7/23/2019 KKB Project List http://slidepdf.com/reader/full/kkb-project-list 1/18 1 | Page Project List 2011 PROJECT NO. CLIENT CONSULTANT PROJECT GENERAL DESCRIPTION OF WORKS 1 Sara-Chem Sdn Bhd Mild steel Navigational Buoy for Marine Base Supply and fabricate 3050mmØ x 5450mm overall height mild steel navigational buoy, comprising of buoyancy chamber couterweight,manholes,lifting and mooring eyes,battery compartment,trestles shoes and trest all shot blasting to SA 3 and painted with 3 coats marine grade epoxy pain 2 Hock Seng Lee Berhad Mild steel plate to pipe casing Supply of labour and equipment for rolling of mild steel plate to pipe casin including of prebending and one longitudinal weld 3 Ban Leong Enterprise Sdn Bhd 6m Street Lighting Column 6m nominal mounting height 1.2m planted galvanised tapered octagona steel street lighting column c/w c- channel (100mm x 50mm x 3mm thk) mount spot lights 4 Electrical Electrical Co. Sdn Bhd 11m and 9m hot-dip galvanised standard high tensile pole for BELB Talian Grid Negeri Sarawak Tahun Zon Tiga Sarikei & Kapit) 11m and 9m hot-dip galvanised standard high tensile pole 5 Hydroicon 6m Street Lighting Column 6m nominal mounting height 0.8m planted galvanised tapered octagona steel street lighting column c/w single short arm 6 Electronic Electrical Co. Sdn Bhd 11m High tension pole and 9m Low Tension Pole for BELB Talian Grid Negeri Sarawak Tahun Zon Tiga(3) Tahun 2010- 2011 (Sarikei & Kapit) Hot Dip Galvanised 11m High Tension Pole, 11m High Tension H-pole, 9m Lo Tension pole 7 Sabah Electricity Sdn Bhd Steel pole to Sabah Electricity Central Store Kolombong, Kota Kinabalu Supply and delivery of LT pole intermediate, 31ft, HT pole intermediate 33ft, HT pole terminal 3 8 MEMC Electrionic Materials, Inc. Steel beams for crane system, filter platform and 1 ton crane girder for MEMC Merdeka Project at Samajaya Industrial Zone Supply,fab,painting,delivery and installation of:- (1) steel beams for cranes system and provision of labou equipment for installation of 2 units crane griders and crane hoists.(2) Filt Platform (3) 1 ton crane girder inclusi of hoist motor c/w JKKP approval 9 Sabah Electricity Sdn Bhd Steel pipe and teekay coupling to Mini Hydro Melangkap, Kota Belud, Sabah Supply, test inspection, delivery and transportation of steel pipe and teek coupling 10 Shorefield Sdn Bhd 9m hot-dip galvanised low tension pole Supply 9m hot-dip galvanised standa low tension pole 11 Chiyoda Steel Structure Fabrication (Package -E) Package E: General Utility Area Inland
18

KKB Project List

Feb 18, 2018

Download

Documents

Larry Tan
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: KKB Project List

7/23/2019 KKB Project List

http://slidepdf.com/reader/full/kkb-project-list 1/18

1 | P a g e  

Project List 2011

PROJECT

NO. 

CLIENT  CONSULTANT  PROJECT  GENERAL DESCRIPTION

OF WORKS 

1 Sara-Chem Sdn

Bhd

Mild steel Navigational Buoy for Marine

Base

Supply and fabricate 3050mmØ x

5450mm overall height mild steelnavigational buoy, comprising of

buoyancy chamber

couterweight,manholes,lifting and

mooring eyes,battery

compartment,trestles shoes and trest

all shot blasting to SA 3 and painted

with 3 coats marine grade epoxy pain

2 Hock Seng Lee

Berhad

Mild steel plate to pipe casing Supply of labour and equipment for

rolling of mild steel plate to pipe casin

including of prebending and one

longitudinal weld

3 Ban Leong

Enterprise SdnBhd

6m Street Lighting Column 6m nominal mounting height 1.2m

planted galvanised tapered octagonasteel street lighting column c/w c-

channel (100mm x 50mm x 3mm thk)

mount spot lights

4 Electrical

Electrical Co.

Sdn Bhd

11m and 9m hot-dip galvanised standard

high tensile pole for BELB Talian Grid

Negeri Sarawak Tahun Zon Tiga Sarikei &

Kapit)

11m and 9m hot-dip galvanised

standard high tensile pole

5 Hydroicon 6m Street Lighting Column 6m nominal mounting height 0.8m

planted galvanised tapered octagona

steel street lighting column c/w single

short arm

6 ElectronicElectrical Co.

Sdn Bhd

11m High tension pole and 9m LowTension Pole for BELB Talian Grid Negeri

Sarawak Tahun Zon Tiga(3) Tahun 2010-

2011 (Sarikei & Kapit)

Hot Dip Galvanised 11m High TensionPole, 11m High Tension H-pole, 9m Lo

Tension pole

7 Sabah

Electricity Sdn

Bhd

Steel pole to Sabah Electricity Central

Store Kolombong, Kota Kinabalu

Supply and delivery of LT pole

intermediate, 31ft, HT pole

intermediate 33ft, HT pole terminal 3

8 MEMC

Electrionic

Materials, Inc.

