PROJECT MANAGEMENT (PM) Ismael Torres-Pizarro, PhD PE Esq. 1
296

My MBA Course on Project Quality Management

Dec 08, 2014

Download

Business

This is the main presentation for the MBA course I teach on Project Quality Management. It is based on a combination of the Critical Chain Approach by Dr Goldratt, the PMBOK (chapter 8) plus my own experience as Sr Validation Project Manager, Lawyer & US ARMY Officer
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: My MBA Course on Project Quality Management

1

PROJECT MANAGEMENT (PM)

Ismael Torres-Pizarro, PhD PE Esq.

Page 2: My MBA Course on Project Quality Management

2

What is a Project?• A plan, a proposal, a scheme– An undertaking requiring coordinate effort– A set of activities aimed to achieve a specific

objective with a clear start, middle and end.

Page 3: My MBA Course on Project Quality Management

3

PMI Defines a “Project” as

• A temporary group activity designed to produce a unique product, service or result.– temporary: it has a defined beginning and end in time, and therefore

defined scope and resources.– Unique: it is not a routine operation, but a specific set of operations

designed to accomplish a singular goal. So a project team often includes people who don’t usually work together – sometimes from different organizations and across multiple geographies.• The development of software for an improved business process, the

construction of a building or bridge, the relief effort after a natural disaster, the expansion of sales into a new geographic market — all are projects.

– And all must be expertly managed to deliver the on-time, on-budget results, learning and integration that organizations need.

Page 4: My MBA Course on Project Quality Management

4

Project Management is…

Page 5: My MBA Course on Project Quality Management

5

PMI Defines “Project Management (PM) ” as

• the application of knowledge, skills and techniques to execute projects effectively and efficiently. It’s a strategic competency for organizations, enabling them to tie project results to business goals — and thus, better compete in their markets.– It has always been practiced informally, but began to emerge as a

distinct profession in the mid-20th century. PMI’s A Guide to the Project Management Body of Knowledge (PMBOK® Guide) identifies its recurring elements.

– Project management processes fall into five groups:• Initiating • Planning • Executing • Monitoring and Controlling • Closing

Page 6: My MBA Course on Project Quality Management

6

Project management knowledge draws on ten areas:

Integration Scope Time

Cost Quality Procurement

Human resources Communications Risk management

Stakeholder management

Page 7: My MBA Course on Project Quality Management

7

PMI Defines “Project Quality Management (PM) ” as

• The processes and activities of the performing organization that determine quality policies, objectives, and responsibilities so that the project will satisfy the needs for which it was undertaken. – Uses policies and procedures to implement, within the

project’s context, the organization’s quality management system and, as appropriate, it supports continuous process improvement activities as undertaken on behalf of the performing organization.

– Works to ensure that the project requirements, including product requirements, are met and validated.

Page 8: My MBA Course on Project Quality Management

8

Implications of Poor PM• Project Performance – ability to match pre-determinate criteria.• Project lead time?• Project budget?• Project scope?

• TEXT CASE FOR SUCCESSFUL PM: U2 (“Dragon Lady”) CIA + NSA Spy plane???

Page 9: My MBA Course on Project Quality Management

9

Page 10: My MBA Course on Project Quality Management

10

Organizations related to PM Quality

• ASQ • https://www.facebook.com/ASQ

– Puerto Rico chapter• https://www.facebook.com/groups/9311093119/

• PMI– https://www.facebook.com/PMInstitute

• Puerto Rico chapter– http://www.pmipr.org/

Page 12: My MBA Course on Project Quality Management

12

Some concepts (2013)• Critical Path Method (CPM): an optimization

algorithm for scheduling the set of project activities developed in the late 1950s by Morgan R. Walker of DuPont and James E. Kelley, Jr. of Remington Rand.

• Program (or Project) Evaluation and Review Technique (PERT): a statistical tool designed to analyze and represent the tasks involved in completing a given project. Developed by the US Navy in the 1950s, commonly used with the CPM.

• GANTT chart: a type of bar chart, developed by Henry Gantt in the 1910s, that illustrates a project schedule.

Page 13: My MBA Course on Project Quality Management

13

Standish Study IT (1990’s)• 30% of all project are cancelled before completion.

– Run out of steam!!!• Most projects scope are cut down to get something done

– Leave technical features out for the next product release/version– Aspect considered “less important” or reduced quality/reliability

• 75% of all projects are finished late• Average over run time is 222%

• ie, a project estimated to end in 1 year takes, on average, approximately 3 years 2.2 months to end

• Average over run budget is 189% of original estimate• ie, a project estimated to cost in $1 million, on average,

approximately final cost is $2.89 millions

Page 14: My MBA Course on Project Quality Management

14

Page 16: My MBA Course on Project Quality Management

16

Typical “solutions”• More detailed planning (Better plan).

– Assumes we can control most of the uncertainties• Re-plan more frequently

• Assumes we cannot control most of the uncertainties

• Assign more project managers to smaller bits of the project– Assumes we can control when we have less to control

• Buy software!!!• Assumes we can control when we have better tools to control

• Assign better project managers to smaller bits of the project– Assumes the issue is poor control; control should be at higher level

management• Assign accountability down

• Assumes the issue is poor control; control should be at lower level management

Page 17: My MBA Course on Project Quality Management

17

So, What the ^*% is “control”???• A system used to maintain a desired output.• A reactive mechanism to handle uncertainty by

monitoring information that points to a threatening situation and taking corrective actions accordingly (Eli Schragenheim)

• Any control mechanisms should have a clear idea what kind of threats it tries to spot

– It is not responding AFTER the problem has done damage; it is to find area of risk and respond BEFORE the damage could occur.• Risk: uncertainties, threats

Page 18: My MBA Course on Project Quality Management

18

Implicit concepts with “control

• “Strategy”& Tactics”– Strategy: What you do to get a date– Tactics: What you do at the date

• Measurement of important variables is needed

Page 20: My MBA Course on Project Quality Management

20

Example: PLANNED ORGANIZATIONAL CHART

Page 21: My MBA Course on Project Quality Management

21

Example: REAL ORGANIZATIONAL CHART

Page 22: My MBA Course on Project Quality Management

22

No plan survives contact with the enemy…Gen. Von Moltke

• Theory of Constraints (TOC)– a management approach that views system as

being limited in achieving its goals by a very small number of constraints. • There is always at least one constraint, and TOC uses a

focusing process to identify the constraint and restructure the rest of the organization around it.

"a chain is no stronger than its weakest link".

Page 23: My MBA Course on Project Quality Management

23

TOC

• Introduced by Dr. Eliyahu M. Goldratt in his 1984 book titled The Goal, geared to help organizations continually achieve their goal. – Goldratt adapted the concept to PM with his book

Critical Chain, 1997.

Page 24: My MBA Course on Project Quality Management

24

The Five Focusing Steps

• Theory of constraints is based on the premise that the rate of goal achievement by a goal-oriented system (i.e., the system's throughput) is limited by at least one constraint.– The argument by reductio ad absurdum is as follows: If there was

nothing preventing a system from achieving higher throughput (i.e., more goal units in a unit of time), its throughput would be infinite — which is impossible in a real-life system.

• Only by increasing flow through the constraint can overall throughput be increased.– A constraint is anything that prevents the system from achieving

more of its goal.

Page 25: My MBA Course on Project Quality Management

25

The Five Focusing Steps Assuming the goal of a system has been articulated and its measurements defined, the steps are:

1. Identify the system's constraint(s) which prevents the organization from obtaining more of the goal in a unit of time.

2. Decide how to exploit the system's constraint(s) how to get the most out of the constraint.

3. Subordinate everything else to the above decision align the whole system or organization to support the decision made above

4. Elevate the system's constraint(s) make other major changes needed to increase the constraint's capacity

5. Warning! If in the previous steps a constraint has been broken, go back to step 1, but do not allow inertia to cause a system's constraint.

Page 26: My MBA Course on Project Quality Management

26

The goal of a business

• "Make more money now and even more money in the future” (that is, maximize throughput)– and its measurements are given by:

• throughput, – the rate at which a system achieves its goal

» The speed we make money thru sales

• inventory, – All what is needed to make money and it is tied up

» Building, raw material, investments, ALL

• operating expenses– All of what is needed in the process of converting inventory into

throughput» money, time, energy, thought, resources, overtime, etc.

Page 27: My MBA Course on Project Quality Management

27

So, what’s the goal in a project?

• Save money?• Make money?

Page 29: My MBA Course on Project Quality Management

29

• We are saying that many local improvements DO NOT necessarily add up to the GLOBAL IMPROVEMENTS.– That is, almost ALL we knew is just wrong!!!• Reason been we think the world is linear, which it is not

Page 30: My MBA Course on Project Quality Management

30

FACTORS

• Time variant => systems = f(time)• Stochastic (probability)=> systems = f(random)• Multiple variables =>systems = f(x,y,z, etc)– ALL THIS MEANS• REAL LIFE =f(time, random, x,y,z, etc.)

Page 31: My MBA Course on Project Quality Management

31

Non-linear

• Nonlinear problems are of interest to engineers, physicists and mathematicians because most physical systems are inherently nonlinear in nature. Nonlinear equations are difficult to solve and give rise to interesting phenomena such as chaos.– Some aspects of the weather (although not the

climate) are seen to be chaotic, where simple changes in one part of the system produce complex effects throughout. A nonlinear system is not random.

Page 32: My MBA Course on Project Quality Management

32

Chaos Theory– http://upload.wikimedia.org/wikipedia/commons/4/45/Double-compoun

d-pendulum.gif– field of study in mathematics, with applications in several disciplines

including physics, engineering, economics and biology. – studies the behavior of dynamical systems that are highly sensitive to

initial conditions, an effect which is popularly referred to as the butterfly effect.

• Small differences in initial conditions (such as those due to rounding errors in numerical computation) yield widely diverging outcomes for such dynamical systems, rendering long-term prediction impossible in general.

• This happens even though these systems are deterministic, meaning that their future behavior is fully determined by their initial conditions, with no random elements involved.

– In other words, the deterministic nature of these systems does not make them predictable!!!

• http://www.youtube.com/watch?v=1FYWJgxST7I• http://www.youtube.com/watch?v=yTmKsKhMcIg

Page 35: My MBA Course on Project Quality Management

35

PM Triangle Quality = f(Budget, Scope, Time)…it must be so?

