BOGOTÁ (COLOMBIA), 12-13 SEPTEMBER 2013 CONSTRUCTION & LAST PLANNER SYSTEM WITH EXCEL 2010 ONE STEP FORWARD IN LEAN SCHEDULING & PLANNING MANAGEMENT
87

Lean Construction & Last Planner System with Excel 2010; One Step Forward in Lean Scheduling & Planning Management

Jan 24, 2023

Download

Documents

Rafael Villazon
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Lean Construction  & Last Planner System  with Excel 2010; One Step Forward in Lean Scheduling  & Planning Management

BOGOTÁ (COLOMBIA), 12-13 SEPTEMBER 2013

LEAN CONSTRUCTION

& LAST PLANNER SYSTEM WITH EXCEL 2010ONE STEP FORWARD IN LEAN

SCHEDULING & PLANNING MANAGEMENT

Page 2: Lean Construction  & Last Planner System  with Excel 2010; One Step Forward in Lean Scheduling  & Planning Management

LEAN CONSTRUCTION & SCHEDULING

UNIANDES BOGOTÁ (COLOMBIA), 12-13

SEPTEMBER 2013

José Luis Ponz [email protected]

[email protected]

Doctor en Arquitectura y Edificación (PhD UPV)Máster en Planificación y Gestión (Matemáticas UV)

Ingeniero de Edificación (UC)Arquitecto Técnico (UPV)

Diplomado en Investigación Operativa (UV)Máster en Economía de la Construcción (UPV)

Page 3: Lean Construction  & Last Planner System  with Excel 2010; One Step Forward in Lean Scheduling  & Planning Management

¿QUÉ ES LEAN CONSTRUCTION?

¿QUÉ ES EL LAST PLANNER SYSTEM?

LPS & SCHEDULING CON EXCEL 2010

PROJECT BASED LEARNING

123

LEAN CONSTRUCTION & SCHEDULING

UNIANDES BOGOTÁ (COLOMBIA), 12-13

SEPTEMBER 2013

4

Page 4: Lean Construction  & Last Planner System  with Excel 2010; One Step Forward in Lean Scheduling  & Planning Management

¿QUÉ ES LEAN CONSTRUCTION?

1

UNIANDES BOGOTÁ (COLOMBIA), 12-13

SEPTEMBER 2013

LEAN CONSTRUCTION & SCHEDULING

Page 5: Lean Construction  & Last Planner System  with Excel 2010; One Step Forward in Lean Scheduling  & Planning Management

¿QUÉ ES LEAN CONSTRUCTION?

¿ES UNA FILOSOFÍA, UNA METODOLOGÍA O UNA TECNOLOGÍA?

¿ES TODO ESO A LA VEZ?UNIANDES BOGOTÁ (COLOMBIA), 12-13

SEPTEMBER 2013

LEAN CONSTRUCTION & SCHEDULING

Page 6: Lean Construction  & Last Planner System  with Excel 2010; One Step Forward in Lean Scheduling  & Planning Management

¿QUÉ ES LEAN CONSTRUCTION?

UNIANDES BOGOTÁ (COLOMBIA), 12-13

SEPTEMBER 2013

EL CONCEPTO LEAN NACE EN 1988 DE JOHN KRAFCIK, ESTUDIANTE DE MÁSTER EN EL MASSACHUSSETTS INSTITUTE OF TECHNOLOGY, EN SU TESINA DE MÁSTER PUBLICADA EN LA SLOAN MANAGEMENT REVIEW.

• BUFFERED PRODUCTION

• LEAN PRODUCTION

LEAN CONSTRUCTION & SCHEDULING

Page 7: Lean Construction  & Last Planner System  with Excel 2010; One Step Forward in Lean Scheduling  & Planning Management

G. BallardL. Koskela P. Napolitano

L.F. Alarcón C. Formoso

E. Pellicer

G. Howell

And so on…….A. Mossman

¿QUÉ ES LEAN CONSTRUCTION?

UNIANDES BOGOTÁ (COLOMBIA), 12-13

SEPTEMBER 2013

LEAN CONSTRUCTION & SCHEDULING

Page 8: Lean Construction  & Last Planner System  with Excel 2010; One Step Forward in Lean Scheduling  & Planning Management

¿QUÉ ES LEAN CONSTRUCTION?

UNIANDES BOGOTÁ (COLOMBIA), 12-13

SEPTEMBER 2013

LEAN CONSTRUCTION & SCHEDULING

Page 9: Lean Construction  & Last Planner System  with Excel 2010; One Step Forward in Lean Scheduling  & Planning Management

¿QUÉ ES LEAN CONSTRUCTION?

¿ES POSIBLE ESTABLECER UNA METODOLOGÍA PARA LA

PLANIFICACIÓN DE LA PRODUCCIÓN

EN LA INDUSTRIA DE LA CONSTRUCCIÓN?

(KOSKELA, 1992)

UNIANDES BOGOTÁ (COLOMBIA), 12-13

SEPTEMBER 2013

LEAN CONSTRUCTION & SCHEDULING

Page 10: Lean Construction  & Last Planner System  with Excel 2010; One Step Forward in Lean Scheduling  & Planning Management

¿QUÉ ES LEAN CONSTRUCTION? ¿POR QUÉ?

MEJORAR LA PRODUCTIVIDADMEJORAR LA EFICIENCIA MEJORAR EL DESEMPEÑOMEJORAR LOS PROCESOSMEJORAR LA SATISFACCIÓN DEL CLIENTE Y CLIENTESMEJORAR LA CALIDADMEJORAR LA SEGURIDAD

LA MEJORA CONTINUA ELIMINANDO PÉRDIDASREDUCIR COSTES PARA INCREMENTAR LOS BENEFICIOS

¿CÓMO?THINKING PROJECTS AS PRODUCTION SYSTEMS

(BALLARD & HOWELL, 2009)

UNIANDES BOGOTÁ (COLOMBIA), 12-13

SEPTEMBER 2013

LEAN CONSTRUCTION & SCHEDULING

Page 11: Lean Construction  & Last Planner System  with Excel 2010; One Step Forward in Lean Scheduling  & Planning Management

LEAN CONSTRUCTION & SCHEDULING

¿QUÉ ES LEAN CONSTRUCTION? PRINCIPIOS METODOLÓGICOS (KOSKELA, 2000)

1. REDUCIR LAS ACTIVIDADES QUE NO AGREGAN VALOR2. INCREMENTAR EL VALOR3. REDUCIR LA VARIABILIDAD4. REDUCIR EL TIEMPO DE LOS CICLOS5. SIMPLIFICAR LOS PROCESOS6. AUMENTAR LA FLEXIBILIDAD DE LOS PROCESOS7. INCREMENTAR LA TRANSPARENCIA DE LOS PROCESOS8. ENFOCAR EL CONTROL EN LOS PROCESOS GLOBALES9. INTRODUCIR LA MEJORA CONTINUA (KAIZEN)10.CONTROLAR Y REFERENCIAR; HACER BENCHMARKING

UNIANDES BOGOTÁ (COLOMBIA), 12-13

SEPTEMBER 2013

NO DOGMATIZAR!

