Top Banner
NRC LICENSE APPLICATION PROCESS STEPHEN J. COHEN HYDROGEOLOGIST/PROJECT MANAGER URANIUM RECOVERY BRANCH
25

NRC LICENSE APPLICATION PROCESS STEPHEN J. COHEN HYDROGEOLOGIST/PROJECT MANAGER URANIUM RECOVERY BRANCH.

Dec 17, 2015

Download

Documents

Gwen Snow
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: NRC LICENSE APPLICATION PROCESS STEPHEN J. COHEN HYDROGEOLOGIST/PROJECT MANAGER URANIUM RECOVERY BRANCH.

NRC LICENSE APPLICATION PROCESS

STEPHEN J. COHENHYDROGEOLOGIST/PROJECT MANAGER

URANIUM RECOVERY BRANCH

Page 2: NRC LICENSE APPLICATION PROCESS STEPHEN J. COHEN HYDROGEOLOGIST/PROJECT MANAGER URANIUM RECOVERY BRANCH.

Submit Applicationto NRC

ConsultSF & C

Pre-LicensingMeeting w/NRC

NRC Acceptance Review

NRC Detailed Technical Review

Issue RAIs to Applicant

Applicant Response/Provides Add’l Info.

NRC Final Review

NRC Prepares SER

NRC Issues License

Adequate InadequateApplicantResubmit

If open issuesremaining

All Open Issues Resolved

NRC LICENSING PROCESS

EIS From NEPA Review

Opportunityfor

Hearing

Page 3: NRC LICENSE APPLICATION PROCESS STEPHEN J. COHEN HYDROGEOLOGIST/PROJECT MANAGER URANIUM RECOVERY BRANCH.

• OBJECTIVE – NOTIFY NRC OF PROJECT AND GET ON NRC BUDGET

• PRE-LICENSING MEETINGS

PRE-LICENSING ACTIVITIES

• SCHEDULES AND PROGRESS UPDATES

Page 4: NRC LICENSE APPLICATION PROCESS STEPHEN J. COHEN HYDROGEOLOGIST/PROJECT MANAGER URANIUM RECOVERY BRANCH.

• SITE INVESTIGATION - EXAMPLES• GEOLOGY• GEOTECHNICAL• HYDROGEOLOGY• HYDROLOGY

• ENVIRONMENTAL INVESTIGATION - EXAMPLES• ARCHAEOLOGY• BACKGROUND• CULTURAL RESOURCES• HEALTH PHYSICS• CROSS-OVER AREAS

PRE-LICENSING ACTIVITIES (cont’d.)

Page 5: NRC LICENSE APPLICATION PROCESS STEPHEN J. COHEN HYDROGEOLOGIST/PROJECT MANAGER URANIUM RECOVERY BRANCH.

LICENSE APPLICATION SUBMITTAL

• NO AMOUNT OF PRE-LICENSING COORDINATION CAN SUBSTITUTE FOR A POORLY PREPARED APPLICATION.

• WHAT IS A GOOD APPLICATION? AN APPLICATION THAT PROVIDES THE NECESSARY

INFORMATION TO ALLOW NRC’S ASSESSMENT OF TECHNICAL, SAFETY AND ENVIRONMENTAL ASPECTS OF A PROJECT.

Page 6: NRC LICENSE APPLICATION PROCESS STEPHEN J. COHEN HYDROGEOLOGIST/PROJECT MANAGER URANIUM RECOVERY BRANCH.

• WHAT DOCUMENTATION IS REQUIRED FOR A LICENSE APPLICATION?

TRANSMITTAL LETTER

FORM 313 – 10 CFR 40.5 AND 40.31

TECHNICAL REPORT

ENVIRONMENTAL REPORT

LICENSE APPLICATION SUBMITTAL (cont’d.)

• NRC’S RESPONSE WHEN APPLICATION IS RECEIVED

FED. REG. NOTICE – OPPORTUNITY FOR HEARING

DOCKET NUMBERS

ALL DOCUMENTS ARE PUBLIC UNLESS WITHOLDING IS APPROVED UNDER 10 CFR 2.390

Page 7: NRC LICENSE APPLICATION PROCESS STEPHEN J. COHEN HYDROGEOLOGIST/PROJECT MANAGER URANIUM RECOVERY BRANCH.

• REVIEW PLANS AND GUIDANCE – BASIC LIST

NUREG-1569 – IN-SITU LEACH MINES

NUREG-1620 – CONVENTIONAL MILL REC PLANS

NUREG-1757 – DECOMMISSIONING

NUREG-1748 – ENVIRONMENTAL REVIEWS

10 CFR PART 40, APPENDIX A

REG. GUIDE 3.5, REV. 1

VARIOUS REG GUIDES

LICENSE APPLICATION SUBMITTAL (cont’d.)

Page 8: NRC LICENSE APPLICATION PROCESS STEPHEN J. COHEN HYDROGEOLOGIST/PROJECT MANAGER URANIUM RECOVERY BRANCH.