Page 36: My MBA Course on Project Quality Management

36

Analogy in PM

• Critical chain (CC) = critical path PLUS the constrained resources– Example: a certain task that could be done in

parallel with another task in a critical path (because they do not have sequential relationship to one another) must be done nevertheless, sequentially, because they require the same resource to do it.

Page 37: My MBA Course on Project Quality Management

37

– So CPM tells it will be like this :

– CC suggest will be done like this:

– But, it will be really like this:

Page 39: My MBA Course on Project Quality Management

39

Chain analogy in PM

• Cost => weight– Each link (task) has its own weight (cost) • Cost is drained in each task, to know the total cost we

just sum each individual task cost.– Accounting cost is linear (mostly)

• Again, what is the goal of any project?– If too difficult to find out, then let’s ask,• What is the goal of the firm?

Max Π

• What is the idea to execute the project then?

Page 40: My MBA Course on Project Quality Management

40

The goal of the Project is to make money for the firm!!!!

• We have to assume (for the time being), that by COMPLETING the project SCOPE, ON TIME, WITHIN THE BUDGET, the firm will make more money than not. – HYPOTHESIS: an unproven theory• EFFECT–> CAUSE-> EFFECT: a way to validate our

hypothesis; it works like this:

Page 41: My MBA Course on Project Quality Management

41

Now we get the goal, measurements?

– its measurements are given by:• throughput,

– the rate at which a system achieves its goal» The speed at what we finish the total project

• In a chain, its strength!!!

• inventory, =>TIME!!!!

• operating expenses– All else of what is needed in the process of converting time

into the end of the project» money, energy, thought, resources, etc.

• The different tasks are sort of the links in a chain

Page 42: My MBA Course on Project Quality Management

42

Page 43: My MBA Course on Project Quality Management

43

Cost vs. Throughput

• It is posed that once a project starts, the budget fixation (Cost world) primes the time (Throughput).– Arguably one of the causes the PM looses focus• A correct financial system must include the economic

losses that losing throughput (time) implies.– It has been argued that financially speaking running late is

more costly than being over budget» The project budget is not geared toward the “economic

loss”, cost of opportunities (being late in the market, interest paid for money invested with no returns, etc.)

Page 44: My MBA Course on Project Quality Management

44

A chain is a strong as its weakest link• Projects are inherent uncertain• Usually you will find 2 set of reasons– Official story (higher level executives)

• Unexpected weather, sudden changes in prices, etc.– It wasn’t me!!! BLAME THE OUTSIDE WORLD

– Unofficial stories (lower level supervisors)• Firm took too long deciding (then, the weather changed, of

course); firm imposed restriction on raw material vendors (then, the supplier increased his prices), forced to select the cheaper supplier instead of the more reliable one, etc.– Yeah!! It was you!!! BLAME THE INSIDE WORLD

Page 46: My MBA Course on Project Quality Management

46

Too much talking…a lot of words with no meaning

Page 47: My MBA Course on Project Quality Management

47

Individual tasks

• How is the process?– PM asked the person how long it takes to do the

task• Then, what happen?

Page 50: My MBA Course on Project Quality Management

50

“Realistic” estimate which it isn’t• It is heavily skewed, mostly based on the worst case scenario

(MURPHY LAW) and,– A lot of time IT IS NOT A REAL TIME DURATION FOR THE TASK but

the TIME WHEN THE EXECUTOR thinks will be able to complete the task!!!!• PM: Give an estimate of how long task X will take• ME: mmm… 2 weeks (it actually takes 2 days, but I have a meeting on

Friday, I want Monday off to get some stuff for my party, I have to finish project Zombie on Tuesday….so, I could start this task on Wednesday morning and have done by Friday afternoon easily)– Some authors claim that estimates are inflated as to get no less than 90% chance

of completion

– You ask for the duration of the activity (how long does it takes) but the answer is a DUE DATE!! (when I think it will be done)

Page 52: My MBA Course on Project Quality Management

52

Page 53: My MBA Course on Project Quality Management

53

Parkinson Law

• Tell me how you measure me and I will tell you how I will behave. (Dr Goldratt)– If I finish early than the estimate, what happens?– If I finish late, what happens?– If I finish on target?

Page 54: My MBA Course on Project Quality Management

54

Student Syndrome

Page 55: My MBA Course on Project Quality Management

55

Food for thought

Page 57: My MBA Course on Project Quality Management

57

Laziness?• Not in the case of Hacienda; if you will have to pay, it is

optimum to pay as late as possible, since the money will be in your account gaining interest for you and you wont pay any penalty.

• However, you could have completed your tax forms earlier and then, just need to handed it in, why expecting to the last day to fill it then?– Maybe because to pay (and knowing we have to pay) it is a thing

we just don’t like to do?– Could be anything similar explains the student syndrome?

• What if the task assigned is not fun, maybe it is hard, boring and totally uncool or unrelated to my own work, motivations, etc?– It is likely that a tasked assignment in a project you are not vested in any way,

you would delay it until you know you cant procrastinaste it no more (because then, the penalty of failure will be too high)

Page 59: My MBA Course on Project Quality Management

59

Page 60: My MBA Course on Project Quality Management

60

PROJECT MANAGEMENT… IS MADE OUT OF PEOPLE!!!

• Organizations and project teams are people. I think we forget this….Yet managers often focus on everything…. but people. Lewis, J. (text author)

• http://www.youtube.com/watch?v=8Sp-VFBbjpE

Page 62: My MBA Course on Project Quality Management

62

Socratic method:

• form of inquiry and debate between individuals with opposing viewpoints based on asking and answering questions to stimulate critical thinking and to illuminate ideas.– widely used in contemporary legal education by

most law schools in the United States.• http://www.youtube.com/watch?v=pZIonnMTLUA

Page 63: My MBA Course on Project Quality Management

63

Earned Value Analysis (Management)

• Purpose is to ensure that value and expenditure stay approximately the same during the project execution. – Early users included the US Department of Defense– to ensure that the project expenditure is in line with the

value of the deliverables• very relevant for expensive projects running over several years

– Deliverables become available only towards the end of the project

– The entire investment is always at risk because something might happen to prevent the project completing.

Page 64: My MBA Course on Project Quality Management

64

• Expenditure is what we have spent, in other words, the actual costs.– They should be as planned but real life =>Price

changes, Extra costs (overtime, expedite deliveries etc.),

• Value is what something is worth

Page 65: My MBA Course on Project Quality Management

65

Situation

• Bob The Builder gets a contract from a family who already has some land to build a house. – The family agrees to make stage payments: 20% of the cost when

the foundations are built, another 40% when the roof has been built, and so on.

– Unfortunately for the family, Bob goes bankrupt before the house is finished.

– The house lies partially completed for some time. It is damaged by the weather and passers-by who remove some of the unused material, because they think the house has been abandoned.

• As time goes by, the value decreases although the expenditure is unchanged.– What can the family do?

Page 66: My MBA Course on Project Quality Management

66

• All projects are like this:– During the project and before the deliverables are

handed over to the project customer, the Work in Progress is analogue to what is built of the house. Its Value is likely to be less than the Expenditure.• This is not very comforting for the project sponsor, (house

owners) who has to provide the budget.• As general rule, the market for “half” completed projects

is not good. This means that until a project is finished, or at least some usable work packages have been completed, the company’s investment in the project is at risk.

Page 67: My MBA Course on Project Quality Management

67

1st of 2 Possibilities (may be others)

• Can we phase our projects in such a way that the value is delivered as early as possible? – This would be much better than getting it all at the

very end. • depends on the particular project.

• Example: building a small but self sufficient supermarket first, then expand it by phases.

Page 68: My MBA Course on Project Quality Management

68

2nd of 2

• Can we somehow track the value of a project without selling it (as the economists would tell us) to check the real value? This is the thinking behind Earned Value Management, EVM.

Page 69: My MBA Course on Project Quality Management

69

Build a garden fence project numerical example

• Owner tell me to use 20 high quality wooden posts, and that she will give me a budget of $20 for each post. – All the other costs are too small to be counted (for example the

wires between the posts) or my labor (which is free of charge).• As project manager, I point out that I am only free for this

heavy work during weekends, provided that there is no rain or snow and that I am not too tired.

• I expect to mount 3 posts per week, including buying the materials, digging and making a concrete foot for each post.

• Each week the project sponsor (owner) comes into the garden to check progress. – What information does she look for?

Page 70: My MBA Course on Project Quality Management

70

• $20 per post for 20 posts, a total of $400. In other words, if she sees 3 posts fully mounted, she says they are worth $60, whatever they actually cost.

• Now, reality kick in:• What actually happens the first weekend is that

some material gets damaged, which the PM had to replace out of the project budget. PM also spent some of the materials budget on beer, when he met a friend at the building materials supplier. – PM actually mounted the 3 posts but spent$90

Page 71: My MBA Course on Project Quality Management

71

• To control costs, we now need to introduce a new parameter to relate costs to the Value of the work that has actually been done. – Unfortunately, without selling the partially built fence

there is no accurate way to estimate value.– So the owner decides to see how much spending she has

planned, in this case $60, and decides that this is good enough to use as a substitute (proxy) for an estimate of value. • It is not the value, but a “convenient” substitute.

– This is a budget amount related to when it should have been spent, but the method calls it “value”.

Page 72: My MBA Course on Project Quality Management

72

Work Performance Measurements: Cost tracking

• Cost Variance, CV: This terminology comes from accounting practice and means how different the costs are (how much they vary) from the plan.

• Cost Performance Index, CPI: This is a normalized indicator of cost performance.– Normalization means that the scale of values

expected is the same for all projects.

Page 73: My MBA Course on Project Quality Management

73

• According to the owner’s original plan, 3 completed posts should have cost 3 x $20 = $ 60.– Earned Value, EV = $60– Actual Cost, AC =$90

• Cost Variance, CV = EV - AC; – in this case $60 - $90 =-$30

• Cost Performance Index, CPI = EV/AC= 60/90≈ 0.67

• If the CPI (0.67) <1 I am over budget; my costs are higher than planned.

• IF CPI= 1 my costs are as planned, I’m right on budget– if CPI > 1 ….=>lying weasel warning!!!!

Page 74: My MBA Course on Project Quality Management

74

5 weeks into the project Cost Control

Everything ok with this picture?

