Climate Risk and Resilience Planning for Wastewater Infrastructure Laurens van der Tak, PE, D.WRE VWEA Education Seminar – Managing Risk through Process and Organizational Innovation May 12, 2016
Climate Risk and Resilience Planning for Wastewater Infrastructure
Laurens van der Tak, PE, D.WRE
VWEA Education Seminar –Managing Risk through Process and Organizational Innovation
May 12, 2016
2
Presentation Outline
Climate Change Threats
Adaptation Strategy Framework
Climate Change Adaptation Case StudiesMiami-Dade Water and Sewer Department
Boston Water and Sewer Commission
3
Climate Change Threats: Rainfall, Extreme Storms and Sea Level Rise - Impacts Vary Based on System Function and Source (Drainage, Riverine, and Coastal)
Precipitation
Precipitation timing,
Sea level rise Storm surge
2- to 10-year storms
100-year storms
Stormwater/DrainageManagement
Localized floodingIncreased CSOs
Riverine Floodplain Management
Regional flooding
Tidal flooding Tropical storms
4
Climate Change will make storms we design for more intense, and increase the frequency (ie risk) of exceeding design criteria for flood protection.
Precipitation
Precipitation timing,
10-year storm depth will increase by
about 1 inch
A 100-yr becomes 50-yr recurrence
5
Adaptation Framework:When dealing with future uncertainty an adaptive planning process provides needed flexibility.
6
Continually Monitor and
Re-assessMonitor sea
level rise, revisit assessments and
re-assess priority
strategies to continually
inform future actions to adapt
to changes in sea level.
Identification of
Vulnerabilities and Risk
Identify and assess
infrastructure that may be
impacted by sea level rise.
Develop a list of potential adaptation strategies
Determine the range of
strategies that will provide the best adaptation
to changing future
conditions based on identified
vulnerabilities.
Link adaptation
strategies to current processReview
adaptation strategies to
identify those that only require
an adjustment or modification
to current policies or programs.
Implement Adaptation Strategies
Identify priority strategies for
implementation: those strategies
that are best aligned with the
values, goals and objectives
of the implementing organization .
Steps to identify strategies to increase resilience to sea level rise:
2 3 4 5 6
Frame the Problem
“What are the overarching questions to
answer and sea level rise
scenarios to plan for, with the
goal of increasing
resilience to sea level rise?”
11
Frame the Problem
“What are the overarching questions to answer and sea level rise scenarios to plan for, with the goal of increasing resilience to
sea level rise?”
7
A problem well-defined, is a problem half solved. ~Charles Kettering
• Are facilities near tidal waters, subject to sea level rise and storm surge?
• Are my operations at risk of riverine flooding or greater I/I from sea level rise and higher rainfall?
• Are my operations at risk from power outages?
• What is the planning horizon for evaluating climate change:
– Service life of assets
– CIP planning cycle, based on growth, land use change, finances
• Select climate scenarios based on your risk tolerance:
– Consider low, medium and/or high future scenarios
1
Frame the Problem
“What are the overarching questions to answer and sea level rise scenarios to plan for, with the goal of increasing resilience to
sea level rise?”
8
Scenario analysis…accounting for future uncertainty
0
20
40
60
80
100
120
140
160
2010 2020 2030 2040 2050 2060 2070 2080 2090 2100
Sea
leve
l abo
ve 2
010,
cm
YearExtrapolated Historic Trend Line Curve 1 (2100 End Point = 70 cm)Curve 2 (2100 End Point = 100 cm) Curve 3 (2100 End Point = 140 cm)
Curves adapted from the NC Coastal Resources Commission Science Panel on Coastal Hazards 2010NC Sea Level Rise Assessment Report (March 2010)
Historic Trend40-cm (1.3-ft)
PrecautionaryTrend100-cm (3.3-ft)
Sea Level Rise Scenarios
9
Continually Monitor and
Re-assessMonitor sea
level rise, revisit assessments and
re-assess priority
strategies to continually
inform future actions to adapt
to changes in sea level.
Develop a list of potential adaptation strategies
Determine the range of
strategies that will provide the best adaptation
to changing future
conditions based on identified
vulnerabilities.
