totales en m 0.00 1563.80 1556.92 0.00 0.00 0.00totales en kg 0.00 934.21 1635.70 0.00 0.00 0.00
totales en varillas 0.00 179.00 179.00 0.00 0.00 0.00
COLUMNAS Y PLACAS 11942.12SECTOR Acolumnasacero vertical TIPO C - 1 1/2" 3 4 12.10 145.20
HOJA DE METRADO DE ACEROOBRA:LUGAR: Arequipa
FECHA Mar-08REALIZADO POR: Juan Carlos Sanz David
ITEM ELEMENTO OBS. ACERO Nº E.E. Nº VAR- LU (m) 1/4" 3/8" 1/2" 5/8" 3/4" 1"
EN LA I. E. MANUEL SCORZA TORRES”
estribos TIPO C - 1 3/8" 3 72 1.00 216.00acero vertical TIPO C - 2 5/8" 1 12 12.10 145.20estribos TIPO C - 2 3/8" 1 65 1.60 104.00estribos TIPO C - 2 3/8" 1 65 1.50 97.50acero vertical TIPO C - 3 1/2" 1 12 12.10 145.20estribos TIPO C - 3 3/8" 1 65 1.70 110.50estribos TIPO C - 3 3/8" 1 65 2.15 139.75
acero vertical TIPO C - 4 5/8" 1 10 12.10 121.00estribos TIPO C - 4 3/8" 1 62 3.10 192.20acero vertical TIPO C - 5 5/8" 1 10 12.10 121.00estribos TIPO C - 5 3/8" 1 62 3.20 198.40acero vertical TIPO C - 6 5/8" 1 8 12.10 96.80estribos TIPO C - 6 3/8" 1 70 1.70 119.00acero vertical TIPO C - 7 5/8" 4 7 12.10 338.80estribos TIPO C - 7 3/8" 4 70 1.26 351.96acero vertical TIPO C - 8 1/2" 2 6 12.10 145.20estribos TIPO C - 8 3/8" 2 70 0.94 131.88placasacero vertical TIPO P - 1 5/8" 4 8 12.10 387.20acero vertical TIPO P - 1 3/8" 4 4 12.10 193.60estribos TIPO P - 1 3/8" 4 66 4.66 1230.24acero vertical TIPO P - 1(b) 5/8" 0 8 8.85 0.00acero vertical TIPO P - 1(b) 3/8" 0 4 8.85 0.00estribos TIPO P - 1(b) 3/8" 0 44 4.66 0.00acero vertical TIPO P - 2 5/8" 2 8 12.10 193.60
acero vertical TIPO P - 2 3/8" 2 4 12.10 96.80estribos TIPO P - 2 3/8" 2 66 4.25 561.00acero vertical escalera TIPO P - 2(b) 5/8" 2 8 12.10 193.60
acero vertical escalera TIPO P - 2(b) 3/8" 0 4 8.85 0.00estribos escalera TIPO P - 2(b) 3/8" 2 66 1.70 224.40
HOJA DE METRADO DE ACEROOBRA:LUGAR: Arequipa
FECHA Mar-08REALIZADO POR: Juan Carlos Sanz David
ITEM ELEMENTO OBS. ACERO Nº E.E. Nº VAR- LU (m) 1/4" 3/8" 1/2" 5/8" 3/4" 1"
EN LA I. E. MANUEL SCORZA TORRES”
acero vertical TIPO P - 3 5/8" 1 12 12.10 145.20acero vertical TIPO P - 3 3/8" 1 6 12.10 72.60estribos TIPO P - 3 3/8" 1 66 4.98 328.68acero vertical TIPO P - 4 5/8" 3 10 12.10 363.00acero vertical TIPO P - 4 3/8" 3 4 12.10 145.20estribos TIPO P - 4 3/8" 3 66 4.66 922.68acero vertical TIPO P - 5 5/8" 1 10 12.10 121.00