Steel beams for crane system, filter

platform and 1 ton crane girder for

MEMC Merdeka Project at Samajaya

Industrial Zone

Supply,fab,painting,delivery and

installation of:- (1) steel beams for

cranes system and provision of labou

equipment for installation of 2 units

crane griders and crane hoists.(2) Filt

Platform (3) 1 ton crane girder inclusi

of hoist motor c/w JKKP approval9 Sabah

Electricity Sdn

Bhd

Steel pipe and teekay coupling to Mini

Hydro Melangkap, Kota Belud, Sabah

Supply, test inspection, delivery and

transportation of steel pipe and teek

coupling

10 Shorefield Sdn

Bhd

9m hot-dip galvanised low tension pole Supply 9m hot-dip galvanised standa

low tension pole

11 Chiyoda Steel Structure Fabrication (Package -E) Package E: General Utility Area Inland

Page 2: KKB Project List

7/23/2019 KKB Project List

http://slidepdf.com/reader/full/kkb-project-list 2/18

2 | P a g e  

Sarawak Sdn

Bhd

for TMP Project, Bintulu transportation charge and insurance

to delivery to project jobsite in Bintul

including unloading. Application of

painting material brand Kansai Paint,

Documentation and inspection charg

12 Esajadi Power

Sdn Bhd

1.8m ID x 8mmthk x 6m(L) mild steel

bare pipe for Sg Pangapayaun MiniHydro Power Plant Kota Kinabalu

Supply and delivery of1.80m Idx

6mmthk x 6m (L) Ms bare pipe FOBKuching Port

13 MEMC

Electrionic

Materials, Inc.

Pipe support Supply,fabricate,painting,delivery and

installation of pipe support

Page 3: KKB Project List

7/23/2019 KKB Project List

http://slidepdf.com/reader/full/kkb-project-list 3/18

3 | P a g e  

Project List 2010

PROJECT

NO. 

CLIENT  CONSULTANT  PROJECT  GENERAL DESCRIPTION

OF WORKS 

1  CMS Clinker

Sdn Bhd 

Perunding SL  Contract No: CNTR/CLKR/10/965: -

Proposed steel structure and equipmentinstallation for Bucket Elevator Kiln

Feeding System at CMS Clinker Plant on

Lot 571, Block 4, Sentah Segu Land

District, Kampung Mambong, Kuching,

Sarawak 

Supply,fabricate,delivery of structure

steel works 

2 Edisi Optima

Sdn Bhd

Jurutera Minsar Proposed New Hanger for Awan Inspirasi

Sdn Bhd At Miri Airport, Sarawak

Steel Structure Works and metal roof

3 KKB Industries

(Sabah) Sdn

Bhd

Kompleks Sukan Blok E-1: - Project

Cadangan Pembinaan Bangunan KD Sri

Tawau, Tawau, Sabah

Supply, fabricate, hdg, delivery and

installation of steel structure

4 Pusat

Pembangunan

KemahiranSarawak (PPKS)

The Proposed Renovation Works to be

Done At Automotive & Welding Institute

Of Sarawak

Supply,fabricate,painting,delivery a

installation of metalworks 6" vice

portable welding bay,6G table

5 Putra Perdana

Construction

Sdn Bhd

Design, Construction, Completion and

Commissioning of Proposed Sarawak

Energy Berhad (SEB) Headquaters

Building On Lot 2833 (Part of Lot 2342),

Block 7, Isthmus, MLTD, Kuching,

Sarawak

Supply,fabricate and installation of

structural steel works

6 Sabah

Electricity Sdn

Bhd

31feet Intermediate Low Tensile Pole to

SESB Central Store Kolombong, Kota

Kinabalu, Sabah

Supply and delivery of 31 feet

Intermediate Low Tensile pole

7 Jawatan

PembinaanDewan

Serbaguna SJK

Chung Hua,

Serian

The Proposed Multi-purpose Hall for

Chung Hua School on Lot 76, SerianBazaar, Serian Town District at

Simanggang Road, Serian.

Supply of labours,materials and

equipment for fabrication and paintinof structural steel works and roof trus

for multi-purpose hall

8 GA Chip

Enterprise

Mild Steel plate for Ship Supply of 22mm x 8' x 30' Grade ABS

mild steel plate

9 ASSAR

Chemicals

Engineering

Services Sdn

Bhd

Perunding SL Supply and Delivery of Tubular steel pipe

piles for The Construction and

Completion of The Proposed ASSAR

Senari Industrial Complex (ASIC II) Oil,

Gas and Chemical (OGC) Jetty and

Marine Operation Centre (MOC) at

Tanjung Manis, Mukah, Sarawak

Supply and delivery of Tubular Steel

Pipe piles

10 Hock Seng Lee

Bhd

Supply of mild steel casing Supply of labour and equipment for

rolling of mild steel plate to pipe casi

inclusive of prebending and one

longitudinal weld

11 Nam Joon

Trading Sdn

6000IG capacity Mild Steel Underground

Tank

Supply of 6000IG capacity single wall,

single compartment mild steel flat

Page 4: KKB Project List

7/23/2019 KKB Project List

http://slidepdf.com/reader/full/kkb-project-list 4/18

4 | P a g e  

Bhd ended underground tank c/w one coa

bituminous paint to external surface

12 CMS Clinker

Sdn Bhd

Proposed Grinding Ball Sorting Machine

(Media) for CMS Cement Pending, Plant

Supply,fabricate,painting,delivery,ins

ation, testing and commissioning of

Mild Steel Grinding Ball Sorting Mach

Complete with Mechanical and

Electrical installation13 CH2M Hill

Malaysia Sdn

Bhd

Package 398615-4001 -The Structural

Steel Works for The Proposed MEMC

Merdeka Project at Samajaya Free

Industrial Zone, Kuching

Supply,fabricate,shot blasting,deliver

and installation of steel structure

14 Sri Datai

Construction

(Sarawak) Sdn

Bhd

The Proposed Quarry Plant Project At

Gunong Sibanyis On Lot 246, Block 5,

Sentah Segu Land District, Kuching

Division, Sarawak

Supply, fabricate, deliver and install fo

steel structural works and roof coveri

15 AWI Builder

Sdn Bhd

Program Menilai,

Membaiki/Menggantikan Jambatan di

Jalan Persekutuan Negeri Sarawak (Fasa

2) - Package A :The Proposed Batu Kawa

Bridge Extension Kuching Division.

