Project Progress – 30th June,2014

Page 2: My home vihanga status report as on 30.06.2014

MY HOME VIHANGA BLOCK - “01” AS ON 30th June, 2014

Basement –II, Basement-I, Ground, First, Second and Third Floor Slabs Completed

Page 3: My home vihanga status report as on 30.06.2014

MY HOME VIHANGA BLOCK -“02” AS ON 30th June, 2014

Basement –II, Basement-I, Ground, First, Floor Slabs Completed

Page 4: My home vihanga status report as on 30.06.2014

MY HOME VIHANGA BLOCK- “03&04” AS ON 30th June, 2014

Basement II Slab Completed

Page 5: My home vihanga status report as on 30.06.2014

MY HOME VIHANGA BLOCK- “05” AS ON 30th June, 2014

PCC Work Completed, Footing work In Progress

Page 6: My home vihanga status report as on 30.06.2014

MY HOME VIHANGA BLOCK- “06” AS ON 30th June, 2014

Footing Completed and Ground Preparation for Grade Slab In Progress

Page 7: My home vihanga status report as on 30.06.2014

MY HOME VIHANGA BLOCK-“07” AS ON 30th June, 2014

Earth Work In Progress

Page 8: My home vihanga status report as on 30.06.2014

MY HOME VIHANGA BLOCK- “08” AS ON 30th June, 2014

Earth Work In Progress

Page 9: My home vihanga status report as on 30.06.2014

MY HOME VIHANGA BLOCK- “09&10” AS ON 30th June, 2014

Earth Work In Progress

Page 10: My home vihanga status report as on 30.06.2014

MY HOME VIHANGA Block-“11&12” AS ON 30th June, 2014

Earth Work In Progress

Page 11: My home vihanga status report as on 30.06.2014

MY HOME VIHANGA BLOCK- “13” AS ON 30th June, 2014

PCC-Work In Progress

Page 12: My home vihanga status report as on 30.06.2014

MY HOME VIHANGA BLOCK- “14” AS ON 30th June, 2014

Earth Work In Progress

Page 13: My home vihanga status report as on 30.06.2014

MY HOME VIHANGA BLOCK- “15” AS ON 30th June, 2014

Basement-II Slab Completed

Page 14: My home vihanga status report as on 30.06.2014

MY HOME VIHANGA BLOCK-“16” AS ON 30th June, 2014

Footing Completed and Ground Preparation work in progress for Grade Slab

Page 15: My home vihanga status report as on 30.06.2014

MY HOME VIHANGA BLOCK-“17” AS ON 30th June, 2014

Footing Completed and Ground Preparation work in progress for Grade Slab

Page 16: My home vihanga status report as on 30.06.2014

MY HOME VIHANGA BLOCK- “18” AS ON 30th June, 2014

Footing Completed and Ground Preparation work in progress for Grade Slab

Page 17: My home vihanga status report as on 30.06.2014

MY HOME VIHANGA BLOCK- “19” AS ON 30th June, 2014

Basement –II Slab Completed

Page 18: My home vihanga status report as on 30.06.2014

MY HOME VIHANGA BLOCK-“20” AS ON 30th June,2014

Basement II Slab Completed