Top Banner
Global Design Effort - CFS Global Design Effort - CFS Oct-20-2010 Oct-20-2010 IWLC2010 IWLC2010 1 ML Single Tunnel Cross Section ML Single Tunnel Cross Section GDE Asian Regional Team GDE Asian Regional Team KEK KEK A. Enomoto A. Enomoto
33

ML Single Tunnel Cross Section GDE Asian Regional Team KEK A. Enomoto

Dec 30, 2015

Download

Documents

vielka-dawson

ML Single Tunnel Cross Section GDE Asian Regional Team KEK A. Enomoto. Contents of Presentation Boundary condition for single tunnel design LHC , XFEL Example Asian Team Design status. Main Linac (ML) RF Unit in RDR - Double-tunnel accelerator configuration -. Service Tunnel. - PowerPoint PPT Presentation
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: ML Single Tunnel Cross Section GDE Asian Regional Team KEK A. Enomoto

Global Design Effort - CFSGlobal Design Effort - CFS

Oct-20-2010Oct-20-2010 IWLC2010IWLC2010 11

ML Single Tunnel Cross SectionML Single Tunnel Cross Section

GDE Asian Regional TeamGDE Asian Regional TeamKEKKEK

A. EnomotoA. Enomoto

Page 2: ML Single Tunnel Cross Section GDE Asian Regional Team KEK A. Enomoto

Global Design Effort - CFSGlobal Design Effort - CFS

Oct-20-2010Oct-20-2010 IWLC2010IWLC2010 22

Contents of PresentationContents of Presentation-Boundary condition for single tunnel designBoundary condition for single tunnel design- LHC , XFEL ExampleLHC , XFEL Example- Asian Team Design statusAsian Team Design status

Page 3: ML Single Tunnel Cross Section GDE Asian Regional Team KEK A. Enomoto

Global Design Effort - CFSGlobal Design Effort - CFS

Oct-20-2010Oct-20-2010 IWLC2010IWLC2010 33

Main Linac (ML) RF Unit in RDR- Double-tunnel accelerator configuration -

AC plug-in power: 150 kWOutput pulse: 120 kV x 130 A = 15.6 MW peak, 1.6 ms, 5 HzAveraged output power: 124.8 kWModulator Efficiency: 83%Power loss: 25.2 kW

Input RF power: ~100 WInput DC pulse: 15.6 MW peak, 1.6 ms, 5 HzOutput RF pulse: 10 MW peak, 1.565 ms, 5 HzAveraged output power: 78.25 kWKlystron Efficiency: 65%Power loss: 46.55 kW

Power Loss: ~5.6 kW (7%)

Service Tunnel

Beam Tunnel

37.956 me- ML 294 RF unitse+ ML 290 RF units

Total 584 RF units

Field gradient: 31.5 MV/mEnergy gain per RF unit : 850 MeV

(with 22% tuning overhead)

Page 4: ML Single Tunnel Cross Section GDE Asian Regional Team KEK A. Enomoto

Global Design Effort - CFSGlobal Design Effort - CFS

Oct-20-2010Oct-20-2010 IWLC2010IWLC201044

RDR ML RF Unit - Double Tunnel Section -

Page 5: ML Single Tunnel Cross Section GDE Asian Regional Team KEK A. Enomoto

Global Design Effort - CFSGlobal Design Effort - CFS

Oct-20-2010Oct-20-2010 IWLC2010IWLC201055

RDR ML RF Unit - Service Tunnel-

35.10 m

Thanks to the FNAL Facilities Engineering Services Section for AutoCAD data!

Page 6: ML Single Tunnel Cross Section GDE Asian Regional Team KEK A. Enomoto

Global Design Effort - CFSGlobal Design Effort - CFS

Oct-20-2010Oct-20-2010 IWLC2010IWLC201066

Cryomodule Assemblywith waveguides for DRFS

(Beam Tunnel)

(Drawing y Matsushita, KEK, RF group)

Page 7: ML Single Tunnel Cross Section GDE Asian Regional Team KEK A. Enomoto

Global Design Effort - CFSGlobal Design Effort - CFS

Oct-20-2010Oct-20-2010 IWLC2010IWLC201077

Clearance

Height

Transport Space

Space reservation for survey

Determination of Tunnel Diameter(for Single Tunnel in floor-mount DRFS)

Page 8: ML Single Tunnel Cross Section GDE Asian Regional Team KEK A. Enomoto

Global Design Effort - CFSGlobal Design Effort - CFS

Oct-20-2010Oct-20-2010 IWLC2010IWLC201088

ILC Cryomodule

S1-Global Cryomodules are compatible with each other.

