Modeling & Simulation of Distribution Networks Distribution Networks - Multi-agent based LFC for islanding operation Seung Tae Cha Centre for Electric Technology (CET) Centre for Electric Technology (CET) Technical University of Denmark (DTU) Sept 22, 2011
35
Embed
Modeling & Simulation of Distribution Networks · response over 1 second is computed in exactly 1 second. –For a ggpyiven time step of say 50 microseconds, all calculations required
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Modeling & Simulation of Distribution NetworksDistribution Networks- Multi-agent based LFC for islanding operation
Seung Tae ChaCentre for Electric Technology (CET)Centre for Electric Technology (CET)Technical University of Denmark (DTU)
Sept 22, 2011
Technical University of Denmark (DTU)
Founded:1829 by Hans Christian Ørsted
Staff:Staff: 550 Faculty members
1550 Researcher / Senior researchers1950 Support staff
Research:1883 Research papers in ISI-journals 175 PhD dissertations
•Physical power system components are DGs, loads, lines etc These agents have fixed data such as
– Breaker agent (open & close)
lines, etc. These agents have fixed data such as – Unit names, min & max power, fuel cost coefficient
Power production value & current status of the unitWorkshop Vind i Øresund, LTH, Lund 20119 DTU Electrical Engineering, Technical University of Denmark
– Power production value & current status of the unit
Multi Agent based Controller
DG agent calculates its cost function based upon its current state, and sends a bid...cumulates...which DG agent shall provide regulation and how much power
Workshop Vind i Øresund, LTH, Lund 201110 DTU Electrical Engineering, Technical University of Denmark
agent shall provide regulation and how much power should be delivered !!
Modified IEEE 9-bus Test System
•The modified IEEE 9 bus system comprises a 60kV •The modified IEEE 9-bus system comprises a 60kV, 50Hz grid which feeds an 11kV network through a 60/11kV transformer.60/11kV transformer.
– 3 DG units (1.5 MW, Bus 1,3,4)8 T/L– 8 T/L
– 1 TR– 4 Loads (6 MW, Bus 5 -8)
Workshop Vind i Øresund, LTH, Lund 201111 DTU Electrical Engineering, Technical University of Denmark
Modified IEEE 9-bus Test System (continue)T2
T-LINE NAME:
T-LINE / CABLECALCULATION BLOCK
T3T-LINE NAME:
T-LINE / CABLECALCULATION BLOCK
T4T-LINE NAME:
T-LINE / CABLECALCULATION BLOCK
T6T-LINE NAME:
