LISD Board of Trustees Construction Committee Meeting Tuesday, December 11, 2001
39

LISD Board of Trustees Construction Committee Meeting Tuesday, December 11, 2001.

Dec 29, 2015

Download

Documents

Opal Flowers
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: LISD Board of Trustees Construction Committee Meeting Tuesday, December 11, 2001.

LISD Board of Trustees

Construction Committee Meeting

Tuesday, December 11, 2001

Page 2: LISD Board of Trustees Construction Committee Meeting Tuesday, December 11, 2001.

Farias Elementary School

Construction Committee Meeting

Tuesday, December 11, 2001

Page 3: LISD Board of Trustees Construction Committee Meeting Tuesday, December 11, 2001.

THIS VIEW IS LOOKING NORTH WEST AT THE BUILDING PAD. PAD IS WET DUE TO RECENT RAINS.

THIS VIEW IS LOOKING NORTH WEST AT THE BUILDING PAD. PAD IS WET DUE TO RECENT RAINS.

Page 4: LISD Board of Trustees Construction Committee Meeting Tuesday, December 11, 2001.

THIS VIEW IS LOOKING NORTHEAST AT THE BUILDING PAD. SURVEYORS ARE SETTING THE CORNER PINS FOR

THE BUILDING.

THIS VIEW IS LOOKING NORTHEAST AT THE BUILDING PAD. SURVEYORS ARE SETTING THE CORNER PINS FOR

THE BUILDING.

Page 5: LISD Board of Trustees Construction Committee Meeting Tuesday, December 11, 2001.

Santa Maria Elementary SchoolSanta Maria Elementary School

Construction Committee MeetingConstruction Committee Meeting

Tuesday, December 11, 2001Tuesday, December 11, 2001

Page 6: LISD Board of Trustees Construction Committee Meeting Tuesday, December 11, 2001.

PLUMBING SUBCONTRACTOR TRENCHING FOR THE INSTALLATION OF PLUMBING LINES.

PLUMBING SUBCONTRACTOR TRENCHING FOR THE INSTALLATION OF PLUMBING LINES.

Page 7: LISD Board of Trustees Construction Committee Meeting Tuesday, December 11, 2001.

THE PLUMBING LINES PREFABRICATED ON SITE FOR INSTALLATION IN THE PLUMBING TRENCH.

THE PLUMBING LINES PREFABRICATED ON SITE FOR INSTALLATION IN THE PLUMBING TRENCH.

Page 8: LISD Board of Trustees Construction Committee Meeting Tuesday, December 11, 2001.

PREPARATION OF THE BUILDING PAD AT THE BUILDING.

PREPARATION OF THE BUILDING PAD AT THE BUILDING.

Page 9: LISD Board of Trustees Construction Committee Meeting Tuesday, December 11, 2001.

Dovalina Elementary SchoolDovalina Elementary School

Construction Committee MeetingConstruction Committee Meeting

Tuesday, December 11, 2001Tuesday, December 11, 2001

Page 10: LISD Board of Trustees Construction Committee Meeting Tuesday, December 11, 2001.

VIEW LOOKING NORTH WEST AT THE CONCRETE FOUNDATION. MASONRY BLOCK WALLS BEING

CONSTRUCTED.

VIEW LOOKING NORTH WEST AT THE CONCRETE FOUNDATION. MASONRY BLOCK WALLS BEING

CONSTRUCTED.

Page 11: LISD Board of Trustees Construction Committee Meeting Tuesday, December 11, 2001.
Page 12: LISD Board of Trustees Construction Committee Meeting Tuesday, December 11, 2001.

SOUTHEAST VIEW OF THE COMPLETED FOUNDATION SYSTEM.

SOUTHEAST VIEW OF THE COMPLETED FOUNDATION SYSTEM.

Page 13: LISD Board of Trustees Construction Committee Meeting Tuesday, December 11, 2001.
Page 14: LISD Board of Trustees Construction Committee Meeting Tuesday, December 11, 2001.

Project:Christen Middle School

Architect: Sepulveda Associates Architects, Inc.