Page 12: Lean Construction  & Last Planner System  with Excel 2010; One Step Forward in Lean Scheduling  & Planning Management

“EN MATERIA DE PLANIFICACIÓN, JAMÁS UN MOVIMIENTO INÚTIL;

EN MATERIA DE ESTRATEGIA NINGÚN PASO EN VANO”EL ARTE DE LA GUERRA

SUN TZU SIGLO VI AC.

“LA PLANIFICACIÓN ES EN GRAN MEDIDA LA TAREA DE HACER QUE SUCEDAN COSAS QUE DE OTRO MODO NO

SUCEDERÍAN”(DAVID EWING)

¿QUÉ ES LEAN CONSTRUCTION?

UNIANDES BOGOTÁ (COLOMBIA), 12-13

SEPTEMBER 2013

LEAN CONSTRUCTION & SCHEDULING

Page 13: Lean Construction  & Last Planner System  with Excel 2010; One Step Forward in Lean Scheduling  & Planning Management

LEAN CONSTRUCTION; WHAT, WHY, HOW?

¿QUÉ ES LEAN CONSTRUCTION?

1

UNIANDES BOGOTÁ (COLOMBIA), 12-13

SEPTEMBER 2013

¿CÓMO APLICAR LEAN CONSTRUCTION?

Page 14: Lean Construction  & Last Planner System  with Excel 2010; One Step Forward in Lean Scheduling  & Planning Management

LEAN CONSTRUCTION & SCHEDULING

¿CÓMO APLICAR LEAN CONSTRUCTION?

LEAN THINKING DE WOMACK: 1. DEFINIR EL VALOR DEL PROYECTO. 2. MAPEAR LOS PROCESOS.

Calcular y controlar los rendimientos de las unidades de obra3. CREAR FLUJO.

Lo más difícil, hay muchos agentes que intervienen en los proyectos y que cada uno sea consciente que es cliente de otro no es tarea fácil.

4. METODOLOGÍA PULLActitud

5. MEJORA CONTINUA.Buscar la Perfección. Reducir costes, reducir los errores y cumplir plazo.

6. APLICAR HERRAMIENTAS LEANLAST PLANNER, IPD, LPDS, PROGRAMACIÓN POR ÁREAS, BIM, 5S, ETC

UNIANDES BOGOTÁ (COLOMBIA), 12-13

SEPTEMBER 2013

NO DOGMATIZAR!

Page 15: Lean Construction  & Last Planner System  with Excel 2010; One Step Forward in Lean Scheduling  & Planning Management

LEAN CONSTRUCTION & SCHEDULING

¿CÓMO APLICAR LEAN CONSTRUCTION?

Y NO OLVIDEMOS QUE…NO SOLO GESTIONAMOS PROYECTOS

GESTIONAMOS PERSONASUNIANDES

BOGOTÁ (COLOMBIA), 12-13 SEPTEMBER 2013

Page 16: Lean Construction  & Last Planner System  with Excel 2010; One Step Forward in Lean Scheduling  & Planning Management

LEAN CONSTRUCTION; WHAT, WHY, HOW?

¿QUÉ ES LEAN CONSTRUCTION?

1

UNIANDES BOGOTÁ (COLOMBIA), 12-13

SEPTEMBER 2013

HERRAMIENTAS LEAN

Page 17: Lean Construction  & Last Planner System  with Excel 2010; One Step Forward in Lean Scheduling  & Planning Management

LEAN CONSTRUCTION & SCHEDULING

¿CÓMO APLICAR LEAN CONSTRUCTION?

HERRAMIENTAS LEAN:

UNIANDES BOGOTÁ (COLOMBIA), 12-13

SEPTEMBER 2013

ANÁLISIS DE PÉRDIDAS Y DESPERDICIOS5S5 WHY´SVALUE STREAM MAPPINGGENCHI GENTBUTSU (GEMBA ATTITUDE OR GO & SEE)INFORME A3KAN BANBIMINTEGRATED PROJECT DELIVERY IPDLAST PLANNER SYSTEM LPS TM

………

Page 18: Lean Construction  & Last Planner System  with Excel 2010; One Step Forward in Lean Scheduling  & Planning Management

LEAN CONSTRUCTION & SCHEDULING

¿CÓMO APLICAR LEAN CONSTRUCTION?

HERRAMIENTAS LEAN: DETECTAR LAS PÉRDIDAS

UNIANDES BOGOTÁ (COLOMBIA), 12-13

SEPTEMBER 2013

MURA: PÉRDIDA POR VARIABILIDAD (PE CALIDAD)MURI: SOBRECARGA SOBRE OPERARIOSMUDA: DESPERDICIO

1.SOBREPRODUCCIÓN2.TRANSPORTE3.PROCESAMIENTO INNECESARIO Y

REPROCESAMIENTO4.ACOPIOS5.RE-TRABAJO POR DEFECTOS6.MOVIMIENTO7.ESPERA8.MAKING-DO

Page 19: Lean Construction  & Last Planner System  with Excel 2010; One Step Forward in Lean Scheduling  & Planning Management

LEAN CONSTRUCTION & SCHEDULING

¿CÓMO APLICAR LEAN CONSTRUCTION?

HERRAMIENTAS LEAN: 5 S

UNIANDES BOGOTÁ (COLOMBIA), 12-13

SEPTEMBER 2013

Page 20: Lean Construction  & Last Planner System  with Excel 2010; One Step Forward in Lean Scheduling  & Planning Management

LEAN CONSTRUCTION & SCHEDULING

¿CÓMO APLICAR LEAN CONSTRUCTION?

HERRAMIENTAS LEAN: 5 WHY´S

Fuente 2013 PFG Inma Sanchis Mestre

UNIANDES BOGOTÁ (COLOMBIA), 12-13

SEPTEMBER 2013

Page 21: Lean Construction  & Last Planner System  with Excel 2010; One Step Forward in Lean Scheduling  & Planning Management

LEAN CONSTRUCTION & SCHEDULING

¿CÓMO APLICAR LEAN CONSTRUCTION?

HERRAMIENTAS LEAN: VALUE STREAM MAPPING

Fuente 2013 PFG Inma Sanchis Mestre

UNIANDES BOGOTÁ (COLOMBIA), 12-13

SEPTEMBER 2013

Page 22: Lean Construction  & Last Planner System  with Excel 2010; One Step Forward in Lean Scheduling  & Planning Management

LEAN CONSTRUCTION & SCHEDULING

¿CÓMO APLICAR LEAN CONSTRUCTION?

HERRAMIENTAS LEAN: INFORME A3

UNIANDES BOGOTÁ (COLOMBIA), 12-13

SEPTEMBER 2013

• BACKGROUND• CURRENT CONDITIONS

• ACTUAL DIAGRAM• CAUSE ANALYSIS

(WHYS)• TARGET CONDITIONS

• MEASURABLE TARGET• TARGET DIAGRAM

• IMPLEMENTATION PLAN• WHAT? WHO? WHEN?

WHERE?• FOLLOW-UP

Page 23: Lean Construction  & Last Planner System  with Excel 2010; One Step Forward in Lean Scheduling  & Planning Management

LEAN CONSTRUCTION & SCHEDULING

¿CÓMO APLICAR LEAN CONSTRUCTION?

