Top Banner
NGAO discussion: NGAO discussion: Science Operations Science Operations NGAO Meeting #4 NGAO Meeting #4 D. Le Mignant D. Le Mignant 22 Jan. 2007 22 Jan. 2007
24

NGAO discussion: Science Operations

Jan 02, 2016

Download

Documents

gail-porter

NGAO discussion: Science Operations. NGAO Meeting #4 D. Le Mignant 22 Jan. 2007. Outline. Words of introduction on the topic Lessons learned Weather impact Efficiency - weather removed The good things here at Keck The good things .. elsewhere Top-level goals for science operations - PowerPoint PPT Presentation
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: NGAO discussion: Science Operations

NGAO discussion:NGAO discussion:Science OperationsScience Operations

NGAO Meeting #4NGAO Meeting #4D. Le Mignant D. Le Mignant 22 Jan. 200722 Jan. 2007

Page 2: NGAO discussion: Science Operations

2

Outline1. Words of introduction on the topic2. Lessons learned

1. Weather impact2. Efficiency - weather removed3. The good things here at Keck4. The good things .. elsewhere

3. Top-level goals for science operations1. Science return 2. Facility-class3. Long-term operations

4. Observing efficiency (and uptime)1. Proposed definitions2. A spiritual agreement

5. Observing models and science data products1. Instrument calibrations, maintenance and performance monitoring2. Automation and flexibility during the observations3. Facility science calibrations4. Planning for science beyond our reach

6. Conclusion and Discussion

Page 3: NGAO discussion: Science Operations

3

Science operations:an important point.. too!

• Science Operations Design choices have a very major impact: – On the design/cost of the AO/Laser and science instruments – On the observing model for the observers– On the science return – On the observatory budget 2010-2020 (see NSF review)– On the Observatory future priorities

• Work in progress– WBS 2.2.3 Observatory Requirements:

• Science Operations Requirements– WBS 3.1.1.11 System Design Approach / System Engineering / Performance Budget

• Observing Efficiency and Observing Uptime– WBS 3.1.2.1.10 System Design Approach / System Engineering / Trade Studies

• Observing Models TS– WBS 3.4.2 System Design Approach / Science Operations

• AO-Instrument operations

Page 4: NGAO discussion: Science Operations

4

Observatory RqtsScience Operations

Science Requirements

Observing Scenarios

Observing Models TS

Observing Efficiency Budget

System Design Approach System Engineering Science Operations Performance budget Trade Studies

3.4.2.1 AO-instruments Ops

Functional and Performance Requirements

Lessons Learned…

Page 5: NGAO discussion: Science Operations

5

101 nights of Keck II LGS AO ops

since Nov. 04 till Jul. 06

Lessons Learned

Page 6: NGAO discussion: Science Operations

6

Lessons learned: weather• From our statistic: ~25% of the allocated time

~18 % are entire nights close dome situation

~ 7% marginal weather affecting 1/5 of the open-dome nights

-> Only ~60% of the nights are ~photometric nights

• Looking at other statistics:- Study for New Initiatives AURA office (Erasmus and van Staden)

- ESO site search (ESPAS, 2003)- www.eso.org/gen-fac/pubs/astclim/espas/espas_reports/ESPAS-MaunaKea.pdf

- Kaufmann and Vechhione (1981)

Observing quality Photometric “Spectroscopic” unusable Usable

Frequency of occurence (%)

45 - 55 17 - 22 20 -25 ~ 70-75%

Page 7: NGAO discussion: Science Operations

7

Kaufmann and Vecchione (1970-1978)

Page 8: NGAO discussion: Science Operations

8

Weather impact:• From ESPAS and AURA report on Mauna Kea:

– Usable nights with LGS < 75%:• About 55% of the nights are >6h of photometric conditions) • An additional fraction 10-15%? are likely usable with LGS (light cirrus)• The maximum of usable time is around 2/3 of the time (240 n/yr)

– Photometry:• Best months are Jan and Feb.• Worst months are October and April

– Winds:• A few nights (~3-4%) are affected by very strong winds• Winds ENE-ESE in the summer, more W and SW in winter

– Seeing • Seeing is considered the best for the existing astronomical sites (0.5”)• Seasonal trends?

– Global warming (long term trend)• 3.7deg / century for Mauna Loa

• Should the science operations takes this information in consideration and study the feasibility of more flexible schedule?

– Increase observing efficiency– Reduce observing support load (?)

Page 9: NGAO discussion: Science Operations

9

Lessons Learned: overheads are too much

1. LGS AO checkout

30min/night

2. Telescope slew and pointing

3. Target ID and centering

4. LGS AO readiness

5 - 10 min/target

5. LGS AO optimization

2min per hour on target

6. Telescope/AO handshakes

30+ sec per dither

7. Scientific instrument setup and readout

Observing strategy

Ref: 2006 SPIE papers and some Keck internal discussion for K1 LGS AO

Page 10: NGAO discussion: Science Operations

10

Lessons learned: Observing Efficiency• Keck NGS AO observing efficiency for nights w/o weather or technical

problems at best vary from 25% (snapshot surveys, Lp and Ms obs) to 60-80% for deep-exposure science programs.