Page 75: My MBA Course on Project Quality Management

75

To-Complete Performance Index, TCPI

• Budget at Completion, BAC: This is just the total budget amount. ($400 in the example).– TCPI=(BAC-EV)/(BAC-AC)– (400-60)/(400-90) = 340/310 ≈ 1.097• If EV=AC, TCPI =1 (everything under control)• If EV >AC, TCPI <1 (lying weasel alarm!!!)• If EV <AC, TCPI>1

– http://www.youtube.com/watch?v=yd1uEvyzCmM

Page 76: My MBA Course on Project Quality Management

76

• Of course, if a project has poor cost performance earlier on, then this needs to get dramatically better towards the end of the project to complete on time and within budget.

• However if nothing changes, except the demands of management, then the chances of the TCPI improving dramatically are near zero.

• In other words, unless the costs are in control from very early on, it is IMPOSSIBLE to catch up, unless changes to the project constraints are agreed. This is called “re-planning”.

Page 77: My MBA Course on Project Quality Management

77

EVM Schedule Control

• Planned Value, PV: makes the same assumption as before: The approved budget ($20 per post) is a good way of linking value and schedule (when it should be achieved).

• Compares EV (as a substitute for the value estimate of the work that has been done) with an estimate of the value that was planned for completion by each inspection day.– IF {the real value of the completed work}

• IS EQUAL TO {the budget for the work that was planned to be completed now (the PV)}– THEN the work is on schedule

Page 78: My MBA Course on Project Quality Management

78

Schedule Performance Index, SPI

• An indication of schedule, a time parameter,even though is derived using amounts of money– SPI =EV/ PV• SPI =1.0, then the progress is on track• SPI<1, we are behind schedule

• Compare against CC, where time (fb) are used to control schedule

Page 79: My MBA Course on Project Quality Management

79

Schedule Variance, SV:

• SV = EV – PV• Again, we are using MONEY amounts to track

SCHEDULE or TIME progress.

Page 81: My MBA Course on Project Quality Management

81

Some definitions

• Estimate (of costs) at Completion, EAC: the total by how much do you think you spend at the end of the project.– Everything we have spent until now (Actual Costs,

AC) + our Estimate [of the remaining costs] to Complete the project, ETC

• Variance at Completion, VAC= BAC –EAC– by how much do you think you will be over or

under budget at the end of the project

Page 83: My MBA Course on Project Quality Management

83

Death by Acronyms

• abbreviations can make it difficult initially to understand EVM– http://www.youtube.com/watch?v=-aeNmupIYQk

• To make it even harder, previous editions of the PMBOK Guide (and other PM books) used different abbreviations.

• Maybe they express more accurately what each of the parameters represents:

l BCWS – budgeted cost of work scheduled (PV)–

l BCWP – budgeted cost of work performed (EV)–

l ACWP – actual cost of work performed (AC)

Page 87: My MBA Course on Project Quality Management

87

The Critical Path Method (CPM)

Page 88: My MBA Course on Project Quality Management

88

PERT: Project GETTING TO CLASS

• Activities:#- Activity -Time RequiredA. Wake-up & get out of bed = 10 minutesB. Shower = 10 minutesC. Dress = 10 minutesD. Prepare Breakfast = 20 minutesE. Eat Breakfast = 15 minutesF. Brush Teeth = 5 minutesG. Transportation to Class = 40 minutes

Page 89: My MBA Course on Project Quality Management

89

Page 90: My MBA Course on Project Quality Management

90

Page 91: My MBA Course on Project Quality Management

91

Network Path

• Path A-D-G-H Length = 15• Path A-F-H Length = 11• Path B-C-D-G-H Length = 20• Path B-C-F-H Length = 16• Path B-E-H Length = 15

Page 92: My MBA Course on Project Quality Management

92

Network CPM

• The critical path is defined as the longest path through the network. Path B-C-D-G-H has a length of 20 weeks, (3 + 4 + 3 + 6 + 4) making it the longest path through the network. The critical path can be shown with double arrows along the activities on the critical path

Page 93: My MBA Course on Project Quality Management

93

Activity slack

• The difference between the late start (LS) and early start (ES) times for an activity. Numerically, (LS – ES) = activity slack.

• Also, the difference between the late finish (LF) and the early finish (EF) times also indicates the amount of slack for an activity. Numerically, (LF - EF) = activity slack

Page 94: My MBA Course on Project Quality Management

94

Page 95: My MBA Course on Project Quality Management

95

STOCHASTIC PERT

So far we have assumed the duration of activities are known with certainty and the actual duration will turn out to be exactly as estimated.

However, in practice this is not possible all the projects involve variability in activity times due to factors such: as lack of prior experience, equipment breakdown, unpredictable weather conditions, late delivery of supplies, and others. (YEAH! RIGHT!!)

Page 96: My MBA Course on Project Quality Management

96

STOCHASTIC PERT

PERT analysis is used when the duration of activities are not known with certainty.

It involves three types of estimates of the duration of an activity instead of one single value as in the case of CPM:1. The optimistic duration a= the time an activity will take under

the most favorable conditions.2. The pessimistic duration b = the time an activity will take

under the most unfavorable conditions.3. The most likely duration m = the most realistic time an

activity will require to be completed, that is, the time an activity will take under normal conditions.

Page 97: My MBA Course on Project Quality Management

97

The duration of an activity is therefore assumed to have a beta probability distribution in PERT analysis. Following this distribution, the expected activity time, te = (a+4m+b)/6, and the variance of the activity completion time, σ2 =[(b-a)/6]2 can be obtained.

Page 99: My MBA Course on Project Quality Management

99

PERT Numerical Example

Page 100: My MBA Course on Project Quality Management

100

Expected completion time of the project

1. The Earliest Start Time (EST): the earliest time at which an activity can start if no delays occur in the project;

2. The Earliest Finish Time (EFT): The earliest time at which an activity can finish if no delays occur in the project;

3. The Latest Start Time (LST): The latest time at which an activity can start without delaying the completion of the project;

4. The Latest Finish Time (LFT): The latest time at which an activity can finish without delaying the completion of the project.

Page 101: My MBA Course on Project Quality Management

101

Expected completion time of the project, μp

μp =max (EFT) = max(LFT)

(=sum of the expected individual durations for the activities in the critical path)

Critical path is: A-B-E-F-G-I-K-M-N-P-Q-R-Finish

μp =44

Page 102: My MBA Course on Project Quality Management

102

Variance of the expected completion time of the project, σp

σp = √(Σσi )

= √ (sum of the individual variances of the duration for the activities in the critical path)

Critical path is: A-B-E-F-G-I-K-MN-P-Q-R-Finish

σp ≈ 1.62

Page 103: My MBA Course on Project Quality Management

103

So, I will ask again, would you still EARLY START tomorrow?♫

• It was posed that EARLY START ALL ACTIVITIES (including those not in the Critical chain) will imply the PM will loose focus, ergo, LATE FINISH FOR THE WHOLE PROJECT!!!– It is been established that most of the tasks/activities

really have a lot of safety buffers already in, so why it is the project always late???• It goes like this:

» People give an estimate, people starts at the latest time possible (specially activities that are in the critical chain), then the project goes late, we beat people up…what do you will happened when we ask for estimates, next project?

Page 104: My MBA Course on Project Quality Management

104

Control & Focus??

• If one link break, the whole chain breaks– We need to focus in the weakest link!!!

• The longest task in the longest path (critical chain)– If physical, it is called a bottleneck; it might also be a

policy/rule/regulation/law, etc. (a non logical way to do business most likely)

– subordinate to physical constraints but we elevate (eliminate) non-physical ones.» Examples of physicals constraints (linked to capacity)» Examples of policies constraints (linked to policy and/or behaviors)• enabling the correct verbalization, in a precisely defined

linguistic context, of the “assumptions” we make about the situation we are analyzing. These assumptions, generally speaking, reflect mental models and limiting beliefs that “constrain” our mind in the search for a solution

Page 106: My MBA Course on Project Quality Management

106

Identify the system's constraint(s)

• What prevents the organization from obtaining more of the goal in a unit of time.– ie, where’s the bottleneck?• In a project, it is the critical chain.

– Here’s where our focus should be.

Page 112: My MBA Course on Project Quality Management

112

Progress Reports

• 90% of the work is done in just one Year– The remaining 10% takes another year to

complete!!!• Possible due to changing path when a block to work

flow is found?– Our current system of measurement and control percentage

of job completed) actually encourages us to change the path (so it looks as we are “moving forward”) but…» Who cares how much we going forward if it is not in the

critical chain??» And it is not, how long will it take for that block become a

critical path?

Page 115: My MBA Course on Project Quality Management

115

Goldratt’s Principle:.

• A project will accumulate delays but will (almost) never accumulate gains.– Our current system ASSUMES progress in one path

compensates for delays in another.• Nothing can be farthest from the truth!!!

– STOCHASTIC FLUCTUATIONS AND DEPENDENT EVENTS

Page 117: My MBA Course on Project Quality Management

117

Pareto

• Cost (linear) thinking assume we can limit our attention to separate links (departments, tasks, etc) and we can optimize the total system by focusing only on the “vital few”– Throughput (the real world) tells us we cant do

that because links are dependent unto each other, e need to focus on the total systems and its interconnections • Second and thirds effects

Page 121: My MBA Course on Project Quality Management

121

So?

• This means that the project manager is responsible for identifying, together with the project customers (sponsor, stakeholders), the requirements and then delivering only that!!!

• It seems the PMBOK thinks that delivering more than agreed is not good; – reason being that it diverts resources, however moderate,

from delivering what was agreed.– My own definition of quality is…. delighting the

customer!!!!• Implies a surprise, something extra, etc.

Page 122: My MBA Course on Project Quality Management

122

• Some sections of the PMBOK Guide are universal and some vary depending on legal and social environments.

• The section on quality lies between these two extremes. – This is also true for Procurement, where

contractual issues are directly affected by both practice and the legal environment

Page 123: My MBA Course on Project Quality Management

123

Three processes

• Planning, Executing and Monitoring & Controlling – Quality Planning does just what it says.

• Like anything else in life, if there is no plan to implement, it will not happen.

– Quality Assurance. This is seen as a management responsibility and means making sure that the quality processes are being properly implemented.• Instrument calibration is an example, because it requires

management authority to establish such a program.