HERRAMIENTAS LEAN: INTEGRATED PROJECT DELIVERY TM

UNIANDES BOGOTÁ (COLOMBIA), 12-13

SEPTEMBER 2013

Page 24: Lean Construction  & Last Planner System  with Excel 2010; One Step Forward in Lean Scheduling  & Planning Management

LEAN CONSTRUCTION & SCHEDULING

¿CÓMO APLICAR LEAN CONSTRUCTION?

HERRAMIENTAS LEAN: INTEGRATED PROJECT DELIVERY TM

Mossman 2009

UNIANDES BOGOTÁ (COLOMBIA), 12-13

SEPTEMBER 2013

Page 25: Lean Construction  & Last Planner System  with Excel 2010; One Step Forward in Lean Scheduling  & Planning Management

LEAN CONSTRUCTION & SCHEDULING

¿CÓMO APLICAR LEAN CONSTRUCTION?

HERRAMIENTAS LEAN: BIM

UNIANDES BOGOTÁ (COLOMBIA), 12-13

SEPTEMBER 2013

Page 26: Lean Construction  & Last Planner System  with Excel 2010; One Step Forward in Lean Scheduling  & Planning Management

LEAN CONSTRUCTION & SCHEDULING

¿CÓMO APLICAR LEAN CONSTRUCTION?

HERRAMIENTAS LEAN: LAST PLANNER SYSTEM TM

UNIANDES BOGOTÁ (COLOMBIA), 12-13

SEPTEMBER 2013

Page 27: Lean Construction  & Last Planner System  with Excel 2010; One Step Forward in Lean Scheduling  & Planning Management

LEAN CONSTRUCTION & SCHEDULING

¿CÓMO APLICAR LEAN CONSTRUCTION?

HERRAMIENTAS LEAN: LAST PLANNER SYSTEM TM

UNIANDES BOGOTÁ (COLOMBIA), 12-13

SEPTEMBER 2013

Fuente 2013 PFG Inma Sanchis Mestre

Page 28: Lean Construction  & Last Planner System  with Excel 2010; One Step Forward in Lean Scheduling  & Planning Management

LEAN CONSTRUCTION & SCHEDULING

¿CÓMO APLICAR LEAN CONSTRUCTION?

HERRAMIENTAS LEAN: LAST PLANNER SYSTEM TM

UNIANDES BOGOTÁ (COLOMBIA), 12-13

SEPTEMBER 2013

Fuente 2013 PFG Inma Sanchis Mestre

Page 29: Lean Construction  & Last Planner System  with Excel 2010; One Step Forward in Lean Scheduling  & Planning Management

LEAN CONSTRUCTION & SCHEDULING

¿CÓMO APLICAR LEAN CONSTRUCTION?

HERRAMIENTAS LEAN: LAST PLANNER SYSTEM TM

UNIANDES BOGOTÁ (COLOMBIA), 12-13

SEPTEMBER 2013

Fuente 2013 PFG Inma Sanchis Mestre

Page 30: Lean Construction  & Last Planner System  with Excel 2010; One Step Forward in Lean Scheduling  & Planning Management

LEAN CONSTRUCTION & SCHEDULING

¿CÓMO APLICAR LEAN CONSTRUCTION?

HERRAMIENTAS LEAN: LAST PLANNER SYSTEM TM

UNIANDES BOGOTÁ (COLOMBIA), 12-13

SEPTEMBER 2013

Fuente 2013 PFG Inma Sanchis Mestre

Page 31: Lean Construction  & Last Planner System  with Excel 2010; One Step Forward in Lean Scheduling  & Planning Management

LEAN CONSTRUCTION & SCHEDULING

¿CÓMO APLICAR LEAN CONSTRUCTION?

HERRAMIENTAS LEAN: LAST PLANNER SYSTEM TM

UNIANDES BOGOTÁ (COLOMBIA), 12-13

SEPTEMBER 2013

Fuente 2013 PFG Inma Sanchis Mestre

Page 32: Lean Construction  & Last Planner System  with Excel 2010; One Step Forward in Lean Scheduling  & Planning Management

¿QUÉ ES LAST PLANNER?

2

LEAN CONSTRUCTION & SCHEDULING

UNIANDES BOGOTÁ (COLOMBIA), 12-13

SEPTEMBER 2013

Page 33: Lean Construction  & Last Planner System  with Excel 2010; One Step Forward in Lean Scheduling  & Planning Management

LEAN CONSTRUCTION & SCHEDULING

¿QUÉ ES THE LAST PLANNER SYSTEM TM?

ES UN TÉCNICA DE PLANIFICACIÓN Y CONTROL EN CASCADA CUYA FINALIDAD PRINCIPAL, ADEMÁS DE CONTROLAR LA PRODUCCIÓN, ES LA REDUCCIÓN DE LA VARIABILIDAD DE LA OBRA MEDIANTE LA APLICACIÓN DE TRES PRINCIPIOS BÁSICOS:

1. COORDINACIÓN DE LOS ÚLTIMOS PLANIFICADORES (AQUELLOS QUE REALMENTE DECIDEN EN LA OBRA) MEDIANTE REUNIONES PERIÓDICAS,

2. COMPROMISO PERSONAL DE LOS DECISORES FINALES (ÚLTIMOS PLANIFICADORES), Y

3. VISIBILIDAD PÚBLICA DE LOS RESULTADOS SEMANALES OBTENIDOS MEDIANTE LA UTILIZACIÓN DE UN INDICADOR BÁSICO DE CONTROL DENOMINADO PORCENTAJE DEL PLAN COMPLETADO (PPC)

RODRÍGUEZ, ALARCÓN Y PELLICER 2011UNIANDES BOGOTÁ (COLOMBIA), 12-13

SEPTEMBER 2013

Page 34: Lean Construction  & Last Planner System  with Excel 2010; One Step Forward in Lean Scheduling  & Planning Management

LEAN CONSTRUCTION & SCHEDULING

¿QUÉ ES THE LAST PLANNER SYSTEM TM?CONCEPTOS:

• ÚLTIMO PLANIFICADOR• PULL SESSION• PRERREQUISITOS Y RESTRICCIONES• INVENTARIO DE ACTIVIDADES EJECUTABLES (SE

DEBE, SE PUEDE, SE HARÁ)• MAIN PROGRAM• PHASE SCHEDULE• LOOK AHEAD PROGRAM• WEEK WORK PLAN• PPC O PAC• CAUSAS DE NO CUMPLIMIENTO

UNIANDES BOGOTÁ (COLOMBIA), 12-13

SEPTEMBER 2013

Page 35: Lean Construction  & Last Planner System  with Excel 2010; One Step Forward in Lean Scheduling  & Planning Management

LEAN CONSTRUCTION & SCHEDULING

LPS. Ballard & Howell, 2003Ponz-Tienda et al. 2011

LEAN THINKING DE WOMACK:

1. DEFINIR EL VALOR2. MAPEAR LOS PROCESOS. 3. CREAR FLUJO. 4. METODOLOGÍA PULL5. MEJORA CONTINUA.

¿QUÉ ES THE LAST PLANNER SYSTEM TM?

