REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES (220 kV & ABOVE) VIS-A-VIS PROGRAMME DURING 2014-2015 As on 30-NOV-2014 Schedule 1. 2. 5. 6. 7. 8. 9. 10. 12. 3. Revised/ Anticipate d 11. Construction progress Status Target Date Remark (Status of all statutory clearences particularly forest clearence and ROW problem, if any needs to be mentioned here.) Towers TL (Nos) STC (Nos) TE (Nos) STG (cKM) Voltage Level 4. Sl No Name of Transmission Lines Total Lengt h CKM Ckts (S/C) & (D/C) DAMODAR VALLEY CORPORATION (DVC) Commissioned 05/14. 74 Gola - Ramgarh 74 1 D/C MAY-14 220 1st stage FOREST clearance obtained from MOEF,GoI in May'12.Compliance made and file moved for 2nd stage clearance.Severe ROW problem in 1 location near Giridih end.Matter is being sorted out.Railway Crossing- Clearance obtained.PTCC obtained. 212 Kodarma-Giridih 325 311 310 98 2 D/C MAR-15 220 Severe ROW problem in most of the locations.Work inside ISP resumed soon.Railway crossing at 1nos.Proposal submitted.In principle approval of railway for line crossing has been obtained.Severe ROW problem in almost all locations outside ISP.Line is being diverted again between location no. 29 to 54 due to severe ROW problem. 37 LILO of Mejia-Kalyaneswari at Burnpur S/S 79 55 0 0 3 D/C JUN-15 220 Working clearance obtained on 6-3-2013 from Dy. Secretary,GoJ,Ranchi.PTCC still awaited.Rectification work of the theft portion of the line is in progress (80 ckm out of 100 ckm has been completed. DEC-08 344 Mejia TPS - Gola 552 541 507 132 4 D/C JAN-15 220 Forest: Working clearance obtained on 26-12-2012.Aviation Clearance:Obtained. PTCC Clearance: PTCC clearance obtained. AUG-10 311 Raghunathpur TPS -Ranchi (PG) 439 439 431 271 5 D/C DEC-14 400 Trasmission Lines: Page 1 of 121 Legends TL: Total Location STC: Stubs Cast TE: Towers Erected STG: Stringing Completed
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES (220 kV & ABOVE) VIS-A-VISPROGRAMME DURING 2014-2015
As on 30-NOV-2014
Schedule
1. 2. 5. 6. 7. 8. 9. 10. 12.3.
Revised/Anticipate
d
11.
Construction progress StatusTarget Date Remark
(Status of all statutory clearences particularly forest clearence and ROWproblem, if any needs to be mentioned here.)
1st stage FOREST clearance obtained from MOEF,GoI in May'12.Compliancemade and file moved for 2nd stage clearance.Severe ROW problem in 1 locationnear Giridih end.Matter is being sorted out.Railway Crossing- Clearanceobtained.PTCC obtained.
212Kodarma-Giridih 325 311 310 982 D/C MAR-15220
Severe ROW problem in most of the locations.Work inside ISP resumedsoon.Railway crossing at 1nos.Proposal submitted.In principle approval ofrailway for line crossing has been obtained.Severe ROW problem in almost alllocations outside ISP.Line is being diverted again between location no. 29 to 54due to severe ROW problem.
37LILO of Mejia-Kalyaneswari at Burnpur S/S 79 55 0 03 D/C JUN-15220
Working clearance obtained on 6-3-2013 from Dy. Secretary,GoJ,Ranchi.PTCCstill awaited.Rectification work of the theft portion of the line is in progress (80ckm out of 100 ckm has been completed.
DEC-08344Mejia TPS - Gola 552 541 507 1324 D/C JAN-15220
Forest: Working clearance obtained on 26-12-2012.Aviation Clearance:Obtained.PTCC Clearance: PTCC clearance obtained.
(Status of all statutory clearences particularly forest clearence and ROWproblem, if any needs to be mentioned here.)
Towers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hCKM
Ckts(S/C)
&(D/C)
Gen. project (Bokaro STPP) delayed. Bokara GIS (DVC scope) also delayed.Matching with gen. proj. Final forest clearance received in Aug'13.Tree cuttingpermission progressively being received.
NOV-112Bypassing of Bhatapara - Raipur as Bhatapara - Bhilai 425 S/C OCT-13400
Commissioned 05/14.MAY-1462Champa Pooling Station - Dharamjaygarh / NearKorba Switching Station line
153 153 153 6226 S/C MAY-14765
Stg-I clearance (191 Ha) awaited. Proposal under process in State Govt. (MP).DEC-152573Champa Pooling Station - Kurukshetra (HVDC) 3474 1795 950 2127 BIPOLE
DEC-15±800
Commissioned 05/14.MAY-14298Champa Pooling Station - Raipur Pooling Station line 387 387 387 29828 D/C MAY-14765
*Completion uncertain. Severe ROW problem in western UP.Progress very slow.NOV-11249Dehradun - Bagpat 444 391 326 5630 D/C MAR-15400
Stage-I Forest clearance for Chattishgarh portion(298Hac.) received in Oct'14.JUL-14868Dharamjaygarh - Jabalpur Pooling Station line 1132 907 804 26031 D/C JUN-15765
Severe ROW problem faced in Karnataka end.AUG-14240Dharmapuri (Salem New) - Somanahalli 318 308 262 9032 D/C FEB-15400
60Drass - Kargil33 S/C MAR-16220
Forest proposal under approval of Cabinet. FAC meeting earlier pospond due toflood in J&K now held. to be put up in Cabniet.
(Status of all statutory clearences particularly forest clearence and ROWproblem, if any needs to be mentioned here.)
Towers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hCKM
Ckts(S/C)
&(D/C)
AC yard at Kurukshetra.
Severe ROW being faced.Stringing commenced from Nov'14.AUG-1430LILO of Dehar - Panipat at Panchkula 40 19 16 166 S/C DEC-14400
Progress affected due to ROW problem & forest clearance.NOV-1234LILO of One Ckt of Baripada - Mendhasal line at Dubri(OPTCL)
48 43 38 367 D/C DEC-14400
Commissioned 07/14.25LILO of 2nd Ckt of Lucknow - Bareliiy line (PG) atShahjahanpur
90 90 90 2568 D/C JUN-14400
DEC-1530LILO of Abdullapur - Sonepat at Kurukshetra (Tripal) 44 42 3569 D/C JUN-15400
30LILO of Aizwol (PG) - Zemabawk at Melriat (PG) 45 0 0 070 D/C DEC-14132
Award placed in Mar'14. Completion matching with Sub station. Severe ROWproblem being faced.
