NO NAMA KEGIATAN BIAYA BOBOT KONTROL 1 Pek. Persiapan Rp 5,000,000 1.8% 1 1.8% 1 1.8% 2 Pek. Pondasi Rp 30,000,000 10.9% 2 10.9% 3 10.9% 3 Pek. Pemasangan sloof Rp 10,000,000 3.6% 1 3.6% 1 3.6% 4 Pek. Kolom Rp 20,000,000 7.3% 2 7.3% 2 7.3% 5 Pek. Pasangan dinding Rp 20,000,000 7.3% 3 7.3% 3 7.3% 6 Pek. Pemasangan kusen Rp 30,000,000 10.9% 2 10.9% 2 10.9% 7 Pek. Ring balk Rp 20,000,000 7.3% 1 7.3% 1 7.3% 8 Pek. Atap Rp 70,000,000 25.5% 2 25.5% 3 25.5% 9 Pek plafon Rp 15,000,000 5.5% 2 5.5% 2 3.0% 10 Pek. Plesteran dinding Rp 15,000,000 5.5% 3 5.5% 2 2.0% 11 Pek. Lantai Rp 30,000,000 10.9% 2 10.9% 2 0.0% 12 Pek. Finishing Rp 10,000,000 3.6% 2 3.6% 1 0.0% Rp275,000,000 100.0% 46 Progres rencana Progres kumulatif rencana Progres realisasi Progres kumulatif realisasi DURASI (minggu)
33

penjadwalan proyek

Feb 14, 2016

Download

Documents

bettergrace

penjadwalan proyek menggunakan microsoft excel
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: penjadwalan proyek

NO NAMA KEGIATAN BIAYA BOBOT KONTROL WAKTU PENYELESAIAN PROYEK (minggu)1 2

1 Pek. Persiapan Rp 5,000,000 1.8%1 1.8% 1.8%1 1.8% 1.8%

2 Pek. Pondasi Rp 30,000,000 10.9%2 10.9% 5.5% 5.5%3 10.9% 5.0% 3.6%

3 Pek. Pemasangan sloof Rp 10,000,000 3.6%1 3.6% 3.6%1 3.6%

4 Pek. Kolom Rp 20,000,000 7.3%2 7.3%2 7.3%

5 Pek. Pasangan dinding Rp 20,000,000 7.3%3 7.3%3 7.3%

6 Pek. Pemasangan kusen Rp 30,000,000 10.9%2 10.9%2 10.9%

7 Pek. Ring balk Rp 20,000,000 7.3%1 7.3%1 7.3%

8 Pek. Atap Rp 70,000,000 25.5%2 25.5%3 25.5%

9 Pek plafon Rp 15,000,000 5.5%2 5.5%2 3.0%

10 Pek. Plesteran dinding Rp 15,000,000 5.5%3 5.5%2 2.0%

11 Pek. Lantai Rp 30,000,000 10.9%2 10.9%2 0.0%

12 Pek. Finishing Rp 10,000,000 3.6%2 3.6%1 0.0%

Rp 275,000,000 100.0% 46Progres rencana 7.3% 9.1%

Progres kumulatif rencana 7.3% 16.4%Progres realisasi 6.8% 3.6%

Progres kumulatif realisasi 6.8% 10.4%

DURASI (minggu)

Page 2: penjadwalan proyek

WAKTU PENYELESAIAN PROYEK (minggu)3 4 5 6 7 8 9 10 11 12 13 14 15

2.3%

3.6%3.6% 3.6%

3.6% 3.6%2.4% 2.4% 2.4%3.0% 2.3% 2.0%

5.5% 5.5%6.0% 4.9%

7.3%7.3%

12.7% 12.7%10.0% 10.0% 5.5%

2.7% 2.7%3.0%1.8% 1.8% 1.8%2.0%

5.5% 5.5%

1.8% 1.8%

3.6% 6.1% 7.9% 7.9% 7.3% 12.7% 12.7% 4.5% 4.5% 7.3% 5.5% 1.8% 1.8%20.0% 26.1% 33.9% 41.8% 49.1% 61.8% 74.5% 79.1% 83.6% 90.9% 96.4% 98.2% 100%

