7/31/2019 Lecture 2 2012 Identification of Contemporary Issues
1/29
7CN003 ContemporaryIssues in Project
ManagementLecture 2Chris Williams
Built Environment
School of Technology (STech)
7/31/2019 Lecture 2 2012 Identification of Contemporary Issues
2/29
Content of this session
What is a Project?
7/31/2019 Lecture 2 2012 Identification of Contemporary Issues
3/29
What is a Project?
Project definition
7/31/2019 Lecture 2 2012 Identification of Contemporary Issues
4/29
Task 1Brainstorm
Working as directed brainstorm what a
project is .
Use the A3 sheets provided and be prepared
to present your content (5 minutes each)
7/31/2019 Lecture 2 2012 Identification of Contemporary Issues
5/29
Brainstorm results
One definition often used is that a project is
A temporary endeavour undertaken to create
a unique product, service or result
It needs organised work efforts
Planned, first in outline, based on scant
information, and then in detail as the project
develops It is limited in respect of resources
7/31/2019 Lecture 2 2012 Identification of Contemporary Issues
6/29
Brain storm results What resources?
Time, Money, People
Have a defined start, and end Have goals or targets that the project should
achieve when eventually completed Have a unique band of stakeholders
Persons or organisations that may influence or areinvolved with the project, or affected by the
outcome positively or negatively Need a variety of people to work together for
a limited time
7/31/2019 Lecture 2 2012 Identification of Contemporary Issues
7/29
Project Management
Project Management can be defined as The application of knowledge, skills tools and techniques to
project activities to meet project requirements
Includes Project Initiation, Planning, Execution and Control all within
pre-defined limits of Scope, Quality Cost and Time
Project Management then needs administrative tasks
for planning, documenting and controlling andleadership for visioning, motivating and promoting
work
7/31/2019 Lecture 2 2012 Identification of Contemporary Issues
8/29
Contemporary
What does contemporary mean?
A dictionary definition says
1. existing, occurring, or living at the same time;
belonging to the same time: something that was done at the same time as something
else
2. of about the same age or date:
a Georgian house still contained contemporary furniture
3. of the present time; modern: of today
7/31/2019 Lecture 2 2012 Identification of Contemporary Issues
9/29
Task 2Brainstorm
Working as directed, given the previous
definition
What does the work contemporary offer to the
term project management
7/31/2019 Lecture 2 2012 Identification of Contemporary Issues
10/29
Brainstormconclusion
It means that what ever the issue is that is
under discussion it is coexistent, concurrent,
simultaneous with today.
Contemporary, contemporaneous, coeval,
coincident all mean happening or existing at
the same time. Contemporary often refers to persons or
their acts or achievements
7/31/2019 Lecture 2 2012 Identification of Contemporary Issues
11/29
Contemporary Issues
So, what are the Contemporary Issues for
Construction Project Management
Some ideas
7/31/2019 Lecture 2 2012 Identification of Contemporary Issues
12/29
Contemporary Issuesin Project Management It can be argued that five challenges are
common to all project-based businesses: Risk
Cost Cash flow Time Resources
The way these factors are managed, bothindividually and collectively, determines thesuccess or failure of a project.
7/31/2019 Lecture 2 2012 Identification of Contemporary Issues
13/29
Contemporary Issuesin Project Management All five factors are variables that should be weighed
against each other before any major decision can be
made.
They have to be considered in the light of otherdrivers that are now moving the construction industry
towards a project-based approach such as Consolidation in the construction industry
Cross-functional collaboration A move towards off-site construction
A future with Building Information Modelling (BIM)
7/31/2019 Lecture 2 2012 Identification of Contemporary Issues
14/29
Consolidation in theConstruction industry Many smaller contracting businesses have
merged or been purchased by larger
concerns recently, while at the top of the
supply chain there have been a number ofhuge mergers and acquisitions.
This activity has created larger construction
conglomerates with multiple divisions, eachoften operating in different disciplines and
starting with unique business models.
7/31/2019 Lecture 2 2012 Identification of Contemporary Issues
15/29
Consolidation in theConstruction industry A traditional builder may well be able to manage
with conventional construction software packages,
but once the business expands to incorporate
utilities, road building, rail maintenance and the
extraction of aggregates, most legacy systems will be
entirely unable to cope.
Increasingly, these larger companies are now hiring
technology leaders with experience from outsideconstruction to add to the corporate gene pool.
7/31/2019 Lecture 2 2012 Identification of Contemporary Issues
16/29
Cross-functionalCollaboration Traditionally, construction companies have
been extremely departmentalised.
Separate departments for estimating,
procurement, valuations and constructionplanning etc.
In many cases even the planning process
itself was carried out on a different system attender stage to that used to manage the
project during construction.
7/31/2019 Lecture 2 2012 Identification of Contemporary Issues
17/29
Cross-functionalCollaboration Unfortunately, in many cases, few (if any) of these
point solutions were integrated with the core
financial system. This meant, for example, that site-
based valuations and applications for payment were
often carried out in complete isolation from the so
called cost control process undertaken in the
accounts department.