Supply, fabricate, painting,delivery an

installation of composite 1-beam and

miscellaneous works

16 CMS Quarries

Sdn Bh

Contract No: CNTR/1310/010/967 - The

Proposed new 350 TPH Crushing

Screening and Stockpiling Plant At

Gunong Sibanyis, Jalan Mambong

Kuching

Supply of all materials,

labour,tools,machinery and equipme

to Fabricate, Erection,

installation,testing and commissionin

17 Borneo

Geotechnic Sdn

Bhd

Hot-Rolled Steel reinforcement bar for

MEMC Project at Samajaya Industrial

Zone, Kuching

Supply of hot rolled steel reinforceme

bar

18 Global Upline

Sdn Bhd

Membina Jalan Hubungan Lapangan

Terbang Antarabangsa

Kuching/Stutong,Kuching (Phase 2) -

Mild steel Bridge Parapet railing for SgGatal

Supply,fabricate,hot-dip galvanising a

installation of mild steel bridge parap

railing a distance of 652.4m

19 Swee Joo

Coastal

Shipping Sdn

Bhd

Mild Steel Tank Supply and fabricate 5.50 length mild

steel tank c/w 2 nos manhole includin

shot blasting to SA2½ and apply 2 coa

epoxy paint

20 H.S.G.J.V

Engineering

Cadangan Penswastaan Pembinaan

Komplek 1 Division Dan Kem 4 Renjer

Diraja di Muara Tuang, Kota Samarahan,

Sarawak

Supply,delivery, installation of

underground tanks, pipeworks,

submersible pumps, fuel dispenser, a

compressor

21 GA Chip

Enterprise

Mild steel plate for fabrication of ship Supply of 22mm x 8' x 30' Grade ABS

mild steel plate

22 Borneo

Geotechnic Sdn

Bhd

Hot-rolled steel reinforcement bar For

MEMC Merdeka Project at Samajaya

Free Industrial Zone, Kuching

Supply and delivery of hot-rolled stee

reinforcement bar to BS 4499 in

standard Y25 x 12m length

23 MEMC Kuching

Sdn Bhd

Hot-Rolled Steel materials for fabrication

of 2 units Junior Furnace Platform for

MEMC Merdeka Project at Samajaya

Free Industrial Zone, Kuching

Supply of Hot-Rolled Steel materials f

fabrication of 2 units Junior Furnace

Platform

24 Sinohydro 10,000LT capacity Mild Steel Skid Tank Supply,fabricate and painting of 1.80

Page 5: KKB Project List

7/23/2019 KKB Project List

http://slidepdf.com/reader/full/kkb-project-list 5/18

5 | P a g e  

Corporation

(M) Sdn Bhd

For Bengoh Dam Project Ø x 4m length 10,000LT diesel tank c/

fitting and epoxy painting to external

surface

25 CH2M Hill

Malaysia Sdn

Bhd

Package 405666-4017 - Architectural

interior works for MEMC Merdeka

Project at Samajaya Free Industrial Zone,

Kuching

Package 405666-4017 - Architectural

interior works for MEMC Merdeka

Project at Samajaya Free Industrial

Zone, Kuching - door Frame (TypeA,B,C,D)

26 MEMC Kuching

Sdn Bhd

Big daddy frame for MEMC Merdeka

Project at Samajaya Free Industrial Zone,

Kuching

The supply,fabricate,painting,delivery

and installation of the big daddy fram

27 MEMC Kuching

Sdn Bhd

Staircase & frame of Poly Disp BBU for

MEMC Merdeka Project at Samajaya

Free Industrial Zone, Kuching

Supply,Fabricate,painting,delivery an

installation of Staircase & frame of P

Disp BBU

28 ALSTOM Hydro

Malaysia Sdn

Bhd

Mild steel components for Bakun

Hydroelectric Project

Supply and delivery of hot-dip

galvanising mild steel angles, plate an

Grade 8.8 bolt & nuts

29 Shorefield Sdn

Bhd

Hot-dip galvanised of mild steel pole

accessories

Supply of Hot-dip galvanised mild ste

pole accessories

30 Shorefield Sdn

Bhd

9m & 11m hot-dip galvanised standard

Low Tension Pole

Supply of 9m & 11m hot-dip galvanis

standard Low Tension Pole

31 IMPSA

(Malaysia ) Sdn

Bhd

GCB support structures for Bakun

Hdyroelectric Project

Design, supply,fabricate and hot-dip

galvanising of GCB support structures

32 Lim Aik Chai

Electrical Sdn

Bhd

9m steel pole 3.8mm thk Supply,fabricate and hot-dip galvanis

of 9m steel pole 3.8mm thk

33 Tung Hin

Enterprise Sdn

Bhd

9m Street Lighting Column 9m nominal mounting height planted

galvanised tapered Octagonal steel

Street Lighting Column c/w 3m single

bracket arm (Base plate size 400 x 40

25mm thk with 400 x 100 x 25mm thkanchor plate and anchor bolts)

34 Lim Aik Chai

Electrical Sdn

Bhd

8m nominal mounting height planted

galvanised tapered octagonal steel

lighting column c/w 3m single& double

bracket

8m nominal mounting height planted

galvanised tapered octagonal steel

lighting column c/w 3m single & doub

bracket

35 Shorefield Sdn

Bhd

9m & 11m hot-dip galvanised standard

Low Tension Pole

9m & 11m hot-dip galvanised standar

Low Tension Pole

36 Global Upline

Sdn Bhd

Supply of hdg highway guardrail for

Stutong Link Road,Kuching (SLRK)

