MEETING MINUTES January 15, 2008 Attendees · MEETING MINUTES January 15, 2008 Attendees: ... The document went from 4 pages to 16, demonstrating how much legalese is required to
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Minutes by: Cindy Preuss, Harris & Associates 1 Secretary, Nor Cal PUG
Presentation: Environmental Considerations with Pipeline Construction by Robin Cort and Erin Darling of RMC Water and Environment. Robin and Erin gave an overview of CEQA and NEPA requirements and applicability to various pipeline projects. In addition, regulatory permit requirements with various governing agencies were covered. The presentation slides were printed and provided to all in attendance, and are
Minutes by: Cindy Preuss, Harris & Associates 2 Secretary, Nor Cal PUG
attached at the end of these minutes. Rather than outline the presentation herein, the reader is directed to the detailed slides at back. A big thank you to Robin and Erin for this informative presentation! General: Seminar Status: Registration forms were sent out last week. We’ve had a lot of vendor interest for tabletop exhibits so these are expected to go fast. As a head’s-up, if individuals have issues getting their checks processed through their agency quickly to accompany their registration forms, these individuals are advised to send in the registration forms sans payment and indicate on the forms when the payment will be forthcoming. Paying at the door is an option as well. This year we expect approximately 175 people. 2008 Speaker Calendar: 2008 is filled up, but the presentations may change place within the year and some speakers have yet to lock in confirmation. As always, Cindy will give as much notice as possible if there is a topic change so that members may plan their attendance accordingly. The 8-hr course on CIPP will be held in October but the exact date has yet to be set. Classes will likely be held at CCCSD but notice will be given as locations are locked in. Bylaws Legal Review: Our Bylaws was revamped by the attorney. The document went from 4 pages to 16, demonstrating how much legalese is required to protect our group and governing body from lawsuits. The Executive Committee will return comments to the lawyer soon, and we expect adoption in March. IRS & State Attorney General’s Filing Status: Jonathan has a meeting with the accountant tomorrow afternoon. Will prepare schedule of annual filing forms and deadlines to keep us on track for future years. Per federal requirements, the financial statement will be posted to the PUG website once we figure out how to do that. Announcements & Project Discussions: The National No-Dig Conference in Dallas is coming up in April 2008. Next Meeting: Our next meeting will be held TUESDAY, MARCH 18, 2008 at the offices of Brown & Caldwell located at 201 N. Civic Dr., Suite 300, Walnut Creek, CA. The topic will be on Permitting Guidelines, given by Serge Glushkoff of the Department of Fish & Game. Please call (925) 827-4900 ext 176 or email [email protected] to RSVP.
Innovative Solutions for Water and the Environment
Environmental Considerations for Pipeline Construction: CEQA and Permitting RequirementsPresentation to Pipe Users Group Meeting
Presenters:Erin DarlingRobin Cort
January 15, 2008
Presentation Outline
• CEQA Overview • Common Challenges & the Future of CEQA• Key environmental permits
404 permitsStreambed alteration agreementsGeneral NPDES permit for construction (SWPPP)
CEQA Overview
• What is NEPA? CEQA?• When does CEQA apply?• Who are the main players in the CEQA process?• What is involved in the CEQA process?