5.9% 6.6% 11.9% 6.9% 7.3% 10.0% 10.0% 10.5% 0.0% 0.0% 0.0% 0.0% 0.0%16.3% 23.0% 34.9% 41.8% 49.1% 59.1% 69.1% 79.6% 79.6% 79.6% 79.6% 79.6% 79.6%

Page 3: penjadwalan proyek

Kontrol

Page 4: penjadwalan proyek

NO NAMA KEGIATAN BIAYA BOBOT KONTROL WAKTU PENYELESAIAN PROYEK (minggu)1 2

1 Pek. Persiapan Rp 5,000,000 1.8%1 1.8% 1.8%1 1.8% 1.8%

2 Pek. Pondasi Rp 30,000,000 10.9%2 10.9% 5.5% 5.5%3 10.9% 5.0% 3.6%

3 Pek. Pemasangan sloof Rp 10,000,000 3.6%1 3.6% 3.6%1 3.6%

4 Pek. Kolom Rp 20,000,000 7.3%2 7.3%2 7.3%

5 Pek. Pasangan dinding Rp 20,000,000 7.3%3 7.3%3 7.3%

6 Pek. Pemasangan kusen Rp 30,000,000 10.9%2 10.9%2 10.9%

7 Pek. Ring balk Rp 20,000,000 7.3%1 7.3%1 7.3%

8 Pek. Atap Rp 70,000,000 25.5%2 25.5%3 20.0%

9 Pek plafon Rp 15,000,000 5.5%2 5.5%2 0.0%

10 Pek. Plesteran dinding Rp 15,000,000 5.5%3 5.5%2 0.0%

11 Pek. Lantai Rp 30,000,000 10.9%2 10.9%2 0.0%

12 Pek. Finishing Rp 10,000,000 3.6%2 3.6%1 0.0%

Rp 275,000,000 100.0% 46Progres rencana 7.3% 9.1%

Progres kumulatif rencana 7.3% 16.4%Progres realisasi 6.8% 3.6%

Progres kumulatif realisasi 6.8% 10.4%

DURASI (minggu)

Page 5: penjadwalan proyek

WAKTU PENYELESAIAN PROYEK (minggu)3 4 5 6 7 8 9 10 11 12 13 14 15

2.3%

3.6%3.6% 3.6%

3.6% 3.6%2.4% 2.4% 2.4%3.0% 2.3% 2.0%

5.5% 5.5%6.0% 4.9%

7.3%7.3%

12.7% 12.7%10.0% 10.0%

2.7% 2.7%

1.8% 1.8% 1.8%

5.5% 5.5%

1.8% 1.8%

3.6% 6.1% 7.9% 7.9% 7.3% 12.7% 12.7% 4.5% 4.5% 7.3% 5.5% 1.8% 1.8%20.0% 26.1% 33.9% 41.8% 49.1% 61.8% 74.5% 79.1% 83.6% 90.9% 96.4% 98.2% 100%

5.9% 6.6% 11.9% 6.9% 7.3% 10.0% 10.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%16.3% 23.0% 34.9% 41.8% 49.1% 59.1% 69.1% 69.1% 69.1% 69.1% 69.1% 69.1% 69.1%