LICENSE APPLICATION SUBMITTAL (cont’d.)

• FORMAT AND CONTENT GUIDANCE

CONVENTIONAL MILL – REG GUIDE 3.5 & NUREG-1620

ISL FACILITIES – NUREG-1569

ENVIRONMENTAL REPORT – NUREG-1748

10 CFR PART 40, APPENDIX A

Page 9: NRC LICENSE APPLICATION PROCESS STEPHEN J. COHEN HYDROGEOLOGIST/PROJECT MANAGER URANIUM RECOVERY BRANCH.

• PROPOSED ACTIVITIES

• SITE CHARACTERISTICS

• MILL PROCESS AND EQUIPMENT

• WASTE MANAGEMENT SYSTEM

• OPERATIONS

• ACCIDENTS

• QUALITY ASSURANCE

CONVENTIONAL MILL APPLICATION CONTENT

Page 10: NRC LICENSE APPLICATION PROCESS STEPHEN J. COHEN HYDROGEOLOGIST/PROJECT MANAGER URANIUM RECOVERY BRANCH.

• 10 CFR PART 40, APPENDIX A, NUREG-1620

RECLAMATION PLAN

SURETY

IMPOUNDMENT DESIGN STANDARDS

ALSO 40 CFR 61.252 – IMPOUNDMENT LIMIT

CONVENTIONAL MILL APPLICATION CONTENT

Page 11: NRC LICENSE APPLICATION PROCESS STEPHEN J. COHEN HYDROGEOLOGIST/PROJECT MANAGER URANIUM RECOVERY BRANCH.

• PROPOSED ACTIVITIES

• SITE CHARACTERIZATION

• DESCRIPTION OF PROPOSED FACILITY

• EFFLUENT CONTROL SYSTEMS

• GROUND WATER RESTORATION, SURFACE

RECLAMATION, AND DECOMMISSIONING

• ACCIDENTS

• QUALITY ASSURANCE

• SURETY ESTIMATE

ISL APPLICATION CONTENT

Page 12: NRC LICENSE APPLICATION PROCESS STEPHEN J. COHEN HYDROGEOLOGIST/PROJECT MANAGER URANIUM RECOVERY BRANCH.

NRC ACCEPTANCE REVIEW

• 90-DAY INITIAL REVIEW

• BASIS OF REVIEW: NUREGS, REG GUIDES, OTHER GUIDANCE.

• ACTIONS FOR INCOMPLETE APPLICATIONS:

CAN BE RETURNED TO APPLICANT FOR RESUBMITTAL.

ACCEPTED WITH REQUEST FOR ADDITIONAL INFORMATION.

• IF APPLICATION IS COMPLETE, ACCEPTANCE LETTER ISSUED.

Page 13: NRC LICENSE APPLICATION PROCESS STEPHEN J. COHEN HYDROGEOLOGIST/PROJECT MANAGER URANIUM RECOVERY BRANCH.

NRC ACCEPTANCE REVIEW (cont’d.)

• ORDER OF REVIEW

APPLICATIONS WILL BE REVIEWED IN THE ORDER THEY ARE ACCEPTED.

SUBMITTING PARTIAL OR HASTILY PREPARED APPLICATIONS TO GET

INTO THE QUEUE IS NOT ACCEPTABLE.

Page 14: NRC LICENSE APPLICATION PROCESS STEPHEN J. COHEN HYDROGEOLOGIST/PROJECT MANAGER URANIUM RECOVERY BRANCH.

TECHNICAL REVIEW OF APPLICATION

• BASIS OF REVIEW – REGULATIONS, NUREGS, REG. GUIDES

• REQUEST FOR ADDITIONAL INFORMATION – GOAL IS ONE REQUEST

ENVIRONMENTAL REVIEW – CONCURRENT WITH TECHNICAL REVIEW

Page 15: NRC LICENSE APPLICATION PROCESS STEPHEN J. COHEN HYDROGEOLOGIST/PROJECT MANAGER URANIUM RECOVERY BRANCH.

TECHNICAL REVIEW OF APPLICATION (cont’d.)

• SOME ADDITIONAL THOUGHTS ON THE FOLLOWING AREAS:

GEOLOGY AND HYDROGEOLOGY

HEALTH PHYSICS

SURFACE WATER HYDROLOGY

BACKGROUND RADIATION AND WATER QUALITY INVESTIGATION

RECLAMATION PLAN AND SURETY

ACCIDENT SCENARIOS

Page 16: NRC LICENSE APPLICATION PROCESS STEPHEN J. COHEN HYDROGEOLOGIST/PROJECT MANAGER URANIUM RECOVERY BRANCH.

GEOLOGY AND HYDROGEOLOGY

• APPLICABLE FOR BOTH ISL AND CONVENTIONAL FACILITIES.