Supply of hdg higway guardrail 4318m

overall length c/w 8pc splicing bolt an

nut

37 Global Upline

Sdn Bhd

Mild steel bridge parapet for Upgrading

of Jalan Kepayan, Kota Kinabalu, Sabah

Supply,fabricate,hdg and installation

mild steel bridge parapet a distance o

1000m

38 Citra Alti Sdn

Bhd

11m and 9m Low Tensile Pole Supply,fabricate and hdg of 11m and

9m x 3.8mm thk LT pole

39 PPES Works

(Sarawak) Sdn

Bhd

Highway guardrail for Kuching-Serian

Road Miles 15 Traffic Light intersection-

Kuching Samarahan Division Boundary

Miles 25

Supply of hot dip galvanised highway

guardrail

Page 6: KKB Project List

7/23/2019 KKB Project List

http://slidepdf.com/reader/full/kkb-project-list 6/18

6 | P a g e  

40 Group

Engineers (M)

Sdn Bhd

9m Street Lighting Column for Samalaju

Project

9m nominal mounting height 1.30m

planted galvanised tapered octagona

Street Lighting Column c/w 1.50m

bracket arm

41 Global Upline

Sdn Bhd

Highway guardrail & accessories for

Stutong Ling Road, Kuching (SLRK)

Project

Supply of hdg higway accessories

including c-channel post,end wind (fis

tail),median terminal,bull noseterminal,M16 hexagon & round bolt &

nut

42 Syarikat Alson

Enterprise

Highway guardrail & Accessories Supply of hot-dip galvanising highway

guardrail 4318(effective length

4000mm) overall length c/w 8pcs

splicing bolt & nut

43 Global Upline

Sdn Bhd

10m Street Lighting Column for

Upgrading of Jalan Kepayan,Kota

Kinabalu (UJK) Project

10m nominal mounting height flange

hot-dip galvanising and painted round

Decorative Steel Street Lighting Colum

complete with base plate and anchor

bolt c/w single arm or double arm

44 Hexacomm

Engineering

Sdn Bhd

4m and 10m mounting height Street

lighting column

4m nominal mounting height hdg mid

hinges flange mounted tapered oct

Steel street lighting column c/w brac

arm and lighting arrestor base plate

45 R.T Cargo Sdn

Bhd

Mild steel plate Supply and hot dip galvanising of

3mmthkx 8' long mild steel plate

46 Lim Aik Chai

Electrical Sdn

Bhd

8m Steel Street Lighting Column 8m nominal mounting height planted

galvanised tapered Octagonal Steel

Street Lighting Column c/w 3m doubl

arm bracket

47 Lim Aik Chai

Electrical Sdn

Bhd

6m Street Lighting Column 6m nominal mounting height 1.30m

planted galvanised tapered octagona

steel street lighting column c/w short

spigot48 Daya Kuasa

Suria Sdn Bhd

9m hot-dip galvanised standard Low

Tension Pole (Type 9S)

9m hot-dip galvanised standard Low

Tension Pole as per SESCO Specificati

Page 7: KKB Project List

7/23/2019 KKB Project List

http://slidepdf.com/reader/full/kkb-project-list 7/18

7 | P a g e  

Project List 2009

PROJECT

NO. 

CLIENT  CONSULTANT  PROJECT  GENERAL DESCRIPTION

OF WORKS 1  F&NCC

Beverages Sdn

Bhd 

CHT Jururunding  Proposed Construction and Completion

of Proposed Infrastructural works on Lot

583, Block 4 Matang Land District for

Messrs Borneo Springs Sdn Bhd,

Matang,Kuching. 

Civil and structure construction and a

other works not included in the above

but deemed, necessary for the

completion of the work or as shown i

the drawings. 

2 Hock Seng Lee

Bhd

Hashim & NEH

(Sarawak) Sdn

Bhd

Cadangan Pembinaan Dan Penyiapan

Dewan Utama Universiti Malaysia,

Sarawak (UNIMAS), Kota Samarahan

Structural Steel Roof Framing for mai

Great Hall, Banquet Hall, Curtain Wal

Mai Orchestra & Gemilang Stage.

3 Swee Joo

Coastal

Shipping Sdn

Bhd

Supply and Fabricate 20 Single

Compartment Mild Steel Tank Container

c/w 2 nos manhole including shot

blasting to SA 2½ and supply 2 coats

epoxy paint

ISO Tank for transportation of palm o

and chemical.

4 Asian Foresty

Company

Design, Supply, Fabriacate and Hot Dip

Galvanising of 4.00m width steel truss

bridge (3M modular construction) as per

manufacturer details

Design and Supply of 30M Maximum

Span Modular Bridge.

5 Jabatan Kerja

Raya Sarawak

Jurutera

Perunding Wahba

Sdn Bhd

Jurutera M&E

Konsult (Sarawak)

Sdn Bhd

Construction and Completion of

proposed Samalaju Water Supply,

Bintulu Division, Sarawak.