T-LINE / CABLECALCULATION BLOCK
T7T-LINE NAME:
T-LINE / CABLECALCULATION BLOCK
T8T-LINE NAME:
T-LINE / CABLECALCULATION BLOCK
T5T-LINE NAME:
T-LINE / CABLECALCULATION BLOCK
T1T-LINE NAME:
T-LINE / CABLECALCULATION BLOCK
0.0W3
0.0W2
0.0W1
GEN1
EF IF VMPUA
B
VGB1
BUS1
C1B1A11.00040 /_-30.08172
BUS #1
GEN2
EF IF VMPUA
B
EF2 VGB2
BUS3
C3B3A31.00039 /_-30.07523
BUS #3
GEN3
EF IF VMPUA
B
EF3 VGB3
BUS4
C4B4A41.00039 /_-30.06276
BUS #4
1 <-- SS --> 1
LINE CONSTANTS:T2
CONTROL ANDMONITOR IN
THIS SUBSYSTEM
1 <-- SS --> 1
LINE CONSTANTS:T3
CONTROL ANDMONITOR IN
THIS SUBSYSTEM
1 <-- SS --> 1
LINE CONSTANTS:T4
CONTROL ANDMONITOR IN
THIS SUBSYSTEM
1 <-- SS --> 1
LINE CONSTANTS:T6
CONTROL ANDMONITOR IN
THIS SUBSYSTEM
1 <-- SS --> 1
LINE CONSTANTS:T7
CONTROL ANDMONITOR IN
THIS SUBSYSTEM
1 <-- SS --> 1
LINE CONSTANTS:T8
CONTROL ANDMONITOR IN
THIS SUBSYSTEM
<-- SS -->S1 -- S1
T-LINE NAME:T1
1
BRKG170
BRKG1
<-- SS -->S1 -- S1
T-LINE NAME:T5
1
BRKG270
BRKG2
<-- SS -->S1 -- S1
T-LINE NAME:T7
1
BRKG3BRKG370
GEN1
IEEE Type ST1ExcitationSystem
Ef If Vpu
Vs
EF1
GEN2
IEEE Type ST1ExcitationSystem
Ef If Vpu
Vs
GEN3
IEEE Type ST1ExcitationSystem
Ef If Vpu
Vs
LINE CONSTANTS:T5
CONTROL ANDMONITOR IN
THIS SUBSYSTEM
1 <-- SS --> 1
LINE CONSTANTS:T1
CONTROL ANDMONITOR IN
THIS SUBSYSTEM
1 <-- SS --> 1
IEE2STPSS
GEN3
Pe w
Vs
1 <-- SS --> 1
IEE2STPSS
GEN2
Pe w
Vs
IEE2STPSS
GEN1
Pe w
Vs
GPC
TMW
B
C
W1
T-LINE NAME:T2
SENDING ENDTERMINAL NAME:
T2SE
1
2
3
GPC
TMW
B
C
W2 TM22
T-LINE NAME:T6
SENDING ENDTERMINAL NAME:
T6SE
1
2
3
GPC
TMW
B
C
W3 TM33
T-LINE NAME:T8
SENDING ENDTERMINAL NAME:
T8SE
1
2
3
<-- SS -->S1 -- S1
<-- BUS -->BUS6 -- BUS1
<-- SS -->S1 -- S1
<-- BUS -->BUS8 -- BUS3
<-- SS -->S1 -- S1
<-- BUS -->BUS7 -- BUS4
<-- BUS -->BUS5 -- BUS1
SENDING ENDTERMINAL NAME:
T1SE
2
3
<-- BUS -->BUS5 -- BUS3
SENDING ENDTERMINAL NAME:
T5SE
2
3
<-- BUS -->BUS4 -- BUS6
RECEIVING ENDTERMINAL NAME:
T7RE
2
3
P3P3
P1P1
IEEE Type 1Governor/Turbine
GEN1
Tm(HP)wTM11
P2P2
IEEE Type 1Governor/Turbine
GEN2
Tm(HP)w
IEEE Type 1Governor/Turbine
GEN3
Tm(HP)w
A5FREQHzA5 A8 Hz
A8FREQ
T-LINE NAME:T3
1
BUS2
C2B2A21.00020 /_-30.06147
BUS #2
T-LINE NAME:T1
180.66666667
80 66666667
BUS5
C5B5A51.00003 /_-30.11053
BUS #5
T-LINE NAME:T2
180.66666667
80 66666667
BUS6
C6B6A61.00015 /_-30.09676
BUS #6
T-LINE NAME:T3
180.66666667
80 66666667
BUS7
C7B7A70.99992 /_-30.09417
BUS #7
BUS8
C8B8A80.99992 /_-30.10040
BUS #8
<-- SS -->S1 S1