UNIANDES BOGOTÁ (COLOMBIA), 12-13

SEPTEMBER 2013

Page 36: Lean Construction  & Last Planner System  with Excel 2010; One Step Forward in Lean Scheduling  & Planning Management

MASTER & PHASE SCHEDULE

LOOK AHEAD PLAN

WEEKLY WORK PLAN

¿QUÉ ES THE LAST PLANNER SYSTEM TM?

LEAN CONSTRUCTION & SCHEDULING

UNIANDES BOGOTÁ (COLOMBIA), 12-13

SEPTEMBER 2013

Page 37: Lean Construction  & Last Planner System  with Excel 2010; One Step Forward in Lean Scheduling  & Planning Management

STRATEGIC GOALSPRODUCTION SCHEDULINGCOMMITMENTS PLANNING

MASTER & PHASE SCHEDULE

LOOK AHEAD PLAN

WEEKLY WORK PLAN

LEAN CONSTRUCTION & SCHEDULING

¿QUÉ ES THE LAST PLANNER SYSTEM TM?

UNIANDES BOGOTÁ (COLOMBIA), 12-13

SEPTEMBER 2013

Page 38: Lean Construction  & Last Planner System  with Excel 2010; One Step Forward in Lean Scheduling  & Planning Management

STRATEGIC GOALSPRODUCTION SCHEDULINGCOMMITMENTS PLANNING

Down

to

Up Up

to

DownMASTER & PHASE SCHEDULE

LOOK AHEAD PLAN

WEEKLY WORK PLAN

LEAN CONSTRUCTION & SCHEDULING

¿QUÉ ES THE LAST PLANNER SYSTEM TM?

UNIANDES BOGOTÁ (COLOMBIA), 12-13

SEPTEMBER 2013

Page 39: Lean Construction  & Last Planner System  with Excel 2010; One Step Forward in Lean Scheduling  & Planning Management

STRATEGIC GOALSPRODUCTION SCHEDULINGCOMMITMENTS PLANNING

MASTER & PHASE SCHEDULE

LOOK AHEAD PLAN

WEEKLY WORK PLAN

LEAN CONSTRUCTION & SCHEDULING

¿QUÉ ES THE LAST PLANNER SYSTEM TM?

UNIANDES BOGOTÁ (COLOMBIA), 12-13

SEPTEMBER 2013

Page 40: Lean Construction  & Last Planner System  with Excel 2010; One Step Forward in Lean Scheduling  & Planning Management

STRATEGIC GOALSPRODUCTION SCHEDULINGCOMMITMENTS PLANNING

EMOTIONAL APPROACH

TECHNOLOGICAL & MATHEMATICAL

APPROACHMASTER & PHASE SCHEDULE

LOOK AHEAD PLAN

WEEKLY WORK PLAN

LEAN CONSTRUCTION & SCHEDULING

THE LAST PLANNER SYSTEM TM. COMPLEJIDAD

UNIANDES BOGOTÁ (COLOMBIA), 12-13

SEPTEMBER 2013

Page 41: Lean Construction  & Last Planner System  with Excel 2010; One Step Forward in Lean Scheduling  & Planning Management

STRATEGIC GOALSPRODUCTION SCHEDULINGCOMMITMENTS PLANNING

NUMBER OF ACTIVITIES

COMPLEXITY OF THE

OPTIMIZATION&

MODELS

MASTER & PHASE SCHEDULE

LOOK AHEAD PLAN

WEEKLY WORK PLAN

LEAN CONSTRUCTION & SCHEDULING

THE LAST PLANNER SYSTEM TM. COMPLEJIDAD

UNIANDES BOGOTÁ (COLOMBIA), 12-13

SEPTEMBER 2013

Page 42: Lean Construction  & Last Planner System  with Excel 2010; One Step Forward in Lean Scheduling  & Planning Management

STRATEGIC GOALSPRODUCTION SCHEDULINGCOMMITMENTS PLANNING

NUMBER OF ACTIVITIES

RISK OF FAILURE IN ESTIMATIONS

MASTER & PHASE SCHEDULE

LOOK AHEAD PLAN

WEEKLY WORK PLAN

LEAN CONSTRUCTION & SCHEDULING

THE LAST PLANNER SYSTEM TM. COMPLEJIDAD

UNIANDES BOGOTÁ (COLOMBIA), 12-13

SEPTEMBER 2013

Page 43: Lean Construction  & Last Planner System  with Excel 2010; One Step Forward in Lean Scheduling  & Planning Management

STRATEGIC GOALSPRODUCTION SCHEDULINGCOMMITMENTS PLANNING

NUMBER OF ACTIVITIES

OVERLAPPINGOVERLAPPINGMASTER & PHASE SCHEDULE

LOOK AHEAD PLAN

WEEKLY WORK PLAN

LEAN CONSTRUCTION & SCHEDULING

THE LAST PLANNER SYSTEM TM. COMPLEJIDAD

UNIANDES BOGOTÁ (COLOMBIA), 12-13

SEPTEMBER 2013

Page 44: Lean Construction  & Last Planner System  with Excel 2010; One Step Forward in Lean Scheduling  & Planning Management

OVERLAPPING:i4

j3

k3

LEAN CONSTRUCTION & SCHEDULING

THE LAST PLANNER SYSTEM TM. COMPLEJIDAD

UNIANDES BOGOTÁ (COLOMBIA), 12-13

SEPTEMBER 2013

(2)FF

(1)SS

(2)SS

(1)FF

Page 45: Lean Construction  & Last Planner System  with Excel 2010; One Step Forward in Lean Scheduling  & Planning Management

OVERLAPPING:

IS NOT SO EASY TO SOLVE AS SEEMS

i

jk

LEAN CONSTRUCTION & SCHEDULING

THE LAST PLANNER SYSTEM TM. COMPLEJIDAD

UNIANDES BOGOTÁ (COLOMBIA), 12-13

SEPTEMBER 2013

(2)FF(1)SS

(2)SS(1)FF

Page 46: Lean Construction  & Last Planner System  with Excel 2010; One Step Forward in Lean Scheduling  & Planning Management

OVERLAPPING: SOLUTION #1

NORMALIZING RELATIONSHIPS

i

jk

LEAN CONSTRUCTION & SCHEDULING

THE LAST PLANNER SYSTEM TM. COMPLEJIDAD

UNIANDES BOGOTÁ (COLOMBIA), 12-13

SEPTEMBER 2013

( 1) (2) (3)jF S FF Dur

( 1) (2) (3)jFS SS Dur

Page 47: Lean Construction  & Last Planner System  with Excel 2010; One Step Forward in Lean Scheduling  & Planning Management

OVERLAPPING: SOLUTION #1

BUT, IF WE INCREASE THE LENGTH OF j (CRITICAL) ……

i

jk

LEAN CONSTRUCTION & SCHEDULING

THE LAST PLANNER SYSTEM TM. COMPLEJIDAD

UNIANDES BOGOTÁ (COLOMBIA), 12-13

SEPTEMBER 2013

( 1) (2) (3)jF S FF Dur

( 1) (2) (3)jFS SS Dur

Page 48: Lean Construction  & Last Planner System  with Excel 2010; One Step Forward in Lean Scheduling  & Planning Management