  Pipe Laying for MSCL pipeworks

  Chamber, pipe support, anchor blo

thrust block & reinstatement of

existing works

  Earthworks for raw water intake an

water treatment plant

  Construction & Completion of Raw

Water Intake Facilities  Construction & Completion of Wat

Treatment Plant

  Pipe laying for HDPE pipeworks

  Mechanical & Electrical installation

Page 8: KKB Project List

7/23/2019 KKB Project List

http://slidepdf.com/reader/full/kkb-project-list 8/18

8 | P a g e  

Project List 2008

PROJECT NO.  CLIENT  CONSULTANT  PROJECT  GENERAL DESCRIPTION

OF WORKS 1000P01-08  Moh Heng Co

Sdn Bhd 

United

Consultants 

The Construction and

Completion of the Proposed

Double Storey Office Cum

Factory at Muara Tebas Land

District 

Construction and Completion of

Warehouse / Factory Building,

including all associated Archieture, RC

works, M&E Services and

Infrastructure Works 

1000P02-08 Asia Depot Sdn

Bhd

Arkitek Mok JY Proposed 2 Storey Office & 1

Storey General Warehouses at

Lahad Datu, Sabah

Construction and Completion of

Warehouse / Factory Building

including all associated Archieture, RC

works, M&E Services and

Infrastructure Works

1000P03-08 F&N Beverages

Sdn Bhd

MARS &

ASSOCIATES Sdn

Bhd

Proposed Warehouse and Office

Extension on Sublot 1 of

Subdivision of Parent Lots at

Jalan Datuk Amar Stephen

Kalong Ningkan, Kuching

Sarawak

Construction and Completion of

Warehouse / Factory Building

including all associated Archieture, RC

works, M&E Services and

Infrastructure Works

SJ#8000015 Global Upline

Sdn Bhd

PY Konsep

Perunding Sdn

Bhd

Project Pembinaan Jejambat Di

Persimpangan Jalan Putatan-

Kepayan Dengan Jalan Lintas,

Dan Jalan Putatan-Kepayan

Dengan Jalan Mat Salleh, Kota

Kinabalu Sabah - Bridge Parapet

Railing

Supply, Hot Dip Galvanising, Delivery

and Installation of Bridge Parapet

Railing and Post

SP#8000003 Alstom Hydro

Malaysia SdnBhd

SSM Associates

Sdn Bhd

Bakun Hydro Electric Project -

System, Hisc, Structure,Platform& Tanks

Supply, Fabricate, Hot Dip Galvanising

and delivery of Steel Structure forPackage EM1

SJ#8000001 LSL Sdn Bhd WE Engineering Supply, Fabricate and Hot Dip

Galvanise, mild steel Polygonal

Monopole c/w anchor bolt,

detachable climbing rung,

feeder mount and Antenna

Mounting

Design, Supply, Fabricate and Hot Dip

Galvanising of Telecommunication

Monopole

SO#8000600 Riaplus Sdn Bhd Nil Supply of 350mm O.D x 10mm x

12.00m length mild steel plain

ended pipe

Supply and Delivery of Steel Pipe Pile

1000P05-08 Malaysia-China

Hydro Joint

Venture

Angkasa

Consulting

Services Sdn Bhd

Bakun Hydroelectric Project

Package CW2-Main Civil Works  – 

Construction and Completion of

Log Boom structures

Manufacture, Fabricate, Supply,

Delivery, Installation and

Commissioning of Log Boom

Structures, including all related R.C.

Works.

JECTS LIST 2009 

Page 9: KKB Project List

7/23/2019 KKB Project List

http://slidepdf.com/reader/full/kkb-project-list 9/18

9 | P a g e  

Project List 2007

PROJECT NO.  CLIENT  CONSULTANT  PROJECT  GENERAL DESCRIPTION

OF WORKS F1/2007  Sinohydro

Corporation

(M) Sdn Bhd 

Nil  Powerhouse for Bakun

Hydroelectric Project

Supply and Delivery of Metal Roofing

Sheet,Rock Wool Single Side 

F2/2007 PPES Works

(Sarawak) Sdn

Bhd.

Jurutera Minsar

Consult Sdn Bhd

The proposed Construction and

Completion of Sarawak

Convention and Exhibition

Centre

Supply, Fabricate,Painting, Delivery and

Installation of Mild steel structural

works

1000P01-07 Sibu Water

Board

Jurutera

Jasa(Sarawak)

Construction , Completion and

commissioning of the proposed

Second raw water intake for

Salim Water Treatment Plant,

Sibu

1200mm ND pipeline, Jetty, Steel

Fender, Generator House,Guard

House,Sub-station,Air Compressor

House,External Works and Mechanical

& Electrical Services.1000P02-07 Global Upline

Sdn Bhd

Jurutera Minsar

Consult Sdn Bhd

Menbina Jalan Hubung

Lapangan Terbang Antara

Bangsa Kuching (KIA/Stutong) ,

Kuching Sarawak-Water Supply

Works (Package CW1)

400mm ND MSCL pipeline & 200mm ND

HDPE pipeline and associated R.C.

works

1000P03-07 Global Upline

Sdn Bhd

Jurutera Minsar

Consult Sdn Bhd

Projek Menaiktaraf

Persimpangan Miri KeLutong -

Pembinaan Jejambat Di Bulatan

Pujut Dan Puchong,Miri ,

Sarawak (Water Supply

450mm ND DI Pipeline ,250mm ND DI

Pipeline,100mm ND,150mm ND & 250

mm ND HDPE pipeline and associated

R.C works .

1000P04-07 Tang Container

and Services

Sdn Bhd

Eswel Engineers

Sdn Bhd

Proposed Extension to Existing

Food And Consumer

Products ,Warehouse on lot

794,Block 7,Muara Tebas Land

District ,Demak Laut Industrial

Park,Kuching.

81.00m X 37.00m Steel Warehouse

Structure with Metal Roofing ,Cladding,

R.C. Works and External Works.

F3-07 PPES Works

(Sarawak)Sdn

Bhd

China National

Machinery &

Equipment Import

& Export

Corporation

The Supply , Fabricate and

Erection of Structural Steel

Work(Including Roof Covering,

Wall Cladding and Accessories)

to coal shed for the proposed

Mukah Coal-Fired Power

Station,Mukah Division,Sarawak

Structural Steel Works with Associated

Metal Roofing and cladding works

F4-07 Syarikat Sesco

Berhad

The Annual Supply and Delivery

of Steel Products

Supply Of Hot Dip galvanized Steel

ProductF5-07 PPES Works

(Sarawak)Sdn

Bhd

China National

Machinery &

Equipment Import

& Export

Corporation

The Construction and

Completion of the Coal handling

related structures for the

proposed Mukah Coal-Fired

Power Station,Mukah Division ,

Sarawak

Structural steel works with associated

Metal roofing and Cladding works.