acero vertical TIPO P - 5 3/8" 1 4 12.10 48.40estribos TIPO P - 5 3/8" 1 66 4.66 307.56acero vertical TIPO P - 6 5/8" 0 24 12.10 0.00acero vertical TIPO P - 6 3/8" 0 12 12.10 0.00estribos TIPO P - 6 3/8" 0 66 7.10 0.00SECTOR Bcolumnasacero vertical TIPO C - 1 5/8" 2 10 12.10 242.00estribos TIPO C - 1 3/8" 2 70 3.80 532.00acero vertical TIPO C - 2 5/8" 2 6 12.10 145.20
estribos TIPO C - 2 3/8" 2 65 1.55 201.50acero vertical TIPO C - 3 1/2" 3 4 12.10 145.20estribos TIPO C - 3 3/8" 3 65 1.00 195.00acero vertical TIPO C - 4 5/8" 2 7 7.80 109.20estribos TIPO C - 4 3/8" 2 43 1.82 156.52acero vertical TIPO C - 5 1/2" 4 6 12.10 290.40estribos TIPO C - 5 3/8" 4 70 1.26 351.96acero vertical TIPO C - 6 1/2" 1 5 7.80 39.00
estribos TIPO C - 6 3/8" 1 43 1.35 58.05placasacero vertical TIPO P - 1 5/8" 2 8 12.10 193.60
acero vertical TIPO P - 1 3/8" 2 4 12.10 96.80estribos TIPO P - 1 3/8" 2 64 4.50 576.00
HOJA DE METRADO DE ACEROOBRA:LUGAR: Arequipa
FECHA Mar-08REALIZADO POR: Juan Carlos Sanz David
ITEM ELEMENTO OBS. ACERO Nº E.E. Nº VAR- LU (m) 1/4" 3/8" 1/2" 5/8" 3/4" 1"
EN LA I. E. MANUEL SCORZA TORRES”
acero vertical TIPO P - 2 5/8" 4 8 12.10 387.20acero vertical TIPO P - 2 3/8" 4 4 12.10 193.60
estribos TIPO P - 2 3/8" 4 64 4.60 1177.60totales en m 0.00 9331.38 910.20 3303.60 0.00 0.00totales en kg 0.00 5574.57 956.26 5411.30 0.00 0.00
totales en varillas 0.00 1068.00 105.00 386.00 0.00 0.00
COLUMNETAS DE ARRIOSTRE 1933.41SECTOR Aacero vertical TIPO CA - 1 3/8" 3 4 4.20 50.40
estribos TIPO CA - 1 1/4" 3 15 0.85 38.25acero vertical TIPO CA - 2 3/8" 23 4 11.80 1085.60estribos TIPO CA - 2 1/4" 23 50 0.80 920.00acero vertical TIPO CA - 3 3/8" 3 4 11.80 141.60estribos TIPO CA - 3 1/4" 3 50 0.95 142.50SECTOR Bacero vertical TIPO CA - 1 3/8" 19 4 11.80 896.80
estribos TIPO CA - 1 1/4" 19 55 0.80 836.00acero vertical TIPO CA - 2 3/8" 2 4 4.20 33.60estribos TIPO CA - 2 1/4" 2 18 0.85 30.60acero vertical TIPO CA - 3 3/8" 2 4 11.80 94.40estribos TIPO CA - 3 1/4" 2 55 1.05 115.50acero vertical TIPO CA - 4 3/8" 1 4 4.20 16.80
estribos TIPO CA - 4 1/4" 1 18 2.50 45.00totales en m 2127.85 2319.20 0.00 0.00 0.00 0.00totales en kg 547.92 1385.49 0.00 0.00 0.00 0.00
totales en varillas 244.00 266.00 0.00 0.00 0.00 0.00
VIGAS 14058.72
HOJA DE METRADO DE ACEROOBRA:LUGAR: Arequipa
FECHA Mar-08REALIZADO POR: Juan Carlos Sanz David
ITEM ELEMENTO OBS. ACERO Nº E.E. Nº VAR- LU (m) 1/4" 3/8" 1/2" 5/8" 3/4" 1"
EN LA I. E. MANUEL SCORZA TORRES”
SECTOR Avigas 1er nivelacero horizontal TIPO V - 101 5/8" 1 4 9.75 39.00acero horizontal TIPO V - 101 1/2" 1 2 5.16 10.32baston positivo TIPO V - 101 5/8" 1 2 2.50 5.00estribos tipo 2 TIPO V - 101 3/8" 1 34 1.50 51.00estribos tipo 3 TIPO V - 101 3/8" 1 16 1.10 17.60