National Environmental Policy Act of 1969
History• Signed into law on Jan 1, 1970• Developed in response to criticism that
environmental factors were being ignored
Key Points• Established a national policy to protect the
environment• Established the Council on Environmental
Quality (CEQ)• Required that all Federal agencies
integrate environmental concerns into their planning and decision making processes
National Environmental Policy Act of 1969
Applicability• Federal projects or projects
involving Federal agencies • Actions that have the
potential to significantly impact the environment
California Environmental Quality Act
History• Enacted in 1970• California the first of 15 states to enact a
law modeled after NEPA
Objectives• Disclose environmental impacts • Avoid or reduce environmental damage
when feasible• Explain why environmental damage
allowed to occur• Foster interagency coordination• Enhance public participation
California Environmental Quality Act
Applicability• Applies to State and local
agencies• CEQA applies to all projects
subject to public agency discretionary action
• CEQA is continuously modified by Legislature and interpreted by the courts
Review for Exemptions
Initial Study
Negative Declaration or
Mitigated Negative Declaration
EIRNotice of Preparation
Scoping
Draft EIR
Public and Agency Review
State Clearinghouse Review
Final EIR
Review of Responses by Commenting Agencies
Agency Decision
Findings: Statement of Overriding Consideration;
Mitigation Monitoring Program
Exempt
NEPA CEQAReview for Exclusions
Environmental Assessment
Finding of No Significant
Impacts
EISNotice of Intent
Scoping
Draft EIS
Public and Agency Review
EPA Filing; Federal Register
Final EIS
Public & Agency Review; EPA filing; Federal Register Notice
Agency Decision
Record of Decision
Excluded
NEPA vs. CEQA - Major Differences
EIS must treat alternatives with relatively similar level of detail
Need only explain why the decision was made
No specific statute of limitation
Must prepare only if there is substantial evidence that project may have significant impact
Only need to consider impacts of each alternative
NEPA
EIR must compare alternatives, but may evaluate them in less detail than the proposed project
Must explain whether each impact was mitigated and if not, why
Short statue of limitation for legal challenges
Must prepare if “fair argument” can be made that the project may have a significant impact
Must mitigate impacts if feasible
CEQA
Integration with other Environmental Laws
• Joint NEPA/CEQA documentsEx: EIR/EIS, Negative Declaration/FONSIState/Local agencies can “adopt” a NEPA document for CEQA compliance, but generally not the other way around
• CEQA-PlusState Revolving Fund (SRF) FundingPartially funded by US EPA, thus is subject to Federal regulationIn addition to CEQA, must comply with:
• Endangered Species Act (ESA)• National Historic Preservation Act (NHPA)• Federal General Conformity Rule for the Clean Air Act (CAA)
• Permitting actions
Activities Subject to CEQA
• Applies to discretionary, not ministerial, actionsDiscretionary: Exercise of judgment or deliberationMinisterial: Compliance with fixed statutes, regulations, standards
• Action is a “Project” as defined by CEQA• Project has the potential to result in a direct or
• Initiated by a Public Agency, including: Public works construction activitiesClearing or grading of landImprovements to existing public structures
• Funded, in whole or in part, by a public agency • Approved by a public agency (permits, leases,
plan changes) • In determining if an activity is a “project” you
must look at all of the parts, components, and phases of the activity
What is a “Significant Effect on the Environment”?
• Substantial, or potentially substantial, adverse change in any of the physical conditions within the area affected by the project including land, air, water, minerals, flora, fauna, ambient noise, and objects of historic or aesthetic significance. A social or economic change by itself shall not be considered a significant effect on the environment (CCR §15382)
Key Players in the CEQA Process
Concerned Citizens and
Organizations
Courts
Trustee Agencies
Project Applicants
Environmental Consultants
Responsible Agencies
Agencies with
Jurisdiction by Law
Lead Agency
(CEQA Deskbook, 1999)
CEQA Lead Agency
• State or local agencyCity or CountyWater or wastewater districtRegulatory agency
• Usually agency proposing project or with primary approval for private project
• Primary responsibility to fulfill CEQA requirements
Screening Criteria for CEQA ProcessIs it an activity with no possibility of a
significant impact?
Is the activity outside the definition of a project?
Is the project described in a Statutory Exemption?
Is the project described in a Categorical Exemption?
Is the project fully covered by a previous EIR, Program EIR, or Master EIR?
Does the Initial Study show that the project will have no significant impact?
Activities outside of CEQA
Notice of Exemption (optional)
Finding of no new impact or mitigated
Negative Declaration
Negative Declaration
EIR
YES
YES
YES
YES
YES
YES
NO
NO
NO
NO
NO
NO
(CEQA Deskbook, 1999)
Exemptions to CEQA
• Statutory Exemptions Legislature established exemptions for many types of projects
• Ministerial actions• Emergency actions• Feasibility or Planning Studies for Possible Future Actions
New or replacement pipelines are exempt if < 1 mile long and in public right-of-way.
