Top Banner

of 36

Metro

Nov 04, 2015

Download

Documents

Bhuvanes Waran

Experience in Delhi metro construction
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
  • Experience of Delhi Metro-Phase II

    HV Receiving Substations with

    IEC 61850 and its Incorporation in

    Phase III

    By:

    Anoop Kumar Gupta, Director (Electrical)

    Mahendra Kumar, Chief General Manager

  • 2DELHI METRO RAIL CORPORATION (DMRC)

    Set up in May95 under the Indian Company Act.

    A joint venture between the GOI and theGNCT Delhi, with equal equity.

    DMRC has the responsibility for construction andoperation of Delhi Metro.

    A Master Plan had been drawn up for DelhiMetro expansion, consisting of 12 lines, covering

    420 kms. to be completed by 2021 in four

    Phases.

  • 3DMRC PROGRESS/ ACHIEVEMENTS SO FAR

    Phase-I 65 kms. Cost Rs.10,571 Cr ( $ 1.7 billion)

    Completed in 7 years and 3 months (2 years & 9 months

    ahead of schedule).

    Phase-II 125 kms. Cost Rs.19,131 Cr ( $ 3.2 Billion )

    Though double the length, completed in half the period

    taken for Phase-I, and five months ahead of schedule.

    Phase III - 136 km at Rs. 44000 Cr ( $ 7.5 Billion)

    Sanctioned in Sept 11 and has been committed to the

    Govt. for completion in 4.5 years.

  • STATUS OF PHASE-III

    Further expansion by 136 kms. 110 km (50 km U/G) inDelhi & 26 km in Haryana (14 km) Line-6 Badarpur to YMCA

    Chowk, Faridabad & (12 km) Mundka to Bahadurgarh.

    The contracts are in place and the work is in progress.

    For the first section Trial run was flagged off inDecember 2013 for the CTST- Mandi house corridor of

    phase III

  • STATUS OF PHASE-III

    5

    Phase-III will be completed by March, 2016

    On completion of Phase-III Delhi will have a

    metro network covering 326 kms.

    Delhi is the fastest growing metro network in

    the world outside China.

  • 6 DMRC is having 142 Stations and 190 Km in operation.This is including high speed Airport Express line having 6

    stations and 23 km section.

    About 2800 train trips a day with 208 train sets (1100Coaches) on 6 lines.

    Each train used to consist of 4 coaches. With the increasein commuters, the trains are progressively being

    lengthened to 6 coaches and finally to 8 coaches. We

    have already near about 100 six car sets.

    Average Ridership more than 2.4 million passengers perday. (meaning about 1,00,000 vehicles off the road)

    Operation Highlights

  • Operation Highlights

    Frequency during peak hours 2 m 40 sec on 2 out of 6lines (on other lines 3 to 5 mts).

    DMRC has around 7,000 employees, besides contractstaff.

    DMRC has assets of Rs 30,000 Cr ( US $ 5 billion) We earn around $ 170 Million from Operations and

    spend around $ 104 M ( Op Ratio 62%)

    Fare : From Rs.8/- to Rs. 30/-. The system is making anoperational profit from Day-1.

    DMRC is able to service and pay back the loans despiteno subsidy from the Government and the Fare Structure

    being lowest in the world except Kolkata.

  • 8 20% of DMRCs revenue is from Non-operationalsources mainly real estate development andadvertisements.

    The system is fully Barrier Free for Physicallychallenged.

    The trains now operate from 6 AM to 11 PM.

    DMRC has introduced feeder bus short loop servicesto help the commuters.

    Punctuality measured with a least count of 60 Sec. andthe punctuality percentage has been above 99%.

