Deeper Water Offshore - 7 th March 2012 Confidentiality class: None (C1) Optimising Projects Optimising Assets, Project Planning & Contracting To Reduce Costs Overall Matthew Green Vattenfall Wind Power UK
20

Optimising Projects Optimising Assets, Project … · Optimising Projects Optimising Assets, Project Planning & Contracting To Reduce Costs Overall Matthew Green – Vattenfall Wind

May 23, 2018

Download

Documents

phungnhu
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Optimising Projects Optimising Assets, Project … · Optimising Projects Optimising Assets, Project Planning & Contracting To Reduce Costs Overall Matthew Green – Vattenfall Wind

Deeper Water Offshore - 7th March 2012

Confidentiality class: None (C1)

Optimising Projects

Optimising Assets, Project Planning & Contracting To

Reduce Costs Overall

Matthew Green – Vattenfall Wind Power UK

Page 2: Optimising Projects Optimising Assets, Project … · Optimising Projects Optimising Assets, Project Planning & Contracting To Reduce Costs Overall Matthew Green – Vattenfall Wind

OFFSHORE WIND - WHERE ARE WE?

Page 3: Optimising Projects Optimising Assets, Project … · Optimising Projects Optimising Assets, Project Planning & Contracting To Reduce Costs Overall Matthew Green – Vattenfall Wind

OFFSHORE WIND - WHERE ARE WE?

Should we think we are a new industry?

• 10 years+ of experience Offshore

• Approaching 4GW installed offshore across Europe (1)

• <1250 Turbines Offshore (2)

• Just passed 6GW of total wind capacity in UK (2)

NO! But we must not stop learning because:

• £/MW installed still rising >£4m and needs to reduce.

• Too many project construction delays

• Too many quality failures in the early life of assets.

OPTIMISATION!

(1) EWEA, (2) RenewablesUK

Page 4: Optimising Projects Optimising Assets, Project … · Optimising Projects Optimising Assets, Project Planning & Contracting To Reduce Costs Overall Matthew Green – Vattenfall Wind

OPTIMISATION

What do we mean by Optimisation?

Reducing Overall Costs

Delivering to Project Schedules

Delivery Quality Assets

INDUSTRIALISATION

STANDARDISATION

EPC CONTRACTING - PARTNERSHIPS

Page 5: Optimising Projects Optimising Assets, Project … · Optimising Projects Optimising Assets, Project Planning & Contracting To Reduce Costs Overall Matthew Green – Vattenfall Wind

The challenge for the industry

Mio€ / MW

Year

Know how transfer

Control and master the business Control and master the price

** based on published figures

Kentish Flats

Lillgrund

Alpha Ventus**

Global Tech**

Butendiek**

Increasing prices due to higher

complexity of windparks (water

depth & distance from shore)

LEC reduction by

CAPEX and OPEX Optimisation

Challenge

Page 6: Optimising Projects Optimising Assets, Project … · Optimising Projects Optimising Assets, Project Planning & Contracting To Reduce Costs Overall Matthew Green – Vattenfall Wind

INDUSTRIALISATION

• Project broken down into well understood

repetitive tasks.

• R&D/Trials/Testing/Pre-commissioning are to

be completed prior to shipping – we must get

beyond prototypes!

• Training/Familiarisation do it all offline &

onshore - Offshore is not the place for

learning curves!

• Suppliers must prove their products/ services

in advance – the challenges are greater but

the opportunities are increasing..

Page 7: Optimising Projects Optimising Assets, Project … · Optimising Projects Optimising Assets, Project Planning & Contracting To Reduce Costs Overall Matthew Green – Vattenfall Wind

INDUSTRIALISATION – Portfolio Planning

• Developers set up for Multiple project delivery.

• Shared Resources

• Better sharing of experience.

• Continuity

• Cross Project Supply Chain Management.

• Standardised Products - Single Product / Multiple Suppliers

• Economy of Scale

• Cross Project Logistics Management.

• Establish dedicated Logistics Bases

• Longer term Vessel Charters

Page 8: Optimising Projects Optimising Assets, Project … · Optimising Projects Optimising Assets, Project Planning & Contracting To Reduce Costs Overall Matthew Green – Vattenfall Wind

OPTIMISATION – Installation Vessels

Know Your Vessels.

• Weather sensitivity for all operations

• Crew Competence & Experience

• Deck Capacity/Flexibility for all operations

• New Builds

• Consider all possible optimisations before

mobilisation.

• Cable vessels?

Page 9: Optimising Projects Optimising Assets, Project … · Optimising Projects Optimising Assets, Project Planning & Contracting To Reduce Costs Overall Matthew Green – Vattenfall Wind

INDUSTRIALISATION - Ports

• What are the Key issues

- Distance to Site/Suppliers

- Facilities/Resources

- Flexibility of Storage

• Access is critical – consider types of

vessel, tide limitations and the effects

of adverse weather

Ports – Choose Carefully!

Page 10: Optimising Projects Optimising Assets, Project … · Optimising Projects Optimising Assets, Project Planning & Contracting To Reduce Costs Overall Matthew Green – Vattenfall Wind

INDUSTRIALISATION – Weather

You can’t control weather!