54LILO of Baripada - Mendhasal at Pindiabil 106 971 D/C JUN-15400
Award placed in May'14.NOV-128LILO of Birpara - Salakati at Alipurduar 2072 D/C SEP-15220
Award placed in May'14.JAN-1524LILO of Bishwanath Chariali - Agra at Alipurduar 3673 HVDC DEC-15±800
Award placed in Aug'13. Survey in Progress.16LILO of Bongaigaon - Siliguri at Alipurduar 2474 D/C SEP-15400
Commissioned 10/14.NOV-1256LILO of Both Ckt Jamshedpur - Rourkela line atChaibasa
90 90 90 5675 D/C OCT-14400
Severe ROW problem in western UP. Completion UncertainNOV-1458LILO of Both Ckt of Dehradun - Bagpat line (QUAD) atSaharanpur
78 35 0 076 D/C MAR-15400
Loop out charged in Dec'13. Loop in held up due to non-availability of forestclearance (9Locs). Stage - I received in Oct'14.
15LILO of Ckt-II Jullandhur - Hamirpur at Hamirpur (PG) 65 57 52 2477 D/C DEC-14220
Severe ROW being faced.Completion likely to be delayed.AUG-1440LILO of Dehar - Bhiwani at Rajpura (PSTCL) 43 31 1978 S/C DEC-14400
Award placed in Aug/11. Engg. in progress.19LILO of Gangtok - Melli at Rangpo 3479 S/C 132
Commissioned 11/14.7LILO of Gangtok - Rangit at Rangpo 21 21 21 680 S/C NOV-14132
MAY-1512LILO of Gaya - Fatehpur at Varanasi line81 S/C 765
Scheme under review in view of CERC direction.JUL-1438LILO of Gazuwaka - Vijayawada at Vemagiri 9582 D/C JUN-14400
LILO of Jiribam - Aizawl at Turial83 D/C 132
Commissioned 03/13.DEC-121LILO of Loktak - Imphal at Imphal (New) line 5 5 5 184 D/C MAR-13132
Completion uncertain.Severe ROW problem in Maharastra.Efforts being made to complete the balance protion of line using under groundcable. Award placed in Sep'13.
SEP-1018LILO of Lonikhand (MSETCL)- Kalwa at Navi Mumbai 25 22 19 1385 D/C MAR-15400
(Status of all statutory clearences particularly forest clearence and ROWproblem, if any needs to be mentioned here.)
Towers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hCKM
Ckts(S/C)
&(D/C)
AwCourt case at 01 loc. Matter reffered to DC. Order awaited.9LILO of Tuticorin JV - Maduri at Tuticorin 16 15 14107 D/C DEC-14400
Investment approval pending.LILO of Vishnu Prayag - Muzaffarnagar at TapovanVishnugarh HEP
108 D/C MAR-15400
(01 ckt. LILO connecting to Mahandragarh- Bhiwani of M/s. Adani of 27 ckm bypassing Bhiwani S/Stn. commissioned on 18.08.11). 2nd commissioned in Jul'12.
35LILO of both ckt of Bawana /Bahadurgarh -Hissar atBhiwani
86 86 86 60109 D/C JUL-12400
Award placed.APR-15172LILO of both ckt of Kolhapur - Mapusa at Kolhapur(new)
167 38 12110 D/C DEC-15400
Court case at 01` loc. Matter reffered to DC. Order awaited.JUL-1420LILO of both ckts of Tuticorin JV - Maduri at TuticorinPooling station
16 15 14111 D/C DEC-14400
.LILO of one circuit of Dulhasti - Kishenpur at RatleHEP.
112 D/C 400
Completion uncertain. Works stand still on a/c of localm disturbance /agitationagainst big dam. Generation uncertain.
Line completed & commissioned in Aug'14.OCT-13480MB TPS (Anuppur) - Jabalpur Pooling Station 600 600 600 492115 D/C AUG-14400
Madhugiri - Bidadi (Quad)116 D/C 400
ROW being faced at Madugiri end.Critical.JUN-14154Madhugiri - Yelhanka 177 105 36117 D/C FEB-15400
Ckt-I (65 Ckm) Commissioned 09/14. Ckt-II (65 Ckm) Ready for commissioning.130Maithon -Gaya line (Balance part) 130118 D/C SEP-14400
Contigency connecting Maithon-Gaya with Koderma-Gaya by-passing multi-cktportion in forest,to rorm Maithon-Koderma line 400KV Maithon-Koderma line(422Ckm)commissioned in Jan'13.Implementation of balance portion affecteddue to Moist problem in jharkhand/Bihar.
AUG-14193Maithon -Gaya line (Q) 742 742 742 552119 D/C DEC-14400
ROW problem is being faced in Nagaland.DEC-1256Mariani (New) - Mokikchung (PG) 163 161 147 54120 D/C DEC-14220
Mauda STPS - Betul 555 96 22121 D/C MAY-16400
Tower erection commenced from Mar'14.MAY-16418Mauda-II - Betul (Quad) line 555 96 22122 D/C MAY-16400
ROW being faced in UP.MAR-15324Meerut - Moga line 922 667 347 120123 S/C MAR-15765
* Completion uncertain as work completely held-up in stretch of 50 Kms sincemore than 05 year due to severe ROW problem in Karnataka portion of lineforest clearance in Karnataka. Work re-started from Dec'13.
Line is now proposed to be terminated at Boisor S/Stn in place of Mumbai newloc. Forest clearance awaited.Contigrncy arrangement to connect Navsari-Boisarwith Vapi-Navi Mumbai line by passing forest area to form Vapi-Navsari line (212Ckm) commissioned in Mar'13.FC proposal submitted to MoEF on 28.07.14 (57Hac.)
(Status of all statutory clearences particularly forest clearence and ROWproblem, if any needs to be mentioned here.)
Towers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hCKM
Ckts(S/C)
&(D/C)
Forest clearance awaited. Critical. Stage-I received in Sep'14.SEP-14341Ranchi (New) - Dharamjaygarh /Near Korba 922 758 390 76145 S/C MAR-15765
Involment of forest,critical. Completion matching with Jharkhand Pooling station.NOV-13136Ranchi - Jharkhand Pool line (Quad) 195 188 140 88146 D/C MAR-15400
Completion matching with Melli S/stn. (re-award in Sep'13).NOV-1352Rangpo - New Melli line (Twin Moose) (20.5 D/C & 1.5M/C)
Efforts being made to complete in FY2014-15.DEC-1552Sagardighi - Baharampur 78 76 69 5152 D/C DEC-14400
Severe ROW being faced in Karnataka.DEC-14244Salem Pooling Station - Madhugiri Pooling Station line 647 538 356 51153 S/C DEC-14765
Line completed. Testing under progress.120Salem Pooling Station - Salem 165 165 165 120154 D/C DEC-14400
Line comleted & commissioned in Dec'12.NOV-1212Sasan - Vindhyachal Pooling Station line 19 19 19 12155 S/C MAY-13765
MAR-154Sasaram - Allahabad line 11 10156 D/C MAY-15400
Completion matchung with Daltanganj S/S delayed due to non-availibility of S/Ssite .