Link adaptation
strategies to current processReview
adaptation strategies to
identify those that only require
an adjustment or modification
to current policies or programs.
Implement Adaptation Strategies
Identify priority strategies for
implementation: those strategies
that are best aligned with the
values, goals and objectives
of the implementing organization .
Frame the Problem
“What are the overarching questions to
answer and sea level rise
scenarios to plan for, with the
goal of increasing
resilience to sea level rise?”
Steps to identify strategies to increase resilience to sea level rise:
1 4 5 6
Identification of Vulnerabilities
and RiskIdentify and assess
infrastructure that may be impacted by sea level
rise.
2
10
Asset Inventory and Risk Evaluations provide a strong foundation for CC Vulnerability Assessments
• Identify major asset types of interest, e.g.:
– Wastewater treatment plants
– Wastewater pump stations
– Gravity sewers and manholes
– Force mains
• Define the critical elevations for these assets
• Identify vulnerable assets.
• Define probability of inundation events and likelihood of damage.
• Determine consequence of failure.
• Determine risk level: high, medium, and low risk groupings.
Identification of Vulnerabilities
and RiskIdentify and assess
infrastructure that may be impacted by sea level
rise.
2
11
Climate risk builds on asset management information to understand critical assets
Sea Level Rise ScenariosExtreme Events
Hazard Characterization
Susceptible AssetsVulnerable ElevationsDamage Thresholds
Consequence of Failure
Asset Characterization
Vulnerability:Risk = P(Event)*
[P(Damage)*P(Consequence)]Adaptation
Options
Driven by Asset Management program data
12
Climate risk builds on asset management information to understand critical assets
Sea Level Rise ScenariosExtreme Events
Hazard Characterization
Susceptible AssetsVulnerable ElevationsDamage Thresholds
Consequence of Failure
Asset Characterization
Vulnerability:Risk = P(Event)*
[P(Damage)*P(Consequence)]Adaptation
Options
13
Climate Vulnerability Assessment Relies on Asset Inventory and Risk Assessment
Manhole Risk Identification
WWTP Electrical Building At Risk from 100-yr storm surge and 100 cm SLR
14
Climate risk builds on asset management information to understand critical assets
Sea Level Rise ScenariosExtreme Events
Hazard Characterization
Susceptible AssetsVulnerable ElevationsDamage Thresholds
Consequence of Failure
Asset Characterization
Vulnerability:Risk = P(Event)*
[P(Damage)*P(Consequence)]Adaptation
Options
• SLR Hazards = SLR scenario x event• SLR scenarios
40 cm rise – historic trends scenario100 cm rise – precautionary scenario
• EventsMean higher high water (MHHW)10-year flood elevation100-year flood elevation
SLR Impacts on Wilmington NC
15
Adaptation Strategies for Improving Flood Resilience
Water Street GI, Onondaga NY
Adaptation Strategies for Stormwater Management and Flood Protection Systems Grey Solutions:
• Raising electrical and mechanical equipment• Sealing wall penetrations• Water tight doors• Adding tide gates to outfalls• Backup generators• Barriers or local surge walls• Adding capacity to the drainage network• Moving flows from one part of the system to another• Emergency response planning
Green Solutions:• Green infrastructure• Coastal wetlands• Renewable energy and Co-generation• Zoning and Land Use Planning
Phasing adaptations to account for uncertainty in projections and risk tolerance
DC Water Blue Plains Flood WallSource: Umair Irfan, eenews.net
16
Climate Change Case Studies• NACWA: Confronting Climate Change Report to Congress
• City of Wilmington, NC
• NYCDEP – Wastewater Resiliency Plan
• Boston Water and Sewer Commission
• North Carolina Sea Level Rise Risk Management
• USEPA Climate Adaptation Strategies Guide
• City of Alexandria, VA
• Fairfax VA, Master Plan
• LA Bureau of Sanitation
• California Bay-Delta
• Colorado River Basin Study
• Berwick, ME
• Miami-Dade Water and Sewer Department
17