Page 6: penjadwalan proyek

Kontrol

Page 7: penjadwalan proyek

NO NAMA KEGIATAN BIAYA BOBOT KONTROL WAKTU PENYELESAIAN PROYEK (minggu)1 2

1 Pek. Persiapan Rp 5,000,000 1.8%1 1.8% 1.8%1 1.8% 1.8%

2 Pek. Pondasi Rp 30,000,000 10.9%2 10.9% 5.5% 5.5%3 10.9% 5.0% 3.6%

3 Pek. Pemasangan sloof Rp 10,000,000 3.6%1 3.6% 3.6%1 3.6%

4 Pek. Kolom Rp 20,000,000 7.3%2 7.3%2 7.3%

5 Pek. Pasangan dinding Rp 20,000,000 7.3%3 7.3%3 7.3%

6 Pek. Pemasangan kusen Rp 30,000,000 10.9%2 10.9%2 10.9%

7 Pek. Ring balk Rp 20,000,000 7.3%1 7.3%1 7.3%

8 Pek. Atap Rp 70,000,000 25.5%2 25.5%3 10.0%

9 Pek plafon Rp 15,000,000 5.5%2 5.5%2 0.0%

10 Pek. Plesteran dinding Rp 15,000,000 5.5%3 5.5%2 0.0%

11 Pek. Lantai Rp 30,000,000 10.9%2 10.9%2 0.0%

12 Pek. Finishing Rp 10,000,000 3.6%2 3.6%1 0.0%

Rp 275,000,000 100.0% 46Progres rencana 7.3% 9.1%

Progres kumulatif rencana 7.3% 16.4%Progres realisasi 6.8% 3.6%

Progres kumulatif realisasi 6.8% 10.4%

DURASI (minggu)

Page 8: penjadwalan proyek

WAKTU PENYELESAIAN PROYEK (minggu)3 4 5 6 7 8 9 10 11 12 13 14 15

2.3%

3.6%3.6% 3.6%

3.6% 3.6%2.4% 2.4% 2.4%3.0% 2.3% 2.0%

5.5% 5.5%6.0% 4.9%

7.3%7.3%

12.7% 12.7%10.0%

2.7% 2.7%

1.8% 1.8% 1.8%

5.5% 5.5%

1.8% 1.8%

3.6% 6.1% 7.9% 7.9% 7.3% 12.7% 12.7% 4.5% 4.5% 7.3% 5.5% 1.8% 1.8%20.0% 26.1% 33.9% 41.8% 49.1% 61.8% 74.5% 79.1% 83.6% 90.9% 96.4% 98.2% 100%

5.9% 6.6% 11.9% 6.9% 7.3% 10.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%16.3% 23.0% 34.9% 41.8% 49.1% 59.1% 59.1% 59.1% 59.1% 59.1% 59.1% 59.1% 59.1%

Page 9: penjadwalan proyek

Kontrol

Page 10: penjadwalan proyek

NO NAMA KEGIATAN BIAYA BOBOT KONTROL WAKTU PENYELESAIAN PROYEK (minggu)1 2

1 Pek. Persiapan Rp 5,000,000 1.8%1 1.8% 1.8%1 1.8% 1.8%

2 Pek. Pondasi Rp 30,000,000 10.9%2 10.9% 5.5% 5.5%3 10.9% 5.0% 3.6%

3 Pek. Pemasangan sloof Rp 10,000,000 3.6%1 3.6% 3.6%1 3.6%

4 Pek. Kolom Rp 20,000,000 7.3%2 7.3%2 7.3%

5 Pek. Pasangan dinding Rp 20,000,000 7.3%3 7.3%3 7.3%

6 Pek. Pemasangan kusen Rp 30,000,000 10.9%2 10.9%2 10.9%

7 Pek. Ring balk Rp 20,000,000 7.3%1 7.3%1 7.3%

8 Pek. Atap Rp 70,000,000 25.5%2 25.5%3 0.0%

9 Pek plafon Rp 15,000,000 5.5%2 5.5%2 0.0%

10 Pek. Plesteran dinding Rp 15,000,000 5.5%3 5.5%2 0.0%

11 Pek. Lantai Rp 30,000,000 10.9%2 10.9%2 0.0%

12 Pek. Finishing Rp 10,000,000 3.6%2 3.6%1 0.0%

Rp 275,000,000 100.0% 46Progres rencana 7.3% 9.1%

Progres kumulatif rencana 7.3% 16.4%Progres realisasi 6.8% 3.6%

Progres kumulatif realisasi 6.8% 10.4%

DURASI (minggu)