Page 9: ML Single Tunnel Cross Section GDE Asian Regional Team KEK A. Enomoto

Global Design Effort - CFSGlobal Design Effort - CFS

Oct-20-2010Oct-20-2010 IWLC2010IWLC201099

12-m cryostats are combined in tunnel to form a “string”.

ILC Cryomodule

Page 10: ML Single Tunnel Cross Section GDE Asian Regional Team KEK A. Enomoto

Global Design Effort - CFSGlobal Design Effort - CFS

Oct-20-2010Oct-20-2010 IWLC2010IWLC20101010

Ceiling CM ExampleEuro-XFEL @DESY

XFEL Design Report

Page 11: ML Single Tunnel Cross Section GDE Asian Regional Team KEK A. Enomoto

Global Design Effort - CFSGlobal Design Effort - CFS

Oct-20-2010Oct-20-2010 IWLC2010IWLC20101111

XFEL Design Report

5200 mm

645 mm

Ceiling CM ExampleEuro-XFEL @DESY

Page 12: ML Single Tunnel Cross Section GDE Asian Regional Team KEK A. Enomoto

Global Design Effort - CFSGlobal Design Effort - CFS

Oct-20-2010Oct-20-2010 IWLC2010IWLC2010 1212

CM diameter is almost the same!

23

35

mm

1700 mm

870 mm

1000 mm

Floor CM ExampleLHC 3800 Tunnel

Page 13: ML Single Tunnel Cross Section GDE Asian Regional Team KEK A. Enomoto

Global Design Effort - CFSGlobal Design Effort - CFS

Oct-20-2010Oct-20-2010 IWLC2010IWLC2010 1313

Floor CM ExampleLHC 3800 Tunnel

# Equipment name # Equipment name

1 Machine cryostat 20 General services safety

2 QRL jumper 22 General services phones

3 Helium warm ring line DN100 23 Lighting

4 Helium recovery line DN150 24 Electrical powering for transport

5 EDA DN150 26 Space reserved for transport

6 EDR DN150 28 Space reserved for survey

7 Water filling DN65 29 Protection barriers

10 Cable tray1 (general services) # Space reserved for an e- machine

11 Cable tray3 (power and optical fibers) 31 Beam loss monitor

12 Cable tray2 (signals) 33 Cable tray 5 (dispersion suppressors)

14 Vacuum pumps 42 Vacuum pumping mobile group

15 Electronics chassis 81 Cablefil

17 Optical fibers 40 83 Telex

19 Communications antenna cable

Page 14: ML Single Tunnel Cross Section GDE Asian Regional Team KEK A. Enomoto

Global Design Effort - CFSGlobal Design Effort - CFS

Oct-20-2010Oct-20-2010 IWLC2010IWLC2010 1414

Floor CM ExampleFNAL Project X Test Facility

1846 mm1222 mm

1219 mm

4826 mm

CM1_TUNNEL_XSEC (Materials from Jerry Leibfritz)

Page 15: ML Single Tunnel Cross Section GDE Asian Regional Team KEK A. Enomoto

Global Design Effort - CFSGlobal Design Effort - CFS

Oct-20-2010Oct-20-2010 IWLC2010IWLC2010 1515

Floor CM ExampleFNAL Project X Test Facility

CM1_TUNNEL (Photos from Jerry Leibfritz)

Page 16: ML Single Tunnel Cross Section GDE Asian Regional Team KEK A. Enomoto

Global Design Effort - CFSGlobal Design Effort - CFS

Oct-20-2010Oct-20-2010 IWLC2010IWLC2010 1616

Discussion at KEK for the clearance from Tunnel Wall

Page 17: ML Single Tunnel Cross Section GDE Asian Regional Team KEK A. Enomoto

Global Design Effort - CFSGlobal Design Effort - CFS

Oct-20-2010Oct-20-2010 IWLC2010IWLC2010 1717

Clearance

~500 mm is minimum

Current Conclusionfor Clearance from Tunnel Wall-

Page 18: ML Single Tunnel Cross Section GDE Asian Regional Team KEK A. Enomoto

Global Design Effort - CFSGlobal Design Effort - CFS

Oct-20-2010Oct-20-2010 IWLC2010IWLC2010 1818

Vacuum pump space was discussed.The present space seems enough to have it under the module body.

Cryomodule Position (2) - Clearance from the Floor -

Clearance

~960 mm@ Beamline height of ~1200 mm

Page 19: ML Single Tunnel Cross Section GDE Asian Regional Team KEK A. Enomoto

Global Design Effort - CFSGlobal Design Effort - CFS

Oct-20-2010Oct-20-2010 IWLC2010IWLC2010 1919

Space Reservation for Alignment

Page 20: ML Single Tunnel Cross Section GDE Asian Regional Team KEK A. Enomoto

Global Design Effort - CFSGlobal Design Effort - CFS

Oct-20-2010Oct-20-2010 IWLC2010IWLC2010 2020

Space Reservation for Alignment

This area should be discussed with machine alignment people.