Miami-Dade Water and Sewer Department
Ocean Outfall Legislation Program
MIAMI-DADE COUNTY WATER AND SEWER DEPARTMENT
Preliminary Facility Hardening Plan
19
OOL Compliance Projects
20
Climate Resilience/Facility Hardening- Objectives and General Approach• Assess projected climate change for key climate variables (sea level rise,
precipitation, wind, inundation due to surge)
• Define critical wastewater assets and risk due to climate change
• Define design criteria to minimize risk
• Develop facility hardening plans and design guidelines for WASD design teams
21
Findings/Recommendations:
•Climate Projections •Facility Hardening Design Guidelines
22
Precipitation IDF ProjectionsImpacts: Peak Flows and Flooding
WASD Pump Station Peak Flows Are Based on 2-yr Storm:• Historically: 4.5” (SFWMD, 2001)• Updated: 4.9” (2014)• Projected: 5.4” to 6” (2040 to 2100)
Source: CH2M / CLIMsystems, January 2015
4.69
8.26
14.51
4.89
8.03
14.48
4.77
8.57
15.49
4.80
8.68
15.84
4.84
8.82
16.26
4.93
9.18
17.42
4.88
9.00
16.83
5.04
9.60
18.74
0
2
4
6
8
10
12
14
16
18
20
2 10 100
Prec
ipita
tion
(Inch
es)
Return Period (Years)
Updated HistoricalNOAA Atlas 142040 RCP 6.0 50%2040 RCP 8.5 50%2075 RCP 6.0 50%2075 RCP 8.5 50%2100 RCP 6.0 50%2100 RCP 8.5 50%
23
2-year 24-hour Precipitation Projections (Design Criteria for Peak Sewer Flows): Implications for PS 187
HorizonRCP, % non-exceedance
2-Year 24-hr Rainfall
(inches)% Changein Rainfall
Peak Flow Rate
(mgd)
% Change in flow
“Current” 4.5 0% 151 0%
2040 RCP6.0/8.5, 50% 4.8 7% 155 3%
2040 RCP8.5, 90% 5.42 20% 167 11%
2075 RCP6.0, 90% 5.58 24% 171 13%
2075 RCP8.5, 90% 6.05 34% 180 19%
5.42 inch, 2040 projection selected based on service life of PS
23
24
Precipitation for 2075: Flooding Impacts, Particularly Coupled with Coastal Storm Surge
100-yr 24hr storm projected to
increase from 14.5” to
17.4” – 20”
25
Stressor: Sea Level RiseImpacts: Coastal Flooding and Increased I/I (due higher GW)
Source: SE FL Climate Compact, DRAFT April 2015
26
Surge Modeling: Modeled Result
Comparison of Peak Surge Elevation (mNGVD)
27
Surge Modeling: Modeled Result
Distribution of boundary Peak Surge Elevations:
Blue:
100yr condition
Red: 100yr
+ 1.23m SLR
Bay
Ocean
Tran
sect
Loc
atio
n123456789
1011121314151617181920212223
0 1 2 3 4 5 6Peak Surge Elevation (mNGVD)
1O2O3O4O5O6O7O8O9O10O11O12O13O14O15O16O17O18O19O20O21O26O29O
CDWWTP CDWWTP
SDWWTP
NDWWTP
28
100-yr 100-yr + SLRProjected Stillwater Elevations:
Surge+2075 SLR+2075 Extreme Rainfall
29
Findings/Recommendations:
•Climate Projections •Facility Hardening Design Guidelines
30
Factors in Setting Risk-based Design Criteria will be used to evaluate cost/benefit of facility hardening
• Planning Horizon to establish the service life:
– 2075 for Critical Long-Term Facilities (e.g. WWTPs)
– 2040 selected for pump station flows (e.g. PS-1)
• Criticality, based on wastewater or pumping facility function, such as:
– Maintenance of facility hydraulics
– Maintenance of equivalent primary treatment, liquid train
– Maintenance of secondary treatment, liquid train
– Maintenance of solids treatment
– Ancillary facilities, such as administration and laboratory buildings
30
31
Factors in Setting Risk-based Design Criteria will be used to evaluate cost/benefit of facility hardening
• Level of protection:
– NOAA (High) SLR curve
– USACE (High) SLR curve
• Level of Freeboard:
– 2 ft for WWTP vs Pump Stations in Coastal Flood Zones, ie. FEMA Zone V (ASCE Standard 24-05/2010 FBC Category IV)
– 1 ft for WWTP vs Pump Stations in Inland Flood Zones, ie. FEMA Zones A, AE (ASCE Standard 24-05/2010 FBC Category III)
• Level of Safety Factor:
– 0 ft for low risk facilities, or
– 1 ft as set by WASD at CDWWTP
31
32
Facility Hardening Costs were Developed for Critical Facilities above Design Flood Elevation
33
Adaptation Strategies / Protective Measures
Identified site-specific protective measures to minimize prolonged service interruption and flood risk, while balancing feasibility, resiliency, and cost.