Page 11: penjadwalan proyek

WAKTU PENYELESAIAN PROYEK (minggu)3 4 5 6 7 8 9 10 11 12 13 14 15

2.3%

3.6%3.6% 3.6%

3.6% 3.6%2.4% 2.4% 2.4%3.0% 2.3% 2.0%

5.5% 5.5%6.0% 4.9%

7.3%7.3%

12.7% 12.7%

2.7% 2.7%

1.8% 1.8% 1.8%

5.5% 5.5%

1.8% 1.8%

3.6% 6.1% 7.9% 7.9% 7.3% 12.7% 12.7% 4.5% 4.5% 7.3% 5.5% 1.8% 1.8%20.0% 26.1% 33.9% 41.8% 49.1% 61.8% 74.5% 79.1% 83.6% 90.9% 96.4% 98.2% 100%

5.9% 6.6% 11.9% 6.9% 7.3% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%16.3% 23.0% 34.9% 41.8% 49.1% 49.1% 49.1% 49.1% 49.1% 49.1% 49.1% 49.1% 49.1%

Page 12: penjadwalan proyek

Kontrol

Page 13: penjadwalan proyek

NO NAMA KEGIATAN BIAYA BOBOT KONTROL WAKTU PENYELESAIAN PROYEK (minggu)1 2

1 Pek. Persiapan Rp 5,000,000 1.8%1 1.8% 1.8%1 1.8% 1.8%

2 Pek. Pondasi Rp 30,000,000 10.9%2 10.9% 5.5% 5.5%3 10.9% 5.0% 3.6%

3 Pek. Pemasangan sloof Rp 10,000,000 3.6%1 3.6% 3.6%1 3.6%

4 Pek. Kolom Rp 20,000,000 7.3%2 7.3%2 7.3%

5 Pek. Pasangan dinding Rp 20,000,000 7.3%3 7.3%3 7.3%

6 Pek. Pemasangan kusen Rp 30,000,000 10.9%2 10.9%2 10.9%

7 Pek. Ring balk Rp 20,000,000 7.3%1 7.3%1 0.0%

8 Pek. Atap Rp 70,000,000 25.5%2 25.5%3 0.0%

9 Pek plafon Rp 15,000,000 5.5%2 5.5%2 0.0%

10 Pek. Plesteran dinding Rp 15,000,000 5.5%3 5.5%2 0.0%

11 Pek. Lantai Rp 30,000,000 10.9%2 10.9%2 0.0%

12 Pek. Finishing Rp 10,000,000 3.6%2 3.6%1 0.0%

Rp 275,000,000 100.0% 46Progres rencana 7.3% 9.1%

Progres kumulatif rencana 7.3% 16.4%Progres realisasi 6.8% 3.6%

Progres kumulatif realisasi 6.8% 10.4%

DURASI (minggu)

Page 14: penjadwalan proyek

WAKTU PENYELESAIAN PROYEK (minggu)3 4 5 6 7 8 9 10 11 12 13 14 15

2.3%

3.6%3.6% 3.6%

3.6% 3.6%2.4% 2.4% 2.4%3.0% 2.3% 2.0%

5.5% 5.5%6.0% 4.9%

7.3%

12.7% 12.7%

2.7% 2.7%

1.8% 1.8% 1.8%

5.5% 5.5%

1.8% 1.8%

3.6% 6.1% 7.9% 7.9% 7.3% 12.7% 12.7% 4.5% 4.5% 7.3% 5.5% 1.8% 1.8%20.0% 26.1% 33.9% 41.8% 49.1% 61.8% 74.5% 79.1% 83.6% 90.9% 96.4% 98.2% 100%

5.9% 6.6% 11.9% 6.9% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%16.3% 23.0% 34.9% 41.8% 41.8% 41.8% 41.8% 41.8% 41.8% 41.8% 41.8% 41.8% 41.8%