OVERLAPPING: SOLUTION #1

APPEARS THE “REVERSE CRITICALITY”

i

jk

LEAN CONSTRUCTION & SCHEDULING

THE LAST PLANNER SYSTEM TM. COMPLEJIDAD

UNIANDES BOGOTÁ (COLOMBIA), 12-13

SEPTEMBER 2013

( 2) (2) (4)jFS F F Dur

( 2) (2) (4)jFS SS Dur

Page 49: Lean Construction  & Last Planner System  with Excel 2010; One Step Forward in Lean Scheduling  & Planning Management

OVERLAPPING: SOLUTION #2

CONSIDERING ALL THE RELATIONSHIPS

i

jk

LEAN CONSTRUCTION & SCHEDULING

THE LAST PLANNER SYSTEM TM. COMPLEJIDAD

UNIANDES BOGOTÁ (COLOMBIA), 12-13

SEPTEMBER 2013

(2)FF(1)SS

(2)SS(1)FF

Page 50: Lean Construction  & Last Planner System  with Excel 2010; One Step Forward in Lean Scheduling  & Planning Management

OVERLAPPING: SOLUTION #2

BUT, IF WE INCREASE THE LENGTH OF J (CRITICAL) ……

i

jk

LEAN CONSTRUCTION & SCHEDULING

THE LAST PLANNER SYSTEM TM. COMPLEJIDAD

UNIANDES BOGOTÁ (COLOMBIA), 12-13

SEPTEMBER 2013

(2)FF(1)SS

(2)SS(1)FF

Page 51: Lean Construction  & Last Planner System  with Excel 2010; One Step Forward in Lean Scheduling  & Planning Management

OVERLAPPING: SOLUTION #2

APPEARS AGAIN, BUT CONTROLLED

i

jk

LEAN CONSTRUCTION & SCHEDULING

THE LAST PLANNER SYSTEM TM. COMPLEJIDAD

UNIANDES BOGOTÁ (COLOMBIA), 12-13

SEPTEMBER 2013

(2)FF(1)SS

(2)SS(1)FF

Page 52: Lean Construction  & Last Planner System  with Excel 2010; One Step Forward in Lean Scheduling  & Planning Management

OVERLAPPING: SOLUTION #3

ALLOWING THE SPLITTING OF ACTIVITIES

i

jk

LEAN CONSTRUCTION & SCHEDULING

THE LAST PLANNER SYSTEM TM. COMPLEJIDAD

UNIANDES BOGOTÁ (COLOMBIA), 12-13

SEPTEMBER 2013

(2)FF(1)SS

(2)SS(1)FF

Page 53: Lean Construction  & Last Planner System  with Excel 2010; One Step Forward in Lean Scheduling  & Planning Management

OVERLAPPING: SOLUTION #3

TIME UNITS?

i

jk

LEAN CONSTRUCTION & SCHEDULING

THE LAST PLANNER SYSTEM TM. COMPLEJIDAD

UNIANDES BOGOTÁ (COLOMBIA), 12-13

SEPTEMBER 2013

(2)FF(1)SS

(2)SS(1)FF

Page 54: Lean Construction  & Last Planner System  with Excel 2010; One Step Forward in Lean Scheduling  & Planning Management

OVERLAPPING: SOLUTION #4

WORK UNITS(Crandall, 1972)

(Valls et al, 1998)

i

jk

LEAN CONSTRUCTION & SCHEDULING

THE LAST PLANNER SYSTEM TM. COMPLEJIDAD

UNIANDES BOGOTÁ (COLOMBIA), 12-13

SEPTEMBER 2013

(2)FF(1)SS

(2)SS(1)FF

Page 55: Lean Construction  & Last Planner System  with Excel 2010; One Step Forward in Lean Scheduling  & Planning Management

OVERLAPPING: SOLUTION #4

BUT, IF WE INCREASE THE LENGTH OF j (CRITICAL) ……

i

jk

LEAN CONSTRUCTION & SCHEDULING

THE LAST PLANNER SYSTEM TM. COMPLEJIDAD

UNIANDES BOGOTÁ (COLOMBIA), 12-13

SEPTEMBER 2013

(2)FF(1)SS

(2)SS(1)FF

Page 56: Lean Construction  & Last Planner System  with Excel 2010; One Step Forward in Lean Scheduling  & Planning Management

OVERLAPPING: SOLUTION #4i

jk

APPEARS AGAIN , AND AGAIN, AND AGAIN, AND …..

(Ponz-Tienda, 2010; Ponz-Tienda & Pellicer, 2014)

LEAN CONSTRUCTION & SCHEDULING

THE LAST PLANNER SYSTEM TM. COMPLEJIDAD

UNIANDES BOGOTÁ (COLOMBIA), 12-13

SEPTEMBER 2013

(2)FF(1)SS

(2)SS(1)FF

Page 57: Lean Construction  & Last Planner System  with Excel 2010; One Step Forward in Lean Scheduling  & Planning Management

OVERLAPPING: SOLUTION #5OPTIMAL SPLITTING OF JOBS

Time Work FeedingFS FS(z) -- --SS SS(z) SS(w) SS(p)FF FF(z) FF(w) FF(p)

SF SF(z) SF(wi

|wj)SF(pi|pj)REVERSE CRITICALITY DISAPPEARS.

PROJECT MAKESPAN IS REDUCED

LEAN CONSTRUCTION & SCHEDULING

THE LAST PLANNER SYSTEM TM. COMPLEJIDAD

(Ponz-Tienda, 2010; Ponz-Tienda & Pellicer, 2014)UNIANDES

BOGOTÁ (COLOMBIA), 12-13 SEPTEMBER 2013

Page 58: Lean Construction  & Last Planner System  with Excel 2010; One Step Forward in Lean Scheduling  & Planning Management

OVERLAPPING: SOLUTION #5OPTIMAL SPLITTING OF JOBSTime Work Feeding W & T F & T F|W & T

FS FS(z) -- -- -- -- --

SS SS(z) SS(w) SS(p) SS(w, z)

SS(p, z)

SS(w|p, z)

FF FF(z) FF(w) FF(p) FF(w, z)

FF(p, z)

FF(w|p, z)

SF SF(z) SF(wi

|wj)SF(pi|pj)

SF(wi|wj, z)

SF(pi|pj, z)

SF(w|p, z)

LEAN CONSTRUCTION & SCHEDULING

THE LAST PLANNER SYSTEM TM. COMPLEJIDAD

(Ponz-Tienda, 2010; Ponz-Tienda & Pellicer, 2014)

UNIANDES BOGOTÁ (COLOMBIA), 12-13

SEPTEMBER 2013

Page 59: Lean Construction  & Last Planner System  with Excel 2010; One Step Forward in Lean Scheduling  & Planning Management

LPS & SCHEDULING CON EXCEL 2010

3

LEAN CONSTRUCTION & SCHEDULING

UNIANDES BOGOTÁ (COLOMBIA), 12-13

SEPTEMBER 2013

Page 60: Lean Construction  & Last Planner System  with Excel 2010; One Step Forward in Lean Scheduling  & Planning Management