acero horizontal TIPO V - 102 5/8" 1 6 9.75 58.50acero horizontal TIPO V - 102 1/2" 1 2 9.75 19.50baston positivo TIPO V - 102 5/8" 1 4 3.30 13.20baston positivo TIPO V - 102 5/8" 1 2 2.30 4.60baston negativo TIPO V - 102 5/8" 1 1 3.75 3.75estribos tipo 1 TIPO V - 102 3/8" 1 63 1.50 94.50acero horizontal TIPO V - 103 5/8" 1 4 9.75 39.00acero horizontal TIPO V - 103 1/2" 1 2 2.60 5.20baston positivo TIPO V - 103 5/8" 1 2 2.00 4.00estribos tipo 2 TIPO V - 103 3/8" 1 48 1.50 72.00
estribos tipo 3 TIPO V - 103 3/8" 1 10 1.10 11.00acero horizontal TIPO V - 104 5/8" 1 6 9.75 58.50acero horizontal TIPO V - 104 1/2" 1 2 9.75 19.50baston positivo TIPO V - 104 5/8" 1 4 3.30 13.20baston positivo TIPO V - 104 5/8" 1 3 2.30 6.90baston negativo TIPO V - 104 5/8" 1 2 3.75 7.50estribos tipo 1 TIPO V - 104 3/8" 1 65 1.50 97.50acero horizontal TIPO V - 105 5/8" 1 4 10.60 42.40
acero horizontal TIPO V - 105 1/2" 1 2 10.60 21.20baston positivo TIPO V - 105 5/8" 1 2 2.00 4.00estribos tipo 2 TIPO V - 105 3/8" 1 44 1.50 66.00
estribos tipo 3 TIPO V - 105 3/8" 1 17 1.10 18.70acero horizontal TIPO V - 106 5/8" 1 6 10.80 64.80
HOJA DE METRADO DE ACEROOBRA:LUGAR: Arequipa
FECHA Mar-08REALIZADO POR: Juan Carlos Sanz David
ITEM ELEMENTO OBS. ACERO Nº E.E. Nº VAR- LU (m) 1/4" 3/8" 1/2" 5/8" 3/4" 1"
EN LA I. E. MANUEL SCORZA TORRES”
acero horizontal TIPO V - 106 1/2" 1 2 10.80 21.60baston positivo TIPO V - 106 5/8" 1 6 3.00 18.00baston positivo TIPO V - 106 5/8" 1 3 0.85 2.55baston negativo TIPO V - 106 5/8" 1 3 4.20 12.60estribos tipo 1 TIPO V - 106 3/8" 1 65 1.50 97.50acero horizontal TIPO V - 107 5/8" 1 6 10.80 64.80acero horizontal TIPO V - 107 1/2" 1 2 10.80 21.60
baston positivo TIPO V - 107 5/8" 1 4 3.85 15.40baston positivo TIPO V - 107 5/8" 1 0 0.00 0.00baston negativo TIPO V - 107 5/8" 1 0 0.00 0.00estribos tipo 1 TIPO V - 107 3/8" 1 65 1.50 97.50acero horizontal TIPO V - 108 5/8" 1 16 10.60 169.60acero horizontal TIPO V - 108 1/2" 1 2 2.60 5.20baston positivo TIPO V - 108 5/8" 1 0 0.00 0.00estribos tipo 1 TIPO V - 108 3/8" 1 65 1.50 97.50acero horizontal eje 1 - 3 TIPO VA - 1 1/2" 0 4 6.85 0.00estribos tipo 4 eje 1 - 3 TIPO VA - 1 1/4" 0 40 0.90 0.00