    Operation Highlights

  • DWARKA

    LAX

    MI N

    AG

    AR

    YAM

    UN

    A B

    AN

    K

    NIR

    MA

    N V

    IHA

    R

    PR

    EET

    VIH

    AR

    KA

    RK

    AR

    DU

    MA

    BOTANICAL GARDEN

    GOLF COURSE

    NOIDA CITY CENTRE

    DHAULA KUAN

    DELHI AEROCITY

    DWARKA SEC 21

    ASH

    RA

    M

    SRIN

    IVA

    SPU

    RI

    `

    KALINDI KUNJ

    PALAM

    DHSRATH PURI

    DABRI MOR

    BOTANICAL GARDEN

    DELHI GATE

    JAMA MASJID

    LAL QUILA

    PHASEI = 65.1KmPHASEII = 125.0 KmPhaseIII = 136.0 KmTotal = 326.0 Km

  • Phase I

    65 kms, 59 metro stations

    6 Receiving HV Substations One at 220 kV and 5 at 66 kV

    One substation i.e. at New Delhi RSS theprotocol at the substation was IEC 870-5-101

    whereas at the other five it was RP 570

    10

    Contd.

  • The entire power supply at RSS, tractionsystem and the auxiliary system is monitored

    & controlled through SCADA system.

    The monitoring and control is exercisedthrough use of Remote terminal units.

    11

    Power Supply in Phase-I

  • Typical Layout for Phase I

    12

    NETWORK

    RTU

    Remote Terminal Unit

    Power

    Supply

    Equipments

    SCADA

    Data Base

    ECC Operating Room

    ECC Technical Room

    Remote VDU (optional)

    PLC

    Local Area Network

    Terminal server

    Operator VDU

    Server Server (redundancy)

    Printer

    Filing

    Mimic Display Panel Printer

    Local console

    (optional)

    Manager Office

    Front End Computers ECC Equipment

    I/O (Field Data) I/O (Field Data)

    Substation Level

    PLC

    PLC PLC

    Example of SCADA architecture

  • Arrangement for Phase-I

    13

  • PS AI DO DO DI ------ DI CPU

    PS- Power Supply Card

    AI- Analogue Input Card

    DO- Digital Output

    DI- Digital Input

    CPU- Central Processing Unit

    Communication between RTUs and Telecomrooms has been provided through one copper

    cable only

    A typical RTU consists of the following:

    14

  • Limitations experienced in Phase I

    Extension-Vendor specific

    Limited flexibility

    Increased time for installation, testing &

    maintenance

  • Phase-II System on IEC 61850

    IEC 61850 protocol for 8 HV Substations ofphase II

    Substation Automation System (SAS) for all RSS(220kV/66kV/132kV - the incoming), 25kV TSS

    (Traction) and 33kV AMS (Auxiliary Supply)

    system

    Communication between substation andOperation Control Centre ( OCC) through IEC

    60870-5-101 protocol

    16

  • System Architecture for SAS- in three levels

    Bay Level

    Station Level

    OCC Level

    17

  • Typical 66kV/33kV/25kV HV substation at Church Road

    18

  • Each bay comprises of one circuit breaker and associateddisconnectors, earth switches and instrument transformers.

    At bay level, the IEDs provide all bay level functions like control(commands outputs), monitoring (status indications, measuredvalues).

    The IEDs are directly connected to the switchgear avoiding theneed for additional interposing of transducers.

    Each bay control IED is independent of the others and itsfunctioning is not affected by any fault occurring in any of theother bay control units of the substation.

    The data exchange among bay level IEDs, and between baylevel and substation level take place via dual fiber-optic inter baybus according to IEC 61850-8-1 protocol.

    19

  • Station Level

    Human Machine Interface enables local station control andmonitoring through the vendor software package compatible

    with IEC 61850.

    DMRC Substation bays are limited the bay bus arrangementprovides independent station-to-bay and bay-to-bay data

    exchange.

    Substation configuration language (SCL) facilitatesintegration of the system by the users/operators and can be

    used without detailed knowledge of real-time systems.

    An authorization mechanism has been provided to prevent system access to unauthorized users

  • OCC Level

    IEC 61850 signals are converted to IEC 60870-5-101 signals through a software based

    gateway for communication from the substation

    to the OCC.

    21

  • Functional description of SAS

    The functions are allocated at bay level to achieve

    the decentralized architecture:-

    Bay control and monitoring functions

    Bay protection functions

    22

  • Phase-II-Typical Block diagram for the functional requirements

    23

  • Achieving the functional requirements

    One Ethernet switch is provided for two/three bays.

    Connection from each IED of the bay to the switch is bya fiber optic link. The switches are connected in a dual

    fault tolerant ring.