Page 15: penjadwalan proyek

Kontrol

Page 16: penjadwalan proyek

NO NAMA KEGIATAN BIAYA BOBOT KONTROL WAKTU PENYELESAIAN PROYEK (minggu)1 2

1 Pek. Persiapan Rp 5,000,000 1.8%1 1.8% 1.8%1 1.8% 1.8%

2 Pek. Pondasi Rp 30,000,000 10.9%2 10.9% 5.5% 5.5%3 10.9% 5.0% 3.6%

3 Pek. Pemasangan sloof Rp 10,000,000 3.6%1 3.6% 3.6%1 3.6%

4 Pek. Kolom Rp 20,000,000 7.3%2 7.3%2 7.3%

5 Pek. Pasangan dinding Rp 20,000,000 7.3%3 7.3%3 5.3%

6 Pek. Pemasangan kusen Rp 30,000,000 10.9%2 10.9%2 6.0%

7 Pek. Ring balk Rp 20,000,000 7.3%1 7.3%1 0.0%

8 Pek. Atap Rp 70,000,000 25.5%2 25.5%3 0.0%

9 Pek plafon Rp 15,000,000 5.5%2 5.5%2 0.0%

10 Pek. Plesteran dinding Rp 15,000,000 5.5%3 5.5%2 0.0%

11 Pek. Lantai Rp 30,000,000 10.9%2 10.9%2 0.0%

12 Pek. Finishing Rp 10,000,000 3.6%2 3.6%1 0.0%

Rp 275,000,000 100.0% 46Progres rencana 7.3% 9.1%

Progres kumulatif rencana 7.3% 16.4%Progres realisasi 6.8% 3.6%

Progres kumulatif realisasi 6.8% 10.4%

DURASI (minggu)

Page 17: penjadwalan proyek

WAKTU PENYELESAIAN PROYEK (minggu)3 4 5 6 7 8 9 10 11 12 13 14 15

2.3%

3.6%3.6% 3.6%

3.6% 3.6%2.4% 2.4% 2.4%3.0% 2.3%

5.5% 5.5%6.0%

7.3%

12.7% 12.7%

2.7% 2.7%

1.8% 1.8% 1.8%

5.5% 5.5%

1.8% 1.8%

3.6% 6.1% 7.9% 7.9% 7.3% 12.7% 12.7% 4.5% 4.5% 7.3% 5.5% 1.8% 1.8%20.0% 26.1% 33.9% 41.8% 49.1% 61.8% 74.5% 79.1% 83.6% 90.9% 96.4% 98.2% 100%

5.9% 6.6% 11.9% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%16.3% 23.0% 34.9% 34.9% 34.9% 34.9% 34.9% 34.9% 34.9% 34.9% 34.9% 34.9% 34.9%

Page 18: penjadwalan proyek

Kontrol

Page 19: penjadwalan proyek

NO NAMA KEGIATAN BIAYA BOBOT KONTROL WAKTU PENYELESAIAN PROYEK (minggu)1 2

1 Pek. Persiapan Rp 5,000,000 1.8%1 1.8% 1.8%1 1.8% 1.8%

2 Pek. Pondasi Rp 30,000,000 10.9%2 10.9% 5.5% 5.5%3 10.9% 5.0% 3.6%

3 Pek. Pemasangan sloof Rp 10,000,000 3.6%1 3.6% 3.6%1 3.6%

4 Pek. Kolom Rp 20,000,000 7.3%2 7.3%2 3.6%

5 Pek. Pasangan dinding Rp 20,000,000 7.3%3 7.3%3 3.0%

6 Pek. Pemasangan kusen Rp 30,000,000 10.9%2 10.9%2 0.0%

7 Pek. Ring balk Rp 20,000,000 7.3%1 7.3%1 0.0%

8 Pek. Atap Rp 70,000,000 25.5%2 25.5%3 0.0%

9 Pek plafon Rp 15,000,000 5.5%2 5.5%2 0.0%

10 Pek. Plesteran dinding Rp 15,000,000 5.5%3 5.5%2 0.0%

11 Pek. Lantai Rp 30,000,000 10.9%2 10.9%2 0.0%

12 Pek. Finishing Rp 10,000,000 3.6%2 3.6%1 0.0%

Rp 275,000,000 100.0% 46Progres rencana 7.3% 9.1%

Progres kumulatif rencana 7.3% 16.4%Progres realisasi 6.8% 3.6%

Progres kumulatif realisasi 6.8% 10.4%

DURASI (minggu)