• THOROUGH DESCRIPTION OF GEOLOGY AND HYDROGEOLOGY.

• DETAILED TESTING AND ANALYSIS INFORMATION

• STATISTICAL ANALYSIS METHODS

Page 17: NRC LICENSE APPLICATION PROCESS STEPHEN J. COHEN HYDROGEOLOGIST/PROJECT MANAGER URANIUM RECOVERY BRANCH.

HEALTH PHYSICS ISSUES

• 10 CFR 40, APPENDIX A CRITERION 7 THROUGH 10

– COMPLETE BASELINE DATA

– PRE/POST OPERATIONAL MONITORING PROGRAM

• NUREG 1569

– BACKGROUND RADIOLOGICAL CHARACTERISTICS

– DECOMMISSIONING GUIDANCE

Page 18: NRC LICENSE APPLICATION PROCESS STEPHEN J. COHEN HYDROGEOLOGIST/PROJECT MANAGER URANIUM RECOVERY BRANCH.

GEOTECHNICAL ENGINEERING

• DESIGN

• OPERATIONS

• DECOMMISSIONING/RECLAMATION

Page 19: NRC LICENSE APPLICATION PROCESS STEPHEN J. COHEN HYDROGEOLOGIST/PROJECT MANAGER URANIUM RECOVERY BRANCH.

SURFACE WATER HYDROLOGY/EROSION PROTECTION – ISL FACILITIES

• SITED TO AVOID FLOODING/EROSION

• EROSION PROTECTION NEAR STREAMS

• IMPOUNDMENTS TO CONTAIN LARGE EVENTS

• DAM SAFETY

• RECLAMATION PLAN

Page 20: NRC LICENSE APPLICATION PROCESS STEPHEN J. COHEN HYDROGEOLOGIST/PROJECT MANAGER URANIUM RECOVERY BRANCH.

SURFACE WATER HYDROLOGY/EROSION PROTECTION – CONVENTIONAL MILLS

• RECLAMATION PLAN WITH APPLICATION

• EROSION PROTECTION DESIGNS NEEDED FOR CHANNELS, EMBANKMENT SLOPES, AND APRONS.

• NUREGS-1620 AND -1623 PROVIDE ACCEPTABLE METHODS FOR EROSION PROTECTION

• OPERATIONAL IMPOUNDMENT CAPACITY/FREEBOARD MAY BE AFFECTED BY LARGE EVENTS

• DAM SAFETY CONSIDERATIONS

Page 21: NRC LICENSE APPLICATION PROCESS STEPHEN J. COHEN HYDROGEOLOGIST/PROJECT MANAGER URANIUM RECOVERY BRANCH.

BACKGROUND INVESTIGATIONS

• BACKGROUND GROUND WATER QUALITY INVESTIGATION – 10 CFR 40, APPENDIX A, CRITERION.

1 YEAR OF SAMPLING

BACKGROUND CONCENTRATIONS APPROVED BY NRC.

• SOILS BACKGROUND INVESTIGATION SUFFICIENT TO IDENTIFY HETEROGENEITIES IN RADIONUCLIDE CONCENTRATIONS.

• BACKGROUND CONCENTRATIONS AT DEPTH COULD BE A CONCERN.

Page 22: NRC LICENSE APPLICATION PROCESS STEPHEN J. COHEN HYDROGEOLOGIST/PROJECT MANAGER URANIUM RECOVERY BRANCH.

ACCIDENT SCENARIOS – A BRIEF DISCUSSION

• SPECTRUM OF POTENTIAL ACCIDENTS

• MEASURES TO PREVENT ACCIDENTS

• EMERGENCY PLANS AND TRAINING

Page 23: NRC LICENSE APPLICATION PROCESS STEPHEN J. COHEN HYDROGEOLOGIST/PROJECT MANAGER URANIUM RECOVERY BRANCH.

RAIs AND RESPONSES

• REQUESTS FOR ADDITIONAL INFORMATION ISSUED TO COMPLETE REVIEW.

• RAI LETTER ISSUED WITH RESPONSE REQUESTED WITHIN 30 TO 45 DAYS.

• GOAL: ONCE RESPONSES ACCEPTED – TECHNICAL REVIEW PROCEEDS.

Page 24: NRC LICENSE APPLICATION PROCESS STEPHEN J. COHEN HYDROGEOLOGIST/PROJECT MANAGER URANIUM RECOVERY BRANCH.

FINAL REVIEW STEPS

• COMPLETE ENVIRONMENTAL REVIEW PROCESS - EIS

• COMPLETE THE SAFETY EVALUATION REPORT

• PUBLISH RECORD OF DECISION

• ISSUE LICENSE AND SAFETY EVALUATION REPORT

• ADJUDICATION

Page 25: NRC LICENSE APPLICATION PROCESS STEPHEN J. COHEN HYDROGEOLOGIST/PROJECT MANAGER URANIUM RECOVERY BRANCH.