<-- SS -->S1 S1
<-- SS -->S1 S1
A8
B8
C8rms
pu
VLOAD8
A7
B7
C7rms
pu
VLOAD7
A6
B6
C6rms
pu
VLOAD6
A5
B5
C5rms
pu
VLOAD5
BRK4BRKG470
<-- SS -->S1 S1
T-LINE NAME:T4
1
<-- BUS -->BUS2 -- BUS7
<-- SS -->S1 -- S1
BRK9A
BRK9B6
N4
60
.99
99
2
80.66666667
80 66666667
frequencyA6
frequency
Hz
A6FREQA7
frequency
Hz
A7FREQ frequency
RECEIVING ENDTERMINAL NAME:
T3RE
2
3
T-LINE NAME:T4
RECEIVING ENDTERMINAL NAME:
T4RE
1
2
3
RECEIVING ENDTERMINAL NAME:
T1RE
2
3
T-LINE NAME:T5
RECEIVING ENDTERMINAL NAME:
T5RE
1
2
3
80.66666667
80.66666667
1.50 MW
RECEIVING ENDTERMINAL NAME:
T2RE
2
3
T-LINE NAME:T7
SENDING ENDTERMINAL NAME:
T7SE
1
2
3
80.66666667
80.66666667
1.50 MW
SENDING ENDTERMINAL NAME:
T3SE
2
3
T-LINE NAME:T8
RECEIVING ENDTERMINAL NAME:
T8RE
1
2
3
80.66666667
80.66666667
1.50 MW
S1 -- S1<-- BUS -->
BUS2 -- BUS7
<-- SS -->S1 -- S1
<-- BUS -->BUS2 -- BUS8
S1 -- S1<-- BUS -->
BUS5 -- BUS1
<-- SS -->S1 -- S1
<-- BUS -->BUS5 -- BUS3
S1 -- S1<-- BUS -->
BUS6 -- BUS1
<-- SS -->S1 -- S1
<-- BUS -->BUS4 -- BUS6
<-- SS -->S1 -- S1
<-- BUS -->BUS7 -- BUS4
1.50 MW
<-- BUS -->BUS2 -- BUS8
S1 -- S1
<-- SS -->S1 -- S1
<-- BUS -->BUS8 -- BUS3
T-LINE NAME:T6
RECEIVING ENDTERMINAL NAME:
T6RE
1
2
3
SENDING ENDTERMINAL NAME:
T4SE
2
3BRK9C
BRK9B
BU
S1
6
N4
8N
47
0/_
-30
.10
04
0
80.66666667
80.66666667
Place control processor wherethe GTNET-DNP card is physically connected.
A
B
C
A
B
C
Tmva = 210
6011
Trf = 2Winding
#1#2 I
Lags
Station9
C9B9A91.00000 /_ 0.00000
BUS #9
SRC1
GPC1
1
1
A
B
C
AC Type
SCR = 1.0 /_0 degZth = Ohms
BRK10A
BRK10C
BRK10B
EX
TE
RN
N3
eN
2e
N1e
1.0
00
00
/_0.0
00
00 SL1
PB21
0
PB11
0 B C
A
CB9S-R
FLIPFLOP
S
R
Q
Q
0.2
0.2
BRKOPEN1
0
time
CB2S-R
FLIPFLOP
S
R
Q
Q
Workshop Vind i Øresund, LTH, Lund 201112 DTU Electrical Engineering, Technical University of Denmark
LagsRISC
1Ell=60.025037kV
P4P4
0.2
Modified IEEE 9-bus Test System (continue)
Workshop Vind i Øresund, LTH, Lund 201113 DTU Electrical Engineering, Technical University of Denmark
Modified IEEE 9-bus Test System (continue)
•Intelligent controller : Reacts to respond quickly to •Intelligent controller : Reacts to respond quickly to the frequency deviation in the event of islanding situationsituation
LFC shceme used to control the speed of the DGs. Measures the system frequency and changes load setting of DGs via the AGC signal based on participation factors calculated using cost-functions associated with each DG.