SJ#7000022 Global Upline Projek Menaiktaraf Supply of Hot Dip Galvanized Steel

Page 10: KKB Project List

7/23/2019 KKB Project List

http://slidepdf.com/reader/full/kkb-project-list 10/18

10 | P a g e  

Sdn Bhd Persimpangan Miri Ke Lutong -

Pembinaan jejambat Di Bulatan

Pujut dan Puchong ,

Miri,Sarawak

bridge Papapet Railing

SJ#7000061 Global Upline

Sdn Bhd

Traffic Improvement and

Management Schemes Along

Jalan Kepayan,Kota Kinabalu

Supply of Hot Dip Galvanized

Decorative Street Lighting colums.

Page 11: KKB Project List

7/23/2019 KKB Project List

http://slidepdf.com/reader/full/kkb-project-list 11/18

11 | P a g e  

Project List 2006

PROJECT NO.  CLIENT  CONSULTANT  PROJECT  GENERAL DESCRIPTION

OF WORKS P1/2006  Global Upline

Sdn Bhd 

Jurutera Minsar

Consult Sdn Bhd 

Naiktaraf Persimpangan BDC/

Jalan Tun Jugah , Kuching Dan

Membina Jalan Hubung

Lapangan Terbang

Antarabangsa, Kuching/Stutong

Mild Steel Cement Lined Pipe and

Associated Works 

PC44/06/MB Syarikat Sesco

Berhad

Nil Contract for the Bienial Supply

and Delivery of Steel Products.

Supply, Fabricate , Hot Dip Galvanising

and Delivery Mild Steel Products.

SJ6000055 Sabah

Electricity Sdn

Bhd

Nil Supply, Fabricate,Hot Dip

Galvanising and Delivery Of Pole

strut 30'

Supply, Fabricate, Hot Dip Galvanizing

and Delivery Of Pole Strut 30'

SJ6000072 Global Upline

Sdn Bhd

Jurutera Minsar

Consult Sdn Bhd

Naiktaraf Persimpangan BDC/

Jalan Tun Jugah , Kuching Bridge

Parapet

Supply, Fabricate,Hot Dip Galvanise,

Delivery and Installation of Mild Steel.

SO6000179 Marudu

Construction

Sdn Bhd

Jurutera Minsar

Consult Sdn Bhd

Supply, Fabricate, Shot

blasting ,Painting, Delivery and

Installation of Mild Steel

Structural Steel Fame for Teluk

Salut 190MW Combined Cycle

Conversion Project.

Structural Steel Works ,Steam Turbine

Building,ACC substation and Platform.

SO6000431 Global Upline

Sdn Bhd

Jurutera Minsar

Consult Sdn Bhd

Upgrading of Labuan Airport,

Wilayah Persekutuan Labuan-

Structural Steel Works(Package

BW1-)

Structural Steel Works for Main

Terminal and Ancillary Building

SO6000431 Global Upline

Sdn Bhd

Jurutera Minsar

Consult Sdn Bhd

Upgrading of Labuan Airport,

Wilayah Persekutuan Labuan-Structural Steel Works for New

5th Squadron Hanger (Package

BW3-)

Structural Steel Works for RMAF Hanger

SO6001021 Global Upline

Sdn Bhd

Jurutera Minsar

Consult Sdn Bhd

Redevelopment of Kota Kinabalu

Internatuional Airport, Sabah

(Package 2 - Airside

Infrastructure, Act & New LCC

Terminal- Structural Steel

Works)

Structural Steel works for Main

Terminal and Ancillary Building.

SO6001764 Inai Kiara Sdn

Bhd

Nil Supply, Fabricate and delivery

FOB Kuching Wharf of 1500mm

diameter steel pipe pile (25mm

Thick Grade 50C), including PileShoe

Supply Fabricate and delivery FOB

Kuching Wharf of 1500mm diameter

steel pipe pile (25mm thick Grade 50C),

including pile.

SO6001988 WCT

Construction

Sdn Bhd

Jurutera Minsar

Consult Sdn Bhd

Upgrading of Kota Kinabalu

International Airport , Sabah -

Package1 Terminal Building and

Landside Infrastructure

Facilities.

Structural Steel Works for Terminal

Building and Landside Infrastructure

Facilities.

Page 12: KKB Project List

7/23/2019 KKB Project List

http://slidepdf.com/reader/full/kkb-project-list 12/18

12 | P a g e  

SO6002031 CM Global Sdn

Bhd

Nil Supply, Fabricate and Primer

Painting of One Unit Mild Steel

Trailer Beam, Cargo Support and

all necessary towing lug and

Bracket.

Supply, Fabricate and Primer Painting of

One Unit Mild Steel Trailer Beam, Cargo

Support and all necessary towing lug

and Bracket.

Page 13: KKB Project List

7/23/2019 KKB Project List

http://slidepdf.com/reader/full/kkb-project-list 13/18

13 | P a g e  

Project List 2005

PROJECT NO. CLIENT CONSULTANT PROJECT GENERAL DESCRIPTION

OF WORKS

P1/2005  KuchingWaterBoard 

Consultant SHCSdn Bhd 

Supply,Delivery ,Installation,Testing &

Commissioning of the proposed

1100mm (N.D) Steel Pipeline

including all associated works

from Jln Matang/ Jln Bt Kawa

Junction to Bukit Siol

Reservoir,Kuching. 

Supply,Delivery,Installation,Testing &Commissioning of 1100mm (N.D) Steel

Pipeline 

P3/2005 Derasas Jaya

Sdn Bhd

1.I.Jong Architect

2.Perunding

Muhandis Sdn

Bhd.