Status: Design Development

Budget: $7,193,380.

Timeline:

Start of Final Design Phase: Jan 2002

Present Final Contract Dwgs: Mar 2002

Completion of Construction: Dec 2003

Page 15: LISD Board of Trustees Construction Committee Meeting Tuesday, December 11, 2001.

Project: Martin High School

Architect: Sepulveda Associates Architects, Inc.

Status: Design Development

Budget: $7,823,946.

Timeline:

Start of Final Design Phase: Dec 2001

Present Final Contract Dwgs: Feb 2002

Completion of Construction: May 2003

Page 16: LISD Board of Trustees Construction Committee Meeting Tuesday, December 11, 2001.

Ochoa/T. Sanchez Elementary School

Construction Committee Meeting

Tuesday, December 11, 2001

Page 17: LISD Board of Trustees Construction Committee Meeting Tuesday, December 11, 2001.

THIS VIEW IS LOOKING SOUTH EAST AT THE BUILDING PAD.

THIS VIEW IS LOOKING SOUTH EAST AT THE BUILDING PAD.

Page 18: LISD Board of Trustees Construction Committee Meeting Tuesday, December 11, 2001.
Page 19: LISD Board of Trustees Construction Committee Meeting Tuesday, December 11, 2001.
Page 20: LISD Board of Trustees Construction Committee Meeting Tuesday, December 11, 2001.

EXISTING CITY SEWER LINE BEING REROUTED. NEW SEWER LINE BEING INSTALLED.

EXISTING CITY SEWER LINE BEING REROUTED. NEW SEWER LINE BEING INSTALLED.

Page 21: LISD Board of Trustees Construction Committee Meeting Tuesday, December 11, 2001.

Project: K.Tarver Elementary School

Architect: Cavazos & Associates Architects

Status: Design Development

Budget: $ 4,606,191.00 Dlls.Timeline:

Start of Final Design Phase: Feb 2002

Present Final Contract Dwgs: April 2002

Completion of Construction: June 2003

Page 22: LISD Board of Trustees Construction Committee Meeting Tuesday, December 11, 2001.

C.L. Milton Elementary School

Construction Committee Meeting

Tuesday, December 11, 2001

Page 23: LISD Board of Trustees Construction Committee Meeting Tuesday, December 11, 2001.

THIS VIEW IS OF THE PAD PREPARATION FOR THE NEW PORTABLE CLASSROOMS.

THIS IS A SOUTH EAST VIEW.

THIS VIEW IS OF THE PAD PREPARATION FOR THE NEW PORTABLE CLASSROOMS.

THIS IS A SOUTH EAST VIEW.

Page 24: LISD Board of Trustees Construction Committee Meeting Tuesday, December 11, 2001.

NORTH EAST VIEW OF THE PAD PREPARATION FOR THE PORTABLE BUILDINGS.

NORTH EAST VIEW OF THE PAD PREPARATION FOR THE PORTABLE BUILDINGS.

Page 25: LISD Board of Trustees Construction Committee Meeting Tuesday, December 11, 2001.

Project: J.C. Martin Elementary School

Architect: Ashley Humphries & Sanchez ArchitectsStatus: Preliminary Design

Budget: $1,997,044.

Timeline:

Start Design Development : Feb 2002

Start of Final Design Phase: April 2002

Present Final Contract Dwgs: June 2002

Completion of Construction: Aug 2003

Page 26: LISD Board of Trustees Construction Committee Meeting Tuesday, December 11, 2001.

Project: Lamar Middle School

Architect: Cavazos & Associates Architects

Status: Final Design Phase

Budget: $ 7,358,620.

Timeline:

Start of Final Design Phase: Aug 2001

Present Final Contract Dwgs: Feb 2002

Completion of Construction: June 2003

Page 27: LISD Board of Trustees Construction Committee Meeting Tuesday, December 11, 2001.

J.W. NIXON HIGH SCHOOL

Construction Committee Meeting

Tuesday, December 11, 2001

Page 28: LISD Board of Trustees Construction Committee Meeting Tuesday, December 11, 2001.

