New North Atlanta High School Weekly Construction Report September 27 th , 2013 Page 1 NNAHS Weekly Progress Report September 27, 2013 THIS WEEK September 23, 2013 – September 27, 2013 Hillside Building: Completion in end of November, 2013 Picture 1: Hillside letters installed Picture 2: Retaining wall by softball field nearing completion Picture 3: Stage lighting nearing completion Picture 4: Gymnasium concourse ceiling grid installation
4

New North Atlanta High School Weekly Construction Report · New North Atlanta High School Weekly Construction Report September 27 ... New North Atlanta High School Weekly Construction

Jul 05, 2019

Download

Documents

dokhanh
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: New North Atlanta High School Weekly Construction Report · New North Atlanta High School Weekly Construction Report September 27 ... New North Atlanta High School Weekly Construction

New North Atlanta High School

Weekly Construction Report September 27th, 2013

Page 1

NNAHS Weekly Progress Report September 27, 2013

THIS WEEK September 23, 2013 – September 27, 2013

Hillside Building: Completion in end of November, 2013

Picture 1: Hillside letters installed Picture 2: Retaining wall by softball field nearing completion

Picture 3: Stage lighting nearing completion Picture 4: Gymnasium concourse ceiling grid installation

Page 2: New North Atlanta High School Weekly Construction Report · New North Atlanta High School Weekly Construction Report September 27 ... New North Atlanta High School Weekly Construction

New North Atlanta High School

Weekly Construction Report September 27th, 2013

Page 2

NNAHS Weekly Progress Report September 27, 2013

Hillside Building (cont’d): Completion in end of November, 2013

Picture 5: Acoustic panels installed in gymnasium Picture 6: Lockers installed in gymnasium locker rooms

Picture 7: Coaches bathrooms nearing completion Picture 8: Gymnasium painting

Page 3: New North Atlanta High School Weekly Construction Report · New North Atlanta High School Weekly Construction Report September 27 ... New North Atlanta High School Weekly Construction

New North Atlanta High School

Weekly Construction Report September 27th, 2013

Page 3

NNAHS Weekly Progress Report September 27, 2013

Hillside Building (cont’d): Completion in end of November, 2013

Picture 9: Proscenium scrim panels installed in auditorium Picture 10: Auditorium concession appliances installed

Picture 11: VCT installed in auditorium corridor Picture 12: Gymnasium storefront installation

Page 4: New North Atlanta High School Weekly Construction Report · New North Atlanta High School Weekly Construction Report September 27 ... New North Atlanta High School Weekly Construction

New North Atlanta High School

Weekly Construction Report September 27th, 2013

Page 4

NNAHS Weekly Progress Report September 27, 2013

NEXT WEEK

September 23 – September 27, 2013

Auditorium Beginning millwork at stage.

Continuing orchestra pit net installation.

Continuing mainstreet tile.

Continuing speaker installation.

Finishing auditorium corridor VCT. (picture 11)

Finishing mainstreet lighting

Finishing proscenium scrim panels at theater stage. (picture 9)

Finishing dance room mirrors and ballet barres.

Finishing stage lighting installation. (Picture 3)

Finishing auditorium corridor ceiling tile. (Picture 4)

Gymnasium Beginning basketball court wood flooring.

Beginning tile installation in coaches’ bathrooms. (picture 7)

Continuing gymnasium door hanging.

Continuing gymnasium paint. (picture 8)

Continuing polishing concrete flooring in gymnasium.

Continuing railings at concourse.

Continuing acoustic panels in gymnasium (Picture 5)

Finishing locker installation. (picture 6)

Finishing epoxy floors in bathrooms.

Finishing athletic storage cages and sealing floors.

Sitework Beginning discuss cage (picture2)

Beginning tree planting

Beginning concrete flatwork at north end of gymnasium.

Continuing sidewalks between concessions building, softball field and tennis courts.

Continuing irrigation at softball and baseball field.

Finishing installation of coping on roof.

Finishing plaza paving.

Finishing coping on roof