Next Generation Composite Manufacturing (Composites Large Scale Project – CLSP) Contact : [email protected] Hannah Tew Paul Gallen HVM Catapult 21 st June 2018
Next Generation Composite Manufacturing
(Composites Large Scale Project –CLSP)
Contact : [email protected]
Hannah TewPaul GallenHVM Catapult21st June 2018
HVM Catapult mission
The HVM Catapult is the catalystfor the future growth and success
of manufacturing in the UK.
HVM Catapult help accelerate new concepts tocommercial reality and thereby createa sustainable high value manufacturing
future for the country.
What we do
Drive growth of manufacturing
Help companies of all sizes incubate and develop new technologies to commercial reality
Take the risk outof innovation
Give business access to:
— World class open sourced equipment
— The UK’s best relevant research knowledge
— At elbow support from engineers, scientists, technicians
— An environment of collaboration andopen innovation• Cross sector• Cross technology• Whole supply chain• Even among direct competitors
AFRC
Nuclear AMRC
MTC
NCC
CPI
AMRC
WMG
HVM Catapult centres
Introduction and Background
• The Next Generation Composite Manufacturing (CLSP) programme aims to support a globally competitive UK automotive composites supply chain from 2020 onwards:
• To capture ongoing value
• To identify and link high productivity technologies with product opportunities
• Leverage cross-sector opportunities and support from significant market changes.
• High Value Manufacturing Catapult (HVM Catapult) is providing collaboration and co-ordination support
• Industrial Strategy Challenge Fund Wave 3 (April ‘18) identified as a funding source to deliver objectives
Implication of the Revolution in Future Mobility Trends
Connected Electric
Autonomous Shared
Weight increases
Drivers for Lightweighting in Transport
RangeCleaner –
emissions targets
Industrial opportunity
Performancedemands
Lightweighting
2016 2020 2025
VehicleMass
New contentNew features (self-steering, ADAS)
Legislation (small overlap crash)~ +5% increase per decade
Hybrid:+10% vs today
CHALLENGEAVERAGE weight reduction of
existing systems must be:10-15% per decade
CHALLENGETYPICAL on-cost not to exceed
£2.50 to £5 per kg of weight saved
Weight Challenge10-15% / decade
UK Automotive Lightweighting Opportunity
CHALLENGEEXISTING vehicle end of life recycling
target requires> 85% recyclability
Programme Mission – Composites in Automotive
Identifying, developing and transforming the UK supply chain for competitive high volume manufacturing of composites for automotive applications and allied markets.
Auto Council TARGET 2025AVERAGE weight reduction of existing
systems of 15%
ACG TARGET 2025TYPICAL on-cost not to exceed £5 per
kg of weight saved
ACG TARGET 2025EXISTING vehicle end of life recycling
> 85% recyclability
ACG TARGET 2025TYPICAL takt time 60s
Global automotive composite prediction (Persistence Market Research)
UK automotive composite prediction (DIT)
Upper
Lower
POTENTIAL MARKET IMPACT £3.5 bn p.a. by 2030
UK supply chain globally competitive
In place for window of opportunity
Lightweighting roadmaps for Automotive
Lightweighting in roadmaps for Aerospace
Project to Programme
Composites Large Scale Project
• Existing £4M project
• Lead by HVM Catapult
• Four centre collaboration
• Focus on High Efficiency Preforming
Next Generation Composite Manufacturing
• Extended £10M ++ project
• Lead by Industry
• 5 OEM’s, 40+ suppliers, 4 HVM Catapult centres
• Focus on supply chain transformation
19th July 2016
CLSP - the facts (so far…)
>30 engineers contributed to CLSP technical activities
4.5 year projectAug 2015 – March
2020
4 HVM Catapult Centres collaborating
~£100 M ISCF wave 3 EOI submitted
UK Composite Cluster developed
> £10 M of relevant CR&D activity across 4
centres
Senior stakeholders involved
BEIS, DIT, InnovateUK, APC, ATI
8 automotive OEMs engaged
• 1 academic paper• 5 academic conference
papers• 8 external conference and
workshop presentations
2 self generated bids submitted by SMEs in
cluster
Cross- sector engagement
(Aero and ATI)
£3.3 M of HVM Catapult funding
Intervention planning underway
International engagement in
progress7 Universities aligned
36 LoS from stakeholders for ISCF
wave 3 bid
Next Generation Composite Manufacturing Overview
• Technology “Pooling” of non IP-protected data and knowledge to accelerate development
• Enabling activities running in parallel and cross-cutting within the demonstrator work-streams:
• Design, modelling & simulation
• Automation
• Cost modelling
• Quality assurance
• Material characterisation
• Capability demonstrator components to showcase selected technologies in OEM relatable applications
• OEM & Tier 1 led scale up projects co-funded through APC to demonstrate the readiness level of the supply chain in manufacturing the demonstrator components at rate, cost and repeatability
CLSP Advisory Group
…….Potential for other OEMS (cross-sector) to join this group
*non-exhaustive list
Cost & Process modelling.