• LGSAO shows roughly the same values, except that it is more impacted by weather and technical problems

For a reliable system in good weather conditions, we are currently mostly limited by

1. Serial (vs parallel) algorithms (DCS /inst/AO) during observations2. Under-designed telescope pointing and acquisition systems3. Under-designed AO nodding/dithering hardware and software4. Under-designed science instrument readout5. Aging (WFC) and/or complex instrumentation (laser)6. Under-designed ancillary systems (photometry, seeing, PSF, etc)7. Minimal maintenance, calibrations and performance monitoring for

science instruments, AO and laser 8. Operations (Laser traffic rules, overall cost including energetic)

Page 11: NGAO discussion: Science Operations

11

Lessons learned: some Keck goodies…

• A flexible and (rather) small community – Ability for observers to combine their observing time– Close interaction between observers and support staff

• Science Instruments– Ability for observers to try new observing modes (“push the limits”), and/or calibrate for

problems they discover.– Possibility to script for simple instruments like NIRC2– New generation of observing software with OSIRIS: OPGui and DRP

• AO / Laser– A best-effort / shared-risk science mode – Ability to optimize (and keep optimizing..), except for the telescope.– Proximity to the instruments for troubleshooting

• Community Experience:– Development, integration of new concepts on large telescope (Keck!, LGS, etc)– New-generation of instrument: OSIRIS, etc– Archive (KOA)

Page 12: NGAO discussion: Science Operations

12

Lessons learned: other observatories’ goodies• A flexible scheduling of the instruments:

– Instrument failures has less impact on observing efficiency– Management of observing and eng. time w.r.t. observing conditions

• Instrumentation Management– Strict review for integration, testing and commissioning processes– High-quality maintenance and calibrations

• All instruments have maintenance schedules with archived calibrations• Easier traceability of problems/trends

• Scientific Operations– Integrated operations

• Automated telescope acquisition (Magic?)• Observing planning tool (obs. seq., AO/inst. config, performance estimate)• Observing sequence templates for instruments / telescope

– Facility calibrations • Flat-field, astrometry, photometry, etc • Ancillary data are archived

– Archived science data for long term use– Data reduction pipeline and support.– Service observing ??

Page 13: NGAO discussion: Science Operations

13

Observatory RqtsScience Operations

Science Requirements

Observing Scenarios

Observing Models TS

Observing Efficiency Budget

System Design Approach System Engineering Science Operations Performance budget Trade Studies

3.4.2.1 AO-instruments Ops

Functional and Performance Requirements

Page 14: NGAO discussion: Science Operations

14

Science Operations Goals for the Next Generation of AO instruments at Keck

(2012 - 2020)The spirit:

“Maximize the scientific return of the allocated observing time with the NGAO instruments from 2012 to 2020”

Top-level goals:1. More than 80% of the time allocated is spent on collecting science-quality data.2. The NGAO system combined with its science instruments is a facility-class

instrument. 3. The Observatory is capable of supporting the equivalent of 240 nights/year for

NGAO science operations.

…btw, are we including the interferometer?..!-)

Page 15: NGAO discussion: Science Operations

15

Some flow-down thoughts 1 - More than 80% of the time allocated should be spent on

collecting science-quality data. 1. Software should permit simultaneous commands to multiple sub-systems, as well as within a

sub-system2. The time allocation method and the Keck science operations model should minimize the average

impact due to lost time from bad observing conditions year-round 3. A heck of an efficient and skilled astronomer!4. > 80% observing efficiency & uptime > 98% ?5. Science instrument performance (image quality, sensitivity, observing efficiency and calibration

stability) are documented, simulated, and monitored by the observatory on a routine basis. 1. The simulation tools should provide key-parameters with a 10 % accuracy within a range of observing

conditions and instrument setup.2. The relative astrometry solution error over the field of view should be less than 2% of a pixel. The

pointing and positioning accuracy error on the science field should be known with an error less than 20% of the measured FWHM.

3. The relative and absolute photometry should be monitored throughout the observations with a precision of xx % at the observed wavelength.

6. Etc

Page 16: NGAO discussion: Science Operations

16

Some flow-down thoughts 2 - The NGAO combined with its science instruments is

facility-class instrument.

1. Facility-class has many implications on safety, operability, reliability, maintainability, lifetime, documentation, configuration management, etc.

2. Sustainability 1. Sustainable development program for the instrument?

2. Observatory cost for the operations (including energetic cost)

3. The Mauna Kea laser projection requirements must be satisfied

4. The NGAO installation, integration, testing and commissioning phases should follow the highest Observatory standards and be reviewed by the Keck community:

5. Interferometer- & Ohana- related requirements:a) NGAO should support IF and Ohana science operations

b) The interferometry modes should not require the NGAO light path for optical alignment in the basement.

Page 17: NGAO discussion: Science Operations

17

Some flow-down thoughts 3 - The Observatory is capable of supporting the equivalent of

240 nights/year for NGAO science operations.