– Quality Control is seen as a technical responsibility, actually carrying out the measurements, recording parameters and recommending changes if needed

Page 124: My MBA Course on Project Quality Management

124

Foundations of Quality

• Customer Satisfaction, based on Fitness for Use and managing expectations.

• Prevention vs. Inspection, in other words, you do not achieve quality merely by eliminating the sub-standard products from the customer delivery.

• Continuous Improvement, in the sense of making relatively small improvements all the time. Building up a big list of improvements for implementation every couple of years is comparatively less effective. This philosophy (Kaizen) was brought to the western world by Japanese car manufacturers.

Page 125: My MBA Course on Project Quality Management

125

• Management Responsibility for quality, because they control the resources required for implementing the quality system.

• Cost of Quality: the costs of everything that is done (PREVENTION COSTS) to achieve quality as well as the costs caused by poor quality. – This includes not just the cost of inspection but also, for example, of

calibration or training for the quality team, product returns, warranty claims etc.

• Grade is a product categorization. For example, photocopier paper is available in two weights, 80 g/m and 100 g/m. These are two grades.– The heavier paper (informally we might call this “better” paper) may cause

the photocopier to jam or block. In this case it is not “high quality photocopier paper” because it does not meet the requirements for working in a photocopier.

Page 127: My MBA Course on Project Quality Management

127

Plan (Design) Quality

• Requires resources and budget– Quality is free (Philip Crosby) meant it pays for

itself in the long run…NOT THAT WE DONT NEED MONEY!!!

• Implemented using various activities

Page 130: My MBA Course on Project Quality Management

130

Input to Quality Planning

• Scope Baseline. – what is in the scope statement and the WBS

• Cost Performance Baseline.• Stakeholders • Schedule Baseline• Risk Factors• Enterprise Environmental Factors• Organizational Process Assets

Page 131: My MBA Course on Project Quality Management

131

Cost-Benefit Analysis

• Decide where to strike the balance between quality measures and their cost. – In theory, “infinite” quality can be achieved at

“infinite” cost but this is not very realistic in most commercial situations.

• It is better to find out (analyze) which quality can be achieved and at what cost. A decision about which measures to apply is then made based on this information.

Page 135: My MBA Course on Project Quality Management

135

The 7 Magnificent quality Tools

1. Cause-and-effect diagram (aka, "fishbone" or Ishikawa diagram)

2. Stratification (alternately, flow chart or run chart)

3. Control chart4. Histogram5. Pareto chart6. Scatter diagram7. Check sheet

Page 158: My MBA Course on Project Quality Management

158

VIP’s in Quality1. Dr. George Box : Time Series Analysis. “all models

are wrong, but some are useful”2. Philip B. Crosby: Quality is Free., Zero Defects3. Dr. W. Edwards Deming: 14 Points, PDCA4. Kaoru Ishikawa: cause & effect diagram5. Dr. Joseph M. Juran: Quality Control Handbook,

Quality Trilogy (Planning, Improvement & Control)6. Dr. Walter Shewhart: Statistical QC (aka SPC),PDCA7. Dr. Genichi Taguchi: DOE

Page 160: My MBA Course on Project Quality Management

160

Projects Outputs

• Quality Management Plan: Main interest– how we are going to manage the quality within the project

• It is part of the Project Management Plan.• includes the strategy , responsibilities and documentation

standards etc.– Quality Metrics: documents the actual measurement values we expect to

get after performing quality control– Quality Checklists: very powerful tool, systemic way to check a particular

domain or field. » No checklist is perfect but if we keep updating it when we find

problems, our experience will become more valuable– Process Improvement Plan: identifies which processes need to be audited

and the targets to achieve– Project Document Updates: as we check the quality issues in our project,

we are very likely to find details that have to be changed and documented

Page 162: My MBA Course on Project Quality Management

162

Quality Audits

• a check in which the person doing it has the authority to ask any questions.

• Very powerful because the auditors may look at the issue from a completely different viewpoint compared with the rest of the team

• Audits can discover aspects that would otherwise be missed. • It is a really valuable way of ensuring that the quality

assurance and control are good. Of course, it is difficult to get acceptance if the auditors appear to be the “quality police”.– So for best results, the company should have an open culture that

allows critical viewpoints

Page 163: My MBA Course on Project Quality Management

163

Quality Control

• Quality Control Measurements– It is an output of QC

• Attribute Sampling: discrete variables• Variables Sampling: continuous variables• Tolerances: indicate if results will be accepted,

provided that they lie within the Control Limits

Page 165: My MBA Course on Project Quality Management

165

CC and Quality

• Critical Chain Approach is a way to manage all of an organization’s projects holistically (considers all aspects of the system within which a process)

• Critical Chain methods focus mostly on improving project cycle time (within quality and scope requirements).– conscious tradeoffs are made in resource cost, in

order to generate a much higher throughput from the project

Page 166: My MBA Course on Project Quality Management

166

• The magnitude of improvement implies that Critical Chain is impacting the entire process of managing projects, and not just one small part.

• It is an application of Theory of Constraints (TOC) principles to project management. TOC assumes that a system is like a chain. A chain is only as strong as its weakest link. The links are interdependent on each other to satisfy a need. – A project operates the same way

Page 167: My MBA Course on Project Quality Management

167

The Goal

• Achieving the project’s goals requires the cooperation of many different people, departments and functions, in a series of interdependent actions.

• The principle difference between this and the concepts underlying the Critical Path Approach is that the critical chain includes logically and resource related tasks, while the critical path includes only logically related tasks.

Page 168: My MBA Course on Project Quality Management

168

Projects are the lifeblood of the organization

• Product development? => A project• Productivity improvement? => A project• Mergers and acquisitions? => A project• Market share? => A project

Project is as money does

Page 169: My MBA Course on Project Quality Management

169

CC• Since projects are undertaken to bring benefits to an organization,

the sooner they are completed, the sooner the benefits are realized. – Critical Chain focuses on the amount of time it takes to complete any

single project• Our throughput is time

• common cause variations – Those causes of variation that are intrinsically part of the process, even after risk mitigation actions, and consistent over time. – Common cause variation, handled thorough Critical Chain planning and

management, can be controlled (up to a point) and therefore allow the project performance to be more predictable.

– Common causes must be addressed at a systemic level.• Ultimately, buffers are established to handle the common cause variation that is

accepted for the project.

Page 170: My MBA Course on Project Quality Management

170

CC• focuses on the factor that most effects the cumulative cycle time of all the projects.

This factor is known as the organization’s strategic or critical resource, also called the "Drum” (bottleneck).– The factor or resource used to determine when a new project can be scheduled.

• Usually, the Drum is the critical resource. However, sometimes the Drum is a policy.• It should be called, the DRUMMER, analogy comes from soldiers marching uniformly at the drummer’s

rate.– She/he/it who marks the advancing rate

• Critical resource – When considering all of the projects that an organization has in place, this is the resource that most impacts the cycle time of the combination of projects.– cycle time (project) – The length of time from the start of the project until its completion.

• Project duration.

• In the Theory of Constraints and Critical Chain, a constraint is the most significant leverage point for improving a system. – In Critical Chain, the constraint is the cycle time of projects, both individually and the

combined cycle time of the entire collection of an organization’s projects

Page 171: My MBA Course on Project Quality Management

171

Causes of long cycle times• There is a difference between elapsed time (duration) and effort.

– Effort can be applied in a dedicated or non-dedicated way. • For example, non-dedicated would have a resource assigned to several tasks

simultaneously, whereas a dedicated resource would be fully assigned to one task until that task is completed. Non-dedicated effort implies extending the duration.

• It is the amount of resource time (e.g., person hours) required for a task

• Critical Chain highlights the importance of dedicating effort to streamline and optimize the cycle time.

• Critical Chain analysis shows that within single projects, the biggest factor impacting cycle times is the practice of estimating tasks according to non-dedicated elapsed time, and subsequently, managing the execution of those tasks to a due date.

Page 173: My MBA Course on Project Quality Management

173

Multi-project• An environment that exists in most organizations where more

than one project is active at any point in time, and active projects share some common resources.– Resources are not infinite

• Within the multi-project environment, the biggest factor impacting cycle times is the resource bottleneck. This factor is created by the current system of pushing work (in the form of new projects, etc.) into the organization, irrespective of the capacity of the most critical resource – the one that most impacts the cycle time of all projects.– Critical Chain addresses both the single and multi-project factors in the

reduction of duration.The constraint controls ALL the projects

Page 174: My MBA Course on Project Quality Management

174

CC Project Quality Management

• TOC and the Critical Chain Approach are quality improvement oriented strategies. – Critical Chain improves the quality of project planning

and execution. – The project plan becomes increasingly stable as the

common, recurring causes of slippage are built into it. – Resources are focused on one task, rather than many

tasks, reducing the quality problems that are typical of environments full of bad multitasking.

Page 175: My MBA Course on Project Quality Management

175

CC Quality Assurance

• Quality Assurance assesses and works to improve the process by which projects are performed.

• Critical Chain highlights the need to address the project management process at the multi-project level as well as the individual project level.– By identifying common causes of project slippage,

not only can their results be included in Project buffers and task estimates, but they can be addressed as improvements in the way the organization as a whole addresses projects.

Page 176: My MBA Course on Project Quality Management

176

Project Dollar Days• One of the quality tools in the multi-project environment, suggested

by Gerald Kendall, is a measurement called Project Dollar Days.• By measuring the number of dollars generated by the collection of

projects (at Net Present Value) divided by the number of resource days consumed by projects, a productivity ratio is developed.

• With this measurement, if a project develops a quality problem, two things typically occur. – First, there is rework necessary to correct the problem, adding to the

number of resource days consumed. – Second, the project may be delivered late, reducing the benefit and

therefore reducing the (NPV). • Therefore, this measurement becomes a natural quality indicator that can be

used by the Project Management Office, senior management and project teams.

Page 177: My MBA Course on Project Quality Management

177

Quality Control

• As defined in the PMBOK® Guide 2000, Quality Control is – “the process of monitoring specific project results to determine

if they comply with relevant quality standards and identifying ways to eliminate causes of unsatisfactory performance.”

• Critical Chain is focused on the identification and elimination of the causes of performance problems.– It promotes the recognition of performance problems that have

systemic causes and highlights the need for addressing these above the individual project level.

