Top Banner
US Army Corps of Engineers BUILDING STRONG ® EPA Lower Passaic River Community Advisory Group Tom Shea, PMP Project Manager 12 March 2015 Passaic River Flood Risk Management Projects
15

Passaic River Flood Risk Management Projectspassaic.sharepointspace.com/Public Documents/Passaic CAG...Submit Pre-Tentatively Selected Plan (TSP) Summary Report to NAD Sep 2016 Conduct

May 27, 2020

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Passaic River Flood Risk Management Projectspassaic.sharepointspace.com/Public Documents/Passaic CAG...Submit Pre-Tentatively Selected Plan (TSP) Summary Report to NAD Sep 2016 Conduct

US Army Corps of Engineers

BUILDING STRONG®

EPA Lower Passaic River

Community Advisory Group

Tom Shea, PMPProject Manager

12 March 2015

Passaic River Flood Risk Management Projects

Page 2: Passaic River Flood Risk Management Projectspassaic.sharepointspace.com/Public Documents/Passaic CAG...Submit Pre-Tentatively Selected Plan (TSP) Summary Report to NAD Sep 2016 Conduct

BUILDING STRONG®

Passaic River Main Stem Project

• Studies began in 1900

• USACE became involved in 1936, 1976 study authority

required a “comprehensive” solution

• Feasibility Study completed in 1987, recommended

the “Tunnel Plan”

• Congress authorized the project in WRDA 1990

• USACE initiated Pre-Construction Engineering and

Design (PED) in 1987 and stopped in 1995 when it

completed a draft General Design Memo

2

Page 3: Passaic River Flood Risk Management Projectspassaic.sharepointspace.com/Public Documents/Passaic CAG...Submit Pre-Tentatively Selected Plan (TSP) Summary Report to NAD Sep 2016 Conduct

BUILDING STRONG®

Passaic River Main Stem Project

• Effort was halted in 1995 at the request of the State

of New Jersey

• Project was further restricted by Section 327(i),

WRDA 2000, which forbids the obligation of funds for

the design or construction of the tunnel element

• The Main Stem portion of the project was never

constructed, other separable elements were (Minish,

Oakland, Molly Ann's Brook)

• The authorized plan includes tidal levees/floodwalls in

Newark, Kearny and Harrison

3

Page 4: Passaic River Flood Risk Management Projectspassaic.sharepointspace.com/Public Documents/Passaic CAG...Submit Pre-Tentatively Selected Plan (TSP) Summary Report to NAD Sep 2016 Conduct

BUILDING STRONG®

Passaic River Flood Risk Management Projects

Tidal Passaic

RiverPassaic Main

Stem

4

Page 5: Passaic River Flood Risk Management Projectspassaic.sharepointspace.com/Public Documents/Passaic CAG...Submit Pre-Tentatively Selected Plan (TSP) Summary Report to NAD Sep 2016 Conduct

BUILDING STRONG®

• Apr 2010 – Governor Christie created Passaic River

Basin Flood Advisory Commission through Executive

Order 23

• Jan 2011 – Commission recommended reevaluation

of the Passaic River Basin for long-term flood damage

reduction at a cost of $15 million

• Mar 2011 – Letter from Governor Christie to Chief of

Engineers that requested support of

• Preservation of Natural Flood Storage Areas

• Reevaluation of the Passaic River Main Stem Study

Restart of the Passaic Main Stem

5

Page 6: Passaic River Flood Risk Management Projectspassaic.sharepointspace.com/Public Documents/Passaic CAG...Submit Pre-Tentatively Selected Plan (TSP) Summary Report to NAD Sep 2016 Conduct

BUILDING STRONG®

1. Levees and Floodwalls� Alternative 14A from 1987

2. Levees, Floodwalls and Channel Modification� Alternative 16A from 1987

3. Tunnel� Duel Inlet – Newark Bay Outlet Tunnel Diversion (authorized plan)

4. Beatties Dam / Two Bridges Improvements � Plan requested by NJDEP in 2011

5. Nonstructural � 10 Year Flood, 1987 plan

6. No Action

Passaic Main Stem

Alternatives in Phase 1

6

Page 7: Passaic River Flood Risk Management Projectspassaic.sharepointspace.com/Public Documents/Passaic CAG...Submit Pre-Tentatively Selected Plan (TSP) Summary Report to NAD Sep 2016 Conduct

BUILDING STRONG®

Passaic Main Stem

Preliminary Alternative Analysis Report

7

• Submitted to NJDEP and HQUSACE in Sep 13.