3.Perunding

Elecmec Sdn Bhd

Proposed Wood Particle Block

Factory and 2 Storey Office on

Plot 7 of Parent Lot 817 ,Block

37 ,Kemena Land District at

Jepak Industrial estate

(JIE) ,Bintulu , Sarawak.

Construct a Wood Particle Block

Factory, 2 Storey Building & associated

infrastructure works 

Page 14: KKB Project List

7/23/2019 KKB Project List

http://slidepdf.com/reader/full/kkb-project-list 14/18

14 | P a g e  

Project List 2004

PROJECT NO. CLIENT CONSULTANT PROJECT GENERAL DESCRIPTION

OF WORKSP1/2004

(SJ400031) 

Kuching Water

Board 

Kuching

Waterboard 

Proposed HDPE Lining and

Reinstatement of Steel Bracings

to 1 Million Gallon Elevated ERP

water Tanks at Samajaya Free

Industrial Zone, Kuching 

HDPE Lining Works and Steel Bracing

Reinstatement Works 

SJ4000032 Shell Malaysia

Trading Sdn

Bhd

Supply, fabricate, hot-dip

galvanising and delivery of shell

metal pallet complete with

locking bar and cable for Port

Dickson, Ipoh and Sepangar Bay

Supply, fabricate, hot-dip galvanising

and delivery of shell metal pallet

P2/2004 Government of

Sarawak -

Jabatan Kerja

Raya

KTA (Sarawak) Sdn

Bhd

The Construction and

Completion of Tasik Biru - Lundu

- Sematan Water Supply,

Pumping Main from Batu Kitang

WTP to Bau Package 1 -

Installation of Pumping main

Kuching Division, Sarawak

The Construction, Completion and

installation of 700mmø pipeline

P3/04

(SO4000359)

Premier Capital

Venture

Corporation

Jurutera Jasa (S)

Sdn Bhd

Upgrading Sarawak Clinker Sdn

Bhd Plant, Mechanical Works

Supply, fabricate, painting, delivery and

installation of Mechanical Works for

Hammer Mill System and Preheater

Primary and Cooler Fans

P4/2004 Sarawak

Electricity

Supply

Corporation

Biennial Supply and Delivery of

Steel Product

Supply, fabricate, hot-dip galvanising

and delivery of Steel Product

P5/2004

(WO#29356)

Global Upline

Sdn Bhd

Construction, Completion and

Commissioning of the Proposed

MSCL pipeline for

Redevelopment of Kuching

International Airport (REKIA)

Supply, installation, testing and

commissioning of 1050mmø and

alternative 457mm MSCL pipeline

P6/2004 Kuching Water

Board

Proposed 600mm ND Steel Main

Renewal along Jalan Datuk

Bandar Mustapa (From Chainage

om to 1552m), Kuching

Supply, installation, testing and

commissioning of 1050mmø and

alternative 457mm MSCL pipeline

P7/2004 Global Upline

Sdn Bhd

Redevelopment of Kuching

International Airport (REKIA)

Redevelopment of Kuching

International Airport (REKIA)

Page 15: KKB Project List

7/23/2019 KKB Project List

http://slidepdf.com/reader/full/kkb-project-list 15/18

15 | P a g e  

Project List 2003

PROJECT NO. CLIENT CONSULTANT PROJECT GENERAL DESCRIPTION

OF WORKSP01/03  DBKS (MBKS)  Construction of Bus Shelters for

the Council of City of Kuching

South for year 2003. 

Construction and completion of

proposed Bus Shelters. 

P02/03 Ibraco Realty

Development

Sdn. Bhd.

CHT Jurunding  Proposed 3 Storey Shophouse at

Tabuan Heights Commercial

Centre at MTLD, Jalan Song

Supply, fabricate, delivery and

installation of structural steel and metal

works

P03/03 Tang Container

& Services Sdn.

Bhd.

Jurutera Jasa (S)

Sdn. Bhd.

Proposed new warehouse on Lot

794, Block 7, Demak Laut

Industrial Park, Sejingkat,

Kuching (Phase II)

Supply, fabricate, and dhg of structural

Steel and metal works

P04/03 PS Geotechnic

Sdn. Bhd

TKY Consultant

Sdn. Bhd

Supply, Delivery, Laying, Testing

& Installation of 800mm ND

MSCL Pipeline for the 2nd 

Kuching Bridge Project Package

CP2/A: Bridge Structure

Remaining Sub-contractor

Works

Supply, Delivery, Laying, Testing and

Installation of 800mm ND MSCL

Pipeline

P05/03 Ibraco Realty

Development

Sdn. Bhd

Jurutera Jasa (S)

Sdn. Bhd

Construction, Completion and

Commissioning of the Proposed

900mm/700mm Diameter Steel

Pipeline from Jalan Airport/Jalan

Stutong to Samajaya

Supply, Delivery, Laying, Testing and

Commissioning of 900mm/700mm

MSCL Pipeline

P06/03 Kuching Water

Board

Jurutera Jasa (S)

Sdn. Bhd

Construction, Completion and

Commissioning of the Proposed

1600mm Diameter Steel Pipelinefrom Jalan Batu Kitang to Jalan

Datuk Stephen Yong/Jalan Batu

Kawa Junction, Kuching

Construction, Completion and

Commissioning of the proposed

1600mm Diameter Steel Pipeline

P07/03 Kuching Water

Board

Konsortium

Malaysia

Supply, Delivery, Laying, Testing

and Commissioning of the

Proposed 800mm Diameter

Steel Pipeline from Jalan

Meranek/Jalan Muara Tabuan

Junction to Samarahan Industrial

Estate

Supply, Delivery, Laying, Testing &

Commissioning of the Proposed 800mm

Diameter Steel Pipeline

Page 16: KKB Project List

7/23/2019 KKB Project List

http://slidepdf.com/reader/full/kkb-project-list 16/18

16 | P a g e  

Project List 2002

PROJECT NO. CLIENT CONSULTANT PROJECT GENERAL DESCRIPTION

OF WORKSP1/02  Shell Timur Sdn

Bhd 

Structural steel works for the

new Lubricants Warehouse at

Sibu Installation. 