acero horizontal eje 6 - 8 TIPO VA - 1 1/2" 1 4 7.42 29.68estribos tipo 4 eje 6 - 8 TIPO VA - 1 1/4" 1 40 0.90 36.00acero horizontal eje 2 - 3 TIPO VA - 1 1/2" 1 4 6.85 27.40estribos tipo 4 eje 2 - 3 TIPO VA - 1 1/4" 1 35 0.90 31.50acero horizontal EJE 4 - 8 TIPO V A -1 1/2" 1 4 15.00 60.00estribos tipo 1 EJE 4 - 8 TIPO V A -1 1/4" 1 75 0.90 67.50acero horizontal EJE 4 - 5 TIPO VB - 1 3/8" 1 4 4.95 19.80estribos tipo 4 EJE 4 - 5 TIPO VB - 1 1/4" 1 26 0.70 18.20
acero horizontal EJE A TIPO V 25x50 5/8" 1 10 28.50 285.00acero horizontal EJE A TIPO V 25x50 3/8" 1 2 28.50 57.00baston positivo EJE A TIPO V 25x50 3/8" 1 4 18.25 73.00
estribos tipo 1 EJE A TIPO V 25x50 3/8" 1 187 1.50 280.50acero horizontal EJE B TIPO V 25x50 5/8" 1 10 28.50 285.00
HOJA DE METRADO DE ACEROOBRA:LUGAR: Arequipa
FECHA Mar-08REALIZADO POR: Juan Carlos Sanz David
ITEM ELEMENTO OBS. ACERO Nº E.E. Nº VAR- LU (m) 1/4" 3/8" 1/2" 5/8" 3/4" 1"
EN LA I. E. MANUEL SCORZA TORRES”
acero horizontal EJE B TIPO V 25x50 3/8" 1 2 28.50 57.00baston positivo EJE B TIPO V 25x50 3/8" 1 4 18.25 73.00estribos tipo 1 EJE B TIPO V 25x50 3/8" 1 187 1.50 280.50acero horizontal EJE C TIPO V 25x50 5/8" 1 10 28.50 285.00acero horizontal EJE C TIPO V 25x50 3/8" 1 2 28.50 57.00baston positivo EJE C TIPO V 25x50 3/8" 1 4 18.25 73.00estribos tipo 1 EJE C TIPO V 25x50 3/8" 1 187 1.50 280.50
acero horizontal EJE 1 - 3 TIPO V 25x30 5/8" 0 4 4.90 0.00estribos tipo 2 EJE 1 - 3 TIPO V 25x30 3/8" 0 28 1.10 0.00acero horizontal EJE 6 - 8 TIPO V 25x30 5/8" 1 4 4.90 19.60estribos tipo 2 EJE 6 - 8 TIPO V 25x30 3/8" 1 28 1.10 30.80vigas 2do nivelacero horizontal TIPO V - 201 5/8" 1 4 9.75 39.00acero horizontal TIPO V - 201 1/2" 1 2 5.16 10.32baston positivo TIPO V - 201 5/8" 1 2 2.50 5.00estribos tipo 2 TIPO V - 201 3/8" 1 34 1.50 51.00estribos tipo 3 TIPO V - 201 3/8" 1 16 1.10 17.60
acero horizontal TIPO V - 202 5/8" 1 6 9.75 58.50acero horizontal TIPO V - 202 1/2" 1 2 9.75 19.50baston positivo TIPO V - 202 5/8" 1 4 3.30 13.20baston positivo TIPO V - 202 5/8" 1 2 2.30 4.60baston negativo TIPO V - 202 5/8" 1 1 3.75 3.75estribos tipo 1 TIPO V - 202 3/8" 1 63 1.50 94.50acero horizontal TIPO V - 203 5/8" 1 4 9.75 39.00acero horizontal TIPO V - 203 1/2" 1 2 2.60 5.20
baston positivo TIPO V - 203 5/8" 1 2 2.00 4.00estribos tipo 2 TIPO V - 203 3/8" 1 48 1.50 72.00estribos tipo 3 TIPO V - 203 3/8" 1 10 1.10 11.00
acero horizontal TIPO V - 204 5/8" 1 6 9.75 58.50acero horizontal TIPO V - 204 1/2" 1 2 9.75 19.50
HOJA DE METRADO DE ACEROOBRA:LUGAR: Arequipa
FECHA Mar-08REALIZADO POR: Juan Carlos Sanz David
ITEM ELEMENTO OBS. ACERO Nº E.E. Nº VAR- LU (m) 1/4" 3/8" 1/2" 5/8" 3/4" 1"
EN LA I. E. MANUEL SCORZA TORRES”