Workshop Vind i Øresund, LTH, Lund 201114 DTU Electrical Engineering, Technical University of Denmark
Case Study Results Case I
Change the set point of Gen#2
C 1 E t l di t d
Workshop Vind i Øresund, LTH, Lund 201115 DTU Electrical Engineering, Technical University of Denmark
Case 1 – External source disconnected
Case Study Results
Case ICase I
Step1. Loss of 1.5 MW power from the grid due to an outage or intentional islandingintentional islanding
Step2. Created an imbalance in the islanded part of the network
Step3. Load agents observe voltage & frequency drop
Step4. Load agents contact DF agent for any available regulation service
Step5. DF agents informs the current service availability and provides Step5. DF agents informs the current service availability and provides its reference (i.e P_Gen2=0.6415)
Step6. Load agents request DG #2 agent for provision of service
St 7 DG #2 t t th t d id th i b Step7. DG #2 agent accepts the request and provides the service by increasing its active power set point
Step 8. Voltage & frequency recover at the nodes of all loads
Workshop Vind i Øresund, LTH, Lund 201116 DTU Electrical Engineering, Technical University of Denmark
Case Study Results
Case ICase I
Workshop Vind i Øresund, LTH, Lund 201117 DTU Electrical Engineering, Technical University of Denmark
50.02A5FREQ
50.02A6FREQ
50 50
49.96
49.98
49.96
49.98
65s10s
0 15 30 45 60 75 9049.94
0 15 30 45 60 75 9049.94
65s10s
The controller was capable of bring back the frequency
50
50.02A7FREQ
50
50.02A8FREQThe controller was capable of bring back the frequency
to 50Hz and restored at about 65 s.
49.98 49.98
49.96 49.96
Workshop Vind i Øresund, LTH, Lund 201118 DTU Electrical Engineering, Technical University of Denmark
0 15 30 45 60 75 9049.94
0 15 30 45 60 75 9049.94
1.05VLOAD5
1.05VLOAD6
0.95
1
0.95
1
0.9 0.9
0 15 30 45 60 75 900.85
0 15 30 45 60 75 900.85
1.05VLOAD6
1 05VLOAD8
The controller was also capable of reducing the voltage deviations and keeping them within the permissible limits.
11
1.05limits.
0.95 0.95
0.9 0.9
Workshop Vind i Øresund, LTH, Lund 201119 DTU Electrical Engineering, Technical University of Denmark
0 15 30 45 60 75 900.85
0 15 30 45 60 75 900.85
Case Study Results
Case IICase II
Workshop Vind i Øresund, LTH, Lund 201120 DTU Electrical Engineering, Technical University of Denmark
50.2A5FREQ
50.2A6FREQ
49.8
50
49.8
50
49.6 49.6
80s10s
0 15 30 45 60 75 9049.4
0 15 30 45 60 75 9049.4
A7FREQ 50 2A8FREQ
80s10s
50
50.2A7FREQ
50
50.2
49.8 49.8
49.6 49.6
Workshop Vind i Øresund, LTH, Lund 201121 DTU Electrical Engineering, Technical University of Denmark
0 15 30 45 60 75 9049.4
0 15 30 45 60 75 9049.4
1.05VLOAD5
1.05VLOAD6
0.95
1
0.95
1
0.9 0.9
0 15 30 45 60 75 900.85
0 15 30 45 60 75 900.85
1
1.05VLOAD7
1
1.05VLOAD8
0.95 0.95
0.9 0.9
Workshop Vind i Øresund, LTH, Lund 201122 DTU Electrical Engineering, Technical University of Denmark
0 15 30 45 60 75 900.85
0 15 30 45 60 75 900.85
Case Study Results Case III
Load Shedding at Bus 8Load Shedding at Bus 8
C 3 E t l di t d
Workshop Vind i Øresund, LTH, Lund 201123 DTU Electrical Engineering, Technical University of Denmark
Case 3 – External source disconnected
Case Study Results
Case IIICase III
Workshop Vind i Øresund, LTH, Lund 201124 DTU Electrical Engineering, Technical University of Denmark
50.15A5FREQ
50.15A6FREQ
50.05
50.1
50.05
50.1
49 95
50
49 95
50
0 15 30 45 60 75 9049.95
0 15 30 45 60 75 9049.95
A7FREQ A8FREQ
90s
50.1
50.15Q
50.1
50.15A8FREQ
The controller was capable of bring back the frequency to 50Hz and restored at about 90 s.
