Project or Phase is the process of finalizing all activities across

all of the Project Management Process to formally complete the

project or phase.

The key benefit of this process is that it provides lessons learned, the

formal ending of project work, and the release of organization

resources to pursue new endeavors.

Page 73: PMP Lecture 4: Project Integration Management

Project Integration Management

InputsProject

management plan

Accepted deliverables

Organizational processassets

Tools and

TechniquesExpert

judgmentMeetings

Analytical techniques

OutputsFinal product,

service, or result transition

Organizational process assets

updates

Page 74: PMP Lecture 4: Project Integration Management

Project Integration Management

InputsProject

management plan

Accepted deliverables

Organizational processassets

Tools and

TechniquesExpert

judgmentMeetings

Analytical techniques

OutputsFinal product,

service, or result transition

Organizational process assets

updates

Page 75: PMP Lecture 4: Project Integration Management

Project Integration Management

1) Project management plan

2) Accepted deliverables

3) Organizational process assets

Page 76: PMP Lecture 4: Project Integration Management

Project Integration Management

InputsProject

management plan

Accepted deliverables

Organizational processassets

Tools and

TechniquesExpert

judgmentMeetings

Analytical techniques

OutputsFinal product,

service, or result transition

Organizational process assets

updates

Page 77: PMP Lecture 4: Project Integration Management

Project Integration Management

1) Expert judgment

2) Meetings

3) Analytical techniques

Page 78: PMP Lecture 4: Project Integration Management

Project Integration Management

InputsProject

management plan

Accepted deliverables

Organizational processassets

Tools and

TechniquesExpert

judgmentMeetings

Analytical techniques

OutputsFinal product,

service, or result transition

Organizational process assets

updates

Page 79: PMP Lecture 4: Project Integration Management

Project Integration Management

1) Final product, service, or result transition

2) Organizational process assets updates

Assets

Project filesProject closure

documentsHistorical

information

Page 80: PMP Lecture 4: Project Integration Management

Project Integration Management

Page 81: PMP Lecture 4: Project Integration Management

Project Integration Management

facebook.com/mloey

[email protected]

twitter.com/mloey

linkedin.com/in/mloey

[email protected]

mloey.github.io

Page 82: PMP Lecture 4: Project Integration Management

Project Integration Management

www.YourCompany.com© 2020 Companyname PowerPoint Business Theme. All Rights Reserved.

THANKS FOR YOUR TIME