– If performance problems cannot be addressed at that level, then Critical Chain recommends being realistic enough to include their impact in project plans!!!

Page 178: My MBA Course on Project Quality Management

178

CC vs CPM

• Critical Chain assumes a good critical path network that has been effectively resource leveled.– some of the actions needed to implement Critical

Chain successfully might be significant quality changes for an organization.

Page 179: My MBA Course on Project Quality Management

179

Team members & task times

• Team members are asked to dedicate themselves to a project task, to complete it as quickly as possible and to periodically report how many days are remaining.

• When planning a project, task times should be estimated much closer to how long the task will take with dedicated resources, rather than elapsed times assuming the organization’s current practice of assigning resources to work on several tasks at once. This also significantly reduces behaviors called “student syndrome” and “Parkinson’s Law”

Page 180: My MBA Course on Project Quality Management

180

Bad multitasking is significantly reduced, permanently.

• The behavior of people who split their time between multiple project tasks in a way that extends the cycle time of individual projects or multiple projects and often results in poor quality results.– The reduction of bad multitasking goes hand in

hand with reducing task estimates to dedicated elapsed times and having people complete tasks before starting new ones, as much as possible

Page 181: My MBA Course on Project Quality Management

181

CC Managing• In executing a project, people are not measured and are not held accountable for completing their

tasks on time. – Managing tasks by due dates is not done.

• People are asked to pass on their outputs to the next resource as quickly as possible. Use of intermediate due dates is limited. This is sometimes called the “relay runner ethic.” It is a controversial issue that will be further addressed in the discussions on Time Management and Human Resource Management.– The relay runner goes as fast as possible to complete her leg of the race and pass the baton to the next runner.– In a project, a task is completed as quickly as possible and the work or resource handed off to the successor(s).

• The relay runner work ethic is a prerequisite to healthy performance in any project environment. If it is in place and rewarded, then punitive management for late task delivery can be eliminated.

• By taking resource dependency, as well as logical task dependency into account, the longest sequence of dependent tasks can be seen more clearly. – This longest sequence, the Critical Chain, may cross logical paths in the

network.MUST MEASURE PROGRESS BY PERCENTAGE OF THE CRITICAL CHAIN

COMPLETED

Page 182: My MBA Course on Project Quality Management

182

Buffer Burn Ratio (BBR)

• 100% of the Critical chain ahead: 100% of the Buffer time available– BBR= 1:1=> ok

• 80% of the Critical chain ahead: 40% of the Buffer time available– BBR= 8:4=> NOT ok!!!• Tasks will consume buffer time, that’s is expected• We need to id what tasks consume more buffer

– We need to pay attention to solve whatever is happening with those tasks

Page 183: My MBA Course on Project Quality Management

183

Buffers

• (schedule contingency reserves) are a key part of the schedule and how it is managed.

• The ability to increase the certainty of project completion dates is closely related to the use of buffers.

• The use of buffers, strategically placed in the plan, allows the planner to clearly accommodate all common cause variations (variations in duration that predictably occur because they are part of the system within which projects are performed).

Page 184: My MBA Course on Project Quality Management

184

Buffer types• BUFFER DEFINITION: An amount of time that represents a schedule

contingency reserve. Buffers are included at various points in a project task network. They provide the ability to eliminate any padding, from individual task duration estimates and to clearly show the predicted and potential project schedule. They are managed to assess the degree of risk remaining for on-time project completion. – Buffer durations are best determined through risk analysis

• Project buffers, • Feeding buffers, • Resource buffers,• Drum buffers• Strategic Resource buffers.

Page 185: My MBA Course on Project Quality Management

185

Project buffers

• The Project buffer is a time period with no scheduled work, placed after the final task of a project in order to protect the completion date from delays, especially along the Critical Chain.

• The Project buffer time is normally 50% of the total time estimates of all the tasks on the Critical Chain, though this can vary and is best determined by performing risk analysis on the tasks.– An average cost is applied to the project buffer for budgetary

purposes, since the project is expected to consume the buffer as it proceeds to completion

Page 186: My MBA Course on Project Quality Management

186

Feeding buffers

• Feeding Buffers are time periods without scheduled work placed at points where a non-critical chain tasks join the Critical Chain.

• This buffer protects the Critical Chain from any delays on the tasks feeding it. – A Feeding buffer is normally 50% of the total time

allocated to the tasks on that feeding chain, though this can vary and is best determined by performing risk analysis on the tasks in the non-critical path

Page 187: My MBA Course on Project Quality Management

187

Resource buffers

• The Resource buffer is intended to alert resources to their approaching responsibility to the Critical Chain. – It is like an alarm clock. It DOES NOT lengthen the

estimated time of the project.

Page 188: My MBA Course on Project Quality Management

188

Drum Buffer

• Period of time ahead of which work being turned over to a Drum resource must be completed. – This ensures that the Drum will not be starved for

work due to late completion of a preceding task• Analog to work in process in front of your most slower

machine (your drummer); if the machine has nothing to work with, it will stop, being the slower thing whatever time is lost there, is lost for the whole system (i.e., throughput is lost forever here!!)

Page 189: My MBA Course on Project Quality Management

189

Strategic Resource buffer

• A time period during which the critical resource will have no scheduled work. This insulates each project that uses the strategic resource from impacts of previous projects and ensures that future projects will not be impacted by uncertainty affecting the strategic resource.– Multi-project environment

Page 190: My MBA Course on Project Quality Management

190

Critical Path

• Uses a concept of slack time or float to determine how much flexibility there is in non-critical path tasks.

• Critical Chain Approach groups tasks on each non-critical (or feeding) path entering into the critical chain and “protects” the critical chain with a Feeding Buffer.

• The feeding buffer is equivalent to a schedule contingency reserve that is local to a part of the project. – The Critical Chain Approach is explicit and systematic

about the use of Feeding buffers throughout the task network.

Page 191: My MBA Course on Project Quality Management

191

Buffers use

• This buffering allows for non-critical tasks to be scheduled at their latest possible start times to discourage costly early investment of work in process. This also significantly reduces behaviors called “student syndrome” and Parkinson’s Law”.–Early starts are discouraged unless there is

a major strategic reason for doing so.

Page 192: My MBA Course on Project Quality Management

192

Caveat

• Often, the Critical Path changes during execution because there is no buffer to absorb the variation in task times. – If implemented correctly, the Critical

Chain plan and the Critical Chain itself do not change throughout the life of the project, because the buffers absorb the uncertainties in task duration.

Page 193: My MBA Course on Project Quality Management

193

Multi-Projects

• Critical Chain recognizes that there are multi-project environments in which projects have resource-based interdependencies. In other words, projects share a common resource pool, for at least some tasks.

Page 194: My MBA Course on Project Quality Management

194

• The Critical Chain Approach identifies the critical resource (called a Drum Resource) across a collection of projects. –When overloaded or not available, this

resource is the one most likely to impact the project cycle time of all projects.

Page 195: My MBA Course on Project Quality Management

195

• The staggered introduction of projects into the system is used to improve the flow of projects, to increase the predictability in each project outcome and to increase the effectiveness of critical resources by minimizing the effect of bad multitasking. – A shorter project cycle time and an increase of the

number of projects that can be pushed through the system without increasing resources result from staggering the release of new projects.

Page 196: My MBA Course on Project Quality Management

196

• Similar to vertical traceability in Critical Path, the Critical Chain plan and detailed schedules are linked entities.–Any logic at the detailed levels

must be reflected in the summary level(s).

Page 197: My MBA Course on Project Quality Management

197

The benefits of Critical Chain will be secured permanently for the organization with the implementation of a performance measurement system, policies and education that are in keeping with the Critical Chain Approach Behaviors must change Buffers must be monitored

Page 198: My MBA Course on Project Quality Management

198

CC AND THE PMBOK® Guide’s 9 KNOWLEDGE AREAS

• A good plan is one that must have a high probability of being achieved. – Good plans are predictable (Well, sort of)

1. Project Integration Management2. Project Scope Management3. Project Time Management4. Project Cost Management5. Project Quality Management6. Project Human Resource Management7. Project Communications Management8. Project Risk Management9. Project Procurement Management

Page 199: My MBA Course on Project Quality Management

199

• Critical Chain and traditional risk management both recognize that the time required to perform any individual task is uncertain. – In fact, some individual tasks can easily take twice as long as estimated,

and this should be considered normal.• Therefore, to have a good plan, Critical Chain insists that the

protection from individual task variances must be accumulated into buffers, and not managed individually.

• Goldratt suggests that to properly insulate a project from variance, the project must have a Project buffer duration of approximately 50% of the length of the Critical Chain. – In practice, the size of the buffer that project managers use today depends a

great deal on the environment – how risky it is, and how variable the task durations are. • In practice, a range of 30-50% is common.

Page 201: My MBA Course on Project Quality Management

201

Normal Variation• Insulating any process from those variable things that normally

happen in projects attains predictability. – For example, if software developers were usually late in a particular

company, then planning a project as though they would be on time would be less than clever. • However, it is quite possible to address the reasons for these people being late

or the extent to which they are late.– Many times in order to do that, a systemic change must be made above and beyond the

project. » In other words, changing the way the organization operates may remove or reduce

the cause of lateness.

• Then, adding a buffer at the end of the path handles the amount of variation that remains in the activity or path. – Critical Chain with risk management and quality management can be

used to address such issues.

Page 202: My MBA Course on Project Quality Management

202

• The buffers, dedicated task times, reduction of bad multitasking, the staggering of the release of new projects according to a strategic resource and various risk mitigation techniques all come together to increase the predictability of successful project completion. – Risk management and quality management can be

applied to reduce the size of buffers and the overall duration of the project (the length of the Critical Chain).

Page 203: My MBA Course on Project Quality Management

203

Critical Chain looks to shrink actual task times in two ways.

• One way is to eliminate padding for individual tasks (if it exists) that everyone (the team member, the resource manager, the project manager and senior management) agrees are highly uncertain.

• What we mean by padding is time built into the task time for protection.– Problem being once an “estimate” is given, it become THE LAW, written

in stone, a “commitment”– Instead of using padding, protection is accumulated in a buffer, and not

allocated to any individual task.• The task duration that remains may have a high probability for

variance, and this is the reason that the task performer cannot be held to hitting the task completion deadline.– http://www.youtube.com/watch?v=Y6OvsJqimfg

Page 204: My MBA Course on Project Quality Management

204

• The biggest opportunity lies in addressing the second way to shrink task times. – This is addressing the difference between the

dedicated elapsed task time and the non-dedicated elapsed task time.