Page 20: penjadwalan proyek

WAKTU PENYELESAIAN PROYEK (minggu)3 4 5 6 7 8 9 10 11 12 13 14 15

2.3%

3.6%3.6% 3.6%

3.6%2.4% 2.4% 2.4%3.0%

5.5% 5.5%

7.3%

12.7% 12.7%

2.7% 2.7%

1.8% 1.8% 1.8%

5.5% 5.5%

1.8% 1.8%

3.6% 6.1% 7.9% 7.9% 7.3% 12.7% 12.7% 4.5% 4.5% 7.3% 5.5% 1.8% 1.8%20.0% 26.1% 33.9% 41.8% 49.1% 61.8% 74.5% 79.1% 83.6% 90.9% 96.4% 98.2% 100%

5.9% 6.6% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%16.3% 23.0% 23.0% 23.0% 23.0% 23.0% 23.0% 23.0% 23.0% 23.0% 23.0% 23.0% 23.0%

Page 21: penjadwalan proyek

Kontrol

Page 22: penjadwalan proyek

NO NAMA KEGIATAN BIAYA BOBOT KONTROL WAKTU PENYELESAIAN PROYEK (minggu)1 2

1 Pek. Persiapan Rp 5,000,000 1.8%1 1.8% 1.8%1 1.8% 1.8%

2 Pek. Pondasi Rp 30,000,000 10.9%2 10.9% 5.5% 5.5%3 10.9% 5.0% 3.6%

3 Pek. Pemasangan sloof Rp 10,000,000 3.6%1 3.6% 3.6%1 3.6%

4 Pek. Kolom Rp 20,000,000 7.3%2 7.3%2 0.0%

5 Pek. Pasangan dinding Rp 20,000,000 7.3%3 7.3%3 0.0%

6 Pek. Pemasangan kusen Rp 30,000,000 10.9%2 10.9%2 0.0%

7 Pek. Ring balk Rp 20,000,000 7.3%1 7.3%1 0.0%

8 Pek. Atap Rp 70,000,000 25.5%2 25.5%3 0.0%

9 Pek plafon Rp 15,000,000 5.5%2 5.5%2 0.0%

10 Pek. Plesteran dinding Rp 15,000,000 5.5%3 5.5%2 0.0%

11 Pek. Lantai Rp 30,000,000 10.9%2 10.9%2 0.0%

12 Pek. Finishing Rp 10,000,000 3.6%2 3.6%1 0.0%

Rp 275,000,000 100.0% 46Progres rencana 7.3% 9.1%

Progres kumulatif rencana 7.3% 16.4%Progres realisasi 6.8% 3.6%

Progres kumulatif realisasi 6.8% 10.4%

DURASI (minggu)

Page 23: penjadwalan proyek

WAKTU PENYELESAIAN PROYEK (minggu)3 4 5 6 7 8 9 10 11 12 13 14 15

2.3%

3.6%3.6% 3.6%

2.4% 2.4% 2.4%

5.5% 5.5%

7.3%

12.7% 12.7%

2.7% 2.7%

1.8% 1.8% 1.8%

5.5% 5.5%

1.8% 1.8%

3.6% 6.1% 7.9% 7.9% 7.3% 12.7% 12.7% 4.5% 4.5% 7.3% 5.5% 1.8% 1.8%20.0% 26.1% 33.9% 41.8% 49.1% 61.8% 74.5% 79.1% 83.6% 90.9% 96.4% 98.2% 100%

5.9% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%16.3% 16.3% 16.3% 16.3% 16.3% 16.3% 16.3% 16.3% 16.3% 16.3% 16.3% 16.3% 16.3%