NOV-12340Sasaram - Deltonganj line 522 490 370 185157 D/C DEC-15400
Commissioned 08/14.NOV-12300Satna - Gwalior line (60 Km D/C Portion) Ckt-II 782 782 782 300158 D/C+S/C
AUG-14765
Severe RoW problem being encountered.OCT-14268Sholapur - Pune 750 742 738 248159 S/C JAN-15765
Contract reviewed through assisment to JV.AUG-12336Sikar - Jaipur line 478 448 325 79160 D/C MAR-15400
Contract reviewed through assisment to JV partner..AUG-12154Sikar - Ratnagarh line 209 202 201 96161 D/C DEC-14400
Line test charged in Jun'12.50Silchar - Hailakandi (Contingency arrangement) 65 65 65 39162 D/C JUN-12132
Severe ROW problem in noney area of Mainpuri.Site progress affecetd.DEC-12332Silchar - Imphal (New) line (to be charged at 132KV) 471 470 418 181163 D/C FEB-15400
Major portion of line in forest. severe ROW in vicinity of Aizwl town due to stiffresistance from influential local owner.
DEC-12286Silchar - Melriat (New) line (charged at 132KV) 436 300 179 95164 D/C DEC-15400
Tripura portion completed, Severe ROW problem in Assam portion. WorksDEC-12256Silchar - Purba Kanchan Bari line (charged at 373 373 373 237165 D/C DEC-14400
DEC-14735Tuticorin Pooling Station - Salem Pooling Station 1000 868 352 40175 D/C MAR-15765
60Unchahar - Fatehpur176 D/C 400
Due to severe ROW portion at Navi-Mumbai end,Line now decided to theterminated at Kudus S/stn. of MSETCL. Contigency arrangement to connectVapi-Navi Mumbai with Navsari-Boisar line by passing ROW area to form Vapi-Navsari line (24 Ckm) commissioned in Mar'13.40KV D/C Vapi-Kala portion (61Ckm0 commissioned in Mar'14. Balance matching with readiness of Kudus S/Sby MSETCL.
Re-tendering of the work has been done5Kukurmara - Azara line 26 3 0 06 S/C onD/C
DEC-14132
Project has been abandoned25Kukurmara - Boko line 162 0 0 07 S/C onD/C
DEC-14132
Balance stringing work held due to non-availability of 132kV line shut-down.10LILO of Jorhat - Bokakhat at Jorhat (West) S/S 9 9 8 28 D/C MAY-15132
Work in progress.12LILO of Namrup - Tinsukia at Bordubi S/S 9 7 0 09 D/C MAY-15132
Completed7LILO of Palatana - Bongaigaon line at Kukurmara(Azara) S/S
14 14 14 710 D/C JUL-14400
Due to water logging issues, erection of towers couldnot be carried out.14LILO of both ckt of Balipara (PG) Samaguri at Sonabil 6 6 0 011 2xD/C DEC-14220
Compensation issue, RoW problems, Forest Clearance and Railway crossing89LILO of both ckt of Chandrapur - Kahilipara/Narengi atSonapur
137 64 31 012 2xD/C MAY-15132
Compensation issue, RoW problems and Railway crossing8LILO of both ckt of Depota - Gohapur at Sonabil S/S 6 6 0 013 2xD/C MAY-15132
RoW & Water logging problems adversely affected foundation works55LILO of both ckt of Samaguri - Sarusajai line atSonapur S/S
41 17 0 014 2xD/C DEC-14220
Right of way issues31LILO of one ckt of Tinsukia - Margherita at Rupai(Doomdooma) S/S
109 108 107 2915 D/C NOV-14132
Work in progress.160Namrup - Mariani line 448 446 420 7616 S/C on DEC-14220
Commissioned 9/14.6LILO of Bawana-Najafgarh at Kanjhawla 33 33 33 62 D/C SEP-14220
Case for extension of time upto 28.02.15 was processed and approval of same isawaited.
11LILO of Kanjhawala - Najafgarh at Mundka 400 kV S/S 35 30 19 03 D/C MAR-15220
Commissioned 9/14.19Maharani Bagh- Gazipur (0.5kM cable on MaharaniBagh side & 8.5kM OH line)
42 42 42 194 D/C SEP-14220
.Cable laid in 23 Sections out of 24 Sections and 114 St. through joints madeout of 138 joints. .Delay in RBI permission to M/s TBEA to openINR account in India received in Nov,13.Erection of Supporting structure for outdoor terminations has been completed
MAY-1126Mundka -Peeragarhi U/G 200 mm, 250 MW5 D/C FEB-15220
.Cable laid in 13 Sections out of 19 Sections. 42 Joints made out of 108 Joints.
.Delay in RBI permission to M/s TBEA to open INR account in India received inNov,13..ROW charges amounting to Rs. 7.6 Crore deposited to Railways . Thepermission is expected within a week.Work has been stopped by TBEA and their sub-contractor for approx. last 4months on account of pending INR payments. Finance deptt. is not releasingpayments amounting to Rs. 2.7 Crore citing WCT/Taxation issues.
17Peeragarhi-Wazirpur U/G 1000 mm, 200 MW6 D/C MAR-15220
(Status of all statutory clearences particularly forest clearence and ROWproblem, if any needs to be mentioned here.)
Towers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hCKM
Ckts(S/C)
&(D/C)
HARYANA VIDYUT PRASARAN NIGAM LIMITED (HVPNL)
Work awarded.The nomenclature of work is Const. of multi-circuit line emantingfrom 400 kV Sub station Deepalpur enrouting 220 kV RGEC Sonepat, 220 kVHSIIDC Rai & 132 kV HSIIDC Rai
MAY-1344Deepalpur-Sonepat HSIIDC Rai 113 44 10 01 M/C MAR-15220
work is in progressAPR-11152Gurgaon Sector 72 - Nuh - Rangla Raipur 322 300 297 612 S/C MAR-15220
Work awarded to M/s K.Ramachandra Rao Transmission & Project Pvt. Ltd. dt.31.01.2014
Work in progress.24Gurgaon Sector-72- Gurgaon Sector-20 108 109 108 244 D/C JUL-15220
Work is in progress.JUL-1342LILO of Chormar - Fathebad line at Hukmawali 165 83 05 D/C MAR-15220
Work yet not awarded.5LILO of Madnpur - Kunihar line at Panchkula sector-326 D/C 220
JAN-112LILO of Moga-Hisar line at RGTPS Khedar7 D/C 400
JUL-1380LILO of both Ckt of Cheeka - Durala at Sonta 64 10 0 08 D/C JUL-15220
Work yet not awarded.And nomenclature has been changed now it become LILO of one circuit of 220KV D/C Sector 72 to Sector 52A, Gurgaon line (on multi circuit towers) at 220 KVsub-station Sector-57, Gurgaon
1LILO of gurgaon Sec -72 - Sector 52 (A) at Sector 579 D/C JUN-14220
220 kV A-4 to A-5 line is under construction(13.5 kM)whereas section of A-3 to A-4 is under review.
1LILO of one circuit A-3 Palla (Faridabad) - A5(Faridabad) at A4 (Faridabad)
59 31 29 310 D/C SEP-14220
Ready for commissioning .36LILO of one ckt of Badshahpur - Bhiwadi at HSIIDCBawal
64 64 64 3611 D/C NOV-14220
The line was charged partly on no load from Masudpur to TL No. 109 on dated16.06.2014 and from Samain to TL No-112 (Single Phase) on dated 01.07.2014to avoid theft of conductor.