� Reaffirmed that the Tunnel Diversion plan remains the

National Economic Development Plan and the non-structural

and levee/floodwall plans were marginally economically

justified.

• In Feb 2014, NJDEP requested that the District pursue the

following three alternatives:

1) Nonstructural alternative,

2) Alternative 14A (levee and floodwall), and

3) Tunnel Diversion Plan

• Public Information Sessions were held late March/early April

2014 to discuss the status of the study and describe the three

alternatives above

Page 8: Passaic River Flood Risk Management Projectspassaic.sharepointspace.com/Public Documents/Passaic CAG...Submit Pre-Tentatively Selected Plan (TSP) Summary Report to NAD Sep 2016 Conduct

BUILDING STRONG®

Passaic Main Stem Path Forward

Preliminary Benefit-to-Cost Ratios Feb 2016

Submit Pre-Tentatively Selected Plan (TSP) Summary Report to NAD Sep 2016

Conduct Pre-TSP Briefing to HQUSACE Sep 2016

Phase 1 Complete Nov 2016

8

Page 9: Passaic River Flood Risk Management Projectspassaic.sharepointspace.com/Public Documents/Passaic CAG...Submit Pre-Tentatively Selected Plan (TSP) Summary Report to NAD Sep 2016 Conduct

BUILDING STRONG®

Passaic River Flood Risk Management Projects

Tidal Passaic

RiverPassaic Main Stem

9

Page 10: Passaic River Flood Risk Management Projectspassaic.sharepointspace.com/Public Documents/Passaic CAG...Submit Pre-Tentatively Selected Plan (TSP) Summary Report to NAD Sep 2016 Conduct

BUILDING STRONG®

Passaic River Tidal Protection Area

• An original component of the overall Passaic River Main Stem

• Broken out as a separate study in USACE Second Interim Report

to Congress, in accordance with PL 113-2 (Sandy Recovery)

• GRR fully funded by Sandy Recovery, although cost-shared

(non-Fed is financed by Fed)

• 3 year and $3M evaluation phase to update costs and

alignment and complete consideration of impacts to the

environment.

• Estimated construction cost is $300M, to be funded by Sandy

Recovery to the extend that funds remain, then go to annual

appropriations

10

Page 11: Passaic River Flood Risk Management Projectspassaic.sharepointspace.com/Public Documents/Passaic CAG...Submit Pre-Tentatively Selected Plan (TSP) Summary Report to NAD Sep 2016 Conduct

BUILDING STRONG®

Passaic River Tidal Protection Area

• Damages caused by the tidal surge flooding

• Severe flooding in all three communities – Harrison, Kearny

and Newark

• Storm surge affected highly developed industrial, commercial,

and residential areas.

• Passaic Valley Sewerage Commission Plant – overflow, flooded,

months to reopen

• PATH, AMTRAK, & NJ Transit – Flooded; FEMA dewatering

mission

• Numerous electrical substations flooded

• Damage to property was sustained; one death reported

11

Page 12: Passaic River Flood Risk Management Projectspassaic.sharepointspace.com/Public Documents/Passaic CAG...Submit Pre-Tentatively Selected Plan (TSP) Summary Report to NAD Sep 2016 Conduct

BUILDING STRONG®12

Page 13: Passaic River Flood Risk Management Projectspassaic.sharepointspace.com/Public Documents/Passaic CAG...Submit Pre-Tentatively Selected Plan (TSP) Summary Report to NAD Sep 2016 Conduct

BUILDING STRONG®

Light Shade Blue is FEMA 100 yr flood zone

Red lines are Authorized Project levees and

floodwalls

Passaic River Tidal Protection Area

Minish Waterfront Project

13

Page 14: Passaic River Flood Risk Management Projectspassaic.sharepointspace.com/Public Documents/Passaic CAG...Submit Pre-Tentatively Selected Plan (TSP) Summary Report to NAD Sep 2016 Conduct

BUILDING STRONG®

Milestone Dates

Draft GRR 20-Apr-16

Chief’s Report 05-Jul-17

Report to Congress 26-Sep-17

Schedule for Passaic Tidal Protection Area

General Reevaluation Report

14

Page 15: Passaic River Flood Risk Management Projectspassaic.sharepointspace.com/Public Documents/Passaic CAG...Submit Pre-Tentatively Selected Plan (TSP) Summary Report to NAD Sep 2016 Conduct

BUILDING STRONG®

Contacts

• USACE Project Manager:

Tom Shea, PMP

(917) 790-8304

[email protected]

or

[email protected]

Preliminary Alternatives Analysis Report can be found at:

www.nan.usace.army.mil/passaic

15