Top Banner
PowerPoint Presentation by Charlie Cook Copyright © 2006 The McGraw-Hill Companies. All rights reserved. THE MANAGERIAL PROCESS Clifford F. Gray Eric W. Larson Third Edition Project Management Project Management Lecture 4 Developing a Project Plan Activity on Node (AON)
24
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: lecture-4

PowerPoint Presentation by Charlie CookCopyright © 2006 The McGraw-Hill Companies. All rights reserved.

THE MANAGERIAL PROCESS Clifford F. Gray

Eric W. LarsonThird Edition

Project ManagementProject Management

Lecture 4 Developing a Project Plan

Activity on Node (AON)

Page 2: lecture-4

PROJECT MANAGEMENT: BACA 4132 2

Page 3: lecture-4

PROJECT MANAGEMENT: BACA 4132 3

Learning Objectives

• At the end of this topic you will be able to:

–Draw the Activity on Node (AON) network

–Analyze the Activity on Node (AON) network

Page 4: lecture-4

PROJECT MANAGEMENT: BACA 4132 4

Comparison of AON and AOA

Methods

Page 5: lecture-4

PROJECT MANAGEMENT: BACA 4132 5

Introduction of AON

• Node of AON

• No free float

Earliest Start Latest Start

Label, Description, Resources

Duration Total Float

Page 6: lecture-4

PROJECT MANAGEMENT: BACA 4132 6

Formula of AON Analysis

• EFT = EST + Duration

• LST = LFT – Duration

• LFT = LST + Duration

• Total Float = Latest Start Time – Earliest Start Time

Latest Start TimeEarliest Start Time

Page 7: lecture-4

PROJECT MANAGEMENT: BACA 4132 7

Activity-on-Node Fundamentals

Page 8: lecture-4

PROJECT MANAGEMENT: BACA 4132 8

Activity-on-Node Fundamentals (cont’d)

Page 9: lecture-4

PROJECT MANAGEMENT: BACA 4132 9

Network Information

Page 10: lecture-4

PROJECT MANAGEMENT: BACA 4132 10

Koll Business Center—Complete Network

Page 11: lecture-4

PROJECT MANAGEMENT: BACA 4132 11

Network Computation Process

• Forward Pass—Earliest Times

–How soon can the activity start? (early start-EST)

–How soon can the project finish? (expected time-EFT)

• Backward Pass—Latest Times

–How late can the activity start? (late start-LST)

–How late can the activity finish? (late finish-LFT)

–Which activities represent the critical path?

–How long can it be delayed? (total float-TF)

Page 12: lecture-4

PROJECT MANAGEMENT: BACA 4132 12

Network Information

TABLE 6.2

Page 13: lecture-4

PROJECT MANAGEMENT: BACA 4132 13

Activity-on-Node Network

Application approval

5

Service check

5

Traffic study

10

Commission approval

10

Wait for construction

170

Construction plans

15

Staff report

15

Occupancy

35

Page 14: lecture-4

PROJECT MANAGEMENT: BACA 4132 14

Activity-on-Node Network Forward Pass

Occupancy

35

Application approval

5

Service check

5

Traffic study

10

Commission approval

10

Wait for construction

170

Construction plans

15

Staff report

15

0

5

5

5

20

20

30

200

Page 15: lecture-4

PROJECT MANAGEMENT: BACA 4132 15

Activity-on-Node Network Backward Pass

Application approval

5

Service check

5

Traffic study

10

Commission approval

10

Wait for construction

170

Construction plans

15

Staff report

15

Occupancy

350

5

15

10 30

185

20

200

Page 16: lecture-4

PROJECT MANAGEMENT: BACA 4132 16

Determining Slack (or Float)

• Slack (or Float)

–The amount of time an activity can be delayed after

the start of a longer parallel activity or activities.

• Total slack

–The amount of time an activity can be delayed without

delaying the entire project.

Page 17: lecture-4

PROJECT MANAGEMENT: BACA 4132 17

Activity-on-Node Network with Total Float

Occupancy

35

Application approval

5

Service check

5

Traffic study

10

Commission approval

10

Wait for construction

170

Construction plans

15

Staff report

15

0

5

5

5

20

20

30

200

Application approval

5

Service check

5

Traffic study

10

Commission approval

10

Wait for construction

170

Construction plans

15

Staff report

15

Occupancy

350

5

15

10 30

185

20

200

0 0

1650

5

10

0

0

Page 18: lecture-4

PROJECT MANAGEMENT: BACA 4132 18

Summary Table

No. Activity Description Duration

(weeks)

Earliest

Start Time

(EST)

Latest

Start Time

(LST)

Earliest

Finish

Time

(EFT)

Latest

Finish

Time (LFT)

Total Float

Page 19: lecture-4

PROJECT MANAGEMENT: BACA 4132 19

Frequently Asked Questions

1. What is the critical path?

2. How long does it take to finish the project?

3. What are the total float for the non-critical

activities?

Page 20: lecture-4

PROJECT MANAGEMENT: BACA 4132 20

Two Errors in Logic

1. Looping

2. Dangling

Page 21: lecture-4

PROJECT MANAGEMENT: BACA 4132 21

Illogical Loop

FIGURE 6.9

Page 22: lecture-4

PROJECT MANAGEMENT: BACA 4132 22

Dangling

K

M

L

Page 23: lecture-4

PROJECT MANAGEMENT: BACA 4132 23

Extended Network Techniques

to Come Close to Reality

• Laddering

–Activities are broken into segments so the following

activity can begin sooner and not delay the work.

• Lags

–The minimum amount of time a dependent activity

must be delayed to begin or end.

• Lengthy activities are broken down to reduce the delay in the start of successor activities.

• Lags can be used to constrain finish-to-start, start-to-start, finish-to-finish, start-to-finish, or combination relationships.