baston positivo TIPO V - 204 5/8" 1 4 3.30 13.20baston positivo TIPO V - 204 5/8" 1 3 2.30 6.90baston negativo TIPO V - 204 5/8" 1 2 3.75 7.50estribos tipo 1 TIPO V - 204 3/8" 1 65 1.50 97.50acero horizontal TIPO V - 205 5/8" 1 4 9.75 39.00acero horizontal TIPO V - 205 1/2" 1 2 9.75 19.50baston positivo TIPO V - 205 5/8" 1 2 2.00 4.00
estribos tipo 2 TIPO V - 205 3/8" 1 44 1.50 66.00estribos tipo 3 TIPO V - 205 3/8" 1 17 1.10 18.70acero horizontal TIPO V - 206 5/8" 1 6 10.80 64.80acero horizontal TIPO V - 206 1/2" 1 2 10.80 21.60baston positivo TIPO V - 206 5/8" 1 6 3.00 18.00baston positivo TIPO V - 206 5/8" 1 3 0.85 2.55baston negativo TIPO V - 206 5/8" 1 3 4.20 12.60estribos tipo 1 TIPO V - 206 3/8" 1 65 1.50 97.50acero horizontal TIPO V - 207 5/8" 1 6 10.80 64.80acero horizontal TIPO V - 207 1/2" 1 2 10.80 21.60
baston positivo TIPO V - 207 5/8" 1 4 3.85 15.40baston positivo TIPO V - 207 5/8" 1 0 0.00 0.00baston negativo TIPO V - 207 5/8" 1 0 0.00 0.00estribos tipo 1 TIPO V - 207 3/8" 1 65 1.50 97.50acero horizontal TIPO V - 208 5/8" 1 16 10.60 169.60acero horizontal TIPO V - 208 1/2" 1 2 2.60 5.20baston positivo TIPO V - 208 5/8" 1 0 0.00 0.00estribos tipo 1 TIPO V - 208 3/8" 1 65 1.50 97.50
acero horizontal eje 1 - 3 TIPO VA - 1 1/2" 0 4 7.82 0.00estribos tipo 4 eje 1 - 3 TIPO VA - 1 1/4" 0 40 0.90 0.00acero horizontal eje 6 - 8 TIPO VA - 1 1/2" 1 4 7.42 29.68
estribos tipo 4 eje 6 - 8 TIPO VA - 1 1/4" 1 40 0.90 36.00acero horizontal EJE 4 - 8 TIPO V A -1 1/2" 1 4 15.00 60.00
HOJA DE METRADO DE ACEROOBRA:LUGAR: Arequipa
FECHA Mar-08REALIZADO POR: Juan Carlos Sanz David
ITEM ELEMENTO OBS. ACERO Nº E.E. Nº VAR- LU (m) 1/4" 3/8" 1/2" 5/8" 3/4" 1"
EN LA I. E. MANUEL SCORZA TORRES”
estribos tipo 1 EJE 4 - 8 TIPO V A -1 1/4" 1 75 0.90 67.50acero horizontal EJE A TIPO V 25x50 5/8" 1 10 28.50 285.00acero horizontal EJE A TIPO V 25x50 3/8" 1 2 28.50 57.00baston positivo EJE A TIPO V 25x50 3/8" 1 4 18.25 73.00estribos tipo 1 EJE A TIPO V 25x50 3/8" 1 187 1.50 280.50acero horizontal EJE B TIPO V 25x50 5/8" 1 10 28.50 285.00acero horizontal EJE B TIPO V 25x50 3/8" 1 2 28.50 57.00