91Masudpur-Samain line 182 182 182 4412 D/C SEP-14220
The Nomenclature of work is LILO of one circuit of Mau Bhiwadi D/C section of220 kV D/C Badshahpur Bhiwadi line at 220 kV substation HSIIDC BawalLine test charge on 19.10.2014
Mau - Bawal 64 64 64 1813 D/C OCT-14220
Work in progress.DEC-1027Palla (Faridabad) - A 5 (Faridabad) 59 31 31 314 D/C DEC-15220
WORK IN PROGRESS52Palwal (Meghpur) - Meerpur Kurali 106 99 90 1415 D/C DEC-14220
Work awarded M/s Varrsana Ispat on dt 01.07.2014.15Panchkula (PGCIL)- Panchkula Sector 3216 D/C AUG-15220
Fund yet to be tied up.80Delina - Wahipora-Kishanganga4 D/C 220
Rerouting of line and ganglas s/s droped. Leh Army S/S shall be connected withLeh S/S.
9Ganglas - Leh Army base 46 22 0 05 S/C DEC-1466
Completedd & will be charge after tree cutting in Gramthang - SankooTransmission Line. Compensation of the trees are pending with DistrictAdministration. Sub-staton has been successfully back-charged on 09/10/2013.
Slow pace of execution of work in Zainkote-Alusteng section. Original Projectcost provision exhausted, For Alusteng - Miarbazar section contract case sent toGovt for approval.
(Status of all statutory clearences particularly forest clearence and ROWproblem, if any needs to be mentioned here.)
Towers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hCKM
Ckts(S/C)
&(D/C)
KARNATAKA POWER TRANSMISSION CORP. LIMITED (KPTCL)
Work under progress.SEP-0670Chikkodi-Kudachi 120 120 90 401 D/C DEC-15220
21/21 sections laid. 20/20 joints completed. Cable testing to be taken up by theagency for which opening of link boxes is required. BBMP permission is requiredto open link boxes.
11HSR Layout - Nimhans S/S 0 0 0 92 UGCable
NOV-14220
Location 41 comes in forest area and hence it was proposed to divert the forestland and the proposal has been submitted to additional principal chiefconservator of forests, Bangalore on 09.10.2013.APCCF made observationsregarding survey which was attended and resubmitted for approval on28.12.2013.The RFO, Hiriyur has inspected the spot on 01.05.2013 andinformed to resubmit the forest boundary details. The location has beenresurveyed and the forest map has been submitted to RFO, Hiriyur on23.05.2014.From RFO, Hiriyur to DCF, Chitradurga, then to CCF, Bellary, then toAPCCF, Bengaluru and then to ACS, GoK on 09.10.2014.To prevent theft, line charged on 03.10.2012 from location 102 to 431 fromGowribidanur end (route length 93 km) and from loc. 102 to 47 on 06.09.2014(route length 14.5 km)by obtaining provisional approval from electricalinspectorate. Total route length idle charged is 107.5 km (route length).02 TBs at Gowribidanur commissioned on 09.11.11 & 20.12.12.
Work under progress.65Ittagi - Kudligi line 119 47 414 D/C MAR-15220
Work under progress.ROW problem for entire line of Gijihally to Kanthenahally limits,case filed in DCcourt, Hassan on 20.03.2013. Being pursued.
8LILO of Arasikere -Kanthenahalli at Arasikere S/S 21 9 25 D/C FEB-15220
220kV loop in tower stub concreting done.Excavation for 220kV loop out tower iscompleted
1LILO of Gadag - Lingapur at Koppal 2 16 D/C MAR-15220
Work under progress.(1) ROW problems at corridor between 4 & 5 pending inJMFC, Hoskote, Additional Civil Judge(Junior division) since 9.12.10.(2)Loc 4 & 5: Case filed by party at High court vide Writ Petition: 46532-533/2012 dtd: 19.11.2012 seeking injunction.(3) Loc 4 : The petitioner has obtained stay order vide WP 32606-32607/2013from the Hon'ble High Court against the proceedings in the OS No: 253/2010 on02.09.13.
SEP-0726LILO of Hoody-Kolar at Hoskote 55 35 31 07 D/C DEC-15220
(Status of all statutory clearences particularly forest clearence and ROWproblem, if any needs to be mentioned here.)
Towers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hCKM
Ckts(S/C)
&(D/C)
(4) Loc 36 : Case No: MAG(CR)/1/13-14 at DC Court, B'lore Rural. Posted forOrders. Being pursued.Work under progress.6LILO of RTPS - Lingasugur S/C line at Mallat (Manvi) 13 12 118 D/C MAR-15220
Forest clearance required for 3.836 hectares in locations 25,34 &35. Stage-Iapproval received on 20.04.11.NPV & compensatory afforestation charges of Rs.28,01,923/- paid on June-2011.Additional NPV & compensatory afforestation charges of Rs.4,04,973/-paid on 01.10.2011.Demarkation of the line corridor in the forest land done on01.04.2013.Letter addressed on 01.04.2013 to forest authorities to process forstage-II. Stage-II clearance approval awaited.
FEB-0835LILO of Shimoga - Mysore at Dandiganahally 70 62 61 229 D/C MAR-15220
Work under progress. (1) Local ROW problems atlocations: (i)9,10,14,16,17,19 - being pursued.(2) Forest approval at Loc 17 to 21 : Stage-I clearance pending. Revised routeproposal through forest area submitted for approval to Aranya Bhavan on9.10.12, Approval awaited.Regarding condition No.4 : Compensatory afforestration charges of Rs.6,08,000/- and condition no.5 : Net present valur (NPV) amount of Rs.15,89,504/- totalingof Rs.21,41,623/- payment made on 06.05.14.DC COURT:For corridor 8-9 & 10-11: Case filed in DC court on 27.05.2013. Being pursued.
9LILO of Somanahalli - Malur at Vikas Tech Park 39 15 0 010 D/C DEC-14220
Work under progress.120Madhugiri - Pavagada line 214 149 12211 D/C MAR-15220
Work under progress.
Constraints : (i) ROW problem at loc 15 & 16 being pursued.(ii) Case filed in DC Court, Hassan for ROW problems at loc. 15,16,28,29,30,31& 32 during March 2013. Being pursued.Case cleared at locations: 30, 31 & 32on 15.07.2014.
SEP-0915Shanthigrama - B4 line ( near Hedanahalli limits) 34 33 30 912 D/C MAR-15220
Kolar_Malur line charged. Malur Somanahalli line partially charged.
Case pending in High Court: (i) At Loc 59 (for stub concreting) : Case pending inHigh Court since 31.08.2013. Being pursued.
(Status of all statutory clearences particularly forest clearence and ROWproblem, if any needs to be mentioned here.)
Towers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hCKM
Ckts(S/C)
&(D/C)
(ii)Loc 84,85,86,88 & 89: Case filed by KPTCL in DC Court on 27.01.2014. Beingpursued.(iii) Loc 84,85,86,88 & 89 : Case filed by party in Court of Junior Civil Judge ,Bangalore Rural district on 11.02.2014. Being pursued.(iv) Loc 135,135A,135B, 135C & 136 : case filed in High Court by party (IndiaInternational School) on 19.06.2013. Being pursued.