THIS IS A VIEW LOOKING WEST AT THE CANOPY ON THE SOUTH END OF THE PORTABLE BUILDING.

THIS IS A VIEW LOOKING WEST AT THE CANOPY ON THE SOUTH END OF THE PORTABLE BUILDING.

Page 29: LISD Board of Trustees Construction Committee Meeting Tuesday, December 11, 2001.

THIS VIEW IS LOOKING NORTH ALONG THE NEW SIDE WALK FOR THE STUDENTS.

THIS VIEW IS LOOKING NORTH ALONG THE NEW SIDE WALK FOR THE STUDENTS.

Page 30: LISD Board of Trustees Construction Committee Meeting Tuesday, December 11, 2001.

THIS VIEW SHOWS THE FENCING ON TOP OF THE EXISTING BLOCK WALL.

THIS VIEW SHOWS THE FENCING ON TOP OF THE EXISTING BLOCK WALL.

Page 31: LISD Board of Trustees Construction Committee Meeting Tuesday, December 11, 2001.

MAIN PATIO DECK. MAIN ENTRANCE TO BUILDINGS.MAIN PATIO DECK. MAIN ENTRANCE TO BUILDINGS.

Page 32: LISD Board of Trustees Construction Committee Meeting Tuesday, December 11, 2001.

Project: Daiches Elementary School

Architect: Turner Hickey & Associates, Inc.

Status: Design Development

Budget: $5,191,225.Timeline:

Start of Final Design Phase: Dec 2001

Present Final Contract Dwgs: March 2002

Completion of Construction: April 2003

Page 33: LISD Board of Trustees Construction Committee Meeting Tuesday, December 11, 2001.

Project: Heights Elementary School

Architect: Pending

Status: Pending

Budget: Pending

Timeline: Pending

Page 34: LISD Board of Trustees Construction Committee Meeting Tuesday, December 11, 2001.

Project: Santo Nino Elementary School

Architect: Frank Architects Inc.

Status: Final Design Phase

Budget: $5,191,225.

Timeline:

Start of Final Design Phase: Sept. 2001

Present Final Contract Dwgs: Jan 2002

Completion of Construction: March 03

Page 35: LISD Board of Trustees Construction Committee Meeting Tuesday, December 11, 2001.

Project: Kawas Elementary School

Architect: Ashley Humphries & Sanchez Architects Status: Construction Documents Phase

Budget: $4,211,386.

Timeline:

Start of Final Design Phase: July 2001

Present Final Contract Dwgs: Oct 2001

Completion of Construction: Dec 2002

Page 36: LISD Board of Trustees Construction Committee Meeting Tuesday, December 11, 2001.

Project: H.B. Zachry Elementary School

Architect: Design Group International, Inc.

Status: Construction Documents Phase

Budget: $1,456,725.Timeline:

Start of Final Design Phase: Oct 2001

Present Final Contract Dwgs: Dec 2001

Completion of Construction: Dec 2002

Page 37: LISD Board of Trustees Construction Committee Meeting Tuesday, December 11, 2001.

Project: H. Ligarde Elementary School

Architect: Ashley Humphries & Sanchez Architects Status: Construction Documents Phase

Budget: $3,388,153.

Timeline:

Start of Final Design Phase: Oct 2001

Present Final Contract Dwgs: Dec 2001

Completion of Construction: Dec 2002

Page 38: LISD Board of Trustees Construction Committee Meeting Tuesday, December 11, 2001.

Project: Cigarroa Middle School

Architect: Ashley Humphries & Sanchez Architects Status: Construction Documents Phase

Budget: $3,314,867.Timeline:

Start of Final Design Phase: July 2001

Present Final Contract Dwgs: Dec 2001

Completion of Construction: June 2003

Page 39: LISD Board of Trustees Construction Committee Meeting Tuesday, December 11, 2001.

Project: Cigarroa High School

Architect: Ashley Humphries & Sanchez Architects Status: Construction Documents Phase

Budget: $8,168,516. Timeline:

Start of Final Design Phase: July 2001

Present Final Contract Dwgs: Dec 2001

Completion of Construction: June 2003