baston positivo EJE B TIPO V 25x50 3/8" 1 4 18.25 73.00estribos tipo 1 EJE B TIPO V 25x50 3/8" 1 187 1.50 280.50acero horizontal EJE C TIPO V 25x50 5/8" 1 10 28.50 285.00acero horizontal EJE C TIPO V 25x50 3/8" 1 2 28.50 57.00baston positivo EJE C TIPO V 25x50 3/8" 1 4 18.25 73.00estribos tipo 1 EJE C TIPO V 25x50 3/8" 1 187 1.50 280.50acero horizontal EJE 1 - 3 TIPO V 25x30 5/8" 0 4 4.90 0.00estribos tipo 2 EJE 1 - 3 TIPO V 25x30 3/8" 0 28 1.10 0.00acero horizontal EJE 6 - 8 TIPO V 25x30 5/8" 1 4 4.90 19.60estribos tipo 2 EJE 6 - 8 TIPO V 25x30 3/8" 1 28 1.10 30.80vigas 3er nivelacero horizontal TIPO V - 303 5/8" 1 4 9.75 39.00acero horizontal TIPO V - 303 1/2" 1 2 2.60 5.20baston positivo TIPO V - 303 5/8" 1 2 2.00 4.00estribos tipo 2 TIPO V - 303 3/8" 1 48 1.50 72.00estribos tipo 3 TIPO V - 303 3/8" 1 10 1.10 11.00acero horizontal TIPO V - 304 5/8" 1 6 9.75 58.50acero horizontal TIPO V - 304 1/2" 1 2 9.75 19.50
baston positivo TIPO V - 304 5/8" 1 4 3.30 13.20baston positivo TIPO V - 304 5/8" 1 3 2.30 6.90baston negativo TIPO V - 304 5/8" 1 2 3.75 7.50
estribos tipo 1 TIPO V - 304 3/8" 1 65 1.50 97.50acero horizontal TIPO V - 305 5/8" 1 4 10.60 42.40
HOJA DE METRADO DE ACEROOBRA:LUGAR: Arequipa
FECHA Mar-08REALIZADO POR: Juan Carlos Sanz David
ITEM ELEMENTO OBS. ACERO Nº E.E. Nº VAR- LU (m) 1/4" 3/8" 1/2" 5/8" 3/4" 1"
EN LA I. E. MANUEL SCORZA TORRES”
acero horizontal TIPO V - 305 1/2" 1 2 10.60 21.20baston positivo TIPO V - 305 5/8" 1 2 2.00 4.00estribos tipo 2 TIPO V - 305 3/8" 1 44 1.50 66.00estribos tipo 3 TIPO V - 305 3/8" 1 17 1.10 18.70acero horizontal TIPO V - 306 5/8" 1 6 10.80 64.80acero horizontal TIPO V - 306 1/2" 1 2 10.80 21.60baston positivo TIPO V - 306 5/8" 1 6 3.00 18.00
baston positivo TIPO V - 306 5/8" 1 3 0.85 2.55baston negativo TIPO V - 306 5/8" 1 3 4.20 12.60estribos tipo 1 TIPO V - 306 3/8" 1 65 1.50 97.50acero horizontal TIPO V - 307 5/8" 1 6 10.80 64.80acero horizontal TIPO V - 307 1/2" 1 2 10.80 21.60baston positivo TIPO V - 307 5/8" 1 4 3.85 15.40baston positivo TIPO V - 307 5/8" 1 0 0.00 0.00baston negativo TIPO V - 307 5/8" 1 0 0.00 0.00estribos tipo 1 TIPO V - 307 3/8" 1 65 1.50 97.50acero horizontal TIPO V - 308 5/8" 1 16 10.60 169.60
acero horizontal TIPO V - 308 1/2" 1 2 2.60 5.20baston positivo TIPO V - 308 5/8" 1 0 0.00 0.00estribos tipo 1 TIPO V - 308 3/8" 1 65 1.50 97.50acero horizontal eje 6 - 8 TIPO VA - 1 1/2" 1 4 7.42 29.68estribos tipo 4 eje 6 - 8 TIPO VA - 1 1/4" 1 40 0.90 36.00acero horizontal EJE 4 - 8 TIPO V A -1 1/2" 1 4 15.00 60.00estribos tipo 1 EJE 4 - 8 TIPO V A -1 1/4" 1 75 0.90 67.50acero horizontal EJE A TIPO V 25x50 5/8" 1 6 20.00 120.00
acero horizontal EJE A TIPO V 25x50 3/8" 1 2 20.00 40.00baston positivo EJE A TIPO V 25x50 3/8" 1 4 18.25 73.00estribos tipo 1 EJE A TIPO V 25x50 3/8" 1 145 1.50 217.50