It could take weeks to reconcile the two figures, andonly then would it be clear whether or not a project
was making money.
7/31/2019 Lecture 2 2012 Identification of Contemporary Issues
18/29
Cross-functionalCollaboration In an industry where real-time information is so
desirable, the inefficiencies of maintaining all thesedata silos has been questioned time and again
Bringing these separate departments together and
getting them working on the same application on thesame database can solve some of the problems thatmany contractors for decades have taken forgranted.
By unifying the data sets, it becomes possible to putin information and receive an accurate picture of theproject from financial and operational perspectives inreal time.
7/31/2019 Lecture 2 2012 Identification of Contemporary Issues
19/29
Cross-functionalCollaboration Unified data is crucial for proper cost-value
reconciliation.
Traditionally, as a contractor measured
earned value on-site, the back-officeaccountants would tally supplier invoices and
determine the costs.
However, reconciling the cost and value
figures takes time and effort, and if any action
is needed to correct a problem, the project
manager may be the last one to know.
7/31/2019 Lecture 2 2012 Identification of Contemporary Issues
20/29
Cross-functionalCollaboration
With cross functional integrated data an
accurate view of the financial health of the
project can be brought up in real time,
anytime. This allows a contractor to make smaller and
more measured adjustments as work
progresses instead of drastic action when it isalready too late.
7/31/2019 Lecture 2 2012 Identification of Contemporary Issues
21/29
Off-site Construction Major contractors are now investing heavily in factories
and production facilities designed to move more workoff the construction site and into a more controlledenvironment.
Mechanical & electrical (M&E) contractors have led the
way, building M&E sub-assemblies off-site anddelivering them just in time. But the off-site construction trend is driving even more
activity into highly controlled factory environments withattendant cost, labour and safety advantages.
Today, entire plant rooms are being designed andconstructed in modules for final assembly in positionwhen the site is ready forthem.
7/31/2019 Lecture 2 2012 Identification of Contemporary Issues
22/29
Off-site Construction
This type of construction activity not only reduces the
amount of work done on site, but significantly limits
exposure to risk that naturally results from doing
intricate work at height.
What this really means from a business process
perspective is that contractors are turning parts of
their operation into manufacturing businesses.
As a result, they are turning to manufacturing
techniques for help implementing lean manufacturingpractices for construction.
7/31/2019 Lecture 2 2012 Identification of Contemporary Issues
23/29
Building informationmodelling (BIM)
Major contractors are feeling pressure from clients to
deliver more structured data about the building and
this is leading to an increased interest in buildinginformation modelling (BIM).
BIM can deliver to the client the essential information
used to plan maintenance activities, maintenance
inventories and budget for the entire lifecycle of thebuilding from handover to decommissioning and
replacement.
7/31/2019 Lecture 2 2012 Identification of Contemporary Issues
24/29
Building informationmodelling (BIM) Some contractors are keen to play a greater
role in the asset lifecycle management
process (ALM).
As one major contractor said, We are no longer builders - we are asset
managers. Its just that some of our assets have
not been built yet!
Building information modelling and ongoing
asset management
7/31/2019 Lecture 2 2012 Identification of Contemporary Issues
25/29
Building informationmodelling (BIM) Considering that a buildings working life
might typically be 30 to 40 times longer thanits construction period, with maintenance
costs similarly multiplied, the case for anintegrated construction and assetmanagement approach is a strong one.
By the mid 1990s, contractors were already
addressing the issue of buildability with thedesign & build approach and increasinglybranching out into the lucrative facilitiesmanagement market in search of the long-
term revenue stability that comes with it.
7/31/2019 Lecture 2 2012 Identification of Contemporary Issues
26/29
Building informationmodelling (BIM) The construction industry suffers more than most in
periods of economic decline. It is pulled down early - as soon as the economy
loses the confidence to invest in the built
environment - and its recovery is held back by theglut of empty properties on the market when theupturn finally arrives.
In order to survive these difficult times, senior
managers need accurate, up to the minuteinformation on the performance of every part of theirbusiness so that problems can be addressed quicklyand action taken where necessary to prevent lossesand to boost profitable activities.
7/31/2019 Lecture 2 2012 Identification of Contemporary Issues
27/29
Conclusion In this presentation four contemporary issues
have been identified and an outline of their
currency and influence on the industry at this
time has been established.
They are Consolidation in the construction industry
Cross-functional collaboration within businesses
A move towards off-site construction A future with Building Information Modelling (BIM)
7/31/2019 Lecture 2 2012 Identification of Contemporary Issues
28/29
Conclusion There could be more that you could identify
yourself
but there may be sufficient there for
establishing a subject area of study for the
module. Refer back to the assessment regime and
consider the work you have to produce over
the next nine weeks (hand in date 3 June2012)
7/31/2019 Lecture 2 2012 Identification of Contemporary Issues
29/29
Any Questions??