Performance Based Cleanups Performance Based Cleanups Florida Department of Environmental Protection Florida Department of Environmental Protection Bureau of Petroleum Storage Systems Bureau of Petroleum Storage Systems Ferda Yilmaz Ferda Yilmaz The 17th Annual UST/LUST National Conference March 2005
23

Performance Based Cleanups - NEIWPCC

Dec 06, 2021

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Performance Based Cleanups - NEIWPCC

Performance Based CleanupsPerformance Based CleanupsFlorida Department of Environmental ProtectionFlorida Department of Environmental Protection

Bureau of Petroleum Storage SystemsBureau of Petroleum Storage Systems

Ferda YilmazFerda Yilmaz

The 17th Annual UST/LUST National Conference March 2005

Page 2: Performance Based Cleanups - NEIWPCC
Page 3: Performance Based Cleanups - NEIWPCC
Page 4: Performance Based Cleanups - NEIWPCC

• Streamlined Site Assessment (StSA)

• Streamlined Remediation– Performance Based Cleanups (PBCs)

Streamlined ProcessesStreamlined Processes

• Streamlined Site Assessment (StSA)

• Streamlined Remediation– Performance Based Cleanups (PBCs)

Page 5: Performance Based Cleanups - NEIWPCC

Total Number of Agreements 356Total Value $70,000 KAvg. Cleanup Cost Tier-1 $355 KAvg. Cleanup Cost Tier-2 $215 KSite Closures 57Time to Closure 2-6 yrs

PBC OverviewPBC Overview

Total Number of Agreements 356Total Value $70,000 KAvg. Cleanup Cost Tier-1 $355 KAvg. Cleanup Cost Tier-2 $215 KSite Closures 57Time to Closure 2-6 yrs

Page 6: Performance Based Cleanups - NEIWPCC

• What is PBC?

• How do we price PBCs?

• How do we negotiate PBCs?

• How do we finalize PBCs?

Performance Based Cleanups (PBCs)Performance Based Cleanups (PBCs)• What is PBC?

– How do we get there?– What are the proposal requirements?

• How do we price PBCs?– Team approach

• How do we negotiate PBCs?– Team approach

• How do we finalize PBCs?

Page 7: Performance Based Cleanups - NEIWPCC

• Simplified

• Major Categories Only

• Line items for major costs

• No T&M detail

Cost Breakdown RequirementsPBC ProposalPBC Proposal

• Simplified

• Major Categories Only

• Line items for major costs

• No T&M detail

Cost Breakdown Requirements

Page 8: Performance Based Cleanups - NEIWPCC

• Baseline Sampling• Remedial Action Plan• Remedial Action Implementation• Operation & Maintenance (O&M)• Post Remedial Monitoring (PRM)• Site Closure

Basic Proposal Elements

PBC Proposal PBC Proposal

• Baseline Sampling• Remedial Action Plan• Remedial Action Implementation• Operation & Maintenance (O&M)• Post Remedial Monitoring (PRM)• Site Closure

Basic Proposal Elements

Page 9: Performance Based Cleanups - NEIWPCC

• Baseline Sampling

– Required if Data > 9 months old

– Include Key & Perimeter wells

– Include all contaminants

PBC Proposal ElementsPBC Proposal Elements

• Baseline Sampling

– Required if Data > 9 months old

– Include Key & Perimeter wells

– Include all contaminants

Page 10: Performance Based Cleanups - NEIWPCC

• Remedial Action Plan

– May be included in PBC

– Pilot test is optional

– Consider level of effort for design

– FDEP review requirements different

PBC Proposal ElementsPBC Proposal Elements

• Remedial Action Plan

– May be included in PBC

– Pilot test is optional

– Consider level of effort for design

– FDEP review requirements different

Page 11: Performance Based Cleanups - NEIWPCC

•Trailer unit •Fenced treatment compound

•Trenching length•Materials

•Number of people •Number of days

• Remedial Action Plan Implementation

– Equipment:

– Construction:

– Labor:

PBC Proposal ElementsPBC Proposal Elements

• Remedial Action Plan Implementation

– Equipment:

– Construction:

– Labor:

•Trailer unit •Fenced treatment compound

•Trenching length•Materials

•Number of people •Number of days

Page 12: Performance Based Cleanups - NEIWPCC

• Operation & Maintenance– Number of years in O&M

– Key & Perimeter well sampling plan– Reporting frequency

– Utilities– Permits– Repairs

PBC Proposal ElementsPBC Proposal Elements

• Operation & Maintenance– Number of years in O&M

– Key & Perimeter well sampling plan– Reporting frequency

– Utilities– Permits– Repairs

Page 13: Performance Based Cleanups - NEIWPCC

• Post Remedial Monitoring

– Key & perimeter well sampling plan

– Reporting frequency

– Consider rebounds

PBC Proposal ElementsPBC Proposal Elements

• Post Remedial Monitoring

– Key & perimeter well sampling plan

– Reporting frequency

– Consider rebounds

Page 14: Performance Based Cleanups - NEIWPCC

• Site Closure

– Well abandonment

– Equipment demobilization

PBC Proposal ElementsPBC Proposal Elements

• Site Closure

– Well abandonment

– Equipment demobilization

Page 15: Performance Based Cleanups - NEIWPCC

Pricing & Negotiation TeamPricing & Negotiation Team

Distribution

Team Member A Team Member B Team Member C

Key & Perimeter Wells Sampling Parameters Sampling Frequency Cleanup Time Reporting Frequency