LOCAL ROW : Loc 137 -147: Row problem for stringing , farmers aredemanding higher compensation.
Work stopped due to severe ROW problems.(1)ROW problem at Loc. No.6 Case pending at JMFC, Anekal since 04.10.2010.Being pursued.(2) Loc Nos. 29-33: Tree cutting permission awaited from forest Department.Being pursued. ACF Malleshwaram orally approved on 12.07.2013 to carry outthe stub work without cutting trees.(3) Local ROW issues at Loc no. 22 24 : Residential Layouts Celebrity Housingproperty. Being pursued locally.
23Somananahalli Malur I & II lines - Jigani 34 6 4 014 D/C DEC-15220
220 kV DC line from 220 kV Tubinakere S/s to Kothipura S/s :(1) (i) ROWproblems pending in JMFC Ramanagara for- (a) Loc 81 since 2009(ii) ROW problems pending in JMFC Channapatna for - (a) Loc 129-130 since2009(2)ROW problems pending in DC Court Ramanagar for (a) Loc 133: Case filedon 24-08-2011.Reserved for orders.(3)ROW problems at locations 208: being pursued locally.
220-66 kV MC line from 220 kV Kothipura to Bidadi S/s:(1) ROW problems pending in DC Court Ramanagar for Loc 15 : Case filed on19-07-2012.(2) ROW problems to be solved locally at 8 locations 2,3,4,4A,5,6,33 & 77
(Status of all statutory clearences particularly forest clearence and ROWproblem, if any needs to be mentioned here.)
Towers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hCKM
Ckts(S/C)
&(D/C)
ROW problem pending at Civil courts and DC court :(i) For Corridor between 20& 21, case pending in Jr. Division, Mangalore since 2010, Being pursued.(ii) ForCorridor between 2-3A-2A, case filed in Civil Judge ( Jr. Division) Mangalore,Interim order received against KPTCL on 28.05.2012. An appeal is filed in theCourt of Civil Judge (Sr. Division), Mangalore. Being pursued.
(Status of all statutory clearences particularly forest clearence and ROWproblem, if any needs to be mentioned here.)
Towers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hCKM
Ckts(S/C)
&(D/C)
MAHARASHTRA STATE ELEC. TRANSMISSION COMPANY LTD. (MSETCL)
Agency has already given a letter on Dt. 14.04.2012 for cancellation of work.44Ambazari - Mankapur 37 0 0 01 M/C MAR-16220
line is to be deleted. As line is not possible due to major ROW problem as linepasseing through N.A. and defence land only.
184Ambazari - New Buttibori-II 0 0 0 02 M/C APR-16220
3 Nos railway crossing involved.Out of which for Loc nos 71-72 stringingis done on Dt.10.04.2014.Permission for Loc No.27-27A is received onDt.10.09.2014.RevisedDemand of 87-88 received fron CR,Nagpur.
After GMRT objection line route diverted from Loc. No.:-242 to 298 hence casted28 Nos fundations anderected 15 Nos. towers are not in use. ROW cases filed at Collector Thane &Collector Pune .Forest involved 114+36.243 , forest proposal being submitted toforest office.Work in progress.
Court cases-2 nos. Next hearing on 21.12.13. Contract of M/s. M.M.Ghatge isclosed at Zone office & that of M/s. B. N. Chaudhari closed at C.O. After closureof contract, fresh tenderisation will be done for balance work the estimate ofwhich was already submitted.
(Status of all statutory clearences particularly forest clearence and ROWproblem, if any needs to be mentioned here.)
Towers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hCKM
Ckts(S/C)
&(D/C)
collector order received for balance 22 foundations,3 cases orderawaited, 2 kept for alignment(total 27). police protection letter issued toconcerned police station forbalance works.
Work will be after completion of 220KV Koradi - Butibori line.42Koradi II - Ambazari 27 0 0 018 D/C onM/C
MAR-16220
Forest involved 10.36Ha.Proposal pending at Forest Nodal Officer Nagpur.MAR-11106Koradi II - Butibori 189 133 117 2219 D/C onM/C
DEC-15220
Forest: 16.9392 Ha (Wardha :3.85 & Nagpur:13.0892 )1st stage approvalreceived.FRA certificate awaited from Collector office Nagpur.3 nos of ROW loc pending at Nagpur.1 no of loc pending at High Court Nagpur.
2 no of ROW cases pending at Collector Office, Nagpur.1 NO ROW casepending at Nagpur & for 1 no police protection required.Forest involved4.122Ha.FRA certificate is awaited from collector office.
"Work in progress.CKM-238.9 6.625CKm line (ie from Gantry of Koradi-II S/Stn to Loc no-07 of Koradi WardhaD/C line ) of 400 KV Koradi II to Wardha (PG) S/S with Quad Conductorlinecomissined on dt.23.03.2013 for giving start-up power to Koradi-II S/Stn..Name of the Line 400 kVKoradi Wardha Line "
(Status of all statutory clearences particularly forest clearence and ROWproblem, if any needs to be mentioned here.)
Towers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hCKM
Ckts(S/C)
&(D/C)
Arbitral award- Group B. LOA issued to S P Power.9LILO of Dhule - Malegaon at Sayne 18 10 10 026 D/C MAR-15220
Line to be deleted.LILO of Ekherla - Babhaleshwar at Nasik TPP27 D/C 220
National Highway NH6 (Dhule-Surat) at loc No 62-63proposal is submitted to NHAI ofiice on 22.01.14.The GM(T) & Project Director PIU Dhule, submitted the proposal to CGM(T),NHAI Mumbai forseeking the permission for crossing.
56LILO of Gangapur - Malegaon (Satana) at Sakri(Shivajinagar)
97 97 97 2828 D/C MAR-15220
Commissioned 11/14.5LILO of Jeur - Karkambh at Shinde SKS 529 D/C NOV-14220
since now not required. This line is to be deleted.10LILO of Kalwa - Padghe at Bhiwandi-IV 0 0 0 030 D/C APR-15220
Arbitral award- Group B. Work order is placed on M/s. Anand Electical on02.09.2013.
8LILO of Kandalgaon - Lonand at Lonand MIDC 10 11 11 031 D/C MAR-15220
ROW issues pending for 2, 39, 42 locations.26LILO of Kolhapur - Sawantwadi at Mudhaltitta 44 40 36 432 D/C MAR-15220
LILO of Parvati - Phursungi at Kondhwa 5 5 5 033 D/C MAR-16220
Arbitral award- Group B. Work order for balance works of line are awarded toM/S Vishwas Elect, Nanded on 26.02.14.
12LILO of Sawangi - Bhokardan at Phulambri 20 8 0 034 D/C MAR-15220
Forest land involved in the route at Loc. No. 16A, proposal yet to be approved.The proposal is returned by Nodal Officer, Nagpur to Dahanu forest dn. forcompliances of Dwellers Act. Obtaining of NOC under Dwellers Act is in processfrom concerned Grampanchayats.