Supply, fabricate, hot-dip galvanising

and installation 

P2/02 KWB Proposed 1400mmØ steel pipes

from Batu Kitang Treatment

Plant to Jalan Batu Kitang / Jalan

Penrisen Junction Kuching.

Supply, Delivery, Laying and

Commissioning

P3/02 Edisi Optima

Sdn Bhd

Renovation of IK Ho workshop

building at Lot 1382, Blk 66,

Jalan Kilang Pending Industrial

Estate Kuching.

Supply and fabricate

P4/02 HDG Division Structural steel works for the

upgrading of the existing

galvanizing units.

Supply, fabricate, painting and site

installation

P5/02 Option Nets

Sdn Bhd

Proposed of construction and

completion of Fish/Prawn feed

Factory Manufacturing and

packaging Factory at Lot 9898

Block 59, Muara Tuang Land

District, Kota Samarahan Ind.

Estate, Samarahan.

Supply and fabricate

P6/02 SWB Proposed system Agihan Bandar

Baru Sibu, Sarawak.

Supply, Delivery, Laying, Testing and

Commissioning

P7/02 KWB Proposed 750mm steel pipeline

from Jalan Penrisen/Jalan MuaraTuang Junction to 9¾ Mile

Reservoir, Kuching, Sarawak.

Supply, Delivery, Laying, Testing and

Commissioning

P8/02 KWB Proposed Upgrading / Renewal

of 500mm Asbestos Cement

(AC) Truck Main to 750mm Steel

Main from 7th Miles Reservoir

to Datu Muda Reservoir.

Supply, Delivery, Laying, Testing and

Commissioning

P9/02 Metro Sedia

Management

Sdn Bhd

Proposed Bitumen Storage &

Delivery facilities at Pending

Port, Kuching, Sarawak.

Construction, Testing and

Commissioning

P10/02 SESCO Biennial Supply and Delivery of

hot-dip galvanised pipes.

Supply, and Delivery

P11/02 P11/02 Proposed Semi Detached LightIndustrial Estate Building on Sub

lots at Parent Lots 1269 & 1185,

Block 12, Jalan Setia Raja (Muara

Tabuan Phase V Stage III)

Supply, Fabricate, Hot-dip galvanizing,Painting, Delivery and Installation

Page 17: KKB Project List

7/23/2019 KKB Project List

http://slidepdf.com/reader/full/kkb-project-list 17/18

17 | P a g e  

Project List 2001

PROJECT NO. CLIENT CONSULTANT PROJECT GENERAL DESCRIPTION

OF WORKSP1/2001  Naim Cendera

Sdn.Bhd. 

Proposed Institute Kemahiran

Belia Negara, Miri (IKBN) 

Supply and install roof truss 

P2/2001 Hock Seng Lee

Bhd

Proposed water reticulation

mains, r.c. drainage and main

access road to Sarawak

Technology Park, Samarahan – 

External Water supply system

Supply, lay, joint, test and fixing bends

along pipe route

P3/2001 SKH Sports

Equipment

Sdn.Bhd.

Construction of Proposed

Warehouse at Siol and Demak

Nines

Construction and completion of

proposed warehouse

P4/2001 Kuching

Waterboard

(Contract No :

KWB/Con.8/2001)

600mm Nominal Diameter Steel

Main along Jln Kuching / Serian

from 9½ Miles Jln Kuching /

Serian to the junction of Jln

Quap & along Jln Kuching /

Serian (from chainage 0m to

905m), Kuching

Supply, delivery and laying

Page 18: KKB Project List

7/23/2019 KKB Project List

http://slidepdf.com/reader/full/kkb-project-list 18/18

18 | P a g e  

Project List 2000

PROJECT NO. CLIENT CONSULTANT PROJECT GENERAL DESCRIPTION

OF WORKSP1/2000  Nishimatsu

Construction

Co. Ltd 

WTS Konsultant  Proposed Phase IV factory

Building for Taiyo Yuden(S) Snd.

Bhd. on lots 1132 & 1188, Blk

12, Off Jalan Setia Raja,

Samajaya Free Industrial Zone -

Factory 8 and miscellaneous

steelwork 

Supply, fabricate, paint, deliver and

erection of structural steelwork and

other miscellaneous steel structures 

P2/2000 Walter Group

International -

IJM Joint

Venture

1st Silicon Waferfab Project,

Kuching. FAB Utility steel

Package at 2nd Floor Level

(Package No. 2SC-P-F27E)

Supply, fabrication, painting and

erection of pipe supporting channels

and etc. 

P3/2000 Mudajaya

Corporation

Bhd.

Lim Consultant

Team

Proposed UTM Hostel at

Samarahan, Kuching

Supply of all materials of steel

structures. 

P4/2000 Syarikat Wisma

Kontrektor

Syarikat Wisma

Kontrektor

Proposed Observation Tower at

Miri - Structural Steelworks

Supply, fabricate and hot-dip galvanised

of structural steelworks

P5/2000 Petronas

Dagangan Bhd.

Supply and fabricate of 4,000Gl

skid tank and underground tank

Supply, fabricate and painting of skid

tank

P6/2000 Kuching Water

Board

Jurutera Jasa (S)

Sdn. Bhd

Construction, completion &

commissioning of the proposed

900mm/700mm steel pipeline

from Jalan Airport/Jalan Stutong

 junction to Samajaya Kuching,

Sarawak

Supply and installation of pipelines