Establish robust design guidelines for future wastewater infrastructure upgrades/designs that assist in mitigating flood risk.
Elevate Equipmenton pads or platforms, to a higher floor, to the roof, or to a new elevated building.
by replacing pumps with submersible pumps and installing watertight boxes around electrical equipment.
Flood-Proof Equipment
Install Static Barrieracross critical flood pathways or around critical areas.
Seal Buildingwith water-tight doors and windows, elevating vents and secondary entrances for access during a flood event.
Sandbag Temporarilyaround doorways, vents, and windows before a surge event.
Install Backup Powervia generators nearby or a plug for a portable generator.
Does not protect equipment but facilitates rapid service recovery.
Source: NYCDEP
34
Facility Hardening Costs - WWTPs
Scenario 1 (Design Elevation 16.0 ft)
CDOOL
(Existing Total CDOOL (Existing
Facilities) TotalCDWWTP 4,576,200$ 4,576,200$ 39,947,600$ 39,947,600$ SDWWTP 1,533,000$ 3,980,000$ 5,513,000$ 16,053,000$ 7,650,000$ 23,703,000$ NDWWTP 9,213,000$ 9,213,000$ 14,578,000$ 14,578,000$ Note: 19,302,200$ 78,228,600$ OOL Facility hardening was only estimated for retrofitting existing facilities. New OOL facilities would be hardened to same design criteria.
Scenario 2 (2075 SLR + FB + SF)
35
Facility Hardening Design Guidelines for Existing and New WWTP Assets
WWTP Summary of Design Criteria for Hardening against Flooding from Surge, Sea Level Rise and Extreme Storm Events.
Existing WWTP Facility Assets New WWTP Facility Assetsft
NGVD29Basis ft
NGVD29Basis
CDWWTP 16.0 FEMA BFE + 3ft SLR from SEFLCC(2011) +FB +SF
20.3 2075 Surge+1.23m(48")SLR + FB +SF+21”(100-yr, 72-hr rainfall)
SDWWTP 16.0 FEMA BFE + 3ft SLR from SEFLCC(2011) +FB +SF
19.0 2075 Surge+1.23m(48")SLR + FB +SF+21”(100-yr, 72-hr rainfall)
NDWWTP 16.0 Same as CDWWTP and SDWWTP 17.1 2075 Surge+1.23m(48")SLR + FB +SF+21”(100-yr, 72-hr rainfall)
FB= Freeboard = 2.0 ft per ASCE Standard 24-05/2010 FBC Category IV
SF= Safety Factor = 1.0 ft per 2014 MWH study at CDWWTP
SLR = 1.23m = 48" per NOAA High projection for 2075 (USACE High projection is 0.93m)
36
Boston Water and Sewer Commission
37
Climate Change Risks
• Increased Rainfall
• Increased river flows and flooding
– Charles River, Neponset River and Mystic River may flood areas of the City during storms
• Sea Level Rise and Storm Surge
38
Forecasted 10-year, 24-hour Design Storm Volumes and Peak Hourly Intensities
Total Storm Volume(inches)
Peak Hourly Intensity(inches per hour)
Scenario 2035 2060 2100 2035 2060 2100
Medium (B2) 5.55 5.76 6.08 1.76 1.83 1.93
Precautionary (A1FI)
5.60 6.03 6.65 1.78 1.91 2.11
BWSC’s current design standard is 4.8 inches
Climate change is increasing the size and intensity of this design storm and it could be 6.65 inches by 2100.
