Page 1: PDRI Webinar Slides

WEBINAR

Achieve Capital Project Success

with Effective Front End Planning

June, 2015

Page 2: PDRI Webinar Slides

Today’s Presenter

2

Sara DeanFounder & Principal Consultant

Page 3: PDRI Webinar Slides

3

We implement front end

planning solutions that

dramatically improve

performance in capital

projects.

Page 4: PDRI Webinar Slides

Webinar Objectives

• Relationship between front end planning and project

performance

• Introduction to the Project Definition Rating Index

(PDRI)

• How can you take advantage of PDRI in your

organisation?

4

How does improved scope definition

deliver increased project performance?

Page 5: PDRI Webinar Slides

5

What is the leading cause of

capital project cost and

schedule overruns?

Poor scope definition

Page 6: PDRI Webinar Slides

Front End Planning

Achieving sufficient scope definition to address risk and make a decision on committing resources to maximise the potential for project success.

6

Page 7: PDRI Webinar Slides

Simply, Front End Planning Is

7

Front end

planning

Right project

Right product

Right way

Scope Definition:

Documenting the scope of work into an organised plan

Page 8: PDRI Webinar Slides

Reasons for Poor Scope Definition

1. Pressure to get product to market faster

2. Restricting key resource involvement

3. Lack of in-house design/planning

capability

4. Overly optimistic leadership

5. Financial pressure to minimise planning

costs

8

Page 9: PDRI Webinar Slides

The Question

9

If we had done a better job of scope definition, would we have improved

the performance of the project?

Page 10: PDRI Webinar Slides

Cost-Influence Diagram

10

Page 11: PDRI Webinar Slides

Critical Success Factors

Defined front end planning process

Scope definition tools

Existing conditions definition

Contracting strategy

Alignment

11

Page 12: PDRI Webinar Slides

12

How do we put this into practice?

Page 13: PDRI Webinar Slides

13

Project Definition Rating Index

A methodology to measure the

level of scope definition

– Comprehensive review

– Identify gaps

– Take appropriate action

– Reduce risk in front end planning

Page 14: PDRI Webinar Slides

Origin of PDRI

• Consortium of 140+ member companies

– Owners, engineering/contractors, suppliers

– Public & private sector

• Renowned for developing capital project

best practices

• One of the most successful is the

Project Definition Rating Index (PDRI)

14

Page 15: PDRI Webinar Slides

PDRI in Action

15

Page 16: PDRI Webinar Slides

Why is PDRI Critical?

• Improves capital project performance

– Benchmarked on over $96B in projects

• Increases stakeholder alignment

• Provides transparency on risk

16

Cost savings of 6 – 25%

Schedule reductions of 6 – 17%

Page 17: PDRI Webinar Slides

Application of PDRI

1 2 3

Early

Review

2i

Final

Review

Page 18: PDRI Webinar Slides

Project Templates

18

Infrastructure

Projects

Building

Projects

Industrial

Projects

• Greenfield & brownfield projects

• Small (less than $10M), large & mega projects

Page 19: PDRI Webinar Slides

Structure of PDRI - Industrial

Basis of Project

Decision50%Basis of Design

42%

Execution

Approach8%

19

Manufacturing Objectives

Business Objectives

Basic Data R&D

Project Scope

Value Engineering

Site Information

Process/Mechanical

Equipment Scope

Civil, Structural & Architectural

Infrastructure

Instrument & Electrical

Procurement Strategy

Deliverables

Project Controls

Project Execution Plan

Page 20: PDRI Webinar Slides

Recommended Participants

• PDRI Facilitator

• Project sponsor

• Project manager

• Engineering design reps

• Key discipline leads

• Maintenance & Operations reps

• Procurement

• Project controls (cost, schedule and risk)

• Regulatory

• Environmental

• Construction manager

20

Page 21: PDRI Webinar Slides

Target Scores

PDRI 1 PDRI 2 PDRI 2i PDRI 3

Feasibility Concept Detailed Scope

(intermediate)

Detailed Scope

550 – 800 450 – 600 300 – 450 150 - 250

21

Page 22: PDRI Webinar Slides

Evolution of PDRI

22

PDRI Spreadsheet

Paper Checklist

Carve for PDRI

Page 23: PDRI Webinar Slides

23

for Projects

Maximise the value of PDRI

for all project stakeholders

for Portfolios

Effective risk management

in front end planning

Implement a repeatable PDRI process

for PDRI

Page 24: PDRI Webinar Slides

Fit-for-purpose Project Templates

Configuration makes project templates

fit-for-purpose to your organisation

24

Business

units

Polices &

procedures

Gate

deliverables

Regulatory

requirements

Industry

terminology

Language

translation

Page 25: PDRI Webinar Slides

25

Project Template Configuration

Page 26: PDRI Webinar Slides

Impact on Front End Planning

• PDRI is a proven methodology to improve scope

definition

– Improves project performance (cost, schedule, change

orders)

– Increases stakeholder alignment

– Transparency on risk

• Incorporates ALL of the critical success factors including

– Assessment of existing conditions

– Contracting strategy

• Supports continuous improvement in front end planning

26for PDRI

Page 27: PDRI Webinar Slides

27

Where do we start?

Page 28: PDRI Webinar Slides

28

120-day roadmap to

success with PDRI

Evaluate PDRI

Try it on a cross-section of projects

Initiate using a structured proof of concept

Achieve a visible success story

Page 29: PDRI Webinar Slides

29

Preparing

Initiating

Growing

Establishing

Benchmark

NeedsAnalysis

Evaluate change areas

Introduction of practice in a

proof of concept

Expansion of practice beyond

proof of concept

Marketing new process to

broad organisation

Initiating use of PDRI

Success Story120-day roadmap

Page 30: PDRI Webinar Slides

Case Study – Major North American City

CONFIDENTIAL 30

Objective

• Demonstrate applicability of PDRI to

front end planning for the City’s major

capital projects

Scope

• Conduct multiple PDRI sessions

• Building & industrial

• Early review & final review

Success Criteria

• Deliver immediate value to each project

• Identify elements posing the greatest

risk to the overall capital program

Page 31: PDRI Webinar Slides

Benefits of the 120-day Program

31

Success StoryShowcase results and acquire

support for expansion of the practice

EducationPurpose-built training for all

impacted stakeholder groups

Immediate Project ResultsBetter scope definitionCost & schedule certainty

Team Alignment

Implementation RoadmapProven strategy to implement

change in process

A repeatable process based on best practices

Page 32: PDRI Webinar Slides

Summary

• The level of scope definition is the greatest driver of cost and

schedule certainty

• Project outcomes is most easily influenced in front end

planning

• Project Definition Rating Index (PDRI) methodology

• The most successful open industry standard to improve scope definition

• Start realising the benefits of improved scope definition today

• Engage the support of Valency - PDRI implementation specialists

32

How does improved scope definition

deliver increased project performance?

Page 33: PDRI Webinar Slides

33