Cost Estimate Range

Exchange Comments

Teleconference/Meeting

15 Days Review Time

Proposal Received

Page 16: Performance Based Cleanups - NEIWPCC

• By e-mail• Copy e-mail to team members• Lay out changes

• Number of key & perimeter wells• Sampling frequency• Sampling parameters• Reporting frequency

Negotiation TeamNegotiation Team

• By e-mail• Copy e-mail to team members• Lay out changes

• Number of key & perimeter wells• Sampling frequency• Sampling parameters• Reporting frequency

Page 17: Performance Based Cleanups - NEIWPCC

PBC Template

Target Levels: Groundwater GCTLs pursuant to 62-770Soil SCTLs pursuant to 62-770Free Product Free Product shall not be present Surface Water No Surface Water Body Affected by ContaminationOther N/A

Key Wells (list): MW-1, MW-7, MW-8, DMW-1

Sampling Frequency (in RA): Quarterly Parameters: BTEX + MTBE by EPA 8021

Perimeter Wells (list): MW-3, MW-4, MW-10, MW-12 Sampling Frequency (in RA): Quarterly

Parameters: BTEX + MTBE by EPA 8021Other Sampling Requirements:Other Analytical Requirements:

PBC Template

This is a cleanup to:

Target Levels: Groundwater GCTLs pursuant to 62-770Soil SCTLs pursuant to 62-770Free Product Free Product shall not be present Surface Water No Surface Water Body Affected by ContaminationOther N/A

Key Wells (list): MW-1, MW-7, MW-8, DMW-1 Sampling Frequency (in RA): Quarterly

Parameters: BTEX + MTBE by EPA 8021Perimeter Wells (list): MW-3, MW-4, MW-10, MW-12

Sampling Frequency (in RA): Quarterly Parameters: BTEX + MTBE by EPA 8021

Other Sampling Requirements:Other Analytical Requirements:

CTLs Tier 1/Elevated Target Levels

Page 18: Performance Based Cleanups - NEIWPCC

PBC TemplatePBC Template

Baseline Data:MW-1, MW-2, MW-3, MW-4, MW-7, MW-8, MW-10, BTEX + MTBE by EPA 8021, PAHs by EPA 8270, TR

Reduction Measurement:Reporting Frequency:Other Reporting:

Baseline Wells:Baseline Parameters:

BTEX + MTBE Other:Total Naphthalenes

Other:SemiannuallyQuarterly

To be collected within 30 days of contract execu Use Existing Data(data must be sent to site manager prior to next activity)

Page 19: Performance Based Cleanups - NEIWPCC

Agreement Ceiling Amount: $234,567.00Agreement Start Date: 8/1/2003

Payment Amt.Milestone 1: System Startup 45% $105,555.15

Milestone 2: 50% Reduction 10% $23,456.70

Milestone 3: 75% Reduction 10% $23,456.70

Milestone 4: 90% Reduction 10% $23,456.70

Milestone 5: Target Levels, all Contaminants, all Med 10% $23,456.70

Milestone 6: Maintain Target Levels 10% $23,456.70

Milestone 7: Site Rehabilitation Completion Order 5% $11,728.35

Milestone 8:

Milestone 9:

Milestone 10:

Total %: 100%

Payment %Milestones

PBC TemplatePBC TemplateAgreement Ceiling Amount: $234,567.00

Agreement Start Date: 8/1/2003Payment Amt.

Milestone 1: System Startup 45% $105,555.15

Milestone 2: 50% Reduction 10% $23,456.70

Milestone 3: 75% Reduction 10% $23,456.70

Milestone 4: 90% Reduction 10% $23,456.70

Milestone 5: Target Levels, all Contaminants, all Med 10% $23,456.70

Milestone 6: Maintain Target Levels 10% $23,456.70

Milestone 7: Site Rehabilitation Completion Order 5% $11,728.35

Milestone 8:

Milestone 9:

Milestone 10:

Total %: 100%

Payment %Milestones

Page 20: Performance Based Cleanups - NEIWPCC

T&M

WOs Inv

RAP 1 2RAC 1 4O&M 1 1 5O&M 2 1 5O&M 3 1 5PRM 1 5SC 1 2

_____________________________

Total 7 28

PBCWOs Inv

RAP 1 1RAC (startup) - 1O&M (50%) - 1O&M (75%) - 1O&M (90%) - 1CTLs - 1Main. CTLs - 1SC - 1Verification 1 1

_________________________________

Total 2 9

Administrative Overhead

T&M

WOs Inv

RAP 1 2RAC 1 4O&M 1 1 5O&M 2 1 5O&M 3 1 5PRM 1 5SC 1 2

_____________________________

Total 7 28

PBCWOs Inv

RAP 1 1RAC (startup) - 1O&M (50%) - 1O&M (75%) - 1O&M (90%) - 1CTLs - 1Main. CTLs - 1SC - 1Verification 1 1

_________________________________

Total 2 9

Page 21: Performance Based Cleanups - NEIWPCC

• Bidding

– Under State Lead Contracts

– No negotiation needed

More Streamlined ProcessMore Streamlined Process

• Bidding

– Under State Lead Contracts• Single site bidding

• Multiple site bidding

– No negotiation needed

Page 22: Performance Based Cleanups - NEIWPCC

• http://www.dep.state.fl.us/waste/categories/pcp/pages/pbc.htm

• Ferda Yilmaz - 850/245-8885

More InformationMore Information

• http://www.dep.state.fl.us/waste/categories/pcp/pages/pbc.htm

• Ferda Yilmaz - 850/245-8885

Page 23: Performance Based Cleanups - NEIWPCC

Questions?Questions?