1. Auto-calibration for NGAO performed by non AO-experts. 2. < 30 minutes of daytime telescope restriction on a science night.3. < 30 minutes per observing night for maintenance and science instrument performance calibrations.4. Observing tools:

1. Simulation module (telescope, natural and laser stars) for calibrating and troubleshooting the AO system, as well as a stable and accurate calibration module (wavelength, flat-field, field distortions, sensitivity) for the science instruments.

2. Atmospheric parameters and system diagnostics for image quality monitoring and PSF reconstruction.

5. A heck of a observing support team:1. Expandable and flexible library of observing sequences for each instrument/type of science/etc. Support

astronomer review the observing sequences prior to the observations. The SA will be on-call and may be present during the observations.

2. The science instrument should be operated remotely or on-site by one Observer or a Support Astronomer.3. The telescope, the AO & laser facility should be operated by two or less Observing Assistants (or

equivalent skills).

Page 18: NGAO discussion: Science Operations

18

Observatory RqtsScience Operations

Science Requirements

Observing Scenarios

Observing Models TS

Observing Efficiency Budget

System Design Approach System Engineering Science Operations Performance budget Trade Studies

3.4.2.1 AO-instruments Ops

Functional and Performance Requirements

Page 19: NGAO discussion: Science Operations

19

Observing Efficiency: we care defining it!

The Observing Efficiency is the open shutter time during dark time when the instrument runs at the performance level where it is designed to operate, for the given observing conditions.

• We care for loss of science return - no matter what!– Observing efficiency is linked to science return during the allocated time (hence weather

and seeing impact should be considered)?

1. Marginal weather accounting: time loss or not, NGS AO data useful or not, etc 2. Idea of allocating few nights by TAC: highest ranked proposal gets best conditions,

etc3. Understanding observing efficiency for NGAO may require tagging the various sets of

data (science, calibrations, etc). 1. Which part of the calibrations are part of the science-quality data?2. Need for facility calibrations

4. Efficiency per brain cell (the best use of everyone's time by not having to re-invent the wheel over and over).

Page 20: NGAO discussion: Science Operations

20

Observing efficiency and uptime (2)A spiritual agreement

1. The time allocation method and the Keck science operations model should minimize the impact due to lost time year-round.

2. Quicker, better slews, setups and moves:1. Smaller telescope pointing error (<2 arcsec?), fast telescope slews (xdeg/min).2. Faster target acquisition and accurate centering on science array3. Faster dither, parallel readout, faster on-line data viewer.4. Fast chopper (few Hz) for thermal NIR imaging? Software permits simultaneous

commands to multiple sub-systems, as well as within a sub-system, in order to minimize time overhead during telescope dither, telescope slew, target acquisition, instrument setup, instrument data readout, etc.

3. The Observatory manages instrument calibrations & performance at a high-quality level.

4. The Observatory provides simulation, planning tools, observing templates, etc.5. The PIs are responsible for performing their observations, given these tools.

• Mean-time-between **any failure mode** should be > 3 hour?• Instrument uptime should remain higher than 98% through the night (12 min)?

Page 21: NGAO discussion: Science Operations

21

Observatory RqtsScience Operations

Science Requirements

Observing Scenarios

Observing Models TS

Observing Efficiency Budget

System Design Approach System Engineering Science Operations Performance budget Trade Studies

3.4.2.1 AO-instruments Ops

Functional and Performance Requirements

Page 22: NGAO discussion: Science Operations

22

Observing Models Preliminary thoughts…

Scheduling

Mode

Ownership

Mngmnt

Science Programs

Weather

Impact

Backup

options

Classical

night/night

PI

PI

1 .. 3

flexible

high NGS AO

NIRSPEC

Night blocks per TAC

TAC

TAC/Keck

1… 5

flexible

Medium

to

Low

NGSAO

NIRSPEC

DEIMOS

Engin.?

NGAO-only

Queue

PI

Keck

1… 5

flexible

Low Iden.

Keck

Queue ??

PI

Keck

1..10

Flexible

Low Iden.

Page 23: NGAO discussion: Science Operations

23

Science data-products Preliminary thoughts…

Science

+ Specifics

Calibration

Support

Ancillary data

Data reduction

Archive

Monitoring

Classical observer Observer no minimum No

So-so

Plus Observer Observer

Archived

Yes minimum Calibrations

Advanced Observer Observatory Yes Minimum

calibrated

Cals+science

performance

Service Observatory Observatory Yes calibrated Cals+science

performance

Page 24: NGAO discussion: Science Operations

24

Conclusion• Next steps:

1. Help build the Observing Scenario Spreadsheet

2. Discussion and feedback: observing modes and science operations are not very well documented.

3. Propose to delay:1. From the WBS Dictionary (3.4.2.1): Define the overall architecture, the method and design the

interfaces for operating the sub-systems of the NG AO-instrumentation. Here AO-instrument refer to AO, laser, SC, science instrument, etc.

2. Discuss operations team's strategy for structuring the remainder of the SD phase tasks under 3.4.2.1

4. More work in many areas. One main challenge: coordinating the work with Keck and the science community, while staying in the numbers of allocated hours.