Project Progress – 20 th Dec 2013
May 09, 2015
Project Progress – 20th Dec 2013
TOP VIEW
SOUTH SIDE RETAINING WALL IN PROGRESS
SOUTH SIDE VIEW TIE BEAMS DONE & COLUMN STARTERS ABOVE TIE BEAM IN PROGRESS
WEST SIDE VIEW
WESTSIDE RETAINING WALL WORK IN PROGRESS
TOP VIEW
SOUTH SIDE VIEW STUB COLUMNS IN PROGRESS
STUB COLUMNS IN PROGRESS
NORTH SIDE VIEW
NORTH –EAST VIEW
BLOCKS EXCAVATION PODIUM AREA UNDER PROGRESS
HT & LT YARD ERECTION & INSPECTION COMPLETED CHARGING TO BE DONE
BATCHING PLANT-2 FOUNDATION IN PROGRESS