Page 205: My MBA Course on Project Quality Management

205

Consider two typical examples.

• First, there is a project that requires a senior management committee approval at a certain point. – The committee will hear a 60-minute presentation and

decide on certain key issues. – These decisions drive the rest of the project.– How long does the project allow for this one task to

occur? • This 60-minute task is scheduled over 45 days. • Why?

– Because the committee only meets once per month. – The next meeting is scheduled in 15 days.

Page 206: My MBA Course on Project Quality Management

206

• We will assume that the committee won’t decide at the first meeting, so two committee meetings, with 30 days in between, are allowed. – This is an example of non-dedicated elapsed time.

• If the cycle time of the project is critical, why not have the committee meet on much shorter notice or agree to resolve the issue at the first meeting? – It is not the efficiency of the committee that is critical, rather it is

cycle time. – Challenging the assumptions underlying when and how the

committee meets and even whether it meets can affect project cycle time and overall throughput.

Page 207: My MBA Course on Project Quality Management

207

• A second example is also typical. • This is where a person, cannot devote 100% of his or her time to

the task at hand. • The task has, for example, 10 days of dedicated time estimated. • The person doing the task is involved in several critical projects.

She also has some regular job duties. And there are several legitimate points, during the 10-day task, at which the person will be waiting for input from other sources for at least several hours.– If the person were able to dedicate herself to this task, pushing herself,

she could complete it in 10 days. • But with the other considerations, she gave an estimate of

elapsed time of 25 days.

Page 208: My MBA Course on Project Quality Management

208

• This 25-day elapsed time is considered legitimate – it is not padding because the person, legitimately, has 15 days of other work and waiting that typically occurs during this time in this organization.– In today’s world, it has become acceptable – a way of life – that managers

allow and even encourage their resources to do tasks in a non-dedicated way. • Managers think that this is the most efficient way to manage

resources. From the point of view of keeping everyone as busy as possible, it is efficient. – From the point of view of generating the biggest increase in company profits

through successful project completion, it is terrible.• As we have said, Critical Chain promotes a systemic change that would

enable the performer to dedicate time to the task, thereby reducing the project duration and increasing the number of projects that can be done by the organization, assuming that the task is on the Critical Chain.

Page 209: My MBA Course on Project Quality Management

209

• At the same time that Critical Chain is protecting a project at the overall level, it demands a dramatic change in the way that Critical Chain project tasks are done.

• Somehow, to get an overall favorable effect on total project duration, task times must be reduced drastically way. – Critical Chain assumes that “management pressure”

is no longer a valid way to shrink the actual time it will take to complete a task.

Page 210: My MBA Course on Project Quality Management

210

Performance Measurement and the Relay Runner Ethic

• Critical Chain recognizes that measuring people by whether they finishing their tasks according to a due date, and including milestones in project plans, – causes people to NOT pass on their task completions early!!!

• Any protection that could be accumulated within a task execution is wasted (as per Parkinson’s Law).

• The Critical Chain Approach promotes and relies on the relay runner work ethic by which. each task is completed in the least amount of dedicated time and successor (resource or logic) activities are alerted when an activity might be finished in less time than originally estimated.

• As part of a Critical Chain implementation, resource managers decide how, and to what extent, resources on the Critical Chain are flexible enough to start work within a range of dates, rather than only on a specific date. – With significantly fewer projects in process in the system at any point in time, resource

managers are able to accommodate this flexibility in assigning their people to tasks.

Page 211: My MBA Course on Project Quality Management

211

The important thing is to get the project done on time, not to get tasks done on time!!!!

• There is a tendency in organizations to “whack” people when they do not comply with their task estimates.

• If they finish early, they are always expected to finish early and if they finish late they are bad guys. – This leads people to not deliver tasks early and to pad their task

estimates to protect themselves from being penalized for being late.

• The relay runner ethic says that people should go as fast as they can (in keeping with good quality) and deliver their results as early as they can. If the performer accepts this and is not penalized for late delivery or early delivery she will be motivated to perform and to estimate accurately.

Page 213: My MBA Course on Project Quality Management

213

CC emphasizes these Project Integration Management Points

Project Plan Development (Planning & Design)

• When creating a plan, list obstacles and intermediate objectives as developed by key team members and anyone who will be impacted by the project. – These must include obstacles to implementing the relay runner work ethic

and the staggering of projects.• The project planning methodology includes the Critical Chain (single

and multi-project) Approach. • One subset of the project plan output includes the Critical Chain plan

– The schedule that shows the Critical Chain and all feeding paths, with all buffers inserted to protect the project.

– The individual task estimates included in the plan reflect only dedicated effort. • Usually, the plan is shown in Critical Path format, with the Critical Chain highlighted

across the paths.

Page 215: My MBA Course on Project Quality Management

215

• Intermediate date constraints are discouraged, except when there is a strategic reason – (e.g., customer payment hinges on it, legal

requirement, inspection).• Scheduled task start dates may be later than

traditionally practiced, and are based upon the placement of Feeding buffers, Project buffer, Strategic Resource Buffer and Drum buffer.

Page 216: My MBA Course on Project Quality Management

216

Project Plan Execution

• The Critical Chain plan is one of the inputs.• Buffer management and Critical Chain knowledge should

be considered key management skills.• An essential output of project execution is buffer

reporting. – Buffer reports include the key ratios comparing the percentage

of Critical Chain that is complete with the percentage of the project buffer consumed at any particular time.

– Another key ratio is the Percentage Feeding Chain complete compared to percentage Feeding Chain buffer consumed.

– The pace by which buffers are used is also a key indicator of the project’s performance over time.

Page 218: My MBA Course on Project Quality Management

218

Project Scope Management• It is well known that finishing certain projects earlier has value to the organization well

out of proportion to their cost. – For example, in the computer industry, a new generation computer chip that is introduced first

into the market generates profits that are several hundred percentage points better than its followers.

– A new hospital wing being constructed will provide value to the community the sooner the project is completed.

• Further, the longer the project takes, the greater the risk that some portion of the originally defined specifications will become obsolete.– By one estimate, changes in an IT development project might be about 1% per month.

• Therefore, Critical Chain plans recognize that doing things that use resources inefficiently, for the sake of shorter total cycle time of the project, has value well beyond the additional cost of the resources. – For example, putting four people on a task, when three could do it most efficiently (as

measured by some productivity factor per person), may still be warranted in Critical Chain, if the overall project duration shortens by a significant amount. • Significant means that the additional cost incurred is less than the measurable benefit.• YOU MUST EXPLAIN THAT TO PEOPLE!! (SHOW DON’T TELL!!!)

Page 219: My MBA Course on Project Quality Management

219

Initiation• One of the outputs from project initiation must be the organization’s

expected benefit from the project. – This means the expected Net Present Value (NPV) to be generated from this project.

• Identification of NPV positive changes if the project is delivered earlier, and NPV negative changes, if the project is delivered later, should also be included.

• This input allows the team to make better decisions regarding the best ways to plan and execute the project.

• Planners can evaluate different ways of breaking down the work and different ways of doing the work based on a solid business case.

• The difference in Critical Chain projects is the emphasis placed on analyzing the value of reduced cycle time. – Managers are more focused on this analysis, because senior management has been

educated, as part of the Critical Chain implementation, on the strategic importance of cycle time.

Page 220: My MBA Course on Project Quality Management

220

Work Breakdown Structure and Work Assignment

• One of the inputs is the NPV analysis described above.• The Work Breakdown Structure (WBS) analysis output

identifies which tasks are reliant on a strategic resource (the Drum resource for the entire organization).

• This requires a conscious effort to determine whether some of this work could be allocated to other resources to increase the number of projects that can be done by the organization.– For example, some work that might naturally or efficiently be

organized under this Drum resource might be organized and separated as a subcontractor package.

Page 221: My MBA Course on Project Quality Management

221

• Effective decision-making requires that the planner look at the NPV of throughput and project cost not just the cost alone, in deciding on the most appropriate approach.

• Work Breakdown Structure analysis recognizes that some items that are most cost efficiently done by one organization unit might be better done by others. – Further breakdown of activities and having the sub-activities done in

parallel by others or by assigning them to less efficient resources are ways of hastening the project’s completion.• For example, if a change to a Web site is required for a project it is usually

most efficient to have it made by the in-house Web specialist. • It is a task she could do in say, half a day.

– However, if that specialist couldn’t get to the task for say, three weeks, it might be worth the extra cost to have the task performed by an outsider group that would cost more but would reduce the elapsed time.

Page 223: My MBA Course on Project Quality Management

223

Project Time Management

• The Critical Chain plan must represent every activity but may not schedule every activity in detail in a large project. – In other words, the Critical Chain plan schedules summary-

level activities. • For example, in a large project involving several thousand activities, a

few hundred high-level activities are typically sufficient to capture the major dependencies for Critical Chain.

• In such cases, it is important that a detailed plan for controlling the work at the detail level is linked properly to the Critical Chain plan. – This is called “vertical traceability” in Critical Path Method

(CPM) scheduling.

Page 225: My MBA Course on Project Quality Management

225

Subcontrating

• Need to be aware that vendors will agree, for a price– Negotiate knowing your time vs. money needs– Negotiate advanced booking of work – Negotiate big bonuses for ending ahead (but

within scope and quality) and huge penalties fro delays• ALWAYS LOOK FOR WIN-WIN (More on this later, ROOT

CAUSE)

Page 226: My MBA Course on Project Quality Management

226

Activity Sequencing

• The Critical Chain method includes any resource dependencies in activity sequencing.– a resource-loaded and-leveled schedule is an

input to the Critical Chain method.• The Project Network Diagram output shows both task

and resource dependencies.

Page 227: My MBA Course on Project Quality Management

227

Activity Duration Estimating

• In general, Critical Chain activity durations are estimated assuming no bad multitasking and resources dedicated to tasks. – The duration is the actual time dedicated to

perform the task, or something very close to this time.

– These assumptions are possible if the organization makes the changes required.

