Lecture 4 Developing a Project Plan
Activity on Node (AON)
Page 2
PROJECT MANAGEMENT: BACA 4132 2
Page 3
PROJECT MANAGEMENT: BACA 4132 3
Learning Objectives
• At the end of this topic you will be able to:
–Draw the Activity on Node (AON) network
–Analyze the Activity on Node (AON) network
Page 4
PROJECT MANAGEMENT: BACA 4132 4
Comparison of AON and AOA
Methods
Page 5
PROJECT MANAGEMENT: BACA 4132 5
Introduction of AON
• Node of AON
• No free float
Earliest Start Latest Start
Label, Description, Resources
Duration Total Float
Page 6
PROJECT MANAGEMENT: BACA 4132 6
Formula of AON Analysis
• EFT = EST + Duration
• LST = LFT – Duration
• LFT = LST + Duration
• Total Float = Latest Start Time – Earliest Start Time
Latest Start TimeEarliest Start Time
Page 7
PROJECT MANAGEMENT: BACA 4132 7
Activity-on-Node Fundamentals
Page 8
PROJECT MANAGEMENT: BACA 4132 8
Activity-on-Node Fundamentals (cont’d)
Page 9
PROJECT MANAGEMENT: BACA 4132 9
Network Information
Page 10
PROJECT MANAGEMENT: BACA 4132 10
Koll Business Center—Complete Network
Page 11
PROJECT MANAGEMENT: BACA 4132 11
Network Computation Process
• Forward Pass—Earliest Times
–How soon can the activity start? (early start-EST)
–How soon can the project finish? (expected time-EFT)
• Backward Pass—Latest Times
–How late can the activity start? (late start-LST)
–How late can the activity finish? (late finish-LFT)
–Which activities represent the critical path?
–How long can it be delayed? (total float-TF)
Page 12
PROJECT MANAGEMENT: BACA 4132 12
Network Information
TABLE 6.2
Page 13
PROJECT MANAGEMENT: BACA 4132 13
Activity-on-Node Network
Application approval
5
Service check
5
Traffic study
10
Commission approval
10
Wait for construction
170
Construction plans
15
Staff report
15
Occupancy
35
Page 14
PROJECT MANAGEMENT: BACA 4132 14
Activity-on-Node Network Forward Pass
Occupancy
35
Application approval
5
Service check
5
Traffic study
10
Commission approval
10
Wait for construction
170
Construction plans
15
Staff report
15
0
5
5
5
20
20
30
200
Page 15
PROJECT MANAGEMENT: BACA 4132 15
Activity-on-Node Network Backward Pass
Application approval
5
Service check
5
Traffic study
10
Commission approval
10
Wait for construction
170
Construction plans
15
Staff report
15
Occupancy
350
5
15
10 30
185
20
200
Page 16
PROJECT MANAGEMENT: BACA 4132 16
Determining Slack (or Float)
• Slack (or Float)
–The amount of time an activity can be delayed after
the start of a longer parallel activity or activities.
• Total slack
–The amount of time an activity can be delayed without
delaying the entire project.
Page 17
PROJECT MANAGEMENT: BACA 4132 17
Activity-on-Node Network with Total Float
Occupancy
35
Application approval
5
Service check
5
Traffic study
10
Commission approval
10
Wait for construction
170
Construction plans
15
Staff report
15
0
5
5
5
20
20
30
200
Application approval
5
Service check
5
Traffic study
10
Commission approval
10
Wait for construction
170
Construction plans
15
Staff report
15
Occupancy
350
5
15
10 30
185
20
200
0 0
1650
5
10
0
0
Page 18
PROJECT MANAGEMENT: BACA 4132 18
Summary Table
No. Activity Description Duration
(weeks)
Earliest
Start Time
(EST)
Latest
Start Time
(LST)
Earliest
Finish
Time
(EFT)
Latest
Finish
Time (LFT)
Total Float
Page 19
PROJECT MANAGEMENT: BACA 4132 19
Frequently Asked Questions
1. What is the critical path?
2. How long does it take to finish the project?
3. What are the total float for the non-critical
activities?
Page 20
PROJECT MANAGEMENT: BACA 4132 20
Two Errors in Logic
1. Looping
2. Dangling
Page 21
PROJECT MANAGEMENT: BACA 4132 21
Illogical Loop
FIGURE 6.9
Page 22
PROJECT MANAGEMENT: BACA 4132 22
Dangling
K
M
L
Page 23
PROJECT MANAGEMENT: BACA 4132 23
Extended Network Techniques
to Come Close to Reality
• Laddering
–Activities are broken into segments so the following
activity can begin sooner and not delay the work.
• Lags
–The minimum amount of time a dependent activity
must be delayed to begin or end.
• Lengthy activities are broken down to reduce the delay in the start of successor activities.
• Lags can be used to constrain finish-to-start, start-to-start, finish-to-finish, start-to-finish, or combination relationships.