acero horizontal EJE B TIPO V 25x50 5/8" 1 6 20.00 120.00acero horizontal EJE B TIPO V 25x50 3/8" 1 2 20.00 40.00
HOJA DE METRADO DE ACEROOBRA:LUGAR: Arequipa
FECHA Mar-08REALIZADO POR: Juan Carlos Sanz David
ITEM ELEMENTO OBS. ACERO Nº E.E. Nº VAR- LU (m) 1/4" 3/8" 1/2" 5/8" 3/4" 1"
EN LA I. E. MANUEL SCORZA TORRES”
baston positivo EJE B TIPO V 25x50 3/8" 1 4 18.25 73.00estribos tipo 1 EJE B TIPO V 25x50 3/8" 1 145 1.50 217.50acero horizontal EJE C TIPO V 25x50 5/8" 1 6 20.00 120.00acero horizontal EJE C TIPO V 25x50 3/8" 1 2 20.00 40.00baston positivo EJE C TIPO V 25x50 3/8" 1 4 18.25 73.00estribos tipo 1 EJE C TIPO V 25x50 3/8" 1 145 1.50 217.50acero horizontal EJE 6 - 8 TIPO V 25x30 5/8" 1 4 4.90 19.60
estribos tipo 2 EJE 6 - 8 TIPO V 25x30 3/8" 1 28 1.10 30.80SECTOR Bvigas 1er nivelacero horizontal TIPO V - 101 5/8" 1 4 9.90 39.60acero horizontal TIPO V - 101 1/2" 1 4 2.60 10.40estribos tipo 2 TIPO V - 101 3/8" 1 22 1.50 33.00estribos tipo 3 TIPO V - 101 3/8" 1 21 1.10 23.10acero horizontal TIPO V - 102 5/8" 1 6 9.90 59.40acero horizontal TIPO V - 102 1/2" 1 2 9.90 19.80baston positivo TIPO V - 102 5/8" 1 4 3.85 15.40
baston positivo TIPO V - 102 5/8" 1 2 2.30 4.60baston negativo TIPO V - 102 5/8" 1 2 4.45 8.90estribos tipo 1 TIPO V - 102 3/8" 1 65 1.50 97.50acero horizontal TIPO V - 103 5/8" 1 4 9.90 39.60acero horizontal TIPO V - 103 1/2" 1 4 2.60 10.40estribos tipo 2 TIPO V - 103 3/8" 1 22 1.50 33.00estribos tipo 3 TIPO V - 103 3/8" 1 27 1.10 29.70acero horizontal TIPO V - 104 5/8" 1 6 9.90 59.40
acero horizontal TIPO V - 104 1/2" 1 2 9.90 19.80baston positivo TIPO V - 104 5/8" 1 4 3.85 15.40baston positivo TIPO V - 104 5/8" 1 2 2.30 4.60
baston negativo TIPO V - 104 5/8" 1 2 4.45 8.90estribos tipo 1 TIPO V - 104 3/8" 1 65 1.50 97.50
HOJA DE METRADO DE ACEROOBRA:LUGAR: Arequipa
FECHA Mar-08REALIZADO POR: Juan Carlos Sanz David
ITEM ELEMENTO OBS. ACERO Nº E.E. Nº VAR- LU (m) 1/4" 3/8" 1/2" 5/8" 3/4" 1"
EN LA I. E. MANUEL SCORZA TORRES”
acero horizontal TIPO V - 105 5/8" 1 4 9.90 39.60acero horizontal TIPO V - 105 1/2" 1 4 2.60 10.40estribos tipo 2 TIPO V - 105 3/8" 1 20 1.50 30.00estribos tipo 3 TIPO V - 105 3/8" 1 27 1.10 29.70acero horizontal TIPO VA - 1 1/2" 1 4 2.71 10.84estribos tipo 4 TIPO VA - 1 1/4" 1 20 0.90 18.00acero horizontal TIPO VS - 1 1/2" 1 4 10.85 43.40