50.05 50.05
0 15 30 45 60 75 9049.95
50
0 15 30 45 60 75 9049.95
50
Workshop Vind i Øresund, LTH, Lund 201125 DTU Electrical Engineering, Technical University of Denmark
0 15 30 45 60 75 90
1 00496
1.00644VLOAD5
1.00628VLOAD6
1.00199
1.00347
1.00496
1.00192
1.00337
1.00483
0.99903
1.00051
0 15 30 45 60 75 900.99756
0.99901
1.00047
0 15 30 45 60 75 900.99755 0 15 30 45 60 75 90
The controller was also capable of reducing the voltage deviations and keeping them within the permissible
1.00462
1.00608VLOAD7
0.83317
0.9998VLOAD8limits.
1.00023
1.00169
1.00315
0.33327
0.4999
0.66653
0 15 30 45 60 75 900.99731
0.99877
0 15 30 45 60 75 908.049E-7
0.16663
Workshop Vind i Øresund, LTH, Lund 201126 DTU Electrical Engineering, Technical University of Denmark
LFC-ON
LFC-OFF
Workshop Vind i Øresund, LTH, Lund 201127 DTU Electrical Engineering, Technical University of Denmark
Conclusions
• A multi-agent based controller for islanding operation of active distribution system has been
d h l bili h f & lproposed to help stabilize the frequency & voltage
• The proposed contoller can respond to the islanding situation fast and efficiently stabilize the frequency under contingency
• However, there are a number of challenges
• Multi-set of DG units & loads, coordination Multi set of DG units & loads, coordination strategies, and scalability
Workshop Vind i Øresund, LTH, Lund 201128 DTU Electrical Engineering, Technical University of Denmark
Bornholm Power System
•The Bornholm power system comprises a 60kV •The Bornholm power system comprises a 60kV, 50Hz grid which feeds an 10kV network through a 60/10kV transformer.60/10kV transformer.
– Peak Load : 63 MW18 S b t ti– 18 Substations
– AC submarine cable connection to Sweden– 44 Transformers– Unit 5 : 25 MW– Unit 6 : 37.5 MW CHP– Wind, Biogas, Diesels (67 MW)
Workshop Vind i Øresund, LTH, Lund 201129 DTU Electrical Engineering, Technical University of Denmark
Workshop Vind i Øresund, LTH, Lund 201130 DTU Electrical Engineering, Technical University of Denmark
Future work
PSO b d L d F C t l f Di t ib ti • PSO based Load Frequency Control for Distribution System
• Coordinated Tuning of PSS and WPS based on SIL Test
Workshop Vind i Øresund, LTH, Lund 201131 DTU Electrical Engineering, Technical University of Denmark
Submitted to IEEE Transactions on Smart Grid, 2011
Power Hardware-In-the-Loop (PHIL) Test
• CONTRIBUTOR : Ranjan Sharma, Qiuwei Wu
• Present at 10th International Workshop on Large Present at 10th International Workshop on Large Scale Integration of Wind Power, 25-26 Oct, 2011
Workshop Vind i Øresund, LTH, Lund 201132 DTU Electrical Engineering, Technical University of Denmark
B2 B1
PMSG WT
RTDS
PMSG WT
C t l C t l C t lControl Control Control
GTAO
K K
GTAIGTAOInterfacing Cards GTAI
CHOPPERH/W d t t CHOPPER
AMPLIFIER
H/W under test
PWM DSP
Workshop Vind i Øresund, LTH, Lund 201133 DTU Electrical Engineering, Technical University of Denmark
BH2 BH1
Amplifier
RTDS
VSC
RTDS DSP Interface
I/O
Workshop Vind i Øresund, LTH, Lund 201134 DTU Electrical Engineering, Technical University of Denmark
Cards
Power Hardware-In-the-Loop (PHIL) Test
• An off-shore wind power plant (WPP) interconnected to the on-shore grid via VSC-HVDC
• To verify the H/W interaction & the control co-ordination between the WPP and the VSC of the HVDC
• To provide a FRT response during the grid faultsp p g g
• Technical challenges remain
D t il d WPP t ti ith bl: Detailed WPP representation with cables
: Inclusion of both end VSCs
Workshop Vind i Øresund, LTH, Lund 201135 DTU Electrical Engineering, Technical University of Denmark