Project Status and Update Mega Expansion Project KFSH& RC, Jeddah Bismilllah ar–Rahman ar-Rahim View on the Oncology Building Follow this link to KFSH&RC-J Website: http://ig.kfshrc.edu.sa/wps/portal/ Monthly Report No. 23 April 2015 Areal view on the Oncology Building
6

Mega Expansion Project KFSH& RC, Jeddah · Page 2 Mega-Expansion Project UPCOMING ACTION ITEMS APRIL SITE ACTIVITIES General Piling Phase II underway 52 of 344 Piles completed (288

Aug 09, 2020

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Mega Expansion Project KFSH& RC, Jeddah · Page 2 Mega-Expansion Project UPCOMING ACTION ITEMS APRIL SITE ACTIVITIES General Piling Phase II underway 52 of 344 Piles completed (288

Project Status and Update

Mega Expansion Project KFSH& RC, Jeddah

Bismilllah ar–Rahman ar-Rahim

View on the Oncology Building

Follow this link to KFSH&RC-J Website: http://ig.kfshrc.edu.sa/wps/portal/

Monthly Report No. 23 April 2015

Areal view on the Oncology Building

Page 2: Mega Expansion Project KFSH& RC, Jeddah · Page 2 Mega-Expansion Project UPCOMING ACTION ITEMS APRIL SITE ACTIVITIES General Piling Phase II underway 52 of 344 Piles completed (288

Page 2 Mega-Expansion Project

UPCOMING ACTION ITEMS

APRIL SITE ACTIVITIES

General

Piling Phase II underway 52 of 344 Piles completed (288 Remaining)

27 cranes are now erected across the site

Oncology

First section of LINAC Vault walls cast successfully

Core 9 elevator walls cast up to level 1; Core walls cast to level 2

Tower level 3 part slab cast

Tower level 2 slab under construction

Block walls to the perimeter of the building and internal walls proceeding

Medical Areas

Raft sections being cast in ACC, D&T and Pediatrics Tunnel

High level raft sections in all areas being cast

Scaffold and slab decking for Tunnel roof underway in ACC and Pediatrics

Scaffold and slab decking to level 2 slab underway in all areas

Academic/Administration/Research complex

Columns up to level 1 in Research & Administration Buildings

Fist section of level 2 slab in Admin cast and underway in Research Building

Waterproofing & rebar to Academic Building raft slab underway

Central Utility Plant (CUP)/Kitchen & Laundry area

Walls in Water Tank under construction

CUP columns and walls cast

Casting Kitchen & Laundry raft strips

Casting CUP & Medical Powerhouses columns

Follow this link to KFSH&RC-J Website: http://ig.kfshrc.edu.sa/wps/portal/

Page 3: Mega Expansion Project KFSH& RC, Jeddah · Page 2 Mega-Expansion Project UPCOMING ACTION ITEMS APRIL SITE ACTIVITIES General Piling Phase II underway 52 of 344 Piles completed (288

Page 3 Mega-Expansion Project

APRIL SITE PHOTOGRAPHS

Follow this link to KFSH&RC-J Website: http://ig.kfshrc.edu.sa/wps/portal/

Oncology: Core 10 Elevator & Stair 30 walls level 1 to level 2

Oncology Tunnel: Core 9 Elevator walls rebar & closing shutters ready to cast

Page 4: Mega Expansion Project KFSH& RC, Jeddah · Page 2 Mega-Expansion Project UPCOMING ACTION ITEMS APRIL SITE ACTIVITIES General Piling Phase II underway 52 of 344 Piles completed (288

Page 4 Mega-Expansion Project

APRIL SITE PHOTOGRAPHS

Follow this link to KFSH&RC-J Website: http://ig.kfshrc.edu.sa/wps/portal/

ACC Tunnel: Rebar to walls; waterproofing & backfilling outside the tunnel

ACC Tunnel: Decking to the Tunnel roof slab

Page 5: Mega Expansion Project KFSH& RC, Jeddah · Page 2 Mega-Expansion Project UPCOMING ACTION ITEMS APRIL SITE ACTIVITIES General Piling Phase II underway 52 of 344 Piles completed (288

Page 5 Mega-Expansion Project

APRIL SITE PHOTOGRAPHS

Follow this link to KFSH&RC-J Website: http://ig.kfshrc.edu.sa/wps/portal/

Administration Building: First section of level 2 slab cast

ICU Tunnel: Puddle flanged sleeves through the Water Tank

Page 6: Mega Expansion Project KFSH& RC, Jeddah · Page 2 Mega-Expansion Project UPCOMING ACTION ITEMS APRIL SITE ACTIVITIES General Piling Phase II underway 52 of 344 Piles completed (288

Page 6 Mega-Expansion Project

APRIL SITE PHOTOGRAPHS

Follow this link to KFSH&RC-J Website: http://ig.kfshrc.edu.sa/wps/portal/

CUP: View looking NE of CUP slab and columns cast

Inpatients North: Construction works around Core 1 Elevators