Page 21: ML Single Tunnel Cross Section GDE Asian Regional Team KEK A. Enomoto

Global Design Effort - CFSGlobal Design Effort - CFS

Oct-20-2010Oct-20-2010 IWLC2010IWLC2010 2121

Transport Space

XFEL CM Transporter

1400 mm

Page 22: ML Single Tunnel Cross Section GDE Asian Regional Team KEK A. Enomoto

Global Design Effort - CFSGlobal Design Effort - CFS

Oct-20-2010Oct-20-2010 IWLC2010IWLC2010 2222

Transport Space

for STEP files to convert design data from IDEAS to INVENTOR.Parts files exceed more than 2600.

Thanks to XFEL design team !

Page 23: ML Single Tunnel Cross Section GDE Asian Regional Team KEK A. Enomoto

Global Design Effort - CFSGlobal Design Effort - CFS

Oct-20-2010Oct-20-2010 IWLC2010IWLC2010 2323

Space Reservation for Alignment

This area should be discussed with machine alignment people.

1700 mm

Page 24: ML Single Tunnel Cross Section GDE Asian Regional Team KEK A. Enomoto

Global Design Effort - CFSGlobal Design Effort - CFS

Oct-20-2010Oct-20-2010 IWLC2010IWLC2010 2424

Asian Team Design Status3-D ML DRFS Tunnel Section

Page 25: ML Single Tunnel Cross Section GDE Asian Regional Team KEK A. Enomoto

Global Design Effort - CFSGlobal Design Effort - CFS

Oct-20-2010Oct-20-2010 IWLC2010IWLC2010 2525

DRFS Single Tunnel Section Dimension

aa

1800 mm

500 mm

Page 26: ML Single Tunnel Cross Section GDE Asian Regional Team KEK A. Enomoto

Global Design Effort - CFSGlobal Design Effort - CFS

Oct-20-2010Oct-20-2010 IWLC2010IWLC2010 2626

DRFS 2-D Plan & Elevation

Page 27: ML Single Tunnel Cross Section GDE Asian Regional Team KEK A. Enomoto

Global Design Effort - CFSGlobal Design Effort - CFS

Oct-20-2010Oct-20-2010 IWLC2010IWLC2010 2727

Single Tunnel with RDR-HLRF

Page 28: ML Single Tunnel Cross Section GDE Asian Regional Team KEK A. Enomoto

Global Design Effort - CFSGlobal Design Effort - CFS

Oct-20-2010Oct-20-2010 IWLC2010IWLC2010 2828

Single Tunnel with RDR-HLRF

Page 29: ML Single Tunnel Cross Section GDE Asian Regional Team KEK A. Enomoto

Global Design Effort - CFSGlobal Design Effort - CFS

Oct-20-2010Oct-20-2010 IWLC2010IWLC2010 2929

• Single tunnel configuration was discussed with the RDR-type HLRF system and with the DRFS type.

• The ILC cryomodule positioning in the single tunnel was discussed referring to examples (XFEL, LHC, Project X, S1 Global)

• Asian Team design with 3-D approach has been well progressed during the half period of FY2010.

Summary

Page 30: ML Single Tunnel Cross Section GDE Asian Regional Team KEK A. Enomoto

APPENDIXBoundary conditions and guidelines for design works

30

Page 31: ML Single Tunnel Cross Section GDE Asian Regional Team KEK A. Enomoto

ML Single-Tunnel Configuration- Distribute RF System (DRFS) -

31

Power Loss: ~5.6 kW (7%)

Beam Tunnel

e- ML 282 RF unitse+ ML 278 RF units

Total 560 RF units

Field gradient 31.5 MV/mEnergy gain per RF unit 850 MeV

(with 22% tuning overhead)

Page 32: ML Single Tunnel Cross Section GDE Asian Regional Team KEK A. Enomoto

ML RF Unit- Distributed RF System (DRFS) -

32

X

26.336 m (~70%) 11.62 m

~5.4 m (L) (every 4th units)

Beam / Service Tunnel

37.956 m

35.100 m

Alcove(Every 4th Units, 152 m)

X

X

One big HV klystron replaced by 13 small klystrons

Cooling WaterSkid andCommon Electricity

1.6 m (W)

2.438 m (H)

11:30-12:00 Shigeki Fukuda, HLRF Requirements

Page 33: ML Single Tunnel Cross Section GDE Asian Regional Team KEK A. Enomoto

SafetyEuro-XFEL @DESY

XFEL Design Report