    Two Ethernet switches are used to connect theredundant HMI and other equipment for communication

    redundancy.

    The HV protection, monitoring & control solution isbased on the IEDs using numerical terminals likeRED670, RET670, REC670 and REB670 on a

    distributed concept based on IEC 61850 protocol.

  • Achieving the functional requirements

    All intra bay interlocks are software based andperformed by the BCUs

    Substation wide interlocks are software based; thedata for the interlocks are transmitted using

    GOOSE messages by the individual IEDs.

  • Experience of Phase II- based on IEC 61850

    Common protocol for all vendors- Contract specificationswere not vendor specific.

    Installation at site, testing & commissioning required lesstime compared to earlier arrangement of phase-I.

    Reduced equipments for maintenance.

    Increased flexibility i.e. in future one or more bays (up to6) can be controlled by using one BCU with dynamic

    mimic display thereby making BCU a more cost effective

    solution when compared to the conventional system.

    Operation is faster at bay level

    26

  • Issues encountered in phase II

    Vendor provided one of the bay protection units(BPU) for distance protection i.e. REO 517 which

    was non compliant to IEC 61850, hence it was

    kept out of the Ethernet ring, and now it is learnt

    that DPR in its different version has been made

    compliant to IEC 61850 protocol.

    This is proposed to be specified in phase-III.

    27

    Issues contd.

  • Location of IEDs and BCUs

    The vendor did not place the IEDs and BCUs on the GISpanels of the 66kV or 25 kV panels due to non availability

    of suitable equipment .It was provided at a varying

    distance of 25-50 meters from the equipments in the

    control room leading to a huge requirement of hardwired

    copper control and monitoring cables.

    This could have been saved by integrating IEDs andBCUs with the GIS (66 kV & 25 kV) panel leading to less

    probability of failure and saving of cost and time during

    installation.

    This is proposed to be ensured in phase III.

    28

  • The protocol at OCC between the front

    end server and the HMI/Mimic display

    is vendor specific and the assistance

    of the same vendor is required for any

    expansion. It is being studied/

    discussed to avoid it.

    29

  • Proposal for Phase-III

    136 km network with 11 additional HVsubstations and augmentation of 2 HV

    RSS

    Traction system will be with 25 kV, ac,single phase, 50 HZ.

    Auxiliary supply will be 33kV ring network stepped down to 400 volts for theauxiliary requirements

    30

  • It is planned to have substations with substationautomation system using IEC 61850 complaint IEDs

    BCUs and Bay Protection Units to be placed on the66kV/25kV GIS panels or near to the field equipment.

    IEC 61850 compliant distance protection relays arespecified.

    With increased number of substations for largenetwork, and need to transfer power supply from

    sources, appropriate response time for operation will

    need to be evaluated.

    31

    Phase III contd.

  • Though extension of existing phase II substationwas not envisaged earlier, now on account of

    new corridors planned, it requires augmentation

    of a few existing substation

    Preliminary study indicated that addition of 2 baysrequired is feasible with the existing arrangement

    based on IEC 61850.

    A typical arrangement is shown in the next slide.

    32

  • Schematic arrangement for Augmentation of HV RSS

    33

  • TO CONCLUDE

    Phase I -The systems were heavily dependenton on-site hard wiring and had its own demerits.

    IEC 61850 based substation automation systemused in Phase-II had factory tested BCUs and

    BPUs with reduced on-site wiring.

    The reduction in wiring and the rationalization offunctionality in relays by substation automation

    has enabled significant savings and enabled

    improved reliability.

    34

    Conclusion contd.

  • In phase III placement of IEDs and BCUs on thepanels should also save space in substations ofphase-III.

    With IEC 61850 continuously getting upgraded, itis expected that the systems and relays alreadyprovided in phase II and likely to be provided inphase-III would communicate with the latestversions of IEC 61850 in future.

    The need is also felt to have an open protocoleven at the OCC level between the front endserver and the HMI/mimic panel.

    35

  • 36

    Thank You

    DMRC Ltd.Metro Bhawan,Fire Brigade Lane,Barakhamba Road, New Delhi - 110 003.