Page 228: My MBA Course on Project Quality Management

228

Schedule Development• Schedules are developed using the Critical Chain method as the

primary tool.• Schedules include a Project buffer, Feeding buffers, Resource

buffers, Strategic Resource buffers and Drum buffers.– Tasks normally start as late as possible.

• The objective is to minimize any work in process and to eliminate “student syndrome” and “Parkinson’s Law”.

– In Critical Chain, early starts would represent investment that was made too early to provide a return. • Early starts also significantly increase the risk of bad multitasking.

– Safety is provided by the buffers and helps to avoid the need for, and hence the practice of padding at the task level. • Padding may occur unless the organization squeezes time from the schedule

to achieve a schedule that shows an earlier completion date.

Page 229: My MBA Course on Project Quality Management

229

• Resource leveling is greatly simplified due to the multi-project Critical Chain practice of staggering the introduction of projects into the system according to the availability of the strategic resources of the organization. – This typically results in the reduction of bad multitasking and of the

number of active projects in the entire organization at a given point in time.

• Experience (???) shows that, because of these practices, more projects can be delivered in the same time period with the same resources. – Also, the ability to use more resources on critical tasks, even though

inefficient in terms of the individual productivity of that resource, makes it easier to compress schedules.

Page 230: My MBA Course on Project Quality Management

230

Note on Safety

• Dr Goldratt’s report the vast majority of employees will try to get at least 80% of chance of finishing on time NOT counting:– Delayed by others (the precedents necessary task

are not late)– Loaded up with others things to do

• Means, when I say 2 weeks to complete I am really saying is:– I will have done in 10 days from now (due date) IF:

» I start right now» I have only this task as my priority

Page 231: My MBA Course on Project Quality Management

231

Sources of “safety”

• When given estimates at least 3 “safeties” buffers are inserted by people1. Based on pessimistic (worst case) experience2. Number of management levels3. They know you will try to cut it down

Page 235: My MBA Course on Project Quality Management

235

Schedule Control

• Buffer management is the primary schedule control mechanism, for the overall project. – In large projects, traditional methods still apply at the

most detailed level.• Team members are not given due dates. – Rather, they are asked to report the days remaining

on each task.• WIP (inventory) in front of a machine is akin to safety time

(FB) in a task , both are buffers– But project FB are akin to perishable inventory

» Time lost is never coming back

Page 237: My MBA Course on Project Quality Management

237

Only place need to be working at 110% (lol)

• Just before the bottleneck– WIP in production (FB in PM)

• THE BOTTLENECK (of course, one minute lost here is lost forever)– The constraint cannot stop, EVER• It must be protected from any disruptions

Page 238: My MBA Course on Project Quality Management

238

Project Cost Management

• As a general principal, the Critical Chain Approach looks for the best impact on the organization, taking into account throughput, operating expense and investment (inventory) as summarized in the NPV.– Throughput - The rate at which an organization generates

money through sales. • Usually, this is revenue received from customers minus the cost

of raw materials (directly variable cost).– In PM ,”Throughput” is time to project completion

– operating expense – All the money, which an organization spends to turn inventory/investment into throughput.

Page 239: My MBA Course on Project Quality Management

239

• Many organizations have resource managers who are measured by the “efficient” use of their resources.

• Critical Chain strategy, using other measures, promotes decisions that support what is best for the project or organization as a whole. – If it reduces the total project duration

significantly (i.e., benefits exceed added costs), this might imply individual resource inefficiency.

Page 241: My MBA Course on Project Quality Management

241

Resource Planning

• Resource requirement quantities are considered in terms of the three global parameters of the TOC – throughput, investment and operating expense.

• The amount of labor resource in a Critical Chain plan is typically significantly smaller than for a traditional plan to accomplish the same work.– This is because the labor consumed with bad

multitasking and non-dedicated task times is removed

Page 242: My MBA Course on Project Quality Management

242

Cost Budgeting: We must control cost while protecting throughput

• The cost baseline should include some calculated worth of the project and Feeding buffers. – These buffers allow for uncertainty in task estimates.

• Generally, a project’s promised delivery date is at the end of the Project buffer. – Therefore, the value of these buffers, perhaps computed at some

average running rate of the activities the buffer is intended to protect, should be translated to allow a Cost buffer as well. • This is equivalent to the traditional project cost reserves

– REMEMBER NOT TO FOCUS ON LOCAL IMPROVEMENTS (COST WORLD) BUT TO FOCUS ON GLOBAL (THROUGHPUT)

– A CHAIN IS AS STRING AS IT WEAKEST LINK (the bottleneck, i.e., the critical chain) FOCUS ON IMPROVEMENTS THERE!!!

Page 243: My MBA Course on Project Quality Management

243

Cost Plus

• Bidding put downward pressure on prices– PROFIT comes from “change orders”• The longer the project and the more change orders, the

higher the profit• No incentive to finish sooner

– THIS IS THE “VAMPIRE SELF-DESTRUCTION BEHAVIOR”» http://www.youtube.com/watch?v=IGrpoxBlCNo» What would happened if, like in some movies lore say,

every time one is bitten becomes a vampire?• So, near the end of times,

• The few humans around, would your drain them or farm them?

Page 244: My MBA Course on Project Quality Management

244

• So, it is in your own self benefit your “victim” (client) is alive and well preserved– http://www.youtube.com/watch?v=g2FqS3aKHRg• The happy “victim” will bring more “victims” for you to

feed

• In any case, a company that delivers fast reliable products and services can charge a premium, even in today’s market

Page 245: My MBA Course on Project Quality Management

245

Cost Control• The TOC suggests that a systems approach is vital, with respect to

cost control and measuring performance to budget. – Some cost tradeoffs during a project are good, provided that the impact

on the organization’s and/or customer’s goals is significant.• The key is to get project managers to better understand the real

cost of a late delivery, to make project cost decisions with those figures in mind, and to keep key decision makers informed so that there are no surprises.– Some organizations use cost as their number one criteria for decisions.

• In Critical Chain, throughput is the number one priority, not cost control. – It does not mean that costs are ignored. Rather, any costs accrued that

do not contribute to throughput are considered a waste

Page 246: My MBA Course on Project Quality Management

246

BEWARE!!!!

• Imagine the following:– Soldiers marching in line, with the slowest guy

somewhere in the middle• The guys behind step up, what happen?• The guys behind step down, what happen?

– At what speed they should walk?

Page 247: My MBA Course on Project Quality Management

247

– Soldier (tasks) in line, with the slowest guy (task) somewhere in the middle• The guys (tasks) behind step up, what happen?• The guys (tasks) behind step down, what happen?

– At what speed they should walk (work)?

Page 249: My MBA Course on Project Quality Management

249

Project Human Resource Management• PERFORMANCE THEOREM: “Tell me how you

measure me, and I will tell you how I’ll behave.”– FIRST COROLLARY TO THE PERFORMANCE

THEOREM : “If my measurements are unclear, no one can predict how I will behave, not even me”. • Lemma from the Performance Theorem: Bad

measurements create bad behavior

Dr. Eli GoldrattMeasurements must induce to do the right for the whole system

Page 254: My MBA Course on Project Quality Management

254

IMPORTANT CHANGES

• To achieve major improvement in project delivery times, an essential ingredient is a drastic change in how team members’ performances are measured on projects.

• A second major change happens at the executive level, to eliminate the constant release of new projects even when key resources are not, available (which encourages bad multitasking).

• The third major change is complete Critical Chain education for team members, project and resource managers and executives.

Page 256: My MBA Course on Project Quality Management

256

Organizational Planning

• As discussed above, there are some major changes to organizational practices, specifically with regard to executives. – Functional executives with budgetary authority often work

independently of each other, releasing projects into the system to meet their quarterly or annual targets.

– When resource conflicts occur, different executives and managers make conflicting demands on resource managers. • The resulting compromise in most organizations is multitasking

of resources – people working on multiple projects simultaneously.

Page 257: My MBA Course on Project Quality Management

257

Bad Measurements comes from Bad Cultures

• An executive trained in TOC takes charge of a whole new company in a totally unknown fro him industry (steel)– Prime measurement: tons/hour• 1st question should be?

– Are you having trouble getting precise measurements of it?» Usual answer is: yeap, no problem

– Do you really need this measurement?» Usual answer is: we never think of that, it’s the way we

do business, etc.

Page 258: My MBA Course on Project Quality Management

258

So what happen then?

• The business was oriented to maximize ‘tons/hours” of steel– So, they produce steel that was sent to inventory, for future

(they hoped) sales• Inventory levels to the roof• Never enough material to do what the customers wanted, never

the product in stock the customer wanted either– Real life systems has one constraints or two tops (that meant THE

SLOWEST THING, at the moment)» Your measurement needs to address throughput thru that

constraint.» THE ONLY PROBLEM WORTH DOING IT IS THE CORE PROBLEM

• Solving it, will solve most of the systems symptoms

Page 259: My MBA Course on Project Quality Management

259

PUSH VS PULL

• In Critical Chain, this practice is stopped, and the “push” system is replaced by a “pull” system.– A new project can only be released into the system when the critical

resource – the Drum resource – can be dedicated to the project. – The project start date is based upon the availability of the Drum

resource.• Team members are asked to eliminate padding, from their task

estimates and are no longer expected to finish their tasks according to a due date.

• All project resources are taught that it doesn’t necessarily matter whether or not a task finishes on time. – What is important is that the project finishes on time or early.

Page 261: My MBA Course on Project Quality Management

261

PUSH SYSTEMS

• MRP (Material Requirements Planning)– Computer based : PP&IC

• MRP II (Manufacturing Resource Planning )– Computer based : Includes MRP + financial+…

• ERP (Enterprise Resource Planning)– Computer based : The whole business (internal &

suppliers + customer, etc.)• Supply chain management, etc

Page 263: My MBA Course on Project Quality Management

263

Page 264: My MBA Course on Project Quality Management

264

• Resource managers manage project resources to complete their tasks as quickly as possible. – There is no such thing as late delivery.

• However, finishing a task early adds further protection to the project.

• The Relay Runner Work Ethic motivates effective performance to get the project done on time. – Instead of insisting that performers finish their tasks on due

dates that are often based on wishful thinking, performers are asked to get their tasks done as quickly as possible.

• This helps to eliminate the student syndrome (waiting for the last minute to get started) and helps to promote shorter cycle times.