Page 24: penjadwalan proyek

Kontrol

Page 25: penjadwalan proyek

NO NAMA KEGIATAN BIAYA BOBOT KONTROL WAKTU PENYELESAIAN PROYEK (minggu)1 2

1 Pek. Persiapan Rp 5,000,000 1.8%1 1.8% 1.8%1 1.8% 1.8%

2 Pek. Pondasi Rp 30,000,000 10.9%2 10.9% 5.5% 5.5%3 8.6% 5.0% 3.6%

3 Pek. Pemasangan sloof Rp 10,000,000 3.6%1 3.6% 3.6%1 0.0%

4 Pek. Kolom Rp 20,000,000 7.3%2 7.3%2 0.0%

5 Pek. Pasangan dinding Rp 20,000,000 7.3%3 7.3%3 0.0%

6 Pek. Pemasangan kusen Rp 30,000,000 10.9%2 10.9%2 0.0%

7 Pek. Ring balk Rp 20,000,000 7.3%1 7.3%1 0.0%

8 Pek. Atap Rp 70,000,000 25.5%2 25.5%3 0.0%

9 Pek plafon Rp 15,000,000 5.5%2 5.5%2 0.0%

10 Pek. Plesteran dinding Rp 15,000,000 5.5%3 5.5%2 0.0%

11 Pek. Lantai Rp 30,000,000 10.9%2 10.9%2 0.0%

12 Pek. Finishing Rp 10,000,000 3.6%2 3.6%1 0.0%

Rp 275,000,000 100.0% 46Progres rencana 7.3% 9.1%

Progres kumulatif rencana 7.3% 16.4%Progres realisasi 6.8% 3.6%

Progres kumulatif realisasi 6.8% 10.4%

DURASI (minggu)

Page 26: penjadwalan proyek

WAKTU PENYELESAIAN PROYEK (minggu)3 4 5 6 7 8 9 10 11 12 13 14 15

3.6% 3.6%

2.4% 2.4% 2.4%

5.5% 5.5%

7.3%

12.7% 12.7%

2.7% 2.7%

1.8% 1.8% 1.8%

5.5% 5.5%

1.8% 1.8%

3.6% 6.1% 7.9% 7.9% 7.3% 12.7% 12.7% 4.5% 4.5% 7.3% 5.5% 1.8% 1.8%20.0% 26.1% 33.9% 41.8% 49.1% 61.8% 74.5% 79.1% 83.6% 90.9% 96.4% 98.2% 100%

0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%10.4% 10.4% 10.4% 10.4% 10.4% 10.4% 10.4% 10.4% 10.4% 10.4% 10.4% 10.4% 10.4%

Page 27: penjadwalan proyek

Kontrol

Page 28: penjadwalan proyek

NO NAMA KEGIATAN BIAYA BOBOT KONTROL WAKTU PENYELESAIAN PROYEK (minggu)1 2

1 Pek. Persiapan Rp 5,000,000 1.8%1 1.8% 1.8%1 1.8% 1.8%

2 Pek. Pondasi Rp 30,000,000 10.9%2 10.9% 5.5% 5.5%3 5.0% 5.0%

3 Pek. Pemasangan sloof Rp 10,000,000 3.6%1 3.6% 3.6%1 0.0%

4 Pek. Kolom Rp 20,000,000 7.3%2 7.3%2 0.0%

5 Pek. Pasangan dinding Rp 20,000,000 7.3%3 7.3%3 0.0%

6 Pek. Pemasangan kusen Rp 30,000,000 10.9%2 10.9%2 0.0%

7 Pek. Ring balk Rp 20,000,000 7.3%1 7.3%1 0.0%

8 Pek. Atap Rp 70,000,000 25.5%2 25.5%3 0.0%

9 Pek plafon Rp 15,000,000 5.5%2 5.5%2 0.0%

10 Pek. Plesteran dinding Rp 15,000,000 5.5%3 5.5%2 0.0%

11 Pek. Lantai Rp 30,000,000 10.9%2 10.9%2 0.0%

12 Pek. Finishing Rp 10,000,000 3.6%2 3.6%1 0.0%

Rp 275,000,000 100.0% 46Progres rencana 7.3% 9.1%

Progres kumulatif rencana 7.3% 16.4%Progres realisasi 6.8% 0.0%

Progres kumulatif realisasi 6.8% 6.8%

DURASI (minggu)