Exemptions to CEQA
• Categorical ExemptionsClasses of projects that generally don’t have significant impactsOver 30 categories (classes) of projects covered, including:
• Minor alterations to existing pipelines• Replacement or reconstruction of existing pipeline involving
negligible or no expansion of capacity
• Notice of Exemption (optional)Shortens time for legal challenge
Initial Studies
When is an Initial Study prepared?• Significance of impacts is not clear• Negative Declaration/Mitigated Negative Declaration
expected to be prepared• Sometimes as part of EIR process
Purpose• Determine potential for significant impacts• Decide what level of analysis should be completed• Refine issues to be addressed in an EIR
Initial Studies
Contents of an Initial Study• Project Description• Environmental setting• Discussion of environmental effects
Standard “checklist” often used • Mitigation measures• Consistency with plans and policies• List of preparers
Thresholds of Significance
• No Impact• Less than Significant• Less than Significant with Mitigation• Significant and Unavoidable
When is a Negative Declaration (ND) prepared?• No substantial evidence that a significant effect may occur• Rarely prepared, often challenged
When is a Mitigated Negative Declaration (MND) prepared?• Initial Study identifies a potentially significant effect• Project proponent makes or agrees to make project revisions that
mitigate effects to a point where “clearly” no significant effect would occur
Contents of an ND/MND• Project Description• Project Location• Identification of project proponent• Proposed finding of no significant effect• Copy of Initial Study justifying the finding• Mitigation measures included in project description to avoid
• No public hearing required• Public comment must be considered but responses are not required
(but a good idea)
Environmental Impact Reports
When is an Environmental Impact Report (EIR) prepared?• An activity is determined to be a project• Project is not exempt from CEQA• Project potentially causes significant and unavoidable effects on the
environment
Purposes of an EIR• Inform decision makers and the public about a project’s significant
environmental effects and ways to reduce them• Demonstrate that the environment is being protected• Ensure political accountability by disclosing to citizens the
environmental values held by their elected and appointed officials
Environmental Impact Reports
Primary Types of EIRs• Project EIR• Program EIR• Master EIR and Focused EIR• Subsequent EIR, Supplemental EIR, Addendum
to EIR
Environmental Impact Reports
Contents of a Draft EIR• Summary• Project Description• Environmental Setting• Significant environmental impacts
Direct, indirect, short-term, long-term, cumulative, unavoidable impacts• Areas of known controversy• Alternatives to the proposed project
No-Project AlternativeEnvironmentally superior alternative
• Mitigation measures for the significant environmental effects• Growth-inducing impacts
Environmental Impact Reports
• Aesthetics• Air Quality• Biological Resources• Cultural Resources• Geology and Soils• Hazards and Hazardous
Materials• Hydrology and Water Quality
• Land Use and Planning• Mineral Resources• Noise• Population and Housing• Public Services• Recreation• Transportation/Traffic• Utilities and Service Systems
Typical Resource Sections
Environmental Impact Reports
Contents of a Final EIR• Comments on Draft EIR• List of commenters• Responses to environmental points raised• Draft EIR
Environmental Impact ReportsInitial Study
(optional)
Notice of Preparation
Review of NOP (30 days)
Public Review (30 – 45 days)
Final EIR Certified
Lead Agency Decides on
Project
Findings Written and Adopted
Draft EIR Notice of completion
Public Hearing
(optional)
Response to Comments
Notice of Determination filed
(5 days from approval)
Mitigation Reporting and
Monitoring Program Adopted
Responsible Agency Decision (180 days from Lead Agency
Decision)
Scoping Meeting
(optional)
Document Comparison
30-day30-dayStatute of LimitationsFindings & NODNeg DecDecisions Document30-45 days min20-30 days minPublic Comment Period
100-1,000 pages15-150 pagesDocument Length12-36 months4-12 monthsTime to Complete
EIRIS/MND
Common Challenges & the Future of CEQA
• CEQA Concerns (from engineers)• Avoiding the Pitfalls• Other CEQA Concerns• Can CEQA Change?