MAR-0716LILO of Tarapur-Borivli at Boisar II 15 15 12 1135 D/C MAR-16220
Commissioned 05/14.154LILO of Waluj - Bhusawal at Thaptitanda 15436 D/C MAY-14400
For 18 nos of ROW loc order received from Collector, C'pur . Police protectionrequired. For 13 nos of ROW locations cases pending at Collector C'pur.
50LILO of Warora - Wardha at Warora 42 11 6 037 D/C MAR-15220
Work in progress.MAY-12154LILO of both ckt 400 kV Bhusawal II - Aurangabad I atAurangabad-II
250 127 52 038 D/C JUN-15400
.LILO of both ckt Parli (GCR) - Beed at Parli39 D/C 220
Work in Progress.97Malegaon - Kalwan 170 153 124 040 D/C SEP-15220
Contract of M/s. R&C is closed. Fresh tenderisation is held up due to non receiptof assurance payment from ISPAT.
30Nagothane - Wadkhal 93 56 44 041 D/C MAR-16220
Work in Progress. Forest NOC received.73Nanded - Bhokar 122 120 111 1442 D/C MAR-15220
Arbitral award- Group C. Tender for balance work to be refloated136Nanded - Krishnoor 51 28 0 043 M/C MAR-16220
(Status of all statutory clearences particularly forest clearence and ROWproblem, if any needs to be mentioned here.)
Towers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hCKM
Ckts(S/C)
&(D/C)
MEGHALAYA ENERGY CORP. LTD. (MeECL)
No issues of forest clearance and no court cases. Work held up due to nonpayment of compensation to the land owners.At the present the assessment isprepared and likely to be cleared within this year.
Work completed and line charged on 28.01.2014.5LILO of Agia - Nangal at Mendipathar 9 9 9 52 D/C JAN-14132
No issue on forest clearance and no court cases.Work held up due to ROWproblem. The PHED,GOMe has complained and filed and FIR against Loc No. 3to 8. Overall status is 90% completed.
10LILO of Mawlai - Cherra at Mawngap. 16 15 15 43 D/C MAR-15132
No issues on forest clearance. Tower materials has been received. Procurementof other line materials is in process.
4LILO of NEHU - Khliehriat line at Mustem 4 0 0 04 D/C MAR-15132
No issues on forest clearance. Materials procurement is in process.6LILO of NEIGRIHMS - Khliehriat at Lad Nongkrem 9 0 0 05 D/C JUL-16132
Land for the substation has been identified and procurement of the same is inprogress.
20LILO of Rongkhon - Ampati at Praharinagar 34 0 0 06 D/C DEC-16132
Work executed by Power Grid. The LILO of the 400 kV Palatana- Bongaigaonline was energised w.e.f. 03.03.2013 through the completed dead-end loop-outtower. Dead end tower falling in the additional land required could not becompleted due to ROW problem. ROW has been resolved and the work for the400 kV Loop out bay has been resumed on the 07.11.2014.
4LILO of one ckt Palatana - Bongaigaon line 10 9 9 47 D/C MAR-15400
Work completed and line charged on 21.12.2011.66Mawngap - Sumer 102 102 102 668 D/C DEC-11132
Work Completed and line charged on 06.08.2013.92Nangalbibra - Agia 316 316 316 929 S/C AUG-13132
No issues on forest clearance and no court cases. Jungle cutting in Meghalayaportion of the line is under progress. Stringing Work is in progress, howeverthere is ROW problem in Loc No. 297 to 300 due to claim of compensation forthe house constructed along the corridor of the line.Matter has been taken upwith the concerned authorities.
92Nangalbibra - Agia line 0 0 0 5210 S/C MAR-15132
No issues of forest clearance. Survey completed. Materials procurement is inprocess.
(Status of all statutory clearences particularly forest clearence and ROWproblem, if any needs to be mentioned here.)
Towers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hCKM
Ckts(S/C)
&(D/C)
POWER TRANSMISSION CORP. OF UTTARAKHAND LTD. (PTCUL)
DPR prepared .sending of DPR to funding agency is in progress146Almora-Pithoragarh 0 0 0 01 D/C JUN-16220
Construction of line as per Connectivity Schedule of Generators in YamunaValley.
94Arakot -Mori and LILO of Arakot -Mori at Hanol Tuni 0 0 0 02 D/C MAR-18220
Construction of line as per Connectivity Schedule of Generatiors in YamunaValley.
52Devsari-Karanprayag 0 0 0 03 D/C NOV-17220
Construction of line as per Connectivity Schedule of Generators in YamunaValley.
76Jakhol -Sankri -Mori and LILO of Jakhol -Sankri -Moriat Natwar Mori
0 0 0 04 D/C MAR-18220
Contract has been awarded on 06.05.11 to M/s TATA Project Ltd., contracteffective date is 14.10.11 and GMVN has not given the permission to cross theAuli Ropeway, hence crossing by underground cable is proposed at Joshimath.Land sliding zone being encountered at village Malli Tangri and Talli Tangri thesurvey and forest case yet to be completed. Forest Case of 51.3 Hect. is underpreparation. Total Progress 6%.
Retendering is under Process.184Kuwari Pass (Pipalkoti)-Karanprayag -Srinagar 0 0 0 07 D/C JUN-16400
Contract has been awarded on 06.05.11 to M/s TATA Project Ltd. contracteffective date is 03.09.11 and will be taken after award of 400 KV Pipalkoti S/s.Total Progress 11%.
2LILO of Muzaffarnagar - Vishnu Prayag at KuwariPass (Pipalkoti)
6 0 0 08 D/C DEC-15400
Construction of line as per Schedule of construction of Singoli HEP and to beconstructed by L&T.
5LILO of Baramwari - Srinagar at Singoli Bhatwari 0 0 0 09 D/C OCT-16220
Tendering is under process.12LILO of Kashipur - Pantnagar line at Jaffarpur10 D/C JUN-15220
Commissioned 06/14.5LILO of Khodri - Rishikesh at Dehradun 10 10 10 511 D/C JUN-14220
The work at Pala Maneri HEP stopped as per GOI order.10LILO of Loharinagpala - Koteshwar at Pala - Maneri 0 0 0 012 D/C 400
Construction of line as per connectivity schedule of generatiors in Yamuna Valley10LILO of Mori - Dehradun line at Nogaon13 D/C MAR-18220
Construction of line as per Schedule of construction of Langrasu.16LILO of Nandprayag -Karanprayag at Langrasu 0 0 0 014 D/C NOV-17220
Tendering is under process.1LILO of Rishikesh-Dehradun at Harrawala 0 0 0 015 D/C MAR-15220
LoA is to be issued.10LILO of Roshnabad -Puhana at Pirankaliyar S/S 0 0 0 016 D/C JUN-15220
(Status of all statutory clearences particularly forest clearence and ROWproblem, if any needs to be mentioned here.)