Automation, Digital Manuf. and rate increase support
Cluster support
Aspirations and Gaps understood
Technology matching
Demonstration of Capabilities(Prototypes, processes, supply chain, digital manufacturing and high value design)
“Pool” of competitive manufacturing
technologies and knowledge
Scaled Industrialisation
OEM & T1 specific projects
• Delive
£10M Challenge
£20M APC
EOI Summary: Next Generation Composites Manufacturing
OEM relevant generic demonstrator
components identified
Representative attributes derived:
VolumeCostRate
QualityWeight
Properties
Existing UK composites supply-chain
capabilities and capacity understood
Highly competitive value chains identified Up to £20M
Funding
UK Supply Chain Development
Technology Development
ComponentDevelopment
Early OEM Engagement
BRUNEL CHALLENGE & “MADE SMARTER”
Design & CAE tools advanced
Long-term high value capture, competitive and innovative UK manufacturing, adoption of productive technologies
OUTCOMES& BENEFITS
Demonstrator – Roof Structure
• Large window apertures
• Monolithic structure
• Variable thickness
• Channelled geometry
• Packaging constraints
• Conventional fixing strategy
• Integration of features – clips, brackets
• E-coating Temps 180C (30 mins)
• Size: ≈ 1.4 × 1.8 m
60 sec Takt time
95% Recyclable
Aim for Zero material waste produced
20-50% Lighter than benchmark
£5/kg weight saved on cost
Demonstrator – Floor Section
• Complex curvatures
• Variable thickness
• Sandwiched cores
• Flexural and torsional rigidity of the car
• Seat and seat-belt mounting points
• Integration of features – clips, brackets
• E-coating Temps 180C (30 mins)
• Size: ≈ 2.5 × 2.0 m
120 sec Takt time
95% Recyclable
20-50% Lighter than benchmark
£5/kg weight saved on cost
Demonstrator – Cross-Car Beam
• Multi-component structural member
• Bolt-in / glue-in
• Closed-section beam
• Geometrically complex end parts
• Conventional attachment strategy
• Crash management
• Tight tolerances
• Integration of features – clips, brackets
• E-coating Temps 180c (30 mins)
• Size: ≈ 1.5 m long
120 sec Takt time
95% Recyclable
20-50% Lighter than benchmark
£5/kg weight saved on cost
Demonstrator – Gearbox / E-motor Case
• Multi-material part
• Fine geometric tolerances
• Compatibility with a range of fluids
• High temperatures
• Dynamic loads
• Size: ≈ 0.5 × 0.3 × 0.3 m
120 sec Takt time
95% Recyclable
20-50% Lighter than benchmark
£5/kg weight saved on cost
HVM Catapult Capabilities – Reinforcement Architecture
HVM Catapult Capabilities – Preform and automation
HVM Catapult Capabilities - Consolidation
Programme Outcomes
• Secure ISCF funding support or equivalent for programme with APC and industry match.
• UK maintains global position in automotive composites, but with higher productivity supply chain delivering to OEM requirements.
• Improved GVA and local content to address “rules of origin” issues.
• Transformation of the UK automotive composites supply chain into globally competitive cluster.
• Pull through capacity for further improvements in materials science, intermediates, virtual engineering and processing.
Contact: [email protected] Our request to you• Get in touch if you are interested and are not
already engaged