A recalculation of historical rainfall through 2012 indicated that their 4.8-inch design storm has increased to 5.2 inches
Copyright © 2014 Boston Water and Sewer Commission 980 Harrison Ave. Boston, MA 02119 617-989-7000
39
Sea Level Rise Projections
Medium SLR Projections through 2100
Component 2035 2060 2100
Global (feet) 0.79 1.54 3.51
Subsidence (feet) 0.08 0.16 0.30
Regional (feet) 0 0 0
Total (feet) 0.87 1.70 3.81
Precautionary SLR Projections through 2100
Component 2035 2060 2100
Global (feet) 1.21 2.20 6.20
Subsidence (feet) 0.08 0.16 0.30
Regional (feet) 0.23 0.39 0.66
Total (feet) 1.52 2.75 7.16
Source: Vermeer & Rahmstorf, 2009
Return Period (years) Boston (mm) Boston (m) Boston (ft)
2 868 0.87 2.85
5 1,067 1.07 3.50
10 1,194 1.19 3.92
20 1,311 1.31 4.30
50 1,457 1.46 4.78
100 1,562 1.56 5.12
200 1,664 1.66 5.46
500 1,793 1.79 5.88
1,000 1,887 1.89 6.19
Storm Surge Heights held Constant with Today
Copyright © 2014 Boston Water and Sewer Commission 980 Harrison Ave. Boston, MA 02119 617-989-7000
40
Evaluated Flooding Risks to Sewer Systems
• Models of the Storm Drain and Sewer Systems (SWMM) to Calculate Flows Now and in The Future
• 2-dimensional computer models (CH2M’s Flood Modeler-FAST) to map surface flooding due to drainage and storm surge
Copyright © 2014 Boston Water and Sewer Commission 980 Harrison Ave. Boston, MA 02119 617-989-7000
41
Flood Modeler Simulation of Hurricane Sandy
Source: Douglas, et. al. 2013.
Copyright © 2014 Boston Water and Sewer Commission 980 Harrison Ave. Boston, MA 02119 617-989-7000
42
Risks Of Flooding With Sea Level Rise And Storm Surge –Year 2060 with 10-year/24-hour Rainfall
Year 2060 Rain
Sea Level Rise, No Storm Surge
Year 2060 Rain
Sea Level Rise, With Storm Surge
Copyright © 2014 Boston Water and Sewer Commission 980 Harrison Ave. Boston, MA 02119 617-989-7000
43
Pump Station Risk Scoring for Precautionary 2100 Scenario with Storm Surge
0
10
20
30
40
50
60
70
80
90
100
MW
RA C
otta
ge F
arm
(MW
RA00
1)
Sulli
van
Squa
re(2
9JPS
1)
Com
mon
wea
lth A
ve(2
2IPS
1)
MW
RA P
rison
Poi
nt(M
WRA
003)
Caru
so(2
9NPS
4)
Trill
ing
Way
(22M
PS2)
Publ
ic A
lley
701
(21J
PS52
6)
Sum
mer
Str
eet
(22M
PS5)
Uni
on P
ark
(21K
PS2)
MW
RA D
eLau
ri(M
WRA
002)
Sym
phon
y H
all
(21I
PS1)
Aust
in S
tree
t(2
7JPS
1)
Port
Nor
folk
(11L
PS31
6)
TOTA
L RIS
K (0
-100
)
PUMP STATION (FACILITY ID)
Pump Station Total Risk Score for P2100 with Storm Surge (23.50 feet)
BWSC MWRA
Copyright © 2014 Boston Water and Sewer Commission 980 Harrison Ave. Boston, MA 02119 617-989-7000
44
Future Condition Without and With Flood Walls
Precautionary 2060 Precautionary 2060 With Flood Walls
Flooding due to SLR and storm surge only, no rainfall in these calculations
Copyright © 2014 Boston Water and Sewer Commission 980 Harrison Ave. Boston, MA 02119 617-989-7000
45
Drainage Would Still Have to be Addressed
Precautionary 2060 With Flood Walls and 10-year/24-hour rainfall
Additional mitigations beyond flood walls along shorelines would be needed to prevent street flooding should a significant rainfall occur during a storm surge event in the future
Copyright © 2014 Boston Water and Sewer Commission 980 Harrison Ave. Boston, MA 02119 617-989-7000
46
Update Design Storm for Drainage and Conveyance Engineering, Planning and Design
• 10-year/24-hour design storm
– 5.20 inches (instead of 4.80 inches)
– Peak hourly intensity of 1.65 inches per hour
• For life cycles through the year 2100:
– Consider range from 5.55 inches to 6.65 inches
– Depending on the life cycle starting and end date.