Page 29: penjadwalan proyek

WAKTU PENYELESAIAN PROYEK (minggu)3 4 5 6 7 8 9 10 11 12 13 14 15

3.6% 3.6%

2.4% 2.4% 2.4%

5.5% 5.5%

7.3%

12.7% 12.7%

2.7% 2.7%

1.8% 1.8% 1.8%

5.5% 5.5%

1.8% 1.8%

3.6% 6.1% 7.9% 7.9% 7.3% 12.7% 12.7% 4.5% 4.5% 7.3% 5.5% 1.8% 1.8%20.0% 26.1% 33.9% 41.8% 49.1% 61.8% 74.5% 79.1% 83.6% 90.9% 96.4% 98.2% 100%

0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%6.8% 6.8% 6.8% 6.8% 6.8% 6.8% 6.8% 6.8% 6.8% 6.8% 6.8% 6.8% 6.8%

Page 30: penjadwalan proyek

Kontrol

Page 31: penjadwalan proyek

NO NAMA KEGIATAN BIAYA BOBOT KONTROL WAKTU PENYELESAIAN PROYEK (minggu)1 2

1 Pek. Persiapan Rp 5,000,000 1.8%1 1.8% 1.8%1 1.8% 1.8%

2 Pek. Pondasi Rp 30,000,000 10.9%2 10.9% 5.5% 5.5%3 10.9% 5.0% 3.6%

3 Pek. Pemasangan sloof Rp 10,000,000 3.6%1 3.6% 3.6%1 3.6%

4 Pek. Kolom Rp 20,000,000 7.3%2 7.3%2 7.3%

5 Pek. Pasangan dinding Rp 20,000,000 7.3%3 7.3%3 7.3%

6 Pek. Pemasangan kusen Rp 30,000,000 10.9%2 10.9%2 10.9%

7 Pek. Ring balk Rp 20,000,000 7.3%1 7.3%1 7.3%

8 Pek. Atap Rp 70,000,000 25.5%2 25.5%3 25.5%

9 Pek plafon Rp 15,000,000 5.5%2 5.5%2 5.5%

10 Pek. Plesteran dinding Rp 15,000,000 5.5%3 5.5%2 5.5%

11 Pek. Lantai Rp 30,000,000 10.9%2 10.9%2 10.9%

12 Pek. Finishing Rp 10,000,000 3.6%2 3.6%1 3.6%

Rp 275,000,000 100.0% 46Progres rencana 7.3% 9.1%

Progres kumulatif rencana 0 7.3% 16.4%Progres realisasi 6.8% 3.6%

Progres kumulatif realisasi 0 6.8% 10.4%Deviasi tiap minggu 0.5% 5.5%

Deviasi kumulatif 0.5% 6.0%

DURASI (minggu)

Page 32: penjadwalan proyek

WAKTU PENYELESAIAN PROYEK (minggu)3 4 5 6 7 8 9 10 11 12 13 14 15

2.3%

3.6%3.6% 3.6%

3.6% 3.6%2.4% 2.4% 2.4%3.0% 2.3% 2.0%

5.5% 5.5%6.0% 4.9%

7.3%7.3%

12.7% 12.7%10.0% 10.0% 5.5%

2.7% 2.7%3.0% 2.5%1.8% 1.8% 1.8%2.0% 2.0% 1.5%

5.5% 5.5%7.0% 3.9%

1.8% 1.8%3.6%

3.6% 6.1% 7.9% 7.9% 7.3% 12.7% 12.7% 4.5% 4.5% 7.3% 5.5% 1.8% 1.8%20.0% 26.1% 33.9% 41.8% 49.1% 61.8% 74.5% 79.1% 83.6% 90.9% 96.4% 98.2% 100%

5.9% 6.6% 11.9% 6.9% 7.3% 10.0% 10.0% 10.5% 4.5% 8.5% 3.9% 0.0% 3.6%16.3% 23.0% 34.9% 41.8% 49.1% 59.1% 69.1% 79.6% 84.1% 92.6% 96.5% 96.5% 100%-2.3% -0.6% -4.1% 1.0% 0.0% 2.7% 2.7% -6.0% 0.0% -1.2% 1.6% 1.8% -1.8%3.7% 3.1% -1.0% 0.0% 0.0% 2.7% 5.4% -0.5% -0.5% -1.7% -0.1% 1.7% -0.1%

Page 33: penjadwalan proyek

100%

50%

0%