estribos tipo 4 TIPO VS - 1 1/4" 1 46 0.90 41.40acero horizontal EJE A TIPO V 25x50 5/8" 1 4 23.65 94.60acero horizontal EJE A TIPO V 25x50 1/2" 1 2 23.65 47.30baston positivo EJE A TIPO V 25x50 1/2" 1 4 18.25 73.00estribos tipo 1 EJE A TIPO V 25x50 3/8" 1 152 1.50 228.00acero horizontal EJE B TIPO V 25x50 5/8" 1 4 18.85 75.40acero horizontal EJE B TIPO V 25x50 1/2" 1 6 18.85 113.10estribos tipo 1 EJE B TIPO V 25x50 3/8" 1 128 1.50 192.00acero horizontal EJE C TIPO V 25x45 5/8" 1 4 17.50 70.00estribos tipo 1 EJE C TIPO V 25x45 3/8" 1 152 1.50 228.00vigas 2do nivelacero horizontal TIPO V - 201 5/8" 1 4 9.90 39.60acero horizontal TIPO V - 201 1/2" 1 4 2.60 10.40estribos tipo 2 TIPO V - 201 3/8" 1 22 1.50 33.00estribos tipo 3 TIPO V - 201 3/8" 1 21 1.10 23.10acero horizontal TIPO V - 202 5/8" 1 6 9.90 59.40acero horizontal TIPO V - 202 1/2" 1 2 9.90 19.80baston positivo TIPO V - 202 5/8" 1 4 3.85 15.40
baston positivo TIPO V - 202 5/8" 1 2 2.30 4.60baston negativo TIPO V - 202 5/8" 1 2 4.45 8.90estribos tipo 1 TIPO V - 202 3/8" 1 65 1.50 97.50
acero horizontal TIPO V - 203 5/8" 1 4 9.90 39.60acero horizontal TIPO V - 203 1/2" 1 4 2.60 10.40
HOJA DE METRADO DE ACEROOBRA:LUGAR: Arequipa
FECHA Mar-08REALIZADO POR: Juan Carlos Sanz David
ITEM ELEMENTO OBS. ACERO Nº E.E. Nº VAR- LU (m) 1/4" 3/8" 1/2" 5/8" 3/4" 1"
EN LA I. E. MANUEL SCORZA TORRES”
estribos tipo 2 TIPO V - 203 3/8" 1 22 1.50 33.00estribos tipo 3 TIPO V - 203 3/8" 1 27 1.10 29.70acero horizontal TIPO V - 204 5/8" 1 6 9.90 59.40acero horizontal TIPO V - 204 1/2" 1 2 9.90 19.80baston positivo TIPO V - 204 5/8" 1 4 3.85 15.40baston positivo TIPO V - 204 5/8" 1 2 2.30 4.60baston negativo TIPO V - 204 5/8" 1 2 4.45 8.90
estribos tipo 1 TIPO V - 204 3/8" 1 65 1.50 97.50acero horizontal TIPO V - 205 5/8" 1 4 9.90 39.60acero horizontal TIPO V - 205 1/2" 1 4 2.60 10.40estribos tipo 2 TIPO V - 205 3/8" 1 20 1.50 30.00estribos tipo 3 TIPO V - 205 3/8" 1 27 1.10 29.70acero horizontal EJE A TIPO V 25x50 5/8" 1 4 17.50 70.00acero horizontal EJE A TIPO V 25x50 1/2" 1 2 17.50 35.00baston positivo EJE A TIPO V 25x50 1/2" 1 4 17.50 70.00estribos tipo 1 EJE A TIPO V 25x50 3/8" 1 114 1.50 171.00acero horizontal EJE B TIPO V 25x50 5/8" 1 4 17.50 70.00
acero horizontal EJE B TIPO V 25x50 1/2" 1 6 17.50 105.00estribos tipo 1 EJE B TIPO V 25x50 3/8" 1 114 1.50 171.00acero horizontal EJE C TIPO V 25x45 5/8" 1 4 17.50 70.00
estribos tipo 1 EJE C TIPO V 25x45 3/8" 1 152 1.50 228.00totales en m 419.60 7531.00 1367.32 4893.25 0.00 0.00
totales en kg 108.05 4499.02 1436.51 8015.14 0.00 0.00
totales en varillas 49.00 862.00 157.00 571.00 0.00 0.00