• Understand the weather and its affects at every location and stage of the

project. Circa 5-10% Project CAPEX is attributable to weather delays!

• Further Offshore = increased weather and year round working.

• You can only base schedules on statistical weather but think of the

production line even it worst scenario:

- Minimise weather sensitivity / Maximise operability

- Investigate and develop less weather sensitive operations/vessels.

Page 11: Optimising Projects Optimising Assets, Project … · Optimising Projects Optimising Assets, Project Planning & Contracting To Reduce Costs Overall Matthew Green – Vattenfall Wind

INDUSTRIALISATION - Supply

• As distance offshore and project sizes increase –

reliance on supplies increases dramatically.

• Any breakdown in the supply lines (Manufacture,

shipment, transhipment, pre-assembly, site supply,

offshore transfer, quality issues, serial defects,

interfacing, insufficient handling equipment,

certification of handling equipment…) any one of these

WILL cause offshore standby time, project delays = £€

• Standardisation can resolve some issues…

Page 12: Optimising Projects Optimising Assets, Project … · Optimising Projects Optimising Assets, Project Planning & Contracting To Reduce Costs Overall Matthew Green – Vattenfall Wind

STANDARDISATION

Time to Establish Basic Standards

• Categorisation and minimum standards for the various aspects of offshore

wind farm construction – comparing apples…

- Installation Methods, Major Components, Subcomponents, SMSs/ERPs/HSE Standards

• Suppliers, developers, installation contractors, consenting bodies &

certification agencies with common references.

• Build on past experience rather than reinvent.

Page 13: Optimising Projects Optimising Assets, Project … · Optimising Projects Optimising Assets, Project Planning & Contracting To Reduce Costs Overall Matthew Green – Vattenfall Wind

PROJECT 3

PROJECT 2

STANDARDISATION

PROTOTYPE

PROJECT 1

Lessons Learned /

Employer Rqmts

+ Product

Improvements

Revised Employer

Requirements

+Product

Improvements

Reduce:

RISK

COST

DELAYS

Testing /

Certification / Type

Approval

Page 14: Optimising Projects Optimising Assets, Project … · Optimising Projects Optimising Assets, Project Planning & Contracting To Reduce Costs Overall Matthew Green – Vattenfall Wind

OPTIMISATION – EPC Contracting

EPC Contracting simplifies and optimises projects execution.

But there are traps:

• Contractor with true expertise for the full EPC scope will be more limited.

• Less commercial interfaces does not mean less technical interfaces!

• How is it possible to ensure performance is maintained to completion?

Page 15: Optimising Projects Optimising Assets, Project … · Optimising Projects Optimising Assets, Project Planning & Contracting To Reduce Costs Overall Matthew Green – Vattenfall Wind

OPTIMISATION – EPC Contracting

Making EPC Work:

Contractor/Supplier Expertise:

• Use only the supply chain who meet all the requirements.

• Tailor Contract Strategy to Suit the supply chain.

• Work With Contractors to build a better supply chain.

Page 16: Optimising Projects Optimising Assets, Project … · Optimising Projects Optimising Assets, Project Planning & Contracting To Reduce Costs Overall Matthew Green – Vattenfall Wind

OPTIMISATION – EPC Contracting

Making EPC Work:

Interfaces

• The developer will always have the

most to lose or gain – so never make

assumptions about interfaces.

• But a successful project benefits all

so…

Look for Contractor/Suppliers who are

looking at ways of expanding not limiting

their involvement in interfaces.

Page 17: Optimising Projects Optimising Assets, Project … · Optimising Projects Optimising Assets, Project Planning & Contracting To Reduce Costs Overall Matthew Green – Vattenfall Wind

OPTIMISATION – Partnerships

Mutually Beneficial Agreements

Adversaries

Partnership

Unproven Targets + Penalties

Realistic Targets + Incentivisation

Performance Optimisation

Long Term Objectives

Closed Approach

Open Approach / Shared Knowledge

One Off Thinking

Sustainability, Security

Page 18: Optimising Projects Optimising Assets, Project … · Optimising Projects Optimising Assets, Project Planning & Contracting To Reduce Costs Overall Matthew Green – Vattenfall Wind

OPTIMISATION – Partnerships

Logical Conclusion…

Partnerships:

• Shared Development – Budget

Shared/Risk Shared?

• Full EPC – Developer/EPC

Relationship.

• Package EPC – Developer/Principle

Contract/EPC Packages.

Page 19: Optimising Projects Optimising Assets, Project … · Optimising Projects Optimising Assets, Project Planning & Contracting To Reduce Costs Overall Matthew Green – Vattenfall Wind

SUMMARY

An Outlook of Challenges and Opportunities:

Ours is a maturing Industry ready for the next level.

The future requires massive expansion and greater challenges

offshore – But success in the future requires lower cost and lower

risk.

Capital & Operational Cost and LEC reduction is only possible by

optimisation from Industrialisation, Standardisation and Effective

Partnerships.

Experienced Supply Chain and Developers pulling in a common

direction.

Page 20: Optimising Projects Optimising Assets, Project … · Optimising Projects Optimising Assets, Project Planning & Contracting To Reduce Costs Overall Matthew Green – Vattenfall Wind