Towers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hCKM
Ckts(S/C)
&(D/C)
Tender has been floated.70LILO of Vyasi HEP - Dehradun at Dehradun (PG) S/S 0 0 0 017 D/C APR-16220
Regarding Forest land Transfer proposal nodal officer Dehradun raised queriesvide letter no 3042 dated 01-06-2013. Reply of the same is being done. Totalprogress 10%
Tendering completed, contract signed with M/s Cobra on 24-12-2013. Workstarted date 24-02-2014. Survey work is in progress. Route alignment 138 Km.detailed survey 127 Km. Location contouring 112 Nos.alternative routealignment through Kotdwar in progress
304Sringar - Kashipur 0 0 0 024 D/C DEC-18400
Contract has been awarded on 06.05.11 to M/s TATA Project Ltd. contracteffective date is 03.09.11 Forest case prepared for 43.694 Hect. and submittedto DFO Joshimath/ DM Chamoli. NOC from 04 Nos. village panchyat NaurakhAgthalla, Tangri Talli and Tangri Malli is pending. Matter is being pursuedGOU/District Administration.
Two nos. NHAI crossing approval awaited, one no. Railway crossing caseapproval recd & NOC from forest deptt.recd. from DFO, Jaipur. The firm has notturn up to execute the work and required material is not available with the firm.
DEC-11213Phagi(Jaipur south-765 kV)-Ajmer line 284 257 184 076 D/C JAN-15400
Koladi - PH Road: OH Line work under progress. Stub: 47/76, TE:29/76completed. Stringing: 3/23.For cable laying from PH road to Koyambedu,administrative approval is under process.
Alamathy - Koyembedu1 D/C 400
Work under progress.Issues involved in line work at Loc.62 & 63 and 163.It isbeing followed up.
Stub setting pending at 6 locations due to ROW issues and it is being followedup. As the contractor M/s.GET has not turned up for work, it is proposed to shortclose the contractor.
Work under Progress. ROW issues involved and is being shorted out.326Karaikudi-Pugalur 460 459 459 2449 D/C DEC-14400
work under progress for 2 reaches and work is awarded on 21.11.14 for 3rdreach.
23Koladi - PH Road 76 47 30 310 D/C MAR-15220
Commissioned 04/14.5LILO of Arasur-Ingur at Karamadai S/S 511 D/C APR-14220
Works are under progress. Objections at Loc.41.For Loc. 6 to 7, NHAI approvalawaited.
32LILO of K.R. Thoppur - Ingur at Thingalur 99 97 97 2112 D/C JAN-15220
Line work completed. Tree cutting to be done for energisation of the line.16LILO of K.R.Thoppur-Deviakurichi at Singapuram 27 27 27 1613 D/C MAR-15220
Commissioned 07/14.4LILO of Kayathar - Anuppankulam at Kayathar 414 D/C JUL-14220
Commissioned 07/14.4LILO of Kayathar - Pasumalai at Kayathar 415 D/C JUL-14220
All works completed. Line will be erergised on completition of SS works.1LILO of Manali - Basin Bridge (BBGTP) at Vyasarpadi 6 6 6 116 D/C DEC-14220
Work awarded and stub setting work commenced.2LILO of Siruseri - Tharamani at Sholinganallur 14 13 0 017 D/C MAR-15220
Due to long penging Court case, approval for revised route is under scrutiny.DEC-1012LILO of Sriperumbadur- Arni at Sunguvarchatram 28 10 3 018 D/C MAR-15220
Work awarded and to be commenced.Road cut advice received from High ways.18LILO of Sriperumbudur - Koyambedu at Guindy (UGCable)
Works are under progress.Objection by land owners involved at locations 160 to190.Issues are being followed up. Multi Circuit tower involved at Loc.236 to 249.
LOI Issued to M/s MPTL on 11.10.10.Contract of the firm M/s MaharashtraPower Transmission Structures Ltd. has been terminated on 20.05.2014 andinform to the concern field officer for the balanced work after getting theapproval of CMD.
10Anpara B-Anpara D 23 23 21 45 D/C NOV-14400
Commissioned 06/14.JAN-123Anpara C - Anpara D 11 11 11 36 S/C JUN-14765
(a) Anpara D - Jhusi section:170 nos. tower foundations out of 541 nos. are heldup as,(i) 45.132 Ha wild life sanctuary is involved. Matter is pending with MoEF sinceDecember 2013, and(ii) 315.716 ha forest land. Proposal was submittd in June 2013.(b) Jhusi - Unnao section: 5 nos tower foundations out of 673 nos. are held updue to pending forest clearance. Proposal for clearance submitted to MoE&F inAugust 2013. Regional office of MoE&F has recommended for stage - Iclearance.
JAN-12416Anpara D - Unnao 1214 1029 944 2557 S/C DEC-14765
Termination point at 400kv s/s Aurai not yet decided. DFCC line crossingbetween loc. 43/0-65/2. River crossing approval pending. 37 no. cropcompensation cases pending. ROW at 15 loc's.
43Aurai - Mizapur 147 126 81 08 S/C NOV-14220
Termination point at 400kV s/s Aurai(PPP) not yet decided. Last 2 Sectionswork held up due to this. ROW at loc. 2/1 , 3/0, 4/0, 5/0, 12/0, 12/1,12/2,17/5,39/3,53/0,53/1, 53/2. The proposed date of complition 28.02.15.
68Aurai - Phoolpur 216 209 194 419 S/C DEC-14220
Gantry at Badaun end yet to be cleared by UPPTCL. Work inturuted due to rain.90Badaun - Sambhal 250 250 242 6610 S/C NOV-14220
Balance 12 No. Fdn hand Seren ROW. The proposed date of complition31.01.15.
(Status of all statutory clearences particularly forest clearence and ROWproblem, if any needs to be mentioned here.)
Towers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hCKM
Ckts(S/C)
&(D/C)
for balance work has been on 'as is where is basis' and as recommended theapproval is send to CSPC on 13.10.14.Contract of the firm M/s Maharashtra Power Transmission Structures Ltd. hasbeen terminated on 20.05.2014 and tenders for balance work has been invitedon 'as is where is basis'.
216Banda - Orai DCQ 295 211 130 014 D/C NOV-14400
.Bara - Karchanna15 D/C 400
64Bara - Meza line 83 83 81 5616 D/C DEC-14400
750Bara TPS - Mainpuri17 2xS/C MAR-15765
Line energised on 26.05.14. Barkhera-pilibhit Section,I ckt. Energisedon10.02.12.II ckt. On 14.2.12
Survey work is under progress.The proposed date of complition 31.10.1560Chhatta - Mathura27 D/C 220
LOI issued to M/s R.S. Infra projects Pvt. Ltd. Remarks Survey completed40Dasna (400) - Faridnagar28 S/C DEC-14220
ROW at Loc No. 18/2, 19A/0, 61/0, 61A/2, 62/0, 63/0,43/1 & 43/2. Rly xingapproval awaited and 116 crop comp. cases not yet paid. River Crossing pilefoundation remaining. The proposed date of complition 31.03.15.
82Deoria - Rasra 250 241 238 7229 S/C NOV-14220
Rly crossing Approval pending for Loc. no 26-27. ROW at Loc No- 31. CropCompensation pending for 55nos com. The proposed date of complition31.01.15.