Common Concerns (from engineers)
• CEQA process takes too long!3 years for an EIR considered standard by some agencies
• It costs too much!As much as 35% of total project planning/design cost
• Inconsistent requirements• Planners want too much information too soon• CEQA process forces project changes at
inconvenient times
Avoiding the Pitfalls• Insufficient budget• Poor communication
Good communication between planners, engineers, lead agency and regulatory agencies is essential
• Incomplete project descriptionsGive options/ranges if final decision has not yet been made
• Inadequate record keepingKeep good records/files (you could get sued!)
• Negative public reactionGood public outreach is essential
• Starting too late
Other Common Concerns
• Documents are cumbersomefocus more on pleasing the lawyers than on protecting the environment
• Gives too much power to the NIMBYs• Inhibits implementation of good projects• Poor integration with other environmental laws
and regulations
Can CEQA Change?• Practice
Larger agencies often lead the way• Legislative changes
Several streamlining reforms passed by the Legislature in mid-90’sBroad legislative reforms would be difficult to implement
• Case lawCEQA regulations are continually altered to reflect results of lawsuits
CEQA Case Law
• CEQA enforcement is left to citizen court challenge
• ~ 1 in 354 Initial Studies end up in a lawsuit• ~ 1 in 18 EIRs end up in a lawsuit• Statues of limitations exist• CEQA lawsuits are often won or lost based on
the evidence in the administrative record
CEQA and Global Warming• In water supply impact analysis, consider global
warming effects when:Describing reliability of proposed water suppliesDescribing reliability of alternativesEvaluating environmental effects of alternatives
• Other impact analyses to includeFlooding risks due to global warmingProject contributions to cumulative air quality impacts, and GHG mitigation measures
My CEQA document is done – now what do I do?
Major Environmental Permits
• 404 Permit – U.S. Army Corps of Engineers• Streambed alteration agreement – California
Department of Fish and Game• General NPDES permit for construction Notice
of Intent – Regional Water Quality Control Board
404 Permit – When is it needed?
• Any project placing fill in a wetland or “water of the U.S.”
• Waters of the U.S. are essentially all surface waters, so permits are required for:
Any pipeline crossing a stream using cut and cover constructionAny pipeline crossing an “adjacent” wetland
Corps Jurisdiction under Section 404
Types of 404 Permits
• Nationwide PermitA general permit authorizing categories of activitiesValid only if applicable conditions are metNationwide 12 authorizes Utility Line Activities
• Bottom contours not changed• ½ acre or less
Most projects require Pre-construction Notification• Individual Permit
Required for any project that exceeds limits established in Nationwide PermitRequires full public interest review of application
404 Permit Process
• Delineate wetlands and obtain Corps verification• Submit application showing amount of wetlands affected• Include mitigation to minimize impacts and compensate
for any unavoidable loss of wetlands• Must demonstrate that you are implementing the “Least
• May require purchase of mitigation credits at a mitigation bank for permanent impacts
• Corps must file public notice before issuing permit
404 Permit – Associated Requirements
• 401 Water Quality Certification – RWQCB• Consultation with USFWS and NMFS• Compliance with Section 106 (National Historic
Preservation Act) - SHPO
404 Permit Schedule Requirements
• Allow at least a year for Individual Permit1-6 months for delineation2-6 months for verification2-4 months for permit processingAdditional time if hearing or NEPA document is needed
• Nationwide permits can be done in 6 months or less
Streambed Alteration Agreement
• DFG has jurisdiction over bed, channel & bank of rivers streams and lakes
• Required for all stream crossings (even if you tunnel under the stream)
• Submit application with detailed crossing design to CDFG
• Include frac-out plan for tunneled crossings
Time frame for Streambed Alteration Agreement
• Takes about 90 daysDFG has 30 days to determine completeness60 days to provide draft agreement to applicantApplicant has 30 days to review and sign
General NPDES Construction Permit
• Required for any construction site over 1 acre• Submit NOI for coverage under general permit to
RWQCB• Requires preparation of Storm Water Pollution
Prevention Plan• NOI typically submitted by contractor