MIDDLE SCHOOL RENOVATION

WEEKLY PROGRESSJUNE 28 – JULY 1

Page 2: MS Renovation - July 2, 2010

6/28/10

A-POD 1ST FLOOR NORTH SIDE

Page 3: MS Renovation - July 2, 2010

6/28/10

C-POD 1ST FLOOR SOUTH SIDE

Page 4: MS Renovation - July 2, 2010

6/28/10

D-POD 2ND FLOOR EAST SIDE

Page 5: MS Renovation - July 2, 2010

6/28/10

E-POD 2ND FLOOR NORTH SIDE

Page 6: MS Renovation - July 2, 2010

6/28/10

F-POD 2ND FLOOR SOUTH SIDE

Page 7: MS Renovation - July 2, 2010

6/28/10

GYM

Page 8: MS Renovation - July 2, 2010

6/28/10

RESTROOMS 1ST FLOOR

Page 9: MS Renovation - July 2, 2010

6/30/10GYM

Page 10: MS Renovation - July 2, 2010

6/30/10A-POD 1ST FLOOR NORTH SIDE

Page 11: MS Renovation - July 2, 2010

6/30/10A-POD 1ST FLOOR NORTH SIDE

Page 12: MS Renovation - July 2, 2010

6/30/10DOORS REMOVED NORTH SIDE AT GYM ENTRANCE

Page 13: MS Renovation - July 2, 2010

6/30/10E-POD 2ND FLOOR NORTH SIDE STEEL WALL

STUDS

Page 14: MS Renovation - July 2, 2010
Page 15: MS Renovation - July 2, 2010

6/30/10F-POD 2ND FLOOR SOUTH SIDE

Page 16: MS Renovation - July 2, 2010

7/1/10GYM

Page 17: MS Renovation - July 2, 2010

7/1/10C-POD 1ST FLOOR SOUTH SIDEPAINTING OF BLOCK WALLS

Page 18: MS Renovation - July 2, 2010

7/1/10C-POD 1ST FLOOR SOUTH SIDE

Page 19: MS Renovation - July 2, 2010

7/1/10A-POD 1ST FLOOR NORTH SIDEMORE BLOCK WALLS ERECTED

Page 20: MS Renovation - July 2, 2010

7/1/10NEW ENTRANCE TO LIBRARY

Page 21: MS Renovation - July 2, 2010

7/1/10F-POD 2ND FLOOR SOUTH SIDE