• Other Recommendations
– Annual rainfall should range from 50.0 to 55.4 inches by the year 2100
– Apply to CSO control and TMDL planning
– Apply to operations and maintenance planning
– Continually monitor and update rainfall statistics
Copyright © 2014 Boston Water and Sewer Commission 980 Harrison Ave. Boston, MA 02119 617-989-7000
47
Design Flood Elevations (DFEs) to Protect Facilities and Operations
Recommended DFEs for Pump Stations and other Structures
Design Condition
Project Life cycles up to the Year(feet – Boston City Base)
2035 2060 2100
Minimum 18.22 19.06 21.16
Higher Risk Mitigation 18.88 20.11 24.50
Recommended DFEs are based on:• The current MHHW elevation of 11.23 feet• Sea Level Rise• 100-year storm surge of 5.12 feet • 1-foot freeboard
Apply to:• Construction of new infrastructure • Capital improvements to existing infrastructure• Tide gates
Copyright © 2014 Boston Water and Sewer Commission 980 Harrison Ave. Boston, MA 02119 617-989-7000
48
New York City DEP
49
NYC Wastewater Resiliency Plan
Strategy: Protect wastewater treatment facilities
Adopt a wastewater facility design standard
Harden pumping stations and wastewater treatment plants
Explore opportunities to expand cogeneration
50
Critical Flood Elevations
26th Ward 12.6 13.5 12.9 Brooklyn-Sewer
Bowery Bay 11.6 15.5 13.9 Queens
Coney Island 10.1 15.5 14.0 Brooklyn-Highway
Hunts Point 10.2 17.5 16.0 Bronx
Jamaica None 13.5 11.9 Queens
Newtown Creek 10.0 13.5 12.0 Brooklyn-Highway
North River 9.7 12.5 10.8 Manhattan
Port Richmond 12.1 14.5 12.4 Staten Island
Oakwood Beach 13.1 16.5 14.4 Staten Island
Owls Head 13.5 14.5 13.0 Brooklyn-Highway
Red Hook 11.7 14.5 13.0 Brooklyn-Highway
Rockaway 11.4 14.5 12.9 Queens
Tallman Island 10.1 15.5 13.9 Queens
Wards Island 10.7 17.5 15.8 Manhattan
51
Building-Level Risk Assessment
Performed site visits and analyzed each facility for flood pathways and threshold elevations.
Locations identified as at-risk if threshold elevations are below the assigned flood elevation (100-yr ABFE + 30-inches SLR).
Electrical Conduits and ManholesTunnels Grates
Rollup Doors Doorways & Windows Areaways
Common Flood Pathways:
52
Asset-Level Risk Assessment
Target Assets include:
• Equipment associated with primary treatment
• Electrical equipment
• Pumps and motors
Target asset identified as at-risk- situated below the assigned flood elevation (100-yr ABFE + 30 inches SLR), and are not submersible.
Electrical assets located underground in the RAS Gallery at 26th Ward WWTP are at risk of flood damage.
53
NYCDEP Wastewater Resilience Plan Comparison of Mitigation Costs and Cost of No Action (ie Benefits of Mitigation)
Source: NYCDEPAll estimates are based on AACE Level 5 Cost Estimate guidelines as noted in the NYCDEP BEDC Cost Estimating Manual
Adaptation Cost No Action Cost Risk Avoided Over 50 years
Thank You