LEAN CONSTRUCTION & SCHEDULING

LPS & SCHEDULING CON EXCEL 2010

UNIANDES BOGOTÁ (COLOMBIA), 12-13

SEPTEMBER 2013

Page 61: Lean Construction  & Last Planner System  with Excel 2010; One Step Forward in Lean Scheduling  & Planning Management

0 20 20 155 155 205

0 20 20 155 155 210

137 167 180 225

137 167 190 230

120 170

127 177

152 222

152 222

185 238

185 238

205 260

205 260

205 240

236 271

216 271 271 296

236 271 271 296

230 281

246 281

200 225 225 270 281 296 296 297

211 236 236 281 281 296 296 297

M achinery25

Proj delivery 1

Sheathing45

50%

25Ext works

15

Other works35

10

10

60%

Paintwork35

Access

50%

30%

Ceiling35

20%

30%

Office partitions

55

50%

40%Dry walls40

60%40%

50%

20%

40%

Floorings office70

Decks40

50% 50%

50%

50%

Closures50

50%

50

50%

Prev W orks Structure

Flooring Stairs

Instalations Ph1

30

40% 30%135

60%

20

LEAN CONSTRUCTION & SCHEDULING

LPS & SCHEDULING CON EXCEL 2010

UNIANDES BOGOTÁ (COLOMBIA), 12-13

SEPTEMBER 2013

Page 62: Lean Construction  & Last Planner System  with Excel 2010; One Step Forward in Lean Scheduling  & Planning Management

LEAN CONSTRUCTION & SCHEDULING

LPS & SCHEDULING CON EXCEL 2010

UNIANDES BOGOTÁ (COLOMBIA), 12-13

SEPTEMBER 2013

Page 63: Lean Construction  & Last Planner System  with Excel 2010; One Step Forward in Lean Scheduling  & Planning Management

LEAN CONSTRUCTION & SCHEDULING

LPS & SCHEDULING CON EXCEL 2010

MAIN PROGRAM

PHASE SCHEDULE &

OPTIMIZACIÓN

PROGRAMACIÓN POR

ÁREAS

COMPROMISO

SLOOKAHEAD &

WWP

UNIANDES BOGOTÁ (COLOMBIA), 12-13

SEPTEMBER 2013

Page 64: Lean Construction  & Last Planner System  with Excel 2010; One Step Forward in Lean Scheduling  & Planning Management

LEAN CONSTRUCTION & SCHEDULING

LPS & SCHEDULING CON EXCEL 2010• MAIN PROGRAM

UNIANDES BOGOTÁ (COLOMBIA), 12-13

SEPTEMBER 2013

Page 65: Lean Construction  & Last Planner System  with Excel 2010; One Step Forward in Lean Scheduling  & Planning Management

LEAN CONSTRUCTION & SCHEDULING

LPS & SCHEDULING CON EXCEL 2010• MAIN PROGRAM

UNIANDES BOGOTÁ (COLOMBIA), 12-13

SEPTEMBER 2013

Page 66: Lean Construction  & Last Planner System  with Excel 2010; One Step Forward in Lean Scheduling  & Planning Management

• MAIN PROGRAM & PRODUCCIÓNRESOURCES

LEAN CONSTRUCTION & SCHEDULING

LPS & SCHEDULING CON EXCEL 2010

UNIANDES BOGOTÁ (COLOMBIA), 12-13

SEPTEMBER 2013

Page 67: Lean Construction  & Last Planner System  with Excel 2010; One Step Forward in Lean Scheduling  & Planning Management

• MAIN PROGRAM Y EVMBCWS / ACWP

LEAN CONSTRUCTION & SCHEDULING

LPS & SCHEDULING CON EXCEL 2010

UNIANDES BOGOTÁ (COLOMBIA), 12-13

SEPTEMBER 2013

Page 68: Lean Construction  & Last Planner System  with Excel 2010; One Step Forward in Lean Scheduling  & Planning Management

• MAIN PROGRAM Y EVMCOST

DEVIATION

LEAN CONSTRUCTION & SCHEDULING

LPS & SCHEDULING CON EXCEL 2010

UNIANDES BOGOTÁ (COLOMBIA), 12-13

SEPTEMBER 2013

Page 69: Lean Construction  & Last Planner System  with Excel 2010; One Step Forward in Lean Scheduling  & Planning Management

• MAIN PROGRAM Y EVMPRODUCTION

LEAN CONSTRUCTION & SCHEDULING

LPS & SCHEDULING CON EXCEL 2010

UNIANDES BOGOTÁ (COLOMBIA), 12-13

SEPTEMBER 2013

Page 70: Lean Construction  & Last Planner System  with Excel 2010; One Step Forward in Lean Scheduling  & Planning Management

• MAIN PROGRAM Y EVMPRODUCTION

DEV.

LEAN CONSTRUCTION & SCHEDULING

LPS & SCHEDULING CON EXCEL 2010

UNIANDES BOGOTÁ (COLOMBIA), 12-13

SEPTEMBER 2013

Page 71: Lean Construction  & Last Planner System  with Excel 2010; One Step Forward in Lean Scheduling  & Planning Management

• PHASE SCHEDULE & OPTIMIZACIÓN

LEAN CONSTRUCTION & SCHEDULING

LPS & SCHEDULING CON EXCEL 2010

UNIANDES BOGOTÁ (COLOMBIA), 12-13

SEPTEMBER 2013

Page 72: Lean Construction  & Last Planner System  with Excel 2010; One Step Forward in Lean Scheduling  & Planning Management

• PHASE SCHEDULE & OPTIMIZACIÓN

LEAN CONSTRUCTION & SCHEDULING

LPS & SCHEDULING CON EXCEL 2010

UNIANDES BOGOTÁ (COLOMBIA), 12-13

SEPTEMBER 2013

Page 73: Lean Construction  & Last Planner System  with Excel 2010; One Step Forward in Lean Scheduling  & Planning Management

PROBLEMAS QUE PODEMOS RESOLVER

• RESOURCE LEVELING PROBLEM (RLP)• RESOURCE CONSTRAINED (RCPSP)• RLP + RCPSP• FUZZY ROBUST• NPV• NPV + RCPSP + RLP + VARIABLE

AVAILABILITY • MULTIPLE EXECUTION MODES• MULTIOBJETIVE ……………

LEAN CONSTRUCTION & SCHEDULING

LPS & SCHEDULING CON EXCEL 2010

UNIANDES BOGOTÁ (COLOMBIA), 12-13

SEPTEMBER 2013

Page 74: Lean Construction  & Last Planner System  with Excel 2010; One Step Forward in Lean Scheduling  & Planning Management

• COMPROMISOS, RESTRICCIONES Y ÁREAS

LEAN CONSTRUCTION & SCHEDULING

LPS & SCHEDULING CON EXCEL 2010

UNIANDES BOGOTÁ (COLOMBIA), 12-13

SEPTEMBER 2013

Page 75: Lean Construction  & Last Planner System  with Excel 2010; One Step Forward in Lean Scheduling  & Planning Management