Work under progress. Progress delayed due to ROW problem and court cases.92Kharagpur - Vidyasagar Park 131 111 77 702 D/C DEC-14220
Work stalled due to poor performance of the vendor.AUG-0820LILO of Arambagh -Rishra at Singur 37 10 2 03 D/C MAY-15220
PGCIL is executing the work as a deposit work of WBPDCL.The work is stalled due to repeated theft. WBPDCL asked PGCIL to take up withthe present vendor for resumption of work or deploy a new vendor by cancellingthe existing contract.
(Status of all statutory clearences particularly forest clearence and ROWproblem, if any needs to be mentioned here.)
Towers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hCKM
Ckts(S/C)
&(D/C)
ESSAR POWER TRANSMISSION CO. LTD. (EPTCL)
78 KM forest involved. Second Stage forest clearance obtained in March'2013.However getting working permission also tree cutting by Forest Departmenthave taken long time. In dec 2013 tree cutting is started,in monsoon work of treecutting was stopped. Now Balance tree cutting is under progress.
(Status of all statutory clearences particularly forest clearence and ROWproblem, if any needs to be mentioned here.)
Towers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hCKM
Ckts(S/C)
&(D/C)
JHABUA POWER LTD. (JHAPL)
Forect Clearance required for 4.4 Ha (4 no. foundation) stage-I approvalreceived. Money for aforestation has been depostied and Stage-II approval, tobe issued from Bhopal is being expecdited. Railway and Highway crossingapprovals received
131Jhabua Power TPS - Jabalpur Pooling Station, (Highcapacity line).
207 150 135 101 D/C DEC-13400
.Termination of Jhabua Power TPS ¿ Jabalpur PoolingStation, at Jablpur (PG) as Interim arragement
(Status of all statutory clearences particularly forest clearence and ROWproblem, if any needs to be mentioned here.)
Towers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hCKM
Ckts(S/C)
&(D/C)
JOINT VENTURE OF PGCIL & JAYPEE (JV(PG&JP))
D/C line upto common point on D/C tower (14 km). work for common point toBina (PG) s/C completed (6km)and work for common point to Bina(MPPTCL) isin progress(6km).
40Bina TPS - Suitable location (along Bina (PG) - Bina(MPPTCL)
1 D/C JUL-12400
.Termination of Ckt of above at Bina (PG) & otuer ckt atBina (MPTCL)
(Status of all statutory clearences particularly forest clearence and ROWproblem, if any needs to be mentioned here.)
Towers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hCKM
Ckts(S/C)
&(D/C)
Kudgi Transmission Company Limited (KTCL)
Survey activity is stopped by villagers of Honnudike and Hobli Gulur villagefalling under Tumkur (Taluk & District) (Effected span: Approx. 2 KMs.)Matter is brought to the notice of District Administration.
36Kudgi TPS - Narendra 46 7 5 01 2xD/C SEP-15400
The villagers are not allowing for any construction work at the respectivelocations and asking for huge compensation.Matter is brought to the notice of District Administration. These locations arenearer to 400/220 kV POWERGRID Bidadi substation. Being terminating point,no alternatives available for re-routing the line.
(Status of all statutory clearences particularly forest clearence and ROWproblem, if any needs to be mentioned here.)
Towers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hCKM
Ckts(S/C)
&(D/C)
NORTH EAST TRANSMISSION CO. LTD. (NETC)
2 tower locations handed over in Aie- Valley by Assam Forest Deptt. after cuttingof 44no of trees on 05.07.2014. Construction of one foundation completed andtower erected.Construction of 2nd foundation commenced and expected by15.11.2014.Completion of 2nd tower erection and stringing expected to becompleted by 30.11.2014.1st stage forest clearance for 2 tower locatons received on 04.09.2014.Necessary payments towards NPV, CA,etc submitted to DFO,GoalparaDivision,Assam on 29.09.2014. Completion of 2 foundations, tower erection andstringing shall take 2 months after 2nd stage forest clearance and handing overof the land by Assam Forest Deptt.
398hec.of forest involved covering 400locs. and 125kMs of route length. FACapproved for both the proposals (M.P. & Chattisgarh) and proposals are pendingwith Minister (MoEF) New Delhi.The element is affected by Force MajeureEvent.Petition No. 73/MP/2014 has been filed in CERC for force majeure &change in law.
39hec.of forest involved in Gujarat and 17hec.in Maharastra.Stage -I clearanceobtained for Maharashtra & Gujarat forest.The element is affected by Force Majeure event vide our letter dated 03.02.2014.1)Excise duty has been increased from 8% to 12% as intimated earlier report.2)Our Dhule Substation has been declared deemed commissioned from 07 thOctober 2014.3)Dhule Dhule transmission line has been declared deemed commissioned from07th Oct2014 as MSTCL bay is not ready for connecting the line.
The Element is affected due to force majeuere for delay in section 164 & forestclearance vide our letter dated 03.02.2014 to all LTTC's.1)Our Bhopal- Bhopal line has been declared deemed commissioned from 29thJune 2014 & Bhopal Substation has been charged on 29th June 2014.2)Bhopal Indore is intent to charge on 19th Nov2014.3)Excise duty has been increased from 8% to 12% as intimated earlier report.
Severe RoW problem in 4locs.& 140hec.forest land in MP involved.Forest proposal with MOEF Delhi & FAC cleared .The element is affected byForce Majeure event.Excise duty has been increased from 8 % to 12%.PetitionNo. 73/MP/2014 has been filed in CERC for force majeure &
237Jabalpur - Bina (JTCL) 610 551 548 1879 S/C FEB-15765
(Status of all statutory clearences particularly forest clearence and ROWproblem, if any needs to be mentioned here.)
Towers
TL(Nos)
STC(Nos)
TE(Nos)
STG(cKM)
VoltageLevel
4.
SlNo
Name ofTransmission
Lines
TotalLengt
hCKM
Ckts(S/C)
&(D/C)
change in law.
Force Majeure event: Delay in forest clearance.Transmission licensee grantedby CERC.Tariff adoption granted by CERC.Project execution plan submitted to CEA & lead LTTC.Kharagpur S/s &Chaibasa S/s bays orientation has been shifted & project has been delayed dueto shifting of bays.Resurvey has to be done for route & forest identification .
Khaigapur (WBSETCL) - Chaibasa (PG)10 D/C 400
Force Majeure event: Delay in forest clearance.Transmission licensee grantedby CERC.Tariff adoption granted by CERC.Project execution plan Project execution plan submitted to CEA & leadLTTC.Purulia S/s & Ranchi S/s bays has been shifted & project has beendelayed due to shifting of bays.Resurvey has to be done for route & forestidentification .
370Purulia PSP (WB) - Ranchi (PG)11 D/C APR-16400
.Force Majeure event: Delay in forest clearance.Transmission licensee grantedby CERC.Tariff adoption granted by CERC.Liberty for extension of COD and additional tariff granted by CERC. TSP hasstarted the work.Project execution plan submitted to CEA & lead LTTC.