Page 265: My MBA Course on Project Quality Management

265

Team Development• To obtain benefits, Critical Chain training is essential for all team

members, project managers, resource managers, project office personnel and executives.– Team members will not respond to requests to provide estimates

that accurately reflect the amount of time it will take assuming dedicated resources, unless they are convinced that management and executives are 100% behind the new measurements.

• As long as people are evaluated based on their ability to hit a due date, they will do their best to create due dates that give them a strong possibility of succeeding.– This generally translates into padding.

• BTW, people refuse to admit they are padding their estimates and really believe their estimates are ‘good & realistic””

Page 266: My MBA Course on Project Quality Management

266

Selecting your team members

Page 267: My MBA Course on Project Quality Management

267

• Often organizations reduce the durations proposed by teams, whether padded or not, in order to publish an acceptable completion date or get a competitive bid. – When task estimates are required that accurately reflect the

dedicated-resource time of the task without adopting the other Critical Chain practices, performer motivation is reduced and their respect for their management is often undermined.• Some common thinking goes like this – “Who in their right mind would

expect that to get done in so short a time in this environment?”

• While Critical Chain is not on the surface a team building approach, it has the effect of improving morale and performance efficiency by highlighting project completion as the common focus of all members of the team, at all levels

Page 268: My MBA Course on Project Quality Management

268

Problem “re-defined”

• TOC states a problem is “precisely defined” when it is presented as a conflict between two necessary conditions.– If two different answers are given by 2 different

systems of measurement, one of them has, at least one faulty assumption.• We need to find the underlying assumptions leading to the

core (root) conflict (problem)– UDE (UnDesirable Effect): the observable behavior of the system

(the symptoms)» CRT: Current Reality Tree. A visual aid to find the core cause

(the illness)

Page 273: My MBA Course on Project Quality Management

273

Project Communications Management

• In a large organization with many active projects, resource managers must have access to current information about all relevant projects.

• In this environment, experience has proven that multiuser, multi-project Critical Chain software is an essential ingredient to make communications work properly.– http://www.youtube.com/watch?v=KaOC9danxNo

Page 274: My MBA Course on Project Quality Management

274

Communications Planning

• Under communications requirements, resource managers must know the status of the Critical Chain plan in order to make correct decisions on the priority of resource assignments. – One way to achieve this is through having online access to all

projects for the resource managers. – Another way is through reporting. Such a system requires various

levels of software training for resource managers, project managers and resources (if they will be entering their own progress reports).

• This must be planned in advance, along with the collaboration of the Information Technology people and relevant software companies.

Page 275: My MBA Course on Project Quality Management

275

Information Distribution

• Critical Chain project information must be accessible, and Critical Chain reports must be scheduled for distribution on a timely basis.– Decisions must be made on how project information will be updated,

and by whom. – Also, the right of access to information by various individuals and

authority levels must be decided. • This will not necessarily be the same for all projects.

• Resource buffers, which act as alarm clocks to alert resources to be ready to start an activity, must be as an integral part of the communications system. – Resource managers must be an integral part of the dynamic project

reporting process

Page 276: My MBA Course on Project Quality Management

276

Performance Reporting

• Buffer reporting, including Buffer Penetration reports, are key to managing the Critical Chain project.– Comparison of percentage of Critical Chain completed

to percentage of Project buffer consumed provides the best estimate of project completion date.

– The rate of consumption of the buffer (either as a percentage or expressed as days consumed per time period) over time, is a good indicator of whether protection of the project is increasing or decreasing

Page 277: My MBA Course on Project Quality Management

277

Project Risk Management• Critical Chain is not a replacement for project risk management.

– The two are complementary.• In many project management environments, the risk of finishing

projects late is very high. • The entire Critical Chain methodology is designed to substantially

reduce risk, by minimizing current practices such as managing task execution to due dates, and allowing tasks to be performed in a non-dedicated way.

• Critical Chain uses pooled protection (buffers) at the right points in a project, and between projects to reduce destabilizing the environment.– In effect, without buffers any significant variation today can change a plan.

The presence of buffers will stabilize the plan, acting as a schedule contingency reserve.

Page 278: My MBA Course on Project Quality Management

278

• Risk management in planning is performed to identify, analyze and respond to project risks. – It results in an understanding of how much time should be allocated to the

project buffers. • What critical chain highlights is the uncertainty found in task estimates,

and therefore project estimates that comes from the bad multitasking, non-dedicated resources, etc.

• Once this is seen, management has the choice of accepting that the project duration is very uncertain and that the project requires a significant schedule contingency reserve or changing the system within which the project is performed.– If the system is changed, then the uncertainty may be reduced along with the

duration.– To the degree that the system is not changed, the buffers for a given project will

be larger.

Page 279: My MBA Course on Project Quality Management

279

• Critical Chain focuses on factors that occur frequently in organizations and cause significant variation in task performance. – In most environments, there is bad multitasking, Student

Syndrome and Parkinson’s Law.• As discussed above, and in the Critical Chain literature,

some of these problems, in turn, lead to cost overruns, poor quality and the pressure to reduce specifications. – In other words, they have a significant impact on the triple

constraints of project management.• SCOPE, BUDGET & LEAD TIME

Page 280: My MBA Course on Project Quality Management

280

• Critical Chain, through the use of buffer management, contributes to risk monitoring and control during the project’s execution.

• It makes it easier to identify the presence of project problems early in the project’s life, and to differentiate between problems based on their impact on the project end date.

• Buffer management also helps to pinpoint the cause of project problems.– Executives claim that this focus allows managers to put needed

attention on exceptions, without having to reschedule the project or go off in many different directions at once.

Page 281: My MBA Course on Project Quality Management

281

Project Procurement Management

• Critical Chain supports the sometimes controversial notion that procurement “subordinates itself to the project”. – This means that the cycle time of the project is the principal

priority. • If the organization has to spend more to get a critical supplier to deliver

earlier, and that early delivery is valued higher than the additional procurement cost, then the procurement will be made at the higher cost.

• Procurement must not be focused on finding the lowest bidder or complying with policies that are in conflict with the project time objective. – Meeting project completion time and quality requirements are important

criteria for supplier selection.

Page 282: My MBA Course on Project Quality Management

282

Procurement Planning

• Make or buy analysis is done, not with traditional cost accounting methods, but with throughput accounting – – how much is the improvement in project cycle time

worth?• The impact of reducing the Critical Chain duration is

considered when making these decisions on those tasks that can be contracted to outside vendors.

– Vendors are encouraged to submit alternative bids that would show trade-offs among shorter cycle times, cost and risk.

Page 285: My MBA Course on Project Quality Management

285

Project finance

• Long-term financing of infrastructure and industrial projects based upon the projected cash flows of the project rather than the balance sheets of its sponsors.

• Usually, a project financing structure involves a number of equity investors, known as 'sponsors', as well as a 'syndicate' of banks or other lending institutions that provide loans to the operation. – They are most commonly non-recourse loans, which are

secured by the project assets and paid entirely from project cash flow, rather than from the general assets or creditworthiness of the project sponsors, a decision in part supported by financial modeling.

Page 286: My MBA Course on Project Quality Management

286

Project Financing• Generally, a special purpose entity is created for each project, thereby

shielding other assets owned by a project sponsor from the detrimental effects of a project failure.

– As a special purpose entity, the project company has no assets other than the project. Capital contribution commitments by the owners of the project company are sometimes necessary to ensure that the project is financially sound or to assure the lenders or the sponsors' commitment.

• Project finance is often more complicated than alternative financing methods.

– Traditionally, project financing has been most commonly used in the extractive (mining), transportation, telecommunications and energy industries.

– More recently, particularly in Europe, project financing principles have been applied to other types of public infrastructure under public–private partnerships (PPP) or, in the UK, private finance initiative (PFI) transactions (e.g., school facilities) as well as sports and entertainment venues.

Page 287: My MBA Course on Project Quality Management

287

Risk identification and allocation is a key component of project finance

• A project may be subject to a number of technical, environmental, economic and political risks, particularly in developing countries and emerging markets. – Financial institutions and project sponsors may conclude that the

risks inherent in project development and operation are unacceptable (unfinanceable).

• To cope with these risks, project sponsors in these industries (such as power plants or railway lines) are generally completed by a number of specialist companies operating in a contractual network with each other that allocates risk in a way that allows financing to take place.

Page 288: My MBA Course on Project Quality Management

288

• Several long-term contracts such as construction, supply, off-take and concession agreements, along with a variety of joint-ownership structures are used to align incentives and deter opportunistic behavior by any party involved in the project.

• The patterns of implementation are sometimes referred to as "project delivery methods." The financing of these projects must be distributed among multiple parties, so as to distribute the risk associated with the project while simultaneously ensuring profits for each party involved.

Page 289: My MBA Course on Project Quality Management

289

• A riskier or more expensive project may require limited recourse financing secured by a surety from sponsors. A complex project finance structure may incorporate corporate finance, securitization, options (derivatives), insurance provisions or other types of collateral enhancement to mitigate unallocated risk.

• Project finance shares many characteristics with maritime finance and aircraft finance; however, the latter two are more specialized fields within the area of asset finance.

Page 290: My MBA Course on Project Quality Management

290

Fear http://www.youtube.com/watch?v=xk-xI_nY2Co

Page 291: My MBA Course on Project Quality Management

291

Project Financial Failure

• Bankruptcy!!!• The tie that binds the stakeholders :– the contract• Construction contract as proxy fro project contracts• Very limited attention by PR Supreme Court

– Its decisions have caused even more confusion!!!!» Constructora Bauza vs García López. 129 DPR 579 (1991)

• http://viciosdeconstruccion.blogspot.com/2007/08/el-vicio-aparente-y-la-aceptacin-de-la.html

Page 292: My MBA Course on Project Quality Management

292

Certifications

Page 293: My MBA Course on Project Quality Management

293

PMI

• http://www.pmi.org/Certification.aspx– Certified Associate in Project Management (CAPM)® – Project Management Professional (PMP)® – Program Management Professional (PgMP)® – Portfolio Management Professional (PfMP)SM

– PMI Agile Certified Practitioner (PMI-ACP)® – PMI Professional in Business Analysis (PMI-PBA)SM – PMI Risk Management Professional (PMI-RMP)®

– PMI Scheduling Professional (PMI-SP)® – OPM3® Professional Certification