• WEEKLY WORK PLAN

LEAN CONSTRUCTION & SCHEDULING

LPS & SCHEDULING CON EXCEL 2010

UNIANDES BOGOTÁ (COLOMBIA), 12-13

SEPTEMBER 2013

Page 76: Lean Construction  & Last Planner System  with Excel 2010; One Step Forward in Lean Scheduling  & Planning Management

W W P

29/04/2013

30/04/2013

01/05/2013

02/05/2013

03/05/2013

04/05/2013

05/05/2013

06/05/2013

07/05/2013

08/05/2013

09/05/2013

10/05/2013

11/05/2013

12/05/2013

13/05/2013

14/05/2013

15/05/2013

16/05/2013

17/05/2013

18/05/2013

19/05/2013

20/05/2013

21/05/2013

22/05/2013

23/05/2013

24/05/2013

25/05/2013

26/05/2013

27/05/2013

28/05/2013

29/05/2013

30/05/2013

31/05/2013

01/06/2013

02/06/2013

03/06/2013

04/06/2013

05/06/2013

06/06/2013

07/06/2013

08/06/2013

09/06/2013

Id Act Activity Class Resp Zone Area Restr Cause Start Finish ScheduledPerform ed Pct (%) Target lun m ar m ié jue vie sáb dom lun2 m ar2 m ié2 jue2 vie2 sáb2 dom 2 lun3 m ar3 m ié3 jue3 vie3 sáb3 dom 3 lun4 m ar4 m ié4 jue4 vie4 sáb4 dom 4 lun5 m ar5 m ié5 jue5 vie5 sáb5 dom 5 lun6 m ar6 m ié6 jue6 vie6 sáb6 dom 6

Act.#1 Activity Num ber #1 Com pr Resp1 Zone 1 Area 1 Rst.#5 M at 29/04/2013 01/05/2013 3.00 2.00 66.67% No 1.0 1.0Act.#2 Activity Num ber #2 Com pr Resp3 Zone 3 Area 2 Rst.#5 30/04/2013 30/04/2013 1.00 1.00 100.00% Yes 1.0Act.#3 Activity Num ber #3 Com pr Resp1 Zone 3 Area 4 Rst.#1 01/05/2013 02/05/2013 2.00 2.00 100.00% Yes 1.0 1.0Act.#4 Activity Num ber #4 Stock Resp7 Zone 2 Area 2 Rst.#5 06/05/2013 10/05/2013 5.00 5.00 100.00% Yes 1.0 1.0 1.0 1.0 1.0Act.#5 Activity Num ber #5 Com pr Resp1 Zone 3 Area 1 Rst.#4 Equ 02/05/2013 03/05/2013 2.00 2.00 100.00% No 1.0 1.0Act.#6 Activity Num ber #6 Com pr Resp3 Zone 2 Area 4 Rst.#2 08/05/2013 15/05/2013 4.00 4.00 100.00% Yes 1.0 1.0 1.0 1.0Act.#7 Activity Num ber #7 Com pr Resp1 Zone 1 Area 1 Rst.#4 W ea 13/05/2013 17/05/2013 12.00 11.00 91.67% No 2.0 2.0 2.0 3.0 2.0Act.#8 Activity Num ber #8 Stock Resp2 Zone 3 Area 2 Rst.#3 09/05/2013 24/05/2013 55.00 56.00 101.82% Yes 2.0 5.0 3.0 5.0 5.0 5.0 5.0 6.0 5.0 6.0 5.0 4.0Act.#9 Activity Num ber #9 Com pr Resp8 Zone 4 Area 3 Rst.#1 Dsg 01/05/2013 08/05/2013 6.00 4.00 66.67% No 1.0 2.0 1.0Act.#10 Activity Num ber #10 Com pr Resp2 Zone 2 Area 3 Rst.#5 06/05/2013 31/05/2013 20.00 19.00 95.00% Yes 1.0 2.0 1.0 1.0 1.0 1.0 2.0 1.0 1.0 1.0 2.0 1.0 1.0 1.0 2.0Act.#11 Activity Num ber #11 Com pr Resp2 Zone 2 Area 2 Rst.#4 13/05/2013 15/05/2013 23.00 21.00 91.30% Yes 5.0 9.0 7.0Act.#12 Activity Num ber #12 Stock Resp4 Zone 1 Area 3 Rst.#7 30/05/2013 07/06/2013 4.00 0.00 0.00%Act.#13 Activity Num ber #13 Com pr Resp7 Zone 7 Area 7 Rst.#1 06/05/2013 10/05/2013 7.00 7.00 100.00% Yes 2.0 1.0 1.0 2.0 1.0Act.#14 Activity Num ber #14 Com pr Resp2 Zone 6 Area 3 Rst.#7 13/05/2013 15/05/2013 12.00 0.00 0.00% YesAct.#15 Activity Num ber #15 Stock Resp3 Zone 2 Area 4 Rst.#4 13/05/2013 15/05/2013 1.00 0.00 0.00% YesCom pleted over Com prom ises 82.85% 63.64%Com pleted over Planed & Stock 74.21% 66.67%

W eek 21 W eek 22 W eek 23

W eek_18_2013 Dates Production

W eek 18 W eek 19 W eek 20

• LOOK AHEAD PLANNING

LEAN CONSTRUCTION & SCHEDULING

LPS & SCHEDULING CON EXCEL 2010

UNIANDES BOGOTÁ (COLOMBIA), 12-13

SEPTEMBER 2013

Page 77: Lean Construction  & Last Planner System  with Excel 2010; One Step Forward in Lean Scheduling  & Planning Management

W W P

29/04/2013

30/04/2013

01/05/2013

02/05/2013

03/05/2013

04/05/2013

05/05/2013

06/05/2013

07/05/2013

08/05/2013

09/05/2013

10/05/2013

11/05/2013

12/05/2013

13/05/2013

14/05/2013

15/05/2013

16/05/2013

17/05/2013

18/05/2013

19/05/2013

20/05/2013

21/05/2013

22/05/2013

23/05/2013

24/05/2013

25/05/2013

26/05/2013

27/05/2013

28/05/2013

29/05/2013

30/05/2013

31/05/2013

01/06/2013

02/06/2013

03/06/2013

04/06/2013

05/06/2013

06/06/2013

07/06/2013

08/06/2013

09/06/2013

Id Act Activity Class Resp Zone Area Restr Cause Start Finish ScheduledPerform ed Pct (%) Target lun m ar m ié jue vie sáb dom lun2 m ar2 m ié2 jue2 vie2 sáb2 dom 2 lun3 m ar3 m ié3 jue3 vie3 sáb3 dom 3 lun4 m ar4 m ié4 jue4 vie4 sáb4 dom 4 lun5 m ar5 m ié5 jue5 vie5 sáb5 dom 5 lun6 m ar6 m ié6 jue6 vie6 sáb6 dom 6

Act.#1 Activity Num ber #1 Com pr Resp1 Zone 1 Area 1 Rst.#5 M at 29/04/2013 01/05/2013 3.00 2.00 66.67% No 1.0 1.0Act.#2 Activity Num ber #2 Com pr Resp3 Zone 3 Area 2 Rst.#5 30/04/2013 30/04/2013 1.00 1.00 100.00% Yes 1.0Act.#3 Activity Num ber #3 Com pr Resp1 Zone 3 Area 4 Rst.#1 01/05/2013 02/05/2013 2.00 2.00 100.00% Yes 1.0 1.0Act.#4 Activity Num ber #4 Stock Resp7 Zone 2 Area 2 Rst.#5 06/05/2013 10/05/2013 5.00 5.00 100.00% Yes 1.0 1.0 1.0 1.0 1.0Act.#5 Activity Num ber #5 Com pr Resp1 Zone 3 Area 1 Rst.#4 Equ 02/05/2013 03/05/2013 2.00 2.00 100.00% No 1.0 1.0Act.#6 Activity Num ber #6 Com pr Resp3 Zone 2 Area 4 Rst.#2 08/05/2013 15/05/2013 4.00 4.00 100.00% Yes 1.0 1.0 1.0 1.0Act.#7 Activity Num ber #7 Com pr Resp1 Zone 1 Area 1 Rst.#4 W ea 13/05/2013 17/05/2013 12.00 11.00 91.67% No 2.0 2.0 2.0 3.0 2.0Act.#8 Activity Num ber #8 Stock Resp2 Zone 3 Area 2 Rst.#3 09/05/2013 24/05/2013 55.00 56.00 101.82% Yes 2.0 5.0 3.0 5.0 5.0 5.0 5.0 6.0 5.0 6.0 5.0 4.0Act.#9 Activity Num ber #9 Com pr Resp8 Zone 4 Area 3 Rst.#1 Dsg 01/05/2013 08/05/2013 6.00 4.00 66.67% No 1.0 2.0 1.0Act.#10 Activity Num ber #10 Com pr Resp2 Zone 2 Area 3 Rst.#5 06/05/2013 31/05/2013 20.00 19.00 95.00% Yes 1.0 2.0 1.0 1.0 1.0 1.0 2.0 1.0 1.0 1.0 2.0 1.0 1.0 1.0 2.0Act.#11 Activity Num ber #11 Com pr Resp2 Zone 2 Area 2 Rst.#4 13/05/2013 15/05/2013 23.00 21.00 91.30% Yes 5.0 9.0 7.0Act.#12 Activity Num ber #12 Stock Resp4 Zone 1 Area 3 Rst.#7 30/05/2013 07/06/2013 4.00 0.00 0.00%Act.#13 Activity Num ber #13 Com pr Resp7 Zone 7 Area 7 Rst.#1 06/05/2013 10/05/2013 7.00 7.00 100.00% Yes 2.0 1.0 1.0 2.0 1.0Act.#14 Activity Num ber #14 Com pr Resp2 Zone 6 Area 3 Rst.#7 13/05/2013 15/05/2013 12.00 0.00 0.00% YesAct.#15 Activity Num ber #15 Stock Resp3 Zone 2 Area 4 Rst.#4 13/05/2013 15/05/2013 1.00 0.00 0.00% YesCom pleted over Com prom ises 82.85% 63.64%Com pleted over Planed & Stock 74.21% 66.67%

W eek 21 W eek 22 W eek 23

W eek_18_2013 Dates Production

W eek 18 W eek 19 W eek 20

• LOOK AHEAD PLANNING

LEAN CONSTRUCTION & SCHEDULING

LPS & SCHEDULING CON EXCEL 2010

UNIANDES BOGOTÁ (COLOMBIA), 12-13

SEPTEMBER 2013

Page 78: Lean Construction  & Last Planner System  with Excel 2010; One Step Forward in Lean Scheduling  & Planning Management

• WEEKLY WORK PLAN

LEAN CONSTRUCTION & SCHEDULING

LPS & SCHEDULING CON EXCEL 2010

UNIANDES BOGOTÁ (COLOMBIA), 12-13

SEPTEMBER 2013

Page 79: Lean Construction  & Last Planner System  with Excel 2010; One Step Forward in Lean Scheduling  & Planning Management

• VERSATILIDAD

LEAN CONSTRUCTION & SCHEDULING

LPS & SCHEDULING CON EXCEL 2010

UNIANDES BOGOTÁ (COLOMBIA), 12-13

SEPTEMBER 2013

J.L. Ponz-Tienda et al. / Automation in Construction 29 (2013) 161–172

Page 80: Lean Construction  & Last Planner System  with Excel 2010; One Step Forward in Lean Scheduling  & Planning Management

• VERSATILIDAD

LEAN CONSTRUCTION & SCHEDULING

LPS & SCHEDULING CON EXCEL 2010

UNIANDES BOGOTÁ (COLOMBIA), 12-13

SEPTEMBER 2013

J.L. Ponz-Tienda et al. / JCEM Publishing Pending

Page 81: Lean Construction  & Last Planner System  with Excel 2010; One Step Forward in Lean Scheduling  & Planning Management

APRENDIZAJE LEANPBL O LEARN BY

DOING

4

LEAN CONSTRUCTION & SCHEDULING

UNIANDES BOGOTÁ (COLOMBIA), 12-13

SEPTEMBER 2013

LO QUE SE OYE , SE OLVIDALO QUE SE VE, SE RECUERDA.

LO QUE SE HACE, SE COMPRENDE.CONFUCIO

Page 82: Lean Construction  & Last Planner System  with Excel 2010; One Step Forward in Lean Scheduling  & Planning Management

LEAN CONSTRUCTION & SCHEDULING

UNIANDES BOGOTÁ (COLOMBIA), 12-13

SEPTEMBER 2013

ETSICCP 2012-2013

Page 83: Lean Construction  & Last Planner System  with Excel 2010; One Step Forward in Lean Scheduling  & Planning Management

LEAN CONSTRUCTION & SCHEDULING

UNIANDES BOGOTÁ (COLOMBIA), 12-13

SEPTEMBER 2013

ETSICCP 2012-2013

Page 84: Lean Construction  & Last Planner System  with Excel 2010; One Step Forward in Lean Scheduling  & Planning Management

LEAN CONSTRUCTION & SCHEDULING

UNIANDES BOGOTÁ (COLOMBIA), 12-13

SEPTEMBER 2013

ETSICCP 2012-2013

Page 85: Lean Construction  & Last Planner System  with Excel 2010; One Step Forward in Lean Scheduling  & Planning Management

LEAN CONSTRUCTION & SCHEDULING

UNIANDES BOGOTÁ (COLOMBIA), 12-13

SEPTEMBER 2013

ETSICCP 2012-2013

Page 86: Lean Construction  & Last Planner System  with Excel 2010; One Step Forward in Lean Scheduling  & Planning Management

LEAN CONSTRUCTION & SCHEDULING

UNIANDES BOGOTÁ (COLOMBIA), 12-13

SEPTEMBER 2013

ETSICCP 2012-2013

Page 87: Lean Construction  & Last Planner System  with Excel 2010; One Step Forward in Lean Scheduling  & Planning Management

LEAN CONSTRUCTION & SCHEDULING

UNIANDES BOGOTÁ (COLOMBIA), 12-13

SEPTEMBER 2013

MUCHAS GRACIAS