Our Biogas Digester / The Septic Tank January, 2012 update
14
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Our biogas plant   jan 2012

Our Biogas Digester / The Septic Tank

January, 2012 update

Page 2: Our biogas plant   jan 2012

The Plan (Courtesy of David Fulford – Kingdom Biogas)

Page 3: Our biogas plant   jan 2012

João local stone mason and general machine wielder.

And Vitor, the local water and sanitation expert, lending his tractor to get rid of some earth and generally check

out our endeavours.

Page 4: Our biogas plant   jan 2012

João, with his digging toy...

We dug to about 2.5m

About one day’s digger time (and

earth moving)

Page 5: Our biogas plant   jan 2012

Kira inspecting the works

And asking why we weren’t making a

pool...

Gravel laid before we poured the

platform for the tank.

Page 6: Our biogas plant   jan 2012

Everything in the round;

The square bit is where sewage liquid is displaced to (and

forced upwards under gas pressure)

15cm wide bricks offering a bit of

insulation.

Nice work by Anton (Romania!)

Page 7: Our biogas plant   jan 2012

Father and son – discussing where we want the pipes to come in.

Some concrete to be added around the edge of tank to avoid collapse when we

back-fill with earth

Page 8: Our biogas plant   jan 2012

Anton preparing holes for the pipe inlets – before the concrete is poured

around the tank

Page 9: Our biogas plant   jan 2012

Next we build a wooden platform on which to build the

earth dome

A rope has been attached to the legs of this wooden

structure so when the concrete above has set we can pull out the legs, let the earth collapse and remove

all the earth from the hole in the square bit – hopefully leaving the dome above

intact!

Page 10: Our biogas plant   jan 2012

Anton and Petrus do a lovely job making this perfectly symetrical dome from earth, then cover with 8mm iron to

reinforce the concrete.

Page 11: Our biogas plant   jan 2012

Anton and Petrus (also father and son) adding the final coat of concrete to the

dome. Note pipe for gas already installed (50mm PVC, to connect to a 32mm gas

pipe later).

Page 12: Our biogas plant   jan 2012

And a close up..

Page 13: Our biogas plant   jan 2012

75mm pipe for kitchen or organic waste to coming from near the future kitchen. Gas

return to come back in same channel.

Page 14: Our biogas plant   jan 2012

The latest: Petrus and